Black Iron Releases Feasibility Study Showing 45.9% IRR, 2.2 Year Payback and U.S. $3.5 Billion NPV for Shymanivske Project

TORONTO, ONTARIO -- (Marketwire) -- 11/15/12 -- Black Iron Inc. ("Black Iron" or the "Company") (TSX:BKI)(FRANKFURT:BIN) is pleased to announce the results of the Bankable Feasibility Study ("BFS") completed on its Shymanivske Iron Ore Project located in Kryviy Rih, Ukraine (the "Project"). The BFS outlines an operation producing 9.2 million tonnes per year of high-grade 68% iron ore concentrate, projecting a 45.9% internal rate of return ("IRR") and a U.S. $3.5 billion net present value ("NPV") at an 8% discount rate.

The BFS was completed by WorleyParsons Canada Services Ltd. ("WorleyParsons"), Watts, Griffis and McOuat Limited ("WGM"), Consulting Geologists and Engineers of Toronto, and P&E Mining Consultants Inc. ("P&E"). Mr. Michael Kociumbas, P.Geo., and Mr. Rick Risto, P.Geo., both with independent firm WGM, are Qualified Persons as defined by NI 43-101. WGM has previously visited the site, collected independent core samples and reviewed the QA/QC data received to date. Mr. Risto has reviewed and approved the underlying sampling, analytical and test data used for the estimate and Mr. Kociumbas is responsible for auditing the in-house mineral resource estimate as supplied by Black Iron. The estimate is classified as Measured, Indicated and Inferred mineral resources, consistent with the CIM definitions referred to in National Instrument 43-101. The complete BFS report will be filed on SEDAR and Black Iron's website within 45 days of the publication of this news release.

The Table below summarizes the key elements of the BFS:

High-Grade 68% Concentrate (all currency is USD, pre-tax)


----------------------------------------------------------------------------
NPV at 8% discount rate                                      $  3.5 billion 
----------------------------------------------------------------------------
IRR                                                                    45.9%
----------------------------------------------------------------------------
Total Estimated Capital Costs (excluding sustaining capital) $ 1094 million 
----------------------------------------------------------------------------
Life of Mine FOB OPEX (Beneficiation, Mine & Transportation) $     43.97 /t 
Mine Gate OPEX (Beneficiation & Mine)                        $     29.67 /t 
----------------------------------------------------------------------------
High-Grade 68% Concentrate Sales Price Forecast - based on                  
 long term CFR benchmark price of $95/T @ 62% iron adjusted                 
 for Black Iron's higher iron content and shorter shipping                  
 distance to end users                                                      
  (Year 1, 2016)                                             $          125 
  (Year 2)                                                   $          117 
  (Year 3 onward; long-term)                                 $          115 
----------------------------------------------------------------------------
Average Annual Cash Flow                                     $  593 million 
----------------------------------------------------------------------------
Estimated Mine Life                                                16 years 
----------------------------------------------------------------------------
Final Product Iron Grade (Fine Iron Ore Concentrate)                 68% Fe 
----------------------------------------------------------------------------
Measured and Indicated Resource (at 31.6% iron)                    645.8 Mt 
----------------------------------------------------------------------------
Proven and Probable Reserves (at 31.1% iron)                       448.2 Mt 
----------------------------------------------------------------------------
Annual Production Rate (average life of mine, post ramp-up                  
 year)                                                               9.2 Mt 
----------------------------------------------------------------------------
Projected Plant Start-up and Commissioning                         Q4, 2015 
----------------------------------------------------------------------------
Projected Commencement of Revenue Generation                       Q1, 2016 
----------------------------------------------------------------------------
Projected Years to Payback (at 8% Discount Rate)                  2.2 years 
----------------------------------------------------------------------------

Matt Simpson, Black Iron's President and CEO, commented, "The operation outlined by this BFS for the Shymanivske Project clearly illustrates the potential for a high-value, low net cost iron ore development project. The projected high NPV, net cash flows, and relatively low unit cost for concentrate arise from Black Iron's advantages, which include an iron ore deposit with significant existing infrastructure (railway, power lines and port) in addition to access to low-cost skilled labour. We continue to deliver on our objective timetable and our results to date, coupled with this engineering study, make a compelling case for expediting the development of the Shymanivske Project."

Financial Sensitivities at Various Discount Rates


----------------------------------------------------------------------------
IRR (pre-tax)                                             45.9%             
----------------------------------------------------------------------------
                                                      Pre-Tax               
                                                      NPV USD        Payback
Discount Rate                                      (Millions)        (Years)
----------------------------------------------------------------------------
0%                                           $           8392            1.9
----------------------------------------------------------------------------
6%                                           $           4328            2.1
----------------------------------------------------------------------------
8%                                           $           3524            2.2
----------------------------------------------------------------------------
10%                                          $           2887            2.3
----------------------------------------------------------------------------

The Project has favourable economic potential across a range of discount rates. The operations outlined in this BFS are projected to generate over U.S. $1136 million in average annual revenue over the life of mine.

On the basis of the metallurgical test work completed for this BFS, it is estimated that the process weight recovery of 32.7% would yield a project life of 16 years at an average strip ratio of 1.63:1, according to the current estimated resource. The Company believes that additional exploration and definition drilling work have the potential to expand the existing resource and upgrade the 188.3 Mt of Inferred mineral resource to the Measured and Indicated classification, potentially adding up to 5 years to the Project life. With successful exploration in the North end of Shymanivske and the addition of resources from the nearly adjacent Zelenivske Project, Black Iron expects to be able to support an even higher annual production rate, which would further increase the already favourable Project NPV.

George Mover, Black Iron's Chief Operating Officer, added, "We are pleased with the level of engineering expertise and rigour behind this BFS. Through the process, we implemented several improvements to the work completed last year for our Preliminary Economic Assessment. We have found and verified solutions to optimize the process flow sheet, to reduce the stripping ratio through mine phasing, and to increase our weight recoveries. As a result, we are now considering an initial operation with 26% higher annual production and 16% lower operating costs than in our previous study. The relatively low-unit operating cost of production, coupled with close proximity to Turkish, European, and Middle East customers, means that this operation has the potential to remain profitable despite fluctuations in the iron ore price."

Details and Assumptions

Total initial capital expenditures are estimated at U.S. $1094 million to produce a high-grade 68% iron ore concentrate. The capital cost estimate excludes the sustaining capital cost of U.S. $689 million. The initial assessment of the preferred port facility indicates that sufficient capacity currently exists for the planned production.


----------------------------------------------------------------------------
Summary of Estimated Initial Capital Costs                    USD (millions)
----------------------------------------------------------------------------
Mining Capitalized Pre-Stripping Costs                                    61
----------------------------------------------------------------------------
Mine Fleet Lease Costs                                                    62
----------------------------------------------------------------------------
Concentrator and Site Infrastructure                                     654
----------------------------------------------------------------------------
Environmental and Tailings Management                                     20
----------------------------------------------------------------------------
Rail Spur                                                                  9
----------------------------------------------------------------------------
Port Facilities                                                          nil
----------------------------------------------------------------------------
Indirect Costs and Land Acquisition                                      189
----------------------------------------------------------------------------
Contingency (10%)                                                         99
----------------------------------------------------------------------------
TOTAL                                                                   1094
----------------------------------------------------------------------------

The total average operating costs over 16 years are estimated at U.S. $43.97 per tonne of high grade 68% iron ore concentrate.


----------------------------------------------------------------------------
                                                                USD/tonne of
                                                                 Concentrate
                                                                    (Average
Summary of Estimated Operating Costs                              Mine Life)
----------------------------------------------------------------------------
Mining                                                     $           13.51
----------------------------------------------------------------------------
Concentrator                                               $           14.30
----------------------------------------------------------------------------
Site Infrastructure                                        $            0.75
----------------------------------------------------------------------------
Sales and General Administration                           $            0.75
----------------------------------------------------------------------------
Environmental and Tailings Management                      $            0.37
----------------------------------------------------------------------------
Rail Transportation                                        $            7.39
----------------------------------------------------------------------------
Port Facility                                              $            6.90
----------------------------------------------------------------------------
TOTAL                                                      $           43.97
----------------------------------------------------------------------------

Consistent with practice in the industry, this BFS has been prepared with an engineering accuracy of +/-15%.

Currency Sensitivity

For the purpose of the BFS an exchange rate of 8.1 UAH per USD has been used for the CAPEX (up to Jan. 2016) and 9.0 UAH per USD for the OPEX and Sustaining Capital (2016 and beyond). Variations in the exchange rates from year 2016 and beyond impact the financial analysis as follows.

Impact of Ukraine Hryvna Exposure - BFS Currency Sensitivity


----------------------------------------------------------------------------
                                                      (UAH/USD)             
                                        ------------------------------------
Exchange Rate as of year 2016 onward          8:1      9:1     10:1     11:1
----------------------------------------------------------------------------
NPV @ 8% discount U.S. $ (millions)          3334     3524     3677     3800
----------------------------------------------------------------------------
Total Estimated Capital Cost                 1094     1094     1094     1094
----------------------------------------------------------------------------
Estimated Operating Cost ($/tonne)          46.73    43.97    41.75    39.96
----------------------------------------------------------------------------
Average Annual Cash Flow U.S. $                                             
 (millions)                                   568      593      613      629
----------------------------------------------------------------------------

Bankable Feasibility Study Report

The BFS has been prepared in accordance with the guidelines of National Instrument 43-101, by the independent firms of WorleyParsons Canada Services Ltd., Watts, Griffis and McOuat Limited and P&E Mining Consultants Inc. WorleyParsons is a leading full-service engineering firm and has experience in the sector that includes the design and construction supervision of many components of some of the world's leading iron ore assets. The final BFS technical report, which will also include the current mineral resource estimate, will be filed on SEDAR within 45 days of the publication of this news release.

Pellet Plant Alternative

Black Iron has investigated an alternative production scenario, which would include the production of high-grade iron ore pellets. The pellet production alternative is not included as part of the BFS.

Analyst and Shareholder Conference Call

Black Iron will host a conference call today at 8:00 a.m., EST (November 15, 2012) to discuss the BFS results. To participate in the call please dial the following:

International: +1 416 340 8527

Toll Free North America: 1 877 240 9772

To register and listen to the webcast of the call, please go to Black Iron's website at www.blackiron.com.

Qualified Persons

The contents of this press release have been prepared under the supervision of and reviewed and approved by Qualified Persons, as follows:


--  Rob Spiering, P.Eng., Project Manager, WorleyParsons QP for the Process
    Plant and Infrastructure;

--  Michael Kociumbas, P.Geo. and Rick Risto, P.Geo., Watts, Griffis and
    McOuat Limited, QPs for mineral resources and QA/QC and data
    verification;

--  Eugene Puritch, P.Eng., P&E Mining Consultants Inc., QP for the mine
    engineering aspects.

These persons are Qualified Persons as defined by NI 43-101, are independent of Black Iron, and have reviewed the content of this press release. For further information, please see the technical report of the Company, which is available on SEDAR at www.sedar.com.

Additional information about the Project can be found in the technical report filed on SEDAR at www.sedar.com, entitled "Resource Estimate - Shymanivske Deposit in Ukraine," and dated January 31, 2011.

About Black Iron

Black Iron is an iron ore exploration and development company, advancing its 100 percent-owned Shymanivske project located in Kryviy Rih, Ukraine. This project contains an NI 43-101 compliant resource, with 645.8 Mt Measured and Indicated mineral resources, consisting of 355.1 Mt Measured mineral resources grading 32.0% Total iron and 19.5% Magnetic iron, and Indicated mineral resources of 290.7 Mt grading 31.1% Total iron and 17.9% Magnetic iron, using a cut-off grade of 10% Magnetic iron. Additionally, the project contains 188.3 Mt of Inferred mineral resources grading 30.1% Total iron and 18.4% Magnetic iron. The project is surrounded by five other operating mines, including ArcelorMittal's iron ore complex. The Company believes that existing infrastructure, including access to power, rail and port facilities, will allow for a quick development timeline to production. Further, the Company holds an exploration permit for the adjacent Zelenivske project, which it intends to further explore to determine its potential. Please visit the Company's website at www.blackiron.com or write us at [email protected] for more information.

Forward-Looking Information

This press release contains forward-looking information which may include, but is not limited to, statements about the results of the FS and the development potential of the Company and its project; the timing and amount of future exploration and development of the project; and the future financial or operating performance of the Company and its projects. Often, but not always, forward-looking information can be identified by the use of words such as "plans," "expects," "is expected," "budget," "scheduled," "estimates," "forecasts," "intends," "anticipates" or "believes" or variations (including negative variations) of such words and phrases, or by the use of words or phrases that state that certain actions, events or results "may," "could," "would," "might" or "will" be taken, occur or be achieved.

Forward-looking information is based on certain assumptions and analyses made by the Company and based on known facts at the time. Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company and/or its subsidiaries to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information contained in this press release, including, without limitation, those described in the Company's public disclosure documents which may be found under the Company's profile on SEDAR. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in such forward-looking information, there may be other factors that may cause actions, events or results to differ from those anticipated, estimated or intended. Should one or more of these risks or uncertainties materialize, or should assumptions underlying such forward-looking information prove incorrect, actual results, performance or achievements may vary materially from those expressed or implied by the forward-looking information contained in this press release. The forward-looking information contained herein is made as of the date of this press release and the Company disclaims any obligation to update or review such information or statements, whether as a result of new information, future events or results or otherwise, except as required by law.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
While some vendors scramble to create and sell you a fancy solution for monitoring your spanking new Amazon Lambdas, hear how you can do it on the cheap using just built-in Java APIs yourself. By exploiting a little-known fact that Lambdas aren’t exactly single threaded, you can effectively identify hot spots in your serverless code. In his session at 20th Cloud Expo, David Martin, Principal Product Owner at CA Technologies, will give a live demonstration and code walkthrough, showing how to o...
SYS-CON Events announced today that Hitachi, the leading provider the Internet of Things and Digital Transformation, will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Hitachi Data Systems, a wholly owned subsidiary of Hitachi, Ltd., offers an integrated portfolio of services and solutions that enable digital transformation through enhanced data management, governance, mobility and analytics. We help globa...
The explosion of new web/cloud/IoT-based applications and the data they generate are transforming our world right before our eyes. In this rush to adopt these new technologies, organizations are often ignoring fundamental questions concerning who owns the data and failing to ask for permission to conduct invasive surveillance of their customers. Organizations that are not transparent about how their systems gather data telemetry without offering shared data ownership risk product rejection, regu...
In his keynote at 19th Cloud Expo, Sheng Liang, co-founder and CEO of Rancher Labs, discussed the technological advances and new business opportunities created by the rapid adoption of containers. With the success of Amazon Web Services (AWS) and various open source technologies used to build private clouds, cloud computing has become an essential component of IT strategy. However, users continue to face challenges in implementing clouds, as older technologies evolve and newer ones like Docker c...
SYS-CON Events announced today that SoftLayer, an IBM Company, has been named “Gold Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2016, at the Javits Center in New York, New York. SoftLayer, an IBM Company, provides cloud infrastructure as a service from a growing number of data centers and network points of presence around the world. SoftLayer’s customers range from Web startups to global enterprises.
Cloud Expo, Inc. has announced today that Aruna Ravichandran, vice president of DevOps Product and Solutions Marketing at CA Technologies, has been named co-conference chair of DevOps at Cloud Expo 2017. The @DevOpsSummit at Cloud Expo New York will take place on June 6-8, 2017, at the Javits Center in New York City, New York, and @DevOpsSummit at Cloud Expo Silicon Valley will take place Oct. 31-Nov. 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
@DevOpsSummit at Cloud taking place June 6-8, 2017, at Javits Center, New York City, is co-located with the 20th International Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long developm...
With major technology companies and startups seriously embracing IoT strategies, now is the perfect time to attend @ThingsExpo 2016 in New York. Learn what is going on, contribute to the discussions, and ensure that your enterprise is as "IoT-Ready" as it can be! Internet of @ThingsExpo, taking place June 6-8, 2017, at the Javits Center in New York City, New York, is co-located with 20th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry p...
Translating agile methodology into real-world best practices within the modern software factory has driven widespread DevOps adoption, yet much work remains to expand workflows and tooling across the enterprise. As models evolve from pockets of experimentation into wholescale organizational reinvention, practitioners find themselves challenged to incorporate the culture and architecture necessary to support DevOps at scale. In his session at @DevOpsSummit at 20th Cloud Expo, Anand Akela, Senior...
SYS-CON Events announced today that Juniper Networks (NYSE: JNPR), an industry leader in automated, scalable and secure networks, will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Juniper Networks challenges the status quo with products, solutions and services that transform the economics of networking. The company co-innovates with customers and partners to deliver automated, scalable and secure network...
SYS-CON Events announced today that Progress, a global leader in application development, has been named “Bronze Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Enterprises today are rapidly adopting the cloud, while continuing to retain business-critical/sensitive data inside the firewall. This is creating two separate data silos – one inside the firewall and the other outside the firewall. Cloud ISVs oft...
Five years ago development was seen as a dead-end career, now it’s anything but – with an explosion in mobile and IoT initiatives increasing the demand for skilled engineers. But apart from having a ready supply of great coders, what constitutes true ‘DevOps Royalty’? It’ll be the ability to craft resilient architectures, supportability, security everywhere across the software lifecycle. In his keynote at @DevOpsSummit at 20th Cloud Expo, Jeffrey Scheaffer, GM and SVP, Continuous Delivery Busine...
As pervasive as cloud technology is -- and as persuasive as the arguments are for using it -- the cloud has its limits. Some companies will always have security concerns about storing data in the cloud and certain high-transaction applications will always be better suited for on-premises storage. Those statements were among the bottom-line takeaways delivered at Cloud Expo this week, a three day, bi-annual event focused on cloud technologies, adoption and associated challenges.
Bert Loomis was a visionary. This general session will highlight how Bert Loomis and people like him inspire us to build great things with small inventions. In their general session at 19th Cloud Expo, Harold Hannon, Architect at IBM Bluemix, and Michael O'Neill, Strategic Business Development at Nvidia, discussed the accelerating pace of AI development and how IBM Cloud and NVIDIA are partnering to bring AI capabilities to "every day," on-demand. They also reviewed two "free infrastructure" pr...
SYS-CON Events announced today that T-Mobile will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. As America's Un-carrier, T-Mobile US, Inc., is redefining the way consumers and businesses buy wireless services through leading product and service innovation. The Company's advanced nationwide 4G LTE network delivers outstanding wireless experiences to 67.4 million customers who are unwilling to compromise on ...