Black Iron Releases Feasibility Study Showing 45.9% IRR, 2.2 Year Payback and U.S. $3.5 Billion NPV for Shymanivske Project

TORONTO, ONTARIO -- (Marketwire) -- 11/15/12 -- Black Iron Inc. ("Black Iron" or the "Company") (TSX:BKI)(FRANKFURT:BIN) is pleased to announce the results of the Bankable Feasibility Study ("BFS") completed on its Shymanivske Iron Ore Project located in Kryviy Rih, Ukraine (the "Project"). The BFS outlines an operation producing 9.2 million tonnes per year of high-grade 68% iron ore concentrate, projecting a 45.9% internal rate of return ("IRR") and a U.S. $3.5 billion net present value ("NPV") at an 8% discount rate.

The BFS was completed by WorleyParsons Canada Services Ltd. ("WorleyParsons"), Watts, Griffis and McOuat Limited ("WGM"), Consulting Geologists and Engineers of Toronto, and P&E Mining Consultants Inc. ("P&E"). Mr. Michael Kociumbas, P.Geo., and Mr. Rick Risto, P.Geo., both with independent firm WGM, are Qualified Persons as defined by NI 43-101. WGM has previously visited the site, collected independent core samples and reviewed the QA/QC data received to date. Mr. Risto has reviewed and approved the underlying sampling, analytical and test data used for the estimate and Mr. Kociumbas is responsible for auditing the in-house mineral resource estimate as supplied by Black Iron. The estimate is classified as Measured, Indicated and Inferred mineral resources, consistent with the CIM definitions referred to in National Instrument 43-101. The complete BFS report will be filed on SEDAR and Black Iron's website within 45 days of the publication of this news release.

The Table below summarizes the key elements of the BFS:

High-Grade 68% Concentrate (all currency is USD, pre-tax)


----------------------------------------------------------------------------
NPV at 8% discount rate                                      $  3.5 billion 
----------------------------------------------------------------------------
IRR                                                                    45.9%
----------------------------------------------------------------------------
Total Estimated Capital Costs (excluding sustaining capital) $ 1094 million 
----------------------------------------------------------------------------
Life of Mine FOB OPEX (Beneficiation, Mine & Transportation) $     43.97 /t 
Mine Gate OPEX (Beneficiation & Mine)                        $     29.67 /t 
----------------------------------------------------------------------------
High-Grade 68% Concentrate Sales Price Forecast - based on                  
 long term CFR benchmark price of $95/T @ 62% iron adjusted                 
 for Black Iron's higher iron content and shorter shipping                  
 distance to end users                                                      
  (Year 1, 2016)                                             $          125 
  (Year 2)                                                   $          117 
  (Year 3 onward; long-term)                                 $          115 
----------------------------------------------------------------------------
Average Annual Cash Flow                                     $  593 million 
----------------------------------------------------------------------------
Estimated Mine Life                                                16 years 
----------------------------------------------------------------------------
Final Product Iron Grade (Fine Iron Ore Concentrate)                 68% Fe 
----------------------------------------------------------------------------
Measured and Indicated Resource (at 31.6% iron)                    645.8 Mt 
----------------------------------------------------------------------------
Proven and Probable Reserves (at 31.1% iron)                       448.2 Mt 
----------------------------------------------------------------------------
Annual Production Rate (average life of mine, post ramp-up                  
 year)                                                               9.2 Mt 
----------------------------------------------------------------------------
Projected Plant Start-up and Commissioning                         Q4, 2015 
----------------------------------------------------------------------------
Projected Commencement of Revenue Generation                       Q1, 2016 
----------------------------------------------------------------------------
Projected Years to Payback (at 8% Discount Rate)                  2.2 years 
----------------------------------------------------------------------------

Matt Simpson, Black Iron's President and CEO, commented, "The operation outlined by this BFS for the Shymanivske Project clearly illustrates the potential for a high-value, low net cost iron ore development project. The projected high NPV, net cash flows, and relatively low unit cost for concentrate arise from Black Iron's advantages, which include an iron ore deposit with significant existing infrastructure (railway, power lines and port) in addition to access to low-cost skilled labour. We continue to deliver on our objective timetable and our results to date, coupled with this engineering study, make a compelling case for expediting the development of the Shymanivske Project."

Financial Sensitivities at Various Discount Rates


----------------------------------------------------------------------------
IRR (pre-tax)                                             45.9%             
----------------------------------------------------------------------------
                                                      Pre-Tax               
                                                      NPV USD        Payback
Discount Rate                                      (Millions)        (Years)
----------------------------------------------------------------------------
0%                                           $           8392            1.9
----------------------------------------------------------------------------
6%                                           $           4328            2.1
----------------------------------------------------------------------------
8%                                           $           3524            2.2
----------------------------------------------------------------------------
10%                                          $           2887            2.3
----------------------------------------------------------------------------

The Project has favourable economic potential across a range of discount rates. The operations outlined in this BFS are projected to generate over U.S. $1136 million in average annual revenue over the life of mine.

On the basis of the metallurgical test work completed for this BFS, it is estimated that the process weight recovery of 32.7% would yield a project life of 16 years at an average strip ratio of 1.63:1, according to the current estimated resource. The Company believes that additional exploration and definition drilling work have the potential to expand the existing resource and upgrade the 188.3 Mt of Inferred mineral resource to the Measured and Indicated classification, potentially adding up to 5 years to the Project life. With successful exploration in the North end of Shymanivske and the addition of resources from the nearly adjacent Zelenivske Project, Black Iron expects to be able to support an even higher annual production rate, which would further increase the already favourable Project NPV.

George Mover, Black Iron's Chief Operating Officer, added, "We are pleased with the level of engineering expertise and rigour behind this BFS. Through the process, we implemented several improvements to the work completed last year for our Preliminary Economic Assessment. We have found and verified solutions to optimize the process flow sheet, to reduce the stripping ratio through mine phasing, and to increase our weight recoveries. As a result, we are now considering an initial operation with 26% higher annual production and 16% lower operating costs than in our previous study. The relatively low-unit operating cost of production, coupled with close proximity to Turkish, European, and Middle East customers, means that this operation has the potential to remain profitable despite fluctuations in the iron ore price."

Details and Assumptions

Total initial capital expenditures are estimated at U.S. $1094 million to produce a high-grade 68% iron ore concentrate. The capital cost estimate excludes the sustaining capital cost of U.S. $689 million. The initial assessment of the preferred port facility indicates that sufficient capacity currently exists for the planned production.


----------------------------------------------------------------------------
Summary of Estimated Initial Capital Costs                    USD (millions)
----------------------------------------------------------------------------
Mining Capitalized Pre-Stripping Costs                                    61
----------------------------------------------------------------------------
Mine Fleet Lease Costs                                                    62
----------------------------------------------------------------------------
Concentrator and Site Infrastructure                                     654
----------------------------------------------------------------------------
Environmental and Tailings Management                                     20
----------------------------------------------------------------------------
Rail Spur                                                                  9
----------------------------------------------------------------------------
Port Facilities                                                          nil
----------------------------------------------------------------------------
Indirect Costs and Land Acquisition                                      189
----------------------------------------------------------------------------
Contingency (10%)                                                         99
----------------------------------------------------------------------------
TOTAL                                                                   1094
----------------------------------------------------------------------------

The total average operating costs over 16 years are estimated at U.S. $43.97 per tonne of high grade 68% iron ore concentrate.


----------------------------------------------------------------------------
                                                                USD/tonne of
                                                                 Concentrate
                                                                    (Average
Summary of Estimated Operating Costs                              Mine Life)
----------------------------------------------------------------------------
Mining                                                     $           13.51
----------------------------------------------------------------------------
Concentrator                                               $           14.30
----------------------------------------------------------------------------
Site Infrastructure                                        $            0.75
----------------------------------------------------------------------------
Sales and General Administration                           $            0.75
----------------------------------------------------------------------------
Environmental and Tailings Management                      $            0.37
----------------------------------------------------------------------------
Rail Transportation                                        $            7.39
----------------------------------------------------------------------------
Port Facility                                              $            6.90
----------------------------------------------------------------------------
TOTAL                                                      $           43.97
----------------------------------------------------------------------------

Consistent with practice in the industry, this BFS has been prepared with an engineering accuracy of +/-15%.

Currency Sensitivity

For the purpose of the BFS an exchange rate of 8.1 UAH per USD has been used for the CAPEX (up to Jan. 2016) and 9.0 UAH per USD for the OPEX and Sustaining Capital (2016 and beyond). Variations in the exchange rates from year 2016 and beyond impact the financial analysis as follows.

Impact of Ukraine Hryvna Exposure - BFS Currency Sensitivity


----------------------------------------------------------------------------
                                                      (UAH/USD)             
                                        ------------------------------------
Exchange Rate as of year 2016 onward          8:1      9:1     10:1     11:1
----------------------------------------------------------------------------
NPV @ 8% discount U.S. $ (millions)          3334     3524     3677     3800
----------------------------------------------------------------------------
Total Estimated Capital Cost                 1094     1094     1094     1094
----------------------------------------------------------------------------
Estimated Operating Cost ($/tonne)          46.73    43.97    41.75    39.96
----------------------------------------------------------------------------
Average Annual Cash Flow U.S. $                                             
 (millions)                                   568      593      613      629
----------------------------------------------------------------------------

Bankable Feasibility Study Report

The BFS has been prepared in accordance with the guidelines of National Instrument 43-101, by the independent firms of WorleyParsons Canada Services Ltd., Watts, Griffis and McOuat Limited and P&E Mining Consultants Inc. WorleyParsons is a leading full-service engineering firm and has experience in the sector that includes the design and construction supervision of many components of some of the world's leading iron ore assets. The final BFS technical report, which will also include the current mineral resource estimate, will be filed on SEDAR within 45 days of the publication of this news release.

Pellet Plant Alternative

Black Iron has investigated an alternative production scenario, which would include the production of high-grade iron ore pellets. The pellet production alternative is not included as part of the BFS.

Analyst and Shareholder Conference Call

Black Iron will host a conference call today at 8:00 a.m., EST (November 15, 2012) to discuss the BFS results. To participate in the call please dial the following:

International: +1 416 340 8527

Toll Free North America: 1 877 240 9772

To register and listen to the webcast of the call, please go to Black Iron's website at www.blackiron.com.

Qualified Persons

The contents of this press release have been prepared under the supervision of and reviewed and approved by Qualified Persons, as follows:


--  Rob Spiering, P.Eng., Project Manager, WorleyParsons QP for the Process
    Plant and Infrastructure;

--  Michael Kociumbas, P.Geo. and Rick Risto, P.Geo., Watts, Griffis and
    McOuat Limited, QPs for mineral resources and QA/QC and data
    verification;

--  Eugene Puritch, P.Eng., P&E Mining Consultants Inc., QP for the mine
    engineering aspects.

These persons are Qualified Persons as defined by NI 43-101, are independent of Black Iron, and have reviewed the content of this press release. For further information, please see the technical report of the Company, which is available on SEDAR at www.sedar.com.

Additional information about the Project can be found in the technical report filed on SEDAR at www.sedar.com, entitled "Resource Estimate - Shymanivske Deposit in Ukraine," and dated January 31, 2011.

About Black Iron

Black Iron is an iron ore exploration and development company, advancing its 100 percent-owned Shymanivske project located in Kryviy Rih, Ukraine. This project contains an NI 43-101 compliant resource, with 645.8 Mt Measured and Indicated mineral resources, consisting of 355.1 Mt Measured mineral resources grading 32.0% Total iron and 19.5% Magnetic iron, and Indicated mineral resources of 290.7 Mt grading 31.1% Total iron and 17.9% Magnetic iron, using a cut-off grade of 10% Magnetic iron. Additionally, the project contains 188.3 Mt of Inferred mineral resources grading 30.1% Total iron and 18.4% Magnetic iron. The project is surrounded by five other operating mines, including ArcelorMittal's iron ore complex. The Company believes that existing infrastructure, including access to power, rail and port facilities, will allow for a quick development timeline to production. Further, the Company holds an exploration permit for the adjacent Zelenivske project, which it intends to further explore to determine its potential. Please visit the Company's website at www.blackiron.com or write us at [email protected] for more information.

Forward-Looking Information

This press release contains forward-looking information which may include, but is not limited to, statements about the results of the FS and the development potential of the Company and its project; the timing and amount of future exploration and development of the project; and the future financial or operating performance of the Company and its projects. Often, but not always, forward-looking information can be identified by the use of words such as "plans," "expects," "is expected," "budget," "scheduled," "estimates," "forecasts," "intends," "anticipates" or "believes" or variations (including negative variations) of such words and phrases, or by the use of words or phrases that state that certain actions, events or results "may," "could," "would," "might" or "will" be taken, occur or be achieved.

Forward-looking information is based on certain assumptions and analyses made by the Company and based on known facts at the time. Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company and/or its subsidiaries to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information contained in this press release, including, without limitation, those described in the Company's public disclosure documents which may be found under the Company's profile on SEDAR. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in such forward-looking information, there may be other factors that may cause actions, events or results to differ from those anticipated, estimated or intended. Should one or more of these risks or uncertainties materialize, or should assumptions underlying such forward-looking information prove incorrect, actual results, performance or achievements may vary materially from those expressed or implied by the forward-looking information contained in this press release. The forward-looking information contained herein is made as of the date of this press release and the Company disclaims any obligation to update or review such information or statements, whether as a result of new information, future events or results or otherwise, except as required by law.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
20th Cloud Expo, taking place June 6-8, 2017, at the Javits Center in New York City, NY, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy.
Manufacturers are embracing the Industrial Internet the same way consumers are leveraging Fitbits – to improve overall health and wellness. Both can provide consistent measurement, visibility, and suggest performance improvements customized to help reach goals. Fitbit users can view real-time data and make adjustments to increase their activity. In his session at @ThingsExpo, Mark Bernardo Professional Services Leader, Americas, at GE Digital, discussed how leveraging the Industrial Internet and...
SYS-CON Events announced today that delaPlex will exhibit at SYS-CON's @CloudExpo, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. delaPlex pioneered Software Development as a Service (SDaaS), which provides scalable resources to build, test, and deploy software. It’s a fast and more reliable way to develop a new product or expand your in-house team.
Web Real-Time Communication APIs have quickly revolutionized what browsers are capable of. In addition to video and audio streams, we can now bi-directionally send arbitrary data over WebRTC's PeerConnection Data Channels. With the advent of Progressive Web Apps and new hardware APIs such as WebBluetooh and WebUSB, we can finally enable users to stitch together the Internet of Things directly from their browsers while communicating privately and securely in a decentralized way.
Information technology (IT) advances are transforming the way we innovate in business, thereby disrupting the old guard and their predictable status-quo. It’s creating global market turbulence. Industries are converging, and new opportunities and threats are emerging, like never before. So, how are savvy chief information officers (CIOs) leading this transition? Back in 2015, the IBM Institute for Business Value conducted a market study that included the findings from over 1,800 CIO interviews ...
"Matrix is an ambitious open standard and implementation that's set up to break down the fragmentation problems that exist in IP messaging and VoIP communication," explained John Woolf, Technical Evangelist at Matrix, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
Web Real-Time Communication APIs have quickly revolutionized what browsers are capable of. In addition to video and audio streams, we can now bi-directionally send arbitrary data over WebRTC's PeerConnection Data Channels. With the advent of Progressive Web Apps and new hardware APIs such as WebBluetooh and WebUSB, we can finally enable users to stitch together the Internet of Things directly from their browsers while communicating privately and securely in a decentralized way.
"We host and fully manage cloud data services, whether we store, the data, move the data, or run analytics on the data," stated Kamal Shannak, Senior Development Manager, Cloud Data Services, IBM, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.
While DevOps most critically and famously fosters collaboration, communication, and integration through cultural change, culture is more of an output than an input. In order to actively drive cultural evolution, organizations must make substantial organizational and process changes, and adopt new technologies, to encourage a DevOps culture. Moderated by Andi Mann, panelists discussed how to balance these three pillars of DevOps, where to focus attention (and resources), where organizations might...
Zerto exhibited at SYS-CON's 18th International Cloud Expo®, which took place at the Javits Center in New York City, NY, in June 2016. Zerto is committed to keeping enterprise and cloud IT running 24/7 by providing innovative, simple, reliable and scalable business continuity software solutions. Through the Zerto Cloud Continuity Platform™, organizations can seamlessly move and protect virtualized workloads between public, private and hybrid clouds. The company’s flagship product, Zerto Virtual...
Some people worry that OpenStack is more flash then substance; however, for many customers this could not be farther from the truth. No other technology equalizes the playing field between vendors while giving your internal teams better access than ever to infrastructure when they need it. In his session at 20th Cloud Expo, Chris Brown, a Solutions Marketing Manager at Nutanix, will talk through some real-world OpenStack deployments and look into the ways this can benefit customers of all sizes....
Extreme Computing is the ability to leverage highly performant infrastructure and software to accelerate Big Data, machine learning, HPC, and Enterprise applications. High IOPS Storage, low-latency networks, in-memory databases, GPUs and other parallel accelerators are being used to achieve faster results and help businesses make better decisions. In his session at 18th Cloud Expo, Michael O'Neill, Strategic Business Development at NVIDIA, focused on some of the unique ways extreme computing is...
The explosion of new web/cloud/IoT-based applications and the data they generate are transforming our world right before our eyes. In this rush to adopt these new technologies, organizations are often ignoring fundamental questions concerning who owns the data and failing to ask for permission to conduct invasive surveillance of their customers. Organizations that are not transparent about how their systems gather data telemetry without offering shared data ownership risk product rejection, regu...
Due of the rise of Hadoop, many enterprises are now deploying their first small clusters of 10 to 20 servers. At this small scale, the complexity of operating the cluster looks and feels like general data center servers. It is not until the clusters scale, as they inevitably do, when the pain caused by the exponential complexity becomes apparent. We've seen this problem occur time and time again. In his session at Big Data Expo, Greg Bruno, Vice President of Engineering and co-founder of StackIQ...
The security needs of IoT environments require a strong, proven approach to maintain security, trust and privacy in their ecosystem. Assurance and protection of device identity, secure data encryption and authentication are the key security challenges organizations are trying to address when integrating IoT devices. This holds true for IoT applications in a wide range of industries, for example, healthcare, consumer devices, and manufacturing. In his session at @ThingsExpo, Lancen LaChance, vic...