Castillian Files NI 43-101 Technical Report for Updated Mineral Resource at Hope Brook Gold Project, Newfoundland

TORONTO, ONTARIO -- (Marketwire) -- 11/19/12 -- Castillian Resources Corp. (TSX VENTURE:CT)(OTCQX:CTIIF) ("Castillian" or the "Company") has filed a National Instrument 43-101 ("NI 43-101") compliant technical report related to its press release issued on October 1, 2012 announcing an updated mineral resource estimate for the Hope Brook Gold Project in southwest Newfoundland.

The independent technical report entitled "Updated Mineral Resource Estimate Technical Report, Hope Brook Gold Project, Newfoundland and Labrador, Canada" (the "Technical Report"), dated October 1, 2012, was prepared for Castillian by AGP Mining Consultants Inc. and Mercator Geological Services Limited. The Technical Report is available under the Company's profile on SEDAR at www.sedar.com and on the Company's website at www.castillian.ca.

Dr. Bill Pearson, P.Geo., President & CEO of Castillian, commented: "The updated NI 43-101 mineral resource estimate is another important step in further advancing the Hope Brook Gold Project. This updated resource was accomplished with a limited, but highly targeted, drilling program. Our technical understanding of the deposit continues to grow and the mineral resources remain open along strike and downdip. We are proceeding with the Phase I exploration drilling program recommended in the Technical Report. Drilling of 6,000 metres at Hope Brook has already commenced with three drills now operating. This program will test six major target areas over a 3.4 kilometre strike length southwest of the former mine."

The updated NI 43-101 compliant mineral resources on the Company's Hope Brook Gold Project, as reported in the press release issued on October 1, 2012, are estimated to contain 590,000 indicated ounces of gold and 548,000 inferred ounces of gold as set out in Table 1 below.


----------------------------------------------------------------------------
----------------------------------------------------------------------------
Table 1: Hope Brook Gold Project as at October 1, 2012 (see press release   
dated October 1, 2012)(i),(ii)                                              
----------------------------------------------------------------------------
----------------------------------------------------------------------------
                  Within constraining shell      Below constraining shell   
                     @ 0.50 g Au/t cut-off         @ 2.0 g Au/t cut-off     
----------------------------------------------------------------------------
----------------------------------------------------------------------------
                               Gold      Gold               Gold       Gold 
Category               Tonnes   g/t       (Oz)      Tonnes  (g/t)       (Oz)
----------------------------------------------------------------------------
Indicated          10,624,000  1.24   422,000    1,743,000  2.99    168,000 
----------------------------------------------------------------------------
Inferred            6,458,000  1.91   397,000    1,792,000  2.62    151,000 
----------------------------------------------------------------------------
----------------------------------------------------------------------------

----------------------------------------------------
                                Total               
----------------------------------------------------
----------------------------------------------------
                                   Gold        Gold 
Category                  Tonnes    g/t         (Oz)
----------------------------------------------------
Indicated             12,367,000   1.48     590,000 
----------------------------------------------------
Inferred               8,251,000   2.07     548,000 
----------------------------------------------------
----------------------------------------------------
(i) Rounding of tonnes as required by NI 43-101 reporting guidelines may    
result in apparent differences between tonnes, grade and contained ounces.  
Mineral resources that are not mineral reserves do not have demonstrated    
economic viability. This estimate of mineral resources may be materially    
affected by environmental, permitting, legal, title, taxation,              
sociopolitical, marketing or other relevant issues.                         
                                                                            
(ii) There is a possible copper credit that is not included in the mineral  
resource estimate due to missing copper assays for the historical drill     
holes.                                                                      

The Technical Report makes a number of recommendations for further work at Hope Brook including:


--  Phase I 
    
    --  Diamond Drilling 6,500 metres 
        
--  Phase II 
    
    --  Diamond Drilling 9,450 metres 
        
    --  Metallurgical work, acid base accounting, preliminary environmental
        and geotechnical evaluations, tailings deposit assessment and
        updated mineral resource estimate 
        
    --  Wireframe model update and Preliminary Economic Assessment (PEA)
        study 

A 6,000 metre Phase I diamond drilling program that will test six priority target areas over a 3.4 kilometre mineralized trend between the past producing Hope Brook Mine and the Chetwynd South Prospect is now in progress. Eighty percent of the planned drilling is outside the current mineral resource (see press release November 5, 2012).

SAMPLING, ASSAYING AND QUALITY CONTROL

All drill core in the Castillian diamond drilling program (NQ (47.6 mm), BQTK (40.6mm) and BQ (36.4mm)) was logged, photographed and then sawn in half with one-half sent to the laboratory for analysis and the other half retained and stored on site. All core samples were prepared and assayed at ALS Chemex, with sample preparation done in Sudbury and analytical work done in Vancouver. All locations of ALS Chemex are ISO 9001:2000 certified. The entire sample received is weighed and crushed to greater than or equal to 70% passing 2mm (10 mesh). A sample split of up to 1000g is then pulverized to greater than or equal to 85% passing 75 microns (200 mesh) to produce a homogenized sample. A 50g aliquot is used for fire assaying with an atomic absorption (AA) finish to determine gold concentration. Copper is initially analyzed using a four acid digestion ICP (inductively coupled plasma-atomic emission spectrometry) method. Any results for copper greater than 10,000 ppm are assayed further by a four acid digestion and "ore grade" ICP method. Internal quality control includes the use of blanks, duplicates and standards in every batch of samples. The Company also conducts internal check assaying using certified external reference standards and blanks. Regular external check assays are performed at a second certified Canadian commercial laboratory. Castillian also inserts external reference standards as well as blank granite drill core in each sample batch as a further external check.

QUALIFIED PERSONS

Dr. Bill Pearson, P.Geo., President and CEO of Castillian, who is a qualified person as defined by NI 43-101, has reviewed and approved the scientific and technical content of this press release. Pierre Desautels, P.Eng., Principal Resource Geologist, and Jay Melnyk, P.Eng., Principal Mining Engineer, both of AGP Mining Consultants and Qualified Persons under NI 43-101 who are independent of the Company, have prepared and authorized the release of the mineral resource estimates presented herein. The Castillian and historical diamond drill hole databases and geological model developed by Castillian were reviewed and validated by Michael Cullen, P.Geo., of Mercator Geological Services, a Qualified Person as defined under NI 43-101 who is independent of the Company.

ABOUT CASTILLIAN

Castillian Resources Corp. is a Canadian mineral exploration company listed on the TSX Venture Exchange under the symbol "CT" and on the OTCQX International under the symbol "CTIIF" The Company has gold and base metal properties in Canada and South America. Castillian's flag ship property is the Hope Brook Gold Project located in southwestern Newfoundland, which has 2.4 million tonnes at 1.48 g Au/t for 590,000 ounces of NI 43-101 compliant indicated mineral resources and 8.2 million tonnes at 2.07 g Au/t for 548,000 ounces of inferred mineral resources. Castillian has outlined an extensive new Gold-in-Soil anomaly trend on its Canadian Creek property in the Yukon that is adjacent to Kaminak's Sugar Gold-in-Soil trend.

Cautionary Note Regarding Forward-looking Information

This press release contains "forward-looking information" within the meaning of applicable Canadian securities legislation. Forward-looking information includes, but is not limited to, statements regarding exploration prospects and timing of future exploration. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to: general business, economic, competitive, political and social uncertainties; the actual results of current exploration activities; future prices of mineral prices; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and shortages and other risks of the mining industry. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking information. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws.

Information Concerning Estimates of Indicated and Inferred Resources

This news release uses the terms "indicated resources" and "inferred resources". Castillian advises investors that although these terms are recognized and required by Canadian regulations (under NI 43-101), the U.S. Securities and Exchange Commission does not recognize them. Investors are cautioned not to assume that any part or all of the mineral deposits in these categories will ever be converted into mineral reserves. In addition, inferred resources have a great amount of uncertainty as to their existence, and economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or pre-feasibility studies, or economic studies except for preliminary economic assessments as defined under NI 43-101. Investors are cautioned not to assume that part or all of an inferred resource exists, or is economically or legally mineable.

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Security, data privacy, reliability, and regulatory compliance are critical factors when evaluating whether to move business applications from in-house, client-hosted environments to a cloud platform. Quality assurance plays a vital role in ensuring that the appropriate level of risk assessment, verification, and validation takes place to ensure business continuity during the migration to a new cloud platform.
SYS-CON Events announced today the Kubernetes and Google Container Engine Workshop, being held November 3, 2016, in conjunction with @DevOpsSummit at 19th Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA. This workshop led by Sebastian Scheele introduces participants to Kubernetes and Google Container Engine (GKE). Through a combination of instructor-led presentations, demonstrations, and hands-on labs, students learn the key concepts and practices for deploying and maintainin...
Aspose.Total for .NET is the most complete package of all file format APIs for .NET as offered by Aspose. It empowers developers to create, edit, render, print and convert between a wide range of popular document formats within any .NET, C#, ASP.NET and VB.NET applications. Aspose compiles all .NET APIs on a daily basis to ensure that it contains the most up to date versions of each of Aspose .NET APIs. If a new .NET API or a new version of existing APIs is released during the subscription peri...
StackIQ has announced the release of Stacki 3.2. Stacki is an easy-to-use Linux server provisioning tool. Stacki 3.2 delivers new capabilities that simplify the automation and integration of site-specific requirements. StackIQ is the commercial entity behind this open source bare metal provisioning tool. Since the release of Stacki in June of 2015, the Stacki core team has been focused on making the Community Edition meet the needs of members of the community, adding features and value, while ...
There will be new vendors providing applications, middleware, and connected devices to support the thriving IoT ecosystem. This essentially means that electronic device manufacturers will also be in the software business. Many will be new to building embedded software or robust software. This creates an increased importance on software quality, particularly within the Industrial Internet of Things where business-critical applications are becoming dependent on products controlled by software. Qua...
In addition to all the benefits, IoT is also bringing new kind of customer experience challenges - cars that unlock themselves, thermostats turning houses into saunas and baby video monitors broadcasting over the internet. This list can only increase because while IoT services should be intuitive and simple to use, the delivery ecosystem is a myriad of potential problems as IoT explodes complexity. So finding a performance issue is like finding the proverbial needle in the haystack.
"We host and fully manage cloud data services, whether we store, the data, move the data, or run analytics on the data," stated Kamal Shannak, Senior Development Manager, Cloud Data Services, IBM, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.
DevOps at Cloud Expo – being held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA – announces that its Call for Papers is open. Born out of proven success in agile development, cloud computing, and process automation, DevOps is a macro trend you cannot afford to miss. From showcase success stories from early adopters and web-scale businesses, DevOps is expanding to organizations of all sizes, including the world's largest enterprises – and delivering real results. Am...
Machine Learning helps make complex systems more efficient. By applying advanced Machine Learning techniques such as Cognitive Fingerprinting, wind project operators can utilize these tools to learn from collected data, detect regular patterns, and optimize their own operations. In his session at 18th Cloud Expo, Stuart Gillen, Director of Business Development at SparkCognition, discussed how research has demonstrated the value of Machine Learning in delivering next generation analytics to imp...
With the proliferation of both SQL and NoSQL databases, organizations can now target specific fit-for-purpose database tools for their different application needs regarding scalability, ease of use, ACID support, etc. Platform as a Service offerings make this even easier now, enabling developers to roll out their own database infrastructure in minutes with minimal management overhead. However, this same amount of flexibility also comes with the challenges of picking the right tool, on the right ...
The 19th International Cloud Expo has announced that its Call for Papers is open. Cloud Expo, to be held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, brings together Cloud Computing, Big Data, Internet of Things, DevOps, Digital Transformation, Microservices and WebRTC to one location. With cloud computing driving a higher percentage of enterprise IT budgets every year, it becomes increasingly important to plant your flag in this fast-expanding business opportuni...
With over 720 million Internet users and 40–50% CAGR, the Chinese Cloud Computing market has been booming. When talking about cloud computing, what are the Chinese users of cloud thinking about? What is the most powerful force that can push them to make the buying decision? How to tap into them? In his session at 18th Cloud Expo, Yu Hao, CEO and co-founder of SpeedyCloud, answered these questions and discussed the results of SpeedyCloud’s survey.
The Internet of Things will challenge the status quo of how IT and development organizations operate. Or will it? Certainly the fog layer of IoT requires special insights about data ontology, security and transactional integrity. But the developmental challenges are the same: People, Process and Platform. In his session at @ThingsExpo, Craig Sproule, CEO of Metavine, demonstrated how to move beyond today's coding paradigm and shared the must-have mindsets for removing complexity from the develo...
SYS-CON Events announced today that MangoApps will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. MangoApps provides modern company intranets and team collaboration software, allowing workers to stay connected and productive from anywhere in the world and from any device.
Large scale deployments present unique planning challenges, system commissioning hurdles between IT and OT and demand careful system hand-off orchestration. In his session at @ThingsExpo, Jeff Smith, Senior Director and a founding member of Incenergy, will discuss some of the key tactics to ensure delivery success based on his experience of the last two years deploying Industrial IoT systems across four continents.