Pacific Coal Resources Ltd. announces third quarter 2012 financial results

TORONTO, Nov. 29, 2012 /PRNewswire/ - Pacific Coal Resources Ltd. (TSXV: PAK) has filed today its unaudited interim condensed consolidated financial statements for the three and nine months ended September 30, 2012, together with its management's discussion and analysis ("MD&A") for the corresponding period. All financial figures contained herein are expressed in U.S. dollars unless otherwise noted. These documents will be posted on the Company's website at www.pacificcoal.ca and under the Company's profile at www.sedar.com.

Hernan Martinez, Executive Chairman, commented: '"The second half of 2012 has thus far seen the Company re-focus on its core competencies by selling our BACF investment and signing an MOU for the sale of our Barranquilla port interest. The sale of the BACF investment, which closed in October, provided us with $5 million in cash, which will be used in operating and selling activities at our producing coal and coke sites.  Coal operations continued through the third quarter of 2012, with 341,248 tonnes of thermal coal produced at our La Caypa and Cerro Largo sites.  We expect production improvements and cost reductions at La Caypa as we replace the current operator in the fourth quarter.  The Company's cost cutting program resulted in a 20% reduction in G&A expenses in the third quarter compared to the second quarter of 2012, with an expected quarterly run rate as of the fourth quarter of 2012 that is approximately 30% below the average in 2011. Management believes the decisions made and actions taken during the quarter and through the remainder of 2012 are positioning the Company towards significantly improved operations and liquidity."

Financial and Operating Summary

A summary of the financial and operating results for the three and nine months ended September 30, 2012 and 2011 is as follows:

         
  Third Quarter Nine Months Ended September 30
(000's except per share and operating data) 2012 2011 2012 2011
         
Operational        
Tonnes of coal produced 341,248 400,909 993,325 1,070,209
Average stripping ratio - operations 11.38 7.61 10.60 7.38
Tonnes of coal sold(1) 366,678 460,189 965,948 1,217,389
Average realized price per tonne sold $             92.53 $            101.01 $            97.67 $           97.65
Operating margin per tonne sold(2)              (5.76) 4.12           (13.95) 10.18
         
Financial        
Revenues $           35,033 $            46,485 $         98,654 $       118,877
Gross margin(3) (4,120) (937) (20,447) 6,371
Net (loss) earnings attributed to shareholders(4)            (15,201) (1,126)        (85,827) (46,380)
Basic and fully diluted (loss) earnings per share (0.05) 0.00 (0.27) (0.16)
Total cash                 135 14,267              135 14,267
Total assets          318,462 392,112 318,462 392,112
Total debt (5) 39,701 32,012 39,701 32,012
(1)  Includes coal purchased from third parties for sale.
(2)  See additional financial measures in MD&A.
(3)  "Gross margin" represents total revenues, net of operating costs, transportation and port services costs, selling costs, depreciation, depletion and amortization, and impairment charges related to inventory.
(4)  2012 includes a non-cash impairment writedown of $45.5 million; including $8.0 million in the third quarter triggered by the planned sale of the Barranquilla port concession and $35.6 million relating to impairment of the Cerro Largo property in the second quarter.
(5)  Includes bank indebtedness, long-term debt (including current portion), and obligations under finance leases (including current portion).

Third Quarter Highlights

  • The Company produced 341,248 tonnes of coal during the third quarter of 2012, representing a 2% increase over the 335,008 tonnes produced in the second quarter of 2012. The Company's stripping ratio for the third quarter was 11.38:1.
  • Production at La Caypa was 251,525 tonnes representing a decrease of approximately 6% from the second quarter of 2012 and 72% of its planned production.  Production was significantly impacted by issues with the mine operator and destabilization of the mine footwall in August 2012. Production at the Cerro Largo mine was 89,723 tonnes, representing an increase of approximately 33% from the second quarter of 2012.
  • Total revenues for the third quarter of 2012 were $35.0 million, consistent with $35.2 million in the second quarter of 2012, on the strength of coal sales of 366,678 tonnes, at an average realized price of $92.53 per tonne.
  • During the third quarter of 2012, cost saving initiatives contributed to a 20% decrease in G&A expenses to $3.6 million as compared to $4.4 million in the second quarter of 2012, in addition to the 12% and 9% decreases already realized in the first and second quarters of 2012 respectively.  G&A in the third quarter included $0.6 million of one-time severance costs associated with staff reductions and $0.4 million of asphaltite research costs. The Company anticipates a quarterly G&A run rate of approximately $2.75 million in the fourth quarter of 2012.
  • In October 2012 the Company sold its Blue Advanced Colloidal Fuels ("BACF") investment for cash proceeds of $5.0 million and in November 2012 signed an MOU in respect of its interest in Sociedad Portuaria Terminal de las Flores S.A. ("SPTF"), which holds the Barranquilla port concession.  The cash generated by these transactions will be used in the Company's operating and selling activities at its producing coal and coke sites.  Sale of the BACF investment contributed to the $3.0 million cash balance at November 29, 2012.
  • The Company continues to work with SRK Consulting (UK) Ltd, to finalize the Company's 43-101 updated technical reports. The Cerro Largo report is expected to be released in the fourth quarter of 2012. The La Caypa report is expected in the second quarter of 2013.
  • The net loss of $15.2 million ($0.05 per share) in the third quarter of 2012 includes a $8.0 million ($0.02 per share) non-cash impairment writedown of SPTF triggered by its planned sale.

Q3 2012 - La Caypa

  Production of Coal
(metric tonnes)
Waste
(bcm (1))
Strip Ratio
Actual Pit 251,525 1,966,372 7.82:1
South Pit - 392,674 -
Total 251,525 2,359,046 9.38:1

(1)     "BCM" is Bank Cubic Metres

During the third quarter of 2012, the Company produced 251,525 tonnes at La Caypa, down approximately 6% from the second quarter and 72% of planned production.  Production at La Caypa during the quarter was negatively impacted by the mine operator's general lack of equipment for loading, hauling, and support at the mine and was compounded by destabilization of the mine footwall in the month of August. Issues with the mine operator resulted in a breach of their contractual obligations, which led the Company to begin the process of replacing them during the fourth quarter of 2012.

Operational stripping ratio at La Caypa, up slightly to 7.82 in the third quarter of 2012 reflected the impact of the mine sidewall development during the quarter. Total stripping ratios at La Caypa include costs incurred in moving waste volumes from the south pit.

Q3 2012 - Cerro Largo

  Production of Coal
(metric tonnes)
Waste
(bcm (1))
Strip Ratio
Total 89,723 1,918,289 21.38:1

(1) "BCM" is Bank Cubic Metres

The Company's production at Cerro Largo of 89,723 tonnes in the third quarter of 2012 was an increase of approximately 33% from second quarter of 2012.  Consistent with the second quarter, the Company continued addressing mud concentration concerns at the bottom of the open pit, although efforts to correct the issue were noted during the quarter with the increase in production and improvement of the stripping ratio to 21.38:1 from 25.53:1 in the second quarter of 2012.

Q3 2012 - Jam

  Q3 2012 Q3 2011
Tonnes produced 476 -

The Company's Jam operation commenced production in the fourth quarter of 2011. In the third quarter of 2012, given current coke market trends the Company decided to maintain production at minimum levels. The Company's Jam activity has focused on repairs to coking infrastructure, with anticipated significant production in the first quarter of 2013.

Revised production guidance

As a result of reduced production in the third quarter of 2012 and the expected change in operator, the Company's 2012 production target at La Caypa has been revised to 970,000 tonnes.  At Cerro Largo, in light of the third quarter results and the ongoing work required to clear the mud concentration in the pit, the Company has revised its 2012 production target for Cerro Largo to 400,000 tonnes.

Corporate update

The Company plans to provide a corporate update and an update on its strategic plan in a subsequent press release to be issued next week.

About Pacific Coal Resources Ltd.

Pacific Coal Resources Ltd. is a Canadian-based mining company engaged in the acquisition, exploration and production of coal and coal-related assets from properties located in Colombia. The Company's common shares and warrants are listed on the TSX Venture Exchange and trade under the symbol "PAK" and "PAK.WT" respectively.

Forward Looking Information:

This news release contains "forward-looking information", which may include, but is not limited to, statements with respect to the future financial or operating performance of the Company and its projects. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or believes" or variations (including negative variations) of such words and phrases, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Pacific Coal to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Forward-looking statements contained herein are made as of the date of this press release and Pacific Coal disclaim, other than as required by law, any obligation to update any forward-looking statements whether as a result of new information, results, future events, circumstances, or if management's estimates or opinions should change, or otherwise. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, the reader is cautioned not to place undue reliance on forward-looking statements.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

 

 

SOURCE Pacific Coal Resources Ltd.

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
As businesses adopt functionalities in cloud computing, it’s imperative that IT operations consistently ensure cloud systems work correctly – all of the time, and to their best capabilities. In his session at @BigDataExpo, Bernd Harzog, CEO and founder of OpsDataStore, presented an industry answer to the common question, “Are you running IT operations as efficiently and as cost effectively as you need to?” He then expounded on the industry issues he frequently came up against as an analyst, and ...
Cloud resources, although available in abundance, are inherently volatile. For transactional computing, like ERP and most enterprise software, this is a challenge as transactional integrity and data fidelity is paramount – making it a challenge to create cloud native applications while relying on RDBMS. In his session at 21st Cloud Expo, Claus Jepsen, Chief Architect and Head of Innovation Labs at Unit4, will explore that in order to create distributed and scalable solutions ensuring high availa...
SYS-CON Events announced today that App2Cloud will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct. 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. App2Cloud is an online Platform, specializing in migrating legacy applications to any Cloud Providers (AWS, Azure, Google Cloud).
In his session at @DevOpsSummit at 20th Cloud Expo, Kelly Looney, director of DevOps consulting for Skytap, showed how an incremental approach to introducing containers into complex, distributed applications results in modernization with less risk and more reward. He also shared the story of how Skytap used Docker to get out of the business of managing infrastructure, and into the business of delivering innovation and business value. Attendees learned how up-front planning allows for a clean sep...
IoT is at the core or many Digital Transformation initiatives with the goal of re-inventing a company's business model. We all agree that collecting relevant IoT data will result in massive amounts of data needing to be stored. However, with the rapid development of IoT devices and ongoing business model transformation, we are not able to predict the volume and growth of IoT data. And with the lack of IoT history, traditional methods of IT and infrastructure planning based on the past do not app...
Internet-of-Things discussions can end up either going down the consumer gadget rabbit hole or focused on the sort of data logging that industrial manufacturers have been doing forever. However, in fact, companies today are already using IoT data both to optimize their operational technology and to improve the experience of customer interactions in novel ways. In his session at @ThingsExpo, Gordon Haff, Red Hat Technology Evangelist, shared examples from a wide range of industries – including en...
To get the most out of their data, successful companies are not focusing on queries and data lakes, they are actively integrating analytics into their operations with a data-first application development approach. Real-time adjustments to improve revenues, reduce costs, or mitigate risk rely on applications that minimize latency on a variety of data sources. Jack Norris reviews best practices to show how companies develop, deploy, and dynamically update these applications and how this data-first...
In IT, we sometimes coin terms for things before we know exactly what they are and how they’ll be used. The resulting terms may capture a common set of aspirations and goals – as “cloud” did broadly for on-demand, self-service, and flexible computing. But such a term can also lump together diverse and even competing practices, technologies, and priorities to the point where important distinctions are glossed over and lost.
Intelligent Automation is now one of the key business imperatives for CIOs and CISOs impacting all areas of business today. In his session at 21st Cloud Expo, Brian Boeggeman, VP Alliances & Partnerships at Ayehu, will talk about how business value is created and delivered through intelligent automation to today’s enterprises. The open ecosystem platform approach toward Intelligent Automation that Ayehu delivers to the market is core to enabling the creation of the self-driving enterprise.
"At the keynote this morning we spoke about the value proposition of Nutanix, of having a DevOps culture and a mindset, and the business outcomes of achieving agility and scale, which everybody here is trying to accomplish," noted Mark Lavi, DevOps Solution Architect at Nutanix, in this SYS-CON.tv interview at @DevOpsSummit at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
"We're here to tell the world about our cloud-scale infrastructure that we have at Juniper combined with the world-class security that we put into the cloud," explained Lisa Guess, VP of Systems Engineering at Juniper Networks, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
Enterprise architects are increasingly adopting multi-cloud strategies as they seek to utilize existing data center assets, leverage the advantages of cloud computing and avoid cloud vendor lock-in. This requires a globally aware traffic management strategy that can monitor infrastructure health across data centers and end-user experience globally, while responding to control changes and system specification at the speed of today’s DevOps teams. In his session at 20th Cloud Expo, Josh Gray, Chie...
Consumers increasingly expect their electronic "things" to be connected to smart phones, tablets and the Internet. When that thing happens to be a medical device, the risks and benefits of connectivity must be carefully weighed. Once the decision is made that connecting the device is beneficial, medical device manufacturers must design their products to maintain patient safety and prevent compromised personal health information in the face of cybersecurity threats. In his session at @ThingsExpo...
"We're a cybersecurity firm that specializes in engineering security solutions both at the software and hardware level. Security cannot be an after-the-fact afterthought, which is what it's become," stated Richard Blech, Chief Executive Officer at Secure Channels, in this SYS-CON.tv interview at @ThingsExpo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
In his session at 20th Cloud Expo, Mike Johnston, an infrastructure engineer at Supergiant.io, discussed how to use Kubernetes to set up a SaaS infrastructure for your business. Mike Johnston is an infrastructure engineer at Supergiant.io with over 12 years of experience designing, deploying, and maintaining server and workstation infrastructure at all scales. He has experience with brick and mortar data centers as well as cloud providers like Digital Ocean, Amazon Web Services, and Rackspace. H...