First Quantum Minerals Provides an Update on Development Activities at Kansanshi and the Trident Project

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 12/12/12 -- First Quantum Minerals Ltd. ("First Quantum" or the "Company") (TSX:FM)(LSE:FQM) is pleased to provide an update on the expansion of the sulphide treatment facilities at the Kansanshi mine and development of the Trident project including advances at the Enterprise nickel project and an increase to the throughput capacity at the Sentinel copper project. Board approval for the sulphide expansion project and the development of Enterprise was granted on the strength of the recently-announced uplift in Mineral Resources and Reserves estimates at Kansanshi and Enterprise.



--  The Sulphide No 3 ("S3") treatment plant at Kansanshi is being designed
    with the capability to treat up to 25 million tonnes per annum ("Mtpa")
    of ore. 
--  This capacity is higher than the 14 - 16 Mtpa previously contemplated,
    is supported by the recently-announced increase in Mineral Resources and
    Reserves at Kansanshi, and is expected to deliver a mine life in excess
    of 16 years. 
--  Engineering design synergies with the Sentinel processing plant,
    currently in construction, are expected to provide significant schedule
    benefits enabling a efficient project ramp up and execution phase that
    will allow S3 to come on-line in 2015. 
--  The capital estimate for the construction of the S3 expansion is USD$565

The Trident project

--  The Enterprise project is being designed with the capacity to treat ore
    at a rate of 4.0 Mtpa at a processing facility that will be constructed
    as an integral part of the Sentinel copper mine, located 12 kilometres
    southeast of the mine. 
--  This will allow significant operational synergies and the sharing of
--  Enterprise is being designed to produce an average of 38,000 tonnes of
    nickel in concentrate per annum with scope to increase to 60,000 tonnes
    when nickel market conditions allow. 
--  Board approval was also received for an increase in throughput capacity
    at Sentinel to 55 Mtpa from the 40 Mtpa previously envisioned. 
--  Altogether, these significant enhancements require a capital investment
    of USD$275 million which lifts the total approved capital estimate for
    the Trident project to USD$2.0 billion. 


The increase in the mine's Mineral Resources and Reserves estimate provided the foundation for the operational and long term development strategies to be confirmed. The increase in sulphide treatment through the new S3 plant will allow up to 400,000 tonnes of copper to be produced annually. At this level of production and with the current defined Mineral Resources and Reserves, Kansanshi's mine life has been significantly increased to 16 years. On-going in-fill drilling could enable the identified Inferred Resources to be upgraded to the Indicated category, thereby further extending mine life.

The treatment plant will be constructed as a stand-alone facility and will draw on the detailed design work that has already been undertaken for the Sentinel sulphide concentrator. The S3 plant will be fed from two semi-mobile crushers that will be located within the existing pit limits of the Main and North West pits.

Concentrate produced from S3 will be pumped to the new smelter facility currently being constructed at Kansanshi for direct treatment.

Trident project

The development of Enterprise brings a third nickel mine to First Quantum, and given the operational and infrastructure synergies with Sentinel is expected to be a low cost producing mine. The 4.0 Mtpa processing plant that will be built at the Sentinel facilities will consist of straight forward crushing, milling and flotation. The plant will be designed with the flexibility so that if nickel ore from the Enterprise is not being processed, it can be used to augment the Sentinel copper throughput capacity by approximately 4 Mtpa.

The increase in the throughput capacity at Sentinel to 55 Mtpa will be achieved by the addition of an expandable secondary crushing circuit as well as the upgrading of specific equipment within the processing plant. These enhancements will help ensure that targeted copper production objectives of 270,000 - 300,000 tonnes per annum of copper can be achieved. The current project timeline for completion in 2014 is unchanged.

On Behalf of the Board of Directors of First Quantum Minerals Ltd.

G. Clive Newall, President


Listed in Standard and Poor's

For further information visit our website at www.first-quantum.com

Forward-Looking Statements

Certain statements and information herein, including all statements that are not historical facts, contain forward-looking statements and forward-looking information within the meaning of applicable securities laws. The forward looking statements include estimates, forecasts and statements as to the Company's mineral reserves and resources at Kansanshi and Enterprise, the Company's expectations of the results of future drilling, the Company's expectations of production and production cost and sales volumes, expected future production capacity, expect timing of completion of project development at Kansanshi, Sentinel and Enterprise, the impact of ore grades on future production, the potential of production disruptions, capital expenditure and mine production costs, the outcome of mine permitting, information with respect to the future price of copper, gold, cobalt, nickel, PGE, and sulphuric acid, estimated mineral reserves and mineral resources, our exploration and development program, estimated future expenses, exploration and development capital requirements, the Company's hedging policy, and our goals and strategies. Often, but not always, forward-looking statements or information can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate" or "believes" or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

With respect to forward-looking statements and information contained herein, we have made numerous assumptions including among other things, assumptions about the price of copper, gold, nickel, PGE, cobalt and sulphuric acid, anticipated costs and expenditures and our ability to achieve our goals. Although our management believes that the assumptions made and the expectations represented by such statements or information are reasonable, there can be no assurance that a forward-looking statement or information herein will prove to be accurate. Forward-looking statements and information by their nature are based on assumptions and involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. These factors include, but are not limited to, future production volumes and costs, costs for inputs such as oil, power and sulphur, political stability in Zambia, Peru, Mauritania, Finland and Australia, adverse weather conditions in Zambia, Finland and Mauritania labour disruptions, mechanical failures, water supply, procurement and delivery of parts and supplies to the operations, the production of off-spec material.

See our annual information form for additional information on risks, uncertainties and other factors relating to the forward-looking statements and information. Although we have attempted to identify factors that would cause actual actions, events or results to differ materially from those disclosed in the forward-looking statements or information, there may be other factors that cause actual results, performances, achievements or events not to be anticipated, estimated or intended. Also, many of these factors are beyond our control. Accordingly, readers should not place undue reliance on forward-looking statements or information. We undertake no obligation to reissue or update forward-looking statements or information as a result of new information or events after the date hereof except as may be required by law. All forward-looking statements and information made herein are qualified by this cautionary statement.

First Quantum Minerals Ltd. - North American contact
Sharon Loung
Director, Investor Relations
(647) 346-3934 or Toll Free: 1 (888) 688-6577
(604) 688-3818 (FAX)
[email protected]

First Quantum Minerals Ltd. - United Kingdom contact
Clive Newall
+44 140 327 3484
+44 140 327 3494 (FAX)
[email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Dion Hinchcliffe is an internationally recognized digital expert, bestselling book author, frequent keynote speaker, analyst, futurist, and transformation expert based in Washington, DC. He is currently Chief Strategy Officer at the industry-leading digital strategy and online community solutions firm, 7Summits.
"We started a Master of Science in business analytics - that's the hot topic. We serve the business community around San Francisco so we educate the working professionals and this is where they all want to be," explained Judy Lee, Associate Professor and Department Chair at Golden Gate University, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
DXWorldEXPO LLC announced today that Dez Blanchfield joined the faculty of CloudEXPO's "10-Year Anniversary Event" which will take place on November 11-13, 2018 in New York City. Dez is a strategic leader in business and digital transformation with 25 years of experience in the IT and telecommunications industries developing strategies and implementing business initiatives. He has a breadth of expertise spanning technologies such as cloud computing, big data and analytics, cognitive computing, m...
Digital Transformation and Disruption, Amazon Style - What You Can Learn. Chris Kocher is a co-founder of Grey Heron, a management and strategic marketing consulting firm. He has 25+ years in both strategic and hands-on operating experience helping executives and investors build revenues and shareholder value. He has consulted with over 130 companies on innovating with new business models, product strategies and monetization. Chris has held management positions at HP and Symantec in addition to ...
Cloud-enabled transformation has evolved from cost saving measure to business innovation strategy -- one that combines the cloud with cognitive capabilities to drive market disruption. Learn how you can achieve the insight and agility you need to gain a competitive advantage. Industry-acclaimed CTO and cloud expert, Shankar Kalyana presents. Only the most exceptional IBMers are appointed with the rare distinction of IBM Fellow, the highest technical honor in the company. Shankar has also receive...
There is a huge demand for responsive, real-time mobile and web experiences, but current architectural patterns do not easily accommodate applications that respond to events in real time. Common solutions using message queues or HTTP long-polling quickly lead to resiliency, scalability and development velocity challenges. In his session at 21st Cloud Expo, Ryland Degnan, a Senior Software Engineer on the Netflix Edge Platform team, will discuss how by leveraging a reactive stream-based protocol,...
Enterprises have taken advantage of IoT to achieve important revenue and cost advantages. What is less apparent is how incumbent enterprises operating at scale have, following success with IoT, built analytic, operations management and software development capabilities - ranging from autonomous vehicles to manageable robotics installations. They have embraced these capabilities as if they were Silicon Valley startups.
DXWorldEXPO LLC announced today that Kevin Jackson joined the faculty of CloudEXPO's "10-Year Anniversary Event" which will take place on November 11-13, 2018 in New York City. Kevin L. Jackson is a globally recognized cloud computing expert and Founder/Author of the award winning "Cloud Musings" blog. Mr. Jackson has also been recognized as a "Top 100 Cybersecurity Influencer and Brand" by Onalytica (2015), a Huffington Post "Top 100 Cloud Computing Experts on Twitter" (2013) and a "Top 50 C...
Digital transformation is about embracing digital technologies into a company's culture to better connect with its customers, automate processes, create better tools, enter new markets, etc. Such a transformation requires continuous orchestration across teams and an environment based on open collaboration and daily experiments. In his session at 21st Cloud Expo, Alex Casalboni, Technical (Cloud) Evangelist at Cloud Academy, explored and discussed the most urgent unsolved challenges to achieve fu...
The standardization of container runtimes and images has sparked the creation of an almost overwhelming number of new open source projects that build on and otherwise work with these specifications. Of course, there's Kubernetes, which orchestrates and manages collections of containers. It was one of the first and best-known examples of projects that make containers truly useful for production use. However, more recently, the container ecosystem has truly exploded. A service mesh like Istio addr...
As DevOps methodologies expand their reach across the enterprise, organizations face the daunting challenge of adapting related cloud strategies to ensure optimal alignment, from managing complexity to ensuring proper governance. How can culture, automation, legacy apps and even budget be reexamined to enable this ongoing shift within the modern software factory? In her Day 2 Keynote at @DevOpsSummit at 21st Cloud Expo, Aruna Ravichandran, VP, DevOps Solutions Marketing, CA Technologies, was jo...
Predicting the future has never been more challenging - not because of the lack of data but because of the flood of ungoverned and risk laden information. Microsoft states that 2.5 exabytes of data are created every day. Expectations and reliance on data are being pushed to the limits, as demands around hybrid options continue to grow.
Poor data quality and analytics drive down business value. In fact, Gartner estimated that the average financial impact of poor data quality on organizations is $9.7 million per year. But bad data is much more than a cost center. By eroding trust in information, analytics and the business decisions based on these, it is a serious impediment to digital transformation.
Business professionals no longer wonder if they'll migrate to the cloud; it's now a matter of when. The cloud environment has proved to be a major force in transitioning to an agile business model that enables quick decisions and fast implementation that solidify customer relationships. And when the cloud is combined with the power of cognitive computing, it drives innovation and transformation that achieves astounding competitive advantage.
Digital Transformation: Preparing Cloud & IoT Security for the Age of Artificial Intelligence. As automation and artificial intelligence (AI) power solution development and delivery, many businesses need to build backend cloud capabilities. Well-poised organizations, marketing smart devices with AI and BlockChain capabilities prepare to refine compliance and regulatory capabilities in 2018. Volumes of health, financial, technical and privacy data, along with tightening compliance requirements by...