VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 12/12/12 -- First Quantum Minerals Ltd. ("First Quantum" or the "Company") (TSX:FM)(LSE:FQM) is pleased to provide an update on the expansion of the sulphide treatment facilities at the Kansanshi mine and development of the Trident project including advances at the Enterprise nickel project and an increase to the throughput capacity at the Sentinel copper project. Board approval for the sulphide expansion project and the development of Enterprise was granted on the strength of the recently-announced uplift in Mineral Resources and Reserves estimates at Kansanshi and Enterprise.

Highlights:

Kansanshi


--  The Sulphide No 3 ("S3") treatment plant at Kansanshi is being designed
    with the capability to treat up to 25 million tonnes per annum ("Mtpa")
    of ore. 
--  This capacity is higher than the 14 - 16 Mtpa previously contemplated,
    is supported by the recently-announced increase in Mineral Resources and
    Reserves at Kansanshi, and is expected to deliver a mine life in excess
    of 16 years. 
--  Engineering design synergies with the Sentinel processing plant,
    currently in construction, are expected to provide significant schedule
    benefits enabling a efficient project ramp up and execution phase that
    will allow S3 to come on-line in 2015. 
--  The capital estimate for the construction of the S3 expansion is USD$565
    million. 

The Trident project


--  The Enterprise project is being designed with the capacity to treat ore
    at a rate of 4.0 Mtpa at a processing facility that will be constructed
    as an integral part of the Sentinel copper mine, located 12 kilometres
    southeast of the mine. 
--  This will allow significant operational synergies and the sharing of
    infrastructure. 
--  Enterprise is being designed to produce an average of 38,000 tonnes of
    nickel in concentrate per annum with scope to increase to 60,000 tonnes
    when nickel market conditions allow. 
--  Board approval was also received for an increase in throughput capacity
    at Sentinel to 55 Mtpa from the 40 Mtpa previously envisioned. 
--  Altogether, these significant enhancements require a capital investment
    of USD$275 million which lifts the total approved capital estimate for
    the Trident project to USD$2.0 billion. 

Kansanshi

The increase in the mine's Mineral Resources and Reserves estimate provided the foundation for the operational and long term development strategies to be confirmed. The increase in sulphide treatment through the new S3 plant will allow up to 400,000 tonnes of copper to be produced annually. At this level of production and with the current defined Mineral Resources and Reserves, Kansanshi's mine life has been significantly increased to 16 years. On-going in-fill drilling could enable the identified Inferred Resources to be upgraded to the Indicated category, thereby further extending mine life.

The treatment plant will be constructed as a stand-alone facility and will draw on the detailed design work that has already been undertaken for the Sentinel sulphide concentrator. The S3 plant will be fed from two semi-mobile crushers that will be located within the existing pit limits of the Main and North West pits.

Concentrate produced from S3 will be pumped to the new smelter facility currently being constructed at Kansanshi for direct treatment.

Trident project

The development of Enterprise brings a third nickel mine to First Quantum, and given the operational and infrastructure synergies with Sentinel is expected to be a low cost producing mine. The 4.0 Mtpa processing plant that will be built at the Sentinel facilities will consist of straight forward crushing, milling and flotation. The plant will be designed with the flexibility so that if nickel ore from the Enterprise is not being processed, it can be used to augment the Sentinel copper throughput capacity by approximately 4 Mtpa.

The increase in the throughput capacity at Sentinel to 55 Mtpa will be achieved by the addition of an expandable secondary crushing circuit as well as the upgrading of specific equipment within the processing plant. These enhancements will help ensure that targeted copper production objectives of 270,000 - 300,000 tonnes per annum of copper can be achieved. The current project timeline for completion in 2014 is unchanged.

On Behalf of the Board of Directors of First Quantum Minerals Ltd.

G. Clive Newall, President

12g3-2b-82-4461

Listed in Standard and Poor's

For further information visit our website at www.first-quantum.com

Forward-Looking Statements

Certain statements and information herein, including all statements that are not historical facts, contain forward-looking statements and forward-looking information within the meaning of applicable securities laws. The forward looking statements include estimates, forecasts and statements as to the Company's mineral reserves and resources at Kansanshi and Enterprise, the Company's expectations of the results of future drilling, the Company's expectations of production and production cost and sales volumes, expected future production capacity, expect timing of completion of project development at Kansanshi, Sentinel and Enterprise, the impact of ore grades on future production, the potential of production disruptions, capital expenditure and mine production costs, the outcome of mine permitting, information with respect to the future price of copper, gold, cobalt, nickel, PGE, and sulphuric acid, estimated mineral reserves and mineral resources, our exploration and development program, estimated future expenses, exploration and development capital requirements, the Company's hedging policy, and our goals and strategies. Often, but not always, forward-looking statements or information can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate" or "believes" or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

With respect to forward-looking statements and information contained herein, we have made numerous assumptions including among other things, assumptions about the price of copper, gold, nickel, PGE, cobalt and sulphuric acid, anticipated costs and expenditures and our ability to achieve our goals. Although our management believes that the assumptions made and the expectations represented by such statements or information are reasonable, there can be no assurance that a forward-looking statement or information herein will prove to be accurate. Forward-looking statements and information by their nature are based on assumptions and involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. These factors include, but are not limited to, future production volumes and costs, costs for inputs such as oil, power and sulphur, political stability in Zambia, Peru, Mauritania, Finland and Australia, adverse weather conditions in Zambia, Finland and Mauritania labour disruptions, mechanical failures, water supply, procurement and delivery of parts and supplies to the operations, the production of off-spec material.

See our annual information form for additional information on risks, uncertainties and other factors relating to the forward-looking statements and information. Although we have attempted to identify factors that would cause actual actions, events or results to differ materially from those disclosed in the forward-looking statements or information, there may be other factors that cause actual results, performances, achievements or events not to be anticipated, estimated or intended. Also, many of these factors are beyond our control. Accordingly, readers should not place undue reliance on forward-looking statements or information. We undertake no obligation to reissue or update forward-looking statements or information as a result of new information or events after the date hereof except as may be required by law. All forward-looking statements and information made herein are qualified by this cautionary statement.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that CA Technologies has been named "Platinum Sponsor" of SYS-CON's 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CA Technologies helps customers succeed in a future where every business - from apparel to energy - is being rewritten by software. From planning to development to management to security, CA creates software that fuels transformation for companies in the applic...
Amazon started as an online bookseller 20 years ago. Since then, it has evolved into a technology juggernaut that has disrupted multiple markets and industries and touches many aspects of our lives. It is a relentless technology and business model innovator driving disruption throughout numerous ecosystems. Amazon’s AWS revenues alone are approaching $16B a year making it one of the largest IT companies in the world. With dominant offerings in Cloud, IoT, eCommerce, Big Data, AI, Digital Assista...
Multiple data types are pouring into IoT deployments. Data is coming in small packages as well as enormous files and data streams of many sizes. Widespread use of mobile devices adds to the total. In this power panel at @ThingsExpo, moderated by Conference Chair Roger Strukhoff, panelists looked at the tools and environments that are being put to use in IoT deployments, as well as the team skills a modern enterprise IT shop needs to keep things running, get a handle on all this data, and deliver...
In his session at @ThingsExpo, Eric Lachapelle, CEO of the Professional Evaluation and Certification Board (PECB), provided an overview of various initiatives to certify the security of connected devices and future trends in ensuring public trust of IoT. Eric Lachapelle is the Chief Executive Officer of the Professional Evaluation and Certification Board (PECB), an international certification body. His role is to help companies and individuals to achieve professional, accredited and worldwide re...
You know you need the cloud, but you’re hesitant to simply dump everything at Amazon since you know that not all workloads are suitable for cloud. You know that you want the kind of ease of use and scalability that you get with public cloud, but your applications are architected in a way that makes the public cloud a non-starter. You’re looking at private cloud solutions based on hyperconverged infrastructure, but you’re concerned with the limits inherent in those technologies.
Both SaaS vendors and SaaS buyers are going “all-in” to hyperscale IaaS platforms such as AWS, which is disrupting the SaaS value proposition. Why should the enterprise SaaS consumer pay for the SaaS service if their data is resident in adjacent AWS S3 buckets? If both SaaS sellers and buyers are using the same cloud tools, automation and pay-per-transaction model offered by IaaS platforms, then why not host the “shrink-wrapped” software in the customers’ cloud? Further, serverless computing, cl...
The taxi industry never saw Uber coming. Startups are a threat to incumbents like never before, and a major enabler for startups is that they are instantly “cloud ready.” If innovation moves at the pace of IT, then your company is in trouble. Why? Because your data center will not keep up with frenetic pace AWS, Microsoft and Google are rolling out new capabilities. In his session at 20th Cloud Expo, Don Browning, VP of Cloud Architecture at Turner, posited that disruption is inevitable for comp...
Wooed by the promise of faster innovation, lower TCO, and greater agility, businesses of every shape and size have embraced the cloud at every layer of the IT stack – from apps to file sharing to infrastructure. The typical organization currently uses more than a dozen sanctioned cloud apps and will shift more than half of all workloads to the cloud by 2018. Such cloud investments have delivered measurable benefits. But they’ve also resulted in some unintended side-effects: complexity and risk. ...
With the introduction of IoT and Smart Living in every aspect of our lives, one question has become relevant: What are the security implications? To answer this, first we have to look and explore the security models of the technologies that IoT is founded upon. In his session at @ThingsExpo, Nevi Kaja, a Research Engineer at Ford Motor Company, discussed some of the security challenges of the IoT infrastructure and related how these aspects impact Smart Living. The material was delivered interac...
It is ironic, but perhaps not unexpected, that many organizations who want the benefits of using an Agile approach to deliver software use a waterfall approach to adopting Agile practices: they form plans, they set milestones, and they measure progress by how many teams they have engaged. Old habits die hard, but like most waterfall software projects, most waterfall-style Agile adoption efforts fail to produce the results desired. The problem is that to get the results they want, they have to ch...
IoT solutions exploit operational data generated by Internet-connected smart “things” for the purpose of gaining operational insight and producing “better outcomes” (for example, create new business models, eliminate unscheduled maintenance, etc.). The explosive proliferation of IoT solutions will result in an exponential growth in the volume of IoT data, precipitating significant Information Governance issues: who owns the IoT data, what are the rights/duties of IoT solutions adopters towards t...
"We are a monitoring company. We work with Salesforce, BBC, and quite a few other big logos. We basically provide monitoring for them, structure for their cloud services and we fit into the DevOps world" explained David Gildeh, Co-founder and CEO of Outlyer, in this SYS-CON.tv interview at DevOps Summit at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
In 2014, Amazon announced a new form of compute called Lambda. We didn't know it at the time, but this represented a fundamental shift in what we expect from cloud computing. Now, all of the major cloud computing vendors want to take part in this disruptive technology. In his session at 20th Cloud Expo, Doug Vanderweide, an instructor at Linux Academy, discussed why major players like AWS, Microsoft Azure, IBM Bluemix, and Google Cloud Platform are all trying to sidestep VMs and containers wit...
While DevOps most critically and famously fosters collaboration, communication, and integration through cultural change, culture is more of an output than an input. In order to actively drive cultural evolution, organizations must make substantial organizational and process changes, and adopt new technologies, to encourage a DevOps culture. Moderated by Andi Mann, panelists discussed how to balance these three pillars of DevOps, where to focus attention (and resources), where organizations might...
"When we talk about cloud without compromise what we're talking about is that when people think about 'I need the flexibility of the cloud' - it's the ability to create applications and run them in a cloud environment that's far more flexible,” explained Matthew Finnie, CTO of Interoute, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.