Orvana Reports Revised Resource and Reserve Estimates for the Upper Mineralized Zone ("UMZ") Copper-Gold-Silver Mine, Bolivia

TORONTO, ONTARIO -- (Marketwire) -- 12/13/12 -- Orvana Minerals Corp. (TSX:ORV), through its wholly-owned subsidiary, Empresa Minera Paititi ("EMIPA"), provides updated National Instrument ("NI") 43-101-compliant resource and reserve estimates for its Don Mario UMZ copper-gold-silver mine operations in Bolivia. During 2012, EMIPA made significant changes to the mining and processing aspects of the operation thus warranting an update.

The updated NI 43-101-compliant resource and reserve estimates are effective October 1, 2012 and are shown in the tables below. The reserve estimate contains approximately 177,000 ounces of gold, 5.6 million ounces of silver, and 120 million pounds of copper, which is a decrease of about 5%, 2%, and 11%, respectively, after considerations for production through September 30, 2012 as well as the exclusion of certain oxide mineralization whose metals cannot be extracted economically (see press release of January 18, 2012); testing of these ores will continue in order to seek a viable extraction method. The most significant change in the mine plan is the processing of Transition ore by a Flotation-Only process instead of the Leach-Precipitation-Flotation ("LPF") process.


                     -----------------------------------------------
                                MEASURED                   INDICATED
                     -----------------------------------------------
                     tonnes, Gold, Copper, Silver, tonnes,    Gold, 
ORE TYPE               '000s   g/t       %     g/t   '000s      g/t 
--------------------------------------------------------------------
Oxides (in situ)         149  1.90    1.74      77     219     1.94 
--------------------------------------------------------------------
Oxides (stockpile)                                     757     1.78 
--------------------------------------------------------------------
Transition (in situ)     701  1.30    1.23      44     938     1.22 
--------------------------------------------------------------------
Transition                                                          
 (stockpile)                                             3     1.40 
--------------------------------------------------------------------
Sulphides                874  1.16    1.15      30   1,344     1.03 
--------------------------------------------------------------------
                       1,724  1.28    1.23      39   3,261     1.32 
                     -----------------------------------------------
                                         TOTAL M&I   4,985     1.31 
                                   ---------------------------------
                                                                    
                     -----------------------------------------------
                                    PROVEN                  PROBABLE
                     -----------------------------------------------
                     tonnes, Gold, Copper, Silver, tonnes,    Gold, 
ORE TYPE               '000s   g/t       %     g/t   '000s      g/t 
--------------------------------------------------------------------
Oxides (in situ)         131  1.85    1.78      83     196     1.86 
--------------------------------------------------------------------
Oxides (stockpile)                                     401     1.74 
--------------------------------------------------------------------
Transition (in situ)     643  1.32    1.22      43     908     1.23 
--------------------------------------------------------------------
Transition                                                          
 (stockpile)                                             3     1.40 
--------------------------------------------------------------------
Sulphides                820  1.13    1.16      30   1,231     1.05 
--------------------------------------------------------------------
                       1,594  1.26    1.23      40   2,739     1.27 
                     -----------------------------------------------
                                          TOTAL 2P   4,333     1.27 
                                   ---------------------------------

                    ------------------------------------------------
                    INDICATED                    INFERRED           
                    ------------------------------------------------
                      Copper, Silver, tonnes,  Gold, Copper, Silver,
ORE TYPE                    %     g/t   '000s    g/t       %     g/t
--------------------------------------------------------------------
Oxides (in situ)         1.88      63      38   1.93    1.80      52
--------------------------------------------------------------------
Oxides (stockpile)       1.79      44                               
--------------------------------------------------------------------
Transition (in situ)     1.18      41      97   0.96    1.10      43
--------------------------------------------------------------------
Transition                                                          
 (stockpile)             1.53      72                               
--------------------------------------------------------------------
Sulphides                1.07      31      28   1.02    0.73      17
--------------------------------------------------------------------
                         1.32      39     162   1.20    1.20      40
                    ------------------------------------------------
                         1.29      39                               
                    -----------------                               
                                                                    
                    ------------------------------------------------
                     PROBABLE            PROVEN + PROBABLE          
                    ------------------------------------------------
                      Copper, Silver, tonnes,  Gold, Copper, Silver,
ORE TYPE                    %     g/t   '000s    g/t       %     g/t
--------------------------------------------------------------------
Oxides (in situ)         1.90      67     327   1.85    1.85      73
--------------------------------------------------------------------
Oxides (stockpile)       1.81      49     401   1.74    1.81      49
--------------------------------------------------------------------
Transition (in situ)     1.17      41   1,551   1.27    1.19      42
--------------------------------------------------------------------
Transition                                                          
 (stockpile)             1.53      72       3   1.40    1.53      72
--------------------------------------------------------------------
Sulphides                1.10      31   2,051   1.08    1.12      31
--------------------------------------------------------------------
                         1.28      40   4,333   1.27    1.26      40
                    ------------------------------------------------
                         1.26      40                               
                    -----------------                               

Note: As of October 1, 2012, the effective date of the Technical Report to be filed.

The mine plan now consists of 720,000 tonnes per year of Flotation-Only processing of Transition and Sulphide ores and 100,800 tonnes per year of LPF processing of oxide ores through 2017; the LPF processing of 224,300 tonnes of certain stockpiled oxide ores will continue in 2018. Model parameters are as follows:


Mine Plan: Flotation-Only            - 2,700 tonnes/day     (263 days/yr)   
           LPF                       - 1,667 tonnes/day     (60 days/yr)    
           224,300-tonne oxide stockpile sent to LPF in 2018                
                                                                            
Gold       Flotation-Only                                                   
 recovery: (Transition)              - 50%                                  
           Flotation-Only (Sulphide) - 60%                                  
           LPF                       - 56%                                  
Copper     Flotation-Only                                                   
 recovery: (Transition)              - 60%                                  
           Flotation-Only (Sulphide) - 80%                                  
           LPF                       - 60%                                  
Silver     Flotation-Only                                                   
 recovery: (Transition)              - 50%                                  
           Flotation-Only (Sulphide) - 60%                                  
           LPF                       - 40%                                  

Key financial input parameters are (all values in US dollars):


Sustaining capital:             $26,900,000                                 
Mine operating cost:            $4.78 per tonne (ore + waste)               
Strip ratio (waste:ore):         0.55:1                                     
Processing cost:                                                            
  LPF:                          $80.23 per tonne ore (Oxide)                
  Flotation -only:              $13.09 per tonne ore (Transition, Sulphide) 
G&A:                            $6.76 per tonne ore (LPF)                   
                                $5.68 per tonne ore (Flotation-Only)        
Copper sales:                   $0.85 per pound (LPF)                       
                                $1.28 per pound (Flotation-Only)            
Gold sales:                     $127.64 per ounce (LPF)                     
                                $168.80 per ounce (Flotation-Only)          
Silver sales:                   $3.40 per ounce (LPF)                       
                                $5.20 per ounce (Flotation-Only)            
Copper price (LOM):             $3.00/pound                                 
Gold price (LOM):               $1,400.00/ounce                             
Silver price (LOM):             $25.00/ounce                                

Certain oxide resources are not included in the mine plan, whether in situ or in stockpile, since treatment by Flotation-Only or LPF processes is not practical and/or not economically viable because of the input price deck or other parameters, but will be processed opportunistically during the life of mine. Likewise, some Transition and Sulphide resources not included in the mine plan will also be mined and processed opportunistically if extraction of the metals is economically viable.

Products made from the LPF process include a copper cement and a talc-rich precious-metal concentrate, and from the Flotation-Only process a copper concentrate with levels of lead from 8% to as high as 20% as well as a lead concentrate. All products are under contract.

"This mine plan outlines a path forward that optimizes the UMZ operation," said Bill Williams, President and Chief Executive Officer of Orvana Minerals Corp. "We will continue to pursue opportunities to improve recoveries as well as seek alternatives to extend production beyond 2018, including exploration in proximal concessions," he added.

During October, production was about 973,000 pounds of copper, 1,440 ounces of gold, and 76,000 ounces of silver. Total cash costs, on a co-product basis including all royalties and based on sales, were approximately $1.80 per pound copper, $910 per ounce gold and $16 per ounce silver. During November, production was about 1,060,000 pounds of copper, 1,290 ounces of gold, and 62,000 ounces of silver at total cash costs of less than $2.00 per pound, less than $980 per ounce, and less than $22.00 per ounce, respectively. Whereas the Flotation-Only process was operable during October and November, the LPF process is currently active and processing will switch over to Flotation-Only next week and continue in January.

The information regarding the NI 43-101-compliant technical report was prepared under the supervision of Francisco Alcalde Garmendia of Kminante Consultores in Santiago, Chile, who is a qualified person for the purposes of NI 43-101 and is independent of EMIPA. The compilation of production information was prepared by Bill Williams, President and Chief Executive Officer of Orvana Minerals Corp, who is a qualified person for the purposes of NI 43-101.

The Technical Report will be filed on www.sedar.com and the Orvana website within 45 days of this release.

About Orvana

Orvana Minerals Corp. is a multi-mine gold and copper producer. Orvana's primary asset is the El Valle-Boinas/Carles gold-copper Mine in northern Spain. Orvana also owns and operates the Don Mario Upper Mineralized Zone Mine in Bolivia, which is a copper-gold-silver deposit. In addition, Orvana is advancing its Copperwood copper project in Michigan, USA. Additional information is available at Orvana's website (www.orvana.com).

Forward Looking Disclaimer

Certain statements in this press release constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws ("forward-looking statements"). Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, potentials, future events or performance (often, but not always, using words or phrases such as "believes", "expects", "plans", "estimates" or "intends" or stating that certain actions, events or results "may", "could", "would", "might", "will" or "are projected to" be taken or achieved) are not statements of historical fact, but are forward-looking statements.

Forward-looking statements relate to, among other things, all aspects of the development of the Upper Mineralized Zone ("UMZ") deposit at the Don Mario Mine in Bolivia, the El Valle-Boinas/Carles Mine in Spain and the Copperwood project in Michigan and their potential operations and production; the outcome and timing of decisions with respect to whether and how to proceed with such development and production; the timing and outcome of any such development and production; estimates of future capital expenditures; mineral resource estimates; estimates of permitting time lines; statements and information regarding future feasibility studies and their results; production forecasts; future transactions; future metal prices; the ability to achieve additional growth and geographic diversification; future production costs; future financial performance, including the ability to increase cash flow and profits; future financing requirements; and mine development plans.

Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by Orvana as of the date of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. The estimates and assumptions of Orvana contained or incorporated by reference in this news release, which may prove to be incorrect, include, but are not limited to, the various assumptions set forth herein and in the Company's most recently filed Annual Information Form, or as otherwise expressly incorporated herein by reference as well as: there being no significant disruptions affecting operations, whether due to labour disruptions, supply disruptions, power disruptions, damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at the UMZ deposit, El Valle-Boinas/Carles Mine and the Copperwood project being consistent with the Company's current expectations; political developments in any jurisdiction in which the Company operates being consistent with its current expectations; certain price assumptions for gold, copper and silver; prices for key supplies being approximately consistent with current levels; production and cost of sales forecasts meeting expectations; the accuracy of the Company's current mineral reserve and mineral resource estimates; and labour and materials costs increasing on a basis consistent with Orvana's current expectations.

A variety of inherent risks, uncertainties and factors, many of which are beyond the Company's control, affect the operations, performance and results of the Company and its business, and could cause actual events or results to differ materially from estimated or anticipated events or results expressed or implied by forward looking statements. Some of these risks, uncertainties and factors include fluctuations in the price of gold, silver and copper; the need to recalculate estimates of resources based on actual production experience; the failure to achieve production estimates; variations in the grade of ore mined; variations in the cost of operations; the availability of qualified personnel; the Company's ability to obtain and maintain all necessary regulatory approvals and licenses; the Company's ability to use cyanide in its mining operations; risks generally associated with mineral exploration and development, including the Company's ability to develop the UMZ deposit, the Copperwood project or the El Valle-Boinas/Carles Mine; the Company's ability to acquire and develop mineral properties and to successfully integrate such acquisitions; the Company's ability to obtain financing when required on terms that are acceptable to the Company; challenges to the Company's interests in its property and mineral rights; current, pending and proposed legislative or regulatory developments or changes in political, social or economic conditions in the countries in which the Company operates; general economic conditions worldwide; and the risks identified in Orvana's Management's Discussion and Analysis for the period ended June 30, 2012 under the heading "Risks and Uncertainties". This list is not exhaustive of the factors that may affect any of the Company's forward-looking statements and reference should also be made to the Company's Annual Information Form for a description of additional risk factors.

Forward-looking statements are based on management's current plans, estimates, projections, beliefs and opinions and, except as required by law, the Company does not undertake any obligation to update forward-looking statements should assumptions related to these plans, estimates, projections, beliefs and opinions change. Readers are cautioned not to put undue reliance on forward-looking statements.

Contacts:
Orvana Minerals Corp.
Natalie Frame
Investor Relations
(289) 200-7640

Orvana Minerals Corp.
Bill Williams
President and Chief Executive Officer
(416) 369-1629
ask_us@orvana.com
www.orvana.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Any startup has to have a clear go –to-market strategy from the beginning. Similarly, any data science project has to have a go to production strategy from its first days, so it could go beyond proof-of-concept. Machine learning and artificial intelligence in production would result in hundreds of training pipelines and machine learning models that are continuously revised by teams of data scientists and seamlessly connected with web applications for tenants and users.
When shopping for a new data processing platform for IoT solutions, many development teams want to be able to test-drive options before making a choice. Yet when evaluating an IoT solution, it’s simply not feasible to do so at scale with physical devices. Building a sensor simulator is the next best choice; however, generating a realistic simulation at very high TPS with ease of configurability is a formidable challenge. When dealing with multiple application or transport protocols, you would be...
IT organizations are moving to the cloud in hopes to approve efficiency, increase agility and save money. Migrating workloads might seem like a simple task, but what many businesses don’t realize is that application migration criteria differs across organizations, making it difficult for architects to arrive at an accurate TCO number. In his session at 21st Cloud Expo, Joe Kinsella, CTO of CloudHealth Technologies, will offer a systematic approach to understanding the TCO of a cloud application...
Connecting to major cloud service providers is becoming central to doing business. But your cloud provider’s performance is only as good as your connectivity solution. Massive Networks will place you in the driver's seat by exposing how you can extend your LAN from any location to include any cloud platform through an advanced high-performance connection that is secure and dedicated to your business-critical data. In his session at 21st Cloud Expo, Paul Mako, CEO & CIO of Massive Networks, wil...
"With Digital Experience Monitoring what used to be a simple visit to a web page has exploded into app on phones, data from social media feeds, competitive benchmarking - these are all components that are only available because of some type of digital asset," explained Leo Vasiliou, Director of Web Performance Engineering at Catchpoint Systems, in this SYS-CON.tv interview at DevOps Summit at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
SYS-CON Events announced today that Secure Channels, a cybersecurity firm, will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Secure Channels, Inc. offers several products and solutions to its many clients, helping them protect critical data from being compromised and access to computer networks from the unauthorized. The company develops comprehensive data encryption security strategie...
An increasing number of companies are creating products that combine data with analytical capabilities. Running interactive queries on Big Data requires complex architectures to store and query data effectively, typically involving data streams, an choosing efficient file format/database and multiple independent systems that are tied together through custom-engineered pipelines. In his session at @BigDataExpo at @ThingsExpo, Tomer Levi, a senior software engineer at Intel’s Advanced Analytics ...
Cloud adoption is often driven by a desire to increase efficiency, boost agility and save money. All too often, however, the reality involves unpredictable cost spikes and lack of oversight due to resource limitations. In his session at 20th Cloud Expo, Joe Kinsella, CTO and Founder of CloudHealth Technologies, tackled the question: “How do you build a fully optimized cloud?” He will examine: Why TCO is critical to achieving cloud success – and why attendees should be thinking holistically ab...
yperConvergence came to market with the objective of being simple, flexible and to help drive down operating expenses. It reduced the footprint by bundling the compute/storage/network into one box. This brought a new set of challenges as the HyperConverged vendors are very focused on their own proprietary building blocks. If you want to scale in a certain way, let’s say you identified a need for more storage and want to add a device that is not sold by the HyperConverged vendor, forget about it....
As businesses adopt functionalities in cloud computing, it’s imperative that IT operations consistently ensure cloud systems work correctly – all of the time, and to their best capabilities. In his session at @BigDataExpo, Bernd Harzog, CEO and founder of OpsDataStore, presented an industry answer to the common question, “Are you running IT operations as efficiently and as cost effectively as you need to?” He then expounded on the industry issues he frequently came up against as an analyst, and ...
Docker containers have brought great opportunities to shorten the deployment process through continuous integration and the delivery of applications and microservices. This applies equally to enterprise data centers as well as the cloud. In his session at 20th Cloud Expo, Jari Kolehmainen, founder and CTO of Kontena, discussed solutions and benefits of a deeply integrated deployment pipeline using technologies such as container management platforms, Docker containers, and the drone.io Cl tool. H...
The goal of Continuous Testing is to shift testing left to find defects earlier and release software faster. This can be achieved by integrating a set of open source functional and performance testing tools in the early stages of your software delivery lifecycle. There is one process that binds all application delivery stages together into one well-orchestrated machine: Continuous Testing. Continuous Testing is the conveyer belt between the Software Factory and production stages. Artifacts are m...
WebRTC is great technology to build your own communication tools. It will be even more exciting experience it with advanced devices, such as a 360 Camera, 360 microphone, and a depth sensor camera. In his session at @ThingsExpo, Masashi Ganeko, a manager at INFOCOM Corporation, will introduce two experimental projects from his team and what they learned from them. "Shotoku Tamago" uses the robot audition software HARK to track speakers in 360 video of a remote party. "Virtual Teleport" uses a...
SYS-CON Events announced today that App2Cloud will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct. 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. App2Cloud is an online Platform, specializing in migrating legacy applications to any Cloud Providers (AWS, Azure, Google Cloud).
Cloud resources, although available in abundance, are inherently volatile. For transactional computing, like ERP and most enterprise software, this is a challenge as transactional integrity and data fidelity is paramount – making it a challenge to create cloud native applications while relying on RDBMS. In his session at 21st Cloud Expo, Claus Jepsen, Chief Architect and Head of Innovation Labs at Unit4, will explore that in order to create distributed and scalable solutions ensuring high availa...