Bacanora Preliminary Economic Assessment for Cajon Borate Deposit Estimated at $113 Million NPV (@8% Discount)

CALGARY, ALBERTA -- (Marketwire) -- 01/04/13 -- BACANORA MINERALS LTD. (TSX VENTURE:BCN) ("Bacanora" or the "Company") is pleased to announce the results of a Preliminary Economic Assessment ("PEA") on the Company's Cajon Borate deposit in Sonora, Mexico.

Highlights of the PEA for a potential colemanite mine and production facility with a mining rate of 231,100 tonnes averaging 10.5% B2O3 per annum to yield 50,000 tonnes of 40-42% colemanite concentrate per year over a 25 year mine life suggest annual revenue of $US25 million for an IRR of 248.5% with a 4 year pay back. Capital costs are estimated at $US7.25 million and average operating costs at $US170/tonne. Net Present Value ("NPV") of the project, discounted at 8%, is $US113 million, assuming an average colemanite concentrate price of $US500/tonne. The preliminary economic assessment includes forward looking information including, but not limited to assumptions concerning colemanite prices, cash flow forecasts, project capital and operating costs, commodity recoveries, mine life and production rates. Readers are cautioned that actual results may vary from those presented. Further testing will need to be undertaken to confirm economic feasibility of the El Cajon deposit. Readers are further cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability.

Preliminary Financial Highlights

----------------------------------------------------------------------------
Open Pit Mine Production per annum             231,100  tonnes @ 10.5% B2O3 
----------------------------------------------------------------------------
Colemanite concentrate production per annum     50,000  tonnes @ 42% B2O3   
----------------------------------------------------------------------------
Revenue ($US500/tonne of colemanite                                         
 concentrate) per annum                            $25  million             
----------------------------------------------------------------------------
NPV (8% Discount)                               $US113  million             
----------------------------------------------------------------------------
Internal rate of return (IRR)                   248.5%                      
----------------------------------------------------------------------------
Average Operating costs                         $US170  per tonne           
----------------------------------------------------------------------------
Total Initial Capital Costs                    $US7.25  million             
----------------------------------------------------------------------------
Expected Mine Life                                  25  years               
----------------------------------------------------------------------------
Pay Back of Capital Costs                            4  year                
----------------------------------------------------------------------------

The Cajon deposit forms part of the Magdalena Borate Project, which is 100% owned by Bacanora's wholly-owned subsidiary, Minera Sonora Borax S.A. de C.V., subject to a 3% royalty in favor of an arm's length third party and a 3% gross overriding royalty in favor of Mr. Colin Orr-Ewing, a director of Bacanora.

Three main borate zones have been located on the Magdalena project area: El Cajon; Bellota and Pozo Nuevo. Other targets include the recently discovered Represo colemanite prospect and the Escuadra occurrence.

Of the main borate zones El Cajon is the most advanced. Drilling by Bacanora (48 holes) and a US Borax subsidiary (11 holes) has identified 3 separate colemanite horizons (units: A, B and C) within the gently south-dipping sediments that underlie the area of El Cajon. The drilling has allowed an indicated borate resource of 11 million tonnes averaging 10.6% B2O3 to be estimated for El Cajon under CIM resource-reserve criteria. The estimate includes indicated resources for unit A of 7.5 million tonnes averaging 10.8% B2O3, 0.8 million tonnes averaging 9.0% B2O3 for unit B and 2.7 million tonnes averaging 10.5% B2O3 for unit C using a cut off of 8% B2O3. The average thickness for each bed making up the 3 units ranges from 4.2 to 9.8 metres. Readers are cautioned that mineral resources used in this PEA are not mineral reserves as they do not have demonstrated economic viability.

Initial metallurgical test work has indicated that a colemanite concentrate grading 38% - 42% B2O3 can be produced from an average feed of 10.5% B2O3 from El Cajon using a combination of scrubbing, de-sliming and flotation. Construction of a pilot plant in order to conduct detailed metallurgy and improve the borate content of the colemanite concentrate, as well as finalize a full scale production flow sheet and produce colemanite concentrates for test marketing is 80% complete. In addition, it is recommended that a boric acid circuit be included in the pilot plant.

Potential buyers of colemanite concentrates have expressed interest in purchasing colemanite from Bacanora should it be able to produce concentrates that meet these consumers' specifications.

Management is very pleased with the preliminary economic assessment of El Cajon and looks forward to completing additional work for the purpose of advancing the project through feasibility and, ultimately, leading to the commercial development of this deposit. The full text of the PEA will be filed on SEDAR as a report in compliance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and will be available on Bacanora's website.

Colemanite is a boron mineral that is used to produce boric acid, a compound used in a number of industrial applications that are in general designed to reduce energy consumption. Colemanite itself has industrial applications in ceramics and agriculture. Current contract prices for colemanite range from $US630 to $US730 per tonne; contract prices for chemical grade boric acid range from $US800 to $US1,250 per tonne, depending on purity.

Carl G. Verley, P.Geo. is the Qualified Person pursuant to NI 43-101 who was the lead author with overall responsibility for the PEA and review of the technical contents of this news release.

Reader Advisory

This press release shall not constitute an offer to sell or the solicitation of an offer to buy any securities nor shall there be any sale of securities in any state in the United States in which such offer, solicitation or sale would be unlawful.

Except for statements of historical fact, this news release contains certain "forward-looking information" within the meaning of applicable securities law. Forward-looking information is frequently characterized by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate" and other similar words, or statements that certain events or conditions "may" or "will" occur. In particular, forward-looking information in this press release includes, but is not limited to, the estimated future value of the Magdalena Borate Project. Although we believe that the expectations reflected in the forward-looking information are reasonable, there can be no assurance that such expectations will prove to be correct. We cannot guarantee future results, performance or achievements. Consequently, there is no representation that the actual results achieved will be the same, in whole or in part, as those set out in the forward-looking information.

Forward-looking information is based on the opinions and estimates of management at the date the statements are made, and are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those anticipated in the forward-looking information. Some of the risks and other factors that could cause the results to differ materially from those expressed in the forward-looking information include, but are not limited to: commodity price volatility; general economic conditions in Canada, the United States, Mexico and globally; industry conditions, governmental regulation, including environmental regulation; unanticipated operating events or performance; failure to obtain industry partner and other third party consents and approvals, if and when required; the availability of capital on acceptable terms; the need to obtain required approvals from regulatory authorities; stock market volatility; competition for, among other things, capital, skilled personnel and supplies; changes in tax laws; and the other risk factors disclosed under our profile on SEDAR at www.sedar.com and within the body of the PEA. Readers are cautioned that this list of risk factors should not be construed as exhaustive.

The forward-looking information contained in this news release is expressly qualified by this cautionary statement. We undertake no duty to update any of the forward-looking information to conform such information to actual results or to changes in our expectations except as otherwise required by applicable securities legislation. Readers are cautioned not to place undue reliance on forward-looking information.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
Bacanora Minerals Ltd.
Paul Conroy
President and Chief Executive Officer
(403) 237-6122
(403) 237-6144 (FAX)

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Amazon is pursuing new markets and disrupting industries at an incredible pace. Almost every industry seems to be in its crosshairs. Companies and industries that once thought they were safe are now worried about being “Amazoned.”. The new watch word should be “Be afraid. Be very afraid.” In his session 21st Cloud Expo, Chris Kocher, a co-founder of Grey Heron, will address questions such as: What new areas is Amazon disrupting? How are they doing this? Where are they likely to go? What are th...
SYS-CON Events announced today that MIRAI Inc. will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. MIRAI Inc. are IT consultants from the public sector whose mission is to solve social issues by technology and innovation and to create a meaningful future for people.
SYS-CON Events announced today that Dasher Technologies will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Dasher Technologies, Inc. ® is a premier IT solution provider that delivers expert technical resources along with trusted account executives to architect and deliver complete IT solutions and services to help our clients execute their goals, plans and objectives. Since 1999, we'v...
Though cloud is the future of enterprise computing, a smooth transition of legacy applications and systems is critical for seamless business operations. IT professionals are eager to start leveraging the cost, scale and other benefits of cloud, but with massive investments already in place in existing infrastructure and a number of compliance and resource hurdles, it can be challenging to move to a cloud-based infrastructure.
SYS-CON Events announced today that NetApp has been named “Bronze Sponsor” of SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. NetApp is the data authority for hybrid cloud. NetApp provides a full range of hybrid cloud data services that simplify management of applications and data across cloud and on-premises environments to accelerate digital transformation. Together with their partners, NetApp emp...
In his session at 21st Cloud Expo, Raju Shreewastava, founder of Big Data Trunk, will provide a fun and simple way to introduce Machine Leaning to anyone and everyone. Together we will solve a machine learning problem and find an easy way to be able to do machine learning without even coding. Raju Shreewastava is the founder of Big Data Trunk (www.BigDataTrunk.com), a Big Data Training and consulting firm with offices in the United States. He previously led the data warehouse/business intellige...
SYS-CON Events announced today that TidalScale, a leading provider of systems and services, will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. TidalScale has been involved in shaping the computing landscape. They've designed, developed and deployed some of the most important and successful systems and services in the history of the computing industry - internet, Ethernet, operating s...
SYS-CON Events announced today that IBM has been named “Diamond Sponsor” of SYS-CON's 21st Cloud Expo, which will take place on October 31 through November 2nd 2017 at the Santa Clara Convention Center in Santa Clara, California.
Infoblox delivers Actionable Network Intelligence to enterprise, government, and service provider customers around the world. They are the industry leader in DNS, DHCP, and IP address management, the category known as DDI. We empower thousands of organizations to control and secure their networks from the core-enabling them to increase efficiency and visibility, improve customer service, and meet compliance requirements.
In his session at 21st Cloud Expo, Michael Burley, a Senior Business Development Executive in IT Services at NetApp, will describe how NetApp designed a three-year program of work to migrate 25PB of a major telco's enterprise data to a new STaaS platform, and then secured a long-term contract to manage and operate the platform. This significant program blended the best of NetApp’s solutions and services capabilities to enable this telco’s successful adoption of private cloud storage and launchi...
Data scientists must access high-performance computing resources across a wide-area network. To achieve cloud-based HPC visualization, researchers must transfer datasets and visualization results efficiently. HPC clusters now compute GPU-accelerated visualization in the cloud cluster. To efficiently display results remotely, a high-performance, low-latency protocol transfers the display from the cluster to a remote desktop. Further, tools to easily mount remote datasets and efficiently transfer...
SYS-CON Events announced today that IBM has been named “Diamond Sponsor” of SYS-CON's 21st Cloud Expo, which will take place on October 31 through November 2nd 2017 at the Santa Clara Convention Center in Santa Clara, California.
Cloud Expo, Inc. has announced today that Andi Mann and Aruna Ravichandran have been named Co-Chairs of @DevOpsSummit at Cloud Expo Silicon Valley which will take place Oct. 31-Nov. 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. "DevOps is at the intersection of technology and business-optimizing tools, organizations and processes to bring measurable improvements in productivity and profitability," said Aruna Ravichandran, vice president, DevOps product and solutions marketing...
Join IBM November 1 at 21st Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA, and learn how IBM Watson can bring cognitive services and AI to intelligent, unmanned systems. Cognitive analysis impacts today’s systems with unparalleled ability that were previously available only to manned, back-end operations. Thanks to cloud processing, IBM Watson can bring cognitive services and AI to intelligent, unmanned systems. Imagine a robot vacuum that becomes your personal assistant tha...
In his Opening Keynote at 21st Cloud Expo, John Considine, General Manager of IBM Cloud Infrastructure, will lead you through the exciting evolution of the cloud. He'll look at this major disruption from the perspective of technology, business models, and what this means for enterprises of all sizes. John Considine is General Manager of Cloud Infrastructure Services at IBM. In that role he is responsible for leading IBM’s public cloud infrastructure including strategy, development, and offering ...