Silver Standard provides 2012 production results and issues 2013 production and cost guidance

VANCOUVER, Jan. 8, 2013 /PRNewswire/ - Silver Standard Resources Inc. (NASDAQ: SSRI, TSX: SSO) ("Silver Standard" or the "Company") announced 2012 production at the Pirquitas mine in Jujuy, Argentina and provided production and cost guidance for 2013.

2012 Operating Highlights:

  • Exceeded silver production guidance: Produced 8.6 million ounces of silver in 2012, exceeding the high-end of the guidance range.  Produced 11.2 million pounds of zinc, near the high-end of 2012 guidance.

  • Delivered strong operating performance:  Milled 4,433 tonnes per day, on average, during 2012, 11% above nominal design.  Silver recovery averaged 76% during 2012.

  • Created value:  Drilled over 53,000 meters at Pirquitas during 2012, aggressively exploring the Cortaderas Breccia and Cortaderas Valley targets. Executed the Company's sales strategy, signing sales agreements with smelters, improving margins and building a strong customer base for 2013.

"In 2012, our team delivered on its commitments," said John Smith, President and CEO.  "At Pirquitas, we exceeded the high-end of our silver production guidance range, producing a record 8.6 million ounces and delivered on our sales strategy.  Exploration remains key to our business model, and we continue to focus on adding value through the drill bit.  In the fourth quarter, we completed the Pitarrilla Feasibility Study, defining a mine with approximately 480 million ounces of reserves and producing 15 million ounces of silver per year on average during the first 18 years of a 32-year project."

Summary of Mine Operating Statistics

    Q4 2012 Q3 2012 % Change
Total material mined Kt 4,415 4,333 1.9%
Ore processed Kt 417 404 3.2%
Silver mill feed grade g/t 212 214 (0.9%)
Zinc mill feed grade % 0.67 0.65 3.1%
Silver recovery % 79.9 77.7 2.8%
Zinc recovery % 42 39 7.7%
Silver produced '000 oz 2,268 2,163 4.9%
Zinc produced '000 lbs 3,176 2,770 14.7%
Silver ounces sold '000 oz 3,218 2,770 16.2%
Zinc pounds sold '000 lbs 2,731 2,152 26.9%

Note: Percent changes are calculated using rounded numbers presented in the table.

Mine Operations

During 2012, the Pirquitas mine produced a record 8.6 million ounces of silver.  The mine produced 2.3 million ounces of silver during the fourth quarter, 4.9% quarter-on-quarter improvement reflecting higher average silver recoveries in the plant and higher mill throughput.  The mine also produced 3.2 million pounds of zinc in the fourth quarter, bringing total zinc production to 11.2 million pounds for the year, near the high-end of the 2012 zinc production guidance range.

Approximately 417,000 tonnes of ore were milled at an average rate of 4,531 tonnes per day during the quarter, 13% above the plant's nominal design.  On an annual basis, the mill processed 4,433 tonnes per day during 2012.

Ore milled during the fourth quarter of 2012 contained an average silver grade of 212 g/t, in line with the 214 g/t reported for the third quarter. The average recovery rate for silver increased to 79.9% from 77.7% in the third quarter.

Outlook for 2013

Silver Standard's estimated production and cost guidance for 2013 are as follows:

  • Produce and sell 8.2 to 8.5 million ounces of silver.
  • Produce over 20 million pounds of zinc.
  • Total cash cost of between $17.00 and $18.50 per silver ounce.
  • Capital expenditures of $25 million at Pirquitas, including approximately $15 million for a tailings facility expansion but excluding capitalized stripping costs.
  • Expenditures of $15 million for exploration across the Company's portfolio.
  • Expenditures of $17 million for development.

Silver Standard plans to spend approximately $15 million on exploration in 2013.  Of this, approximately $7 million is budgeted for exploration at our Mexican projects, with the balance mainly budgeted for Argentina and Peru.  The Company may increase its exploration budget or redirect exploration spending in response to positive results.

The Company expects to spend a minimum of $17 million on development in 2013.  Of this, approximately $8 million and $7 million will be incurred at the Pitarrilla and San Luis projects, respectively, in line with our goal of advancing these projects to construction decisions.  Should construction decisions be made, development expenditures would increase significantly.  Planned investments in advance of construction decisions include optimization, land acquisition, community agreements, permitting and financing.        

John Smith, President and CEO of Silver Standard, commented on the Company's 2013 guidance, "Following a strong 2012, we continue to focus on delivering strong and predictable results at Pirquitas.  In the first half of the year we are moving from Phase 1 to Phase 2 of the San Miguel open-pit.  Due to ore and stockpile sequencing, we plan to produce approximately 2 million ounces of silver in the first quarter of 2013 with production strengthening as we move through the year.  At the same time, our team will continue with permitting, engineering and partnering activities at Pitarrilla. We remain focused on progressing towards a construction decision."

Silver Standard is required to adopt the accounting standard IFRIC 20 "Stripping Costs in the Production Phase of a Surface Mine" effective January 1, 2013.  The Company estimates that the adoption of IFRIC 20 will result in the capitalization of approximately $24 million of mining costs in 2013 that will be amortized in subsequent periods.

Changes to the Presentation of Non-GAAP Financial Measures

Commencing with its 2012 annual filings, Silver Standard plans to revise its non-GAAP "total cash cost" and "total production cost" disclosure methodology. Under the revised methodology, the Company will report total cash cost and total production cost on a "per payable ounce sold" basis, rather than on a per ounce produced basis as reported previously. Silver concentrate export duties that are being accrued but not paid will be reallocated to total cost to reflect their non-cash nature as the Company has an order in its favor against their payment.

Total cash cost will consist of the cost of inventory, third party smelting, refining and transportation and royalties less by-product credits.  Total production cost will consist of total cash cost plus depreciation, depletion, amortization (including amortization of deferred stripping costs) and silver concentrate export duties. The divisor for both measures is payable silver ounces sold in the period.

The 2013 total cash cost guidance incorporates these changes.

Technical Disclosure

The scientific and technical data contained in this news release has been reviewed and approved by Andrew W. Sharp, BEng, FAusIMM, a Qualified Person under National Instrument 43-101 who has consented to having his name included in this news release. Mr. Andrew W. Sharp has been employed by the Company as Vice President, Technical Services, since September, 2011.

On December 17, 2012, we filed a technical report entitled "NI 43-101 Technical Report on the Pitarrilla Project, Durango, State, Mexico" in accordance with the requirements of NI 43-101 and in support of a feasibility study for the Pitarrilla project.  A copy of the Technical Report is available under our profile on SEDAR at www.sedar.com.

Cautionary Note Regarding Forward-Looking Statements:

Statements in this news release are forward-looking statements within the meaning of the U.S. Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of Canadian securities laws (collectively "forward-looking statements"). All statements, other than statements of historical fact, are forward-looking statements. Generally, forward-looking statements can be identified by the use of words or phrases such as; "expects", "anticipates", "plans", projects", "estimates", "assumes", "intends", "strategy", "goals", "objectives", "potential" or variations thereof, or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms or similar expressions. The forward-looking statements in this news release relate to, among other things: future production of silver and other metals; future mining costs and cash costs per ounce of silver; the price of silver and other metals; the effects of laws, regulations and government policies affecting the Company's operations or potential future operations; future successful development of the Company's projects; the sufficiency of the Company's current working capital, anticipated operating cash flow or the Company's ability to raise necessary funds; estimated production rates for silver and other payable metal produced by the Company; timing of production and the cash and total costs of production at the Pirquitas mine; the estimated cost of sustaining capital; ongoing or future development plans and capital replacement, improvement or remediation programs; the estimates of expected or anticipated economic returns from the Company's mining projects including: future sales of the metals, concentrates or other products produced by the Company; and the Company's plans and expectations for its properties and operations.

These forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ from those expressed or implied, including, without limitation, risks relating to: uncertainty of production and cost estimates for the Pirquitas mine, the Pitarrilla project and the San Luis project; future development risks, including start-up delays and operational issues; uncertainty in the Company's ability to replace its mineral reserves; risks related to the Company's ability to obtain adequate financing for its planned development activities and further exploration programs; fluctuations in spot and forward prices for silver, gold and base metals and certain other commodities; the Company's history of losses and the potential for future losses; risks related to general economic conditions, including recent events in global financial markets; the future value of Pretium's shares and the Company's ability to monetize the full value of its interest in Pretium; counterparty and market risks related to the sale of the Company's concentrates; changes in national and local legislation, taxation (including employee profit sharing arrangements), exchange controls or regulations and political or economic developments or changes in Argentina, Mexico, Peru, Canada, the United States or other countries where the Company holds assets or may carry on business; import and export regulations in Argentina, including potential export tax on production from the Pirquitas mine, that may impact cash flow, concentrate sales and importation of goods and services required for the Pirquitas mine; differences in U.S. and Canadian practices for reporting mineral resources and mineral reserves; uncertainty in the accuracy of mineral reserves and mineral resources estimates and in the Company's ability to extract mineralization profitably; the Company's ability to successfully acquire additional commercially mineable mineral rights; lack of suitable infrastructure or damage to existing infrastructure; the Company's revenue being derived solely from the Pirquitas mine; risks related to the delay in obtaining or failure to obtain required permits, or non-compliance with permits the Company has obtained; increased costs and restrictions on operations due to compliance with environmental laws and regulations; risks related to reclamation activities on the Company's properties; risks and hazards associated with the business of mineral exploration, development and mining (including operating in foreign jurisdictions, environmental hazards, industrial accidents, unusual or unexpected geological or structure formations, pressures, cave-ins and flooding); risks related to governmental regulations, including environmental regulations; risks related to anti-corruption laws; regulations and pending legislation governing issues involving climate change, as well as the physical impacts of climate change; uncertainties related to title to the Company's mineral properties and the surface rights thereon, including the Company's ability to economically acquire the surface rights to certain of the Company's exploration and development projects, and uncertainties due to past or present indigenous inhabitation of the Company's properties; inadequate insurance or the Company's inability to obtain insurance; civil disobedience in the countries where the Company's properties are located; safety and security risks; actions required of the Company under human rights law; exchange rate fluctuations among the U.S. dollar and the currencies of the countries in which the Company operates (such as the Canadian dollar, Argentine peso, Peruvian sol and Mexican peso); increased competition in the mining industry for mining services, properties, equipment, qualified personnel and management; shortage of equipment or supplies, including as a result of local sourcing requirements; the Company's ability to attract and retain qualified personnel and management to grow the Company's business; the Company's ability to maintain adequate internal control over financial reporting;  risks related to the Company's adoption of IFRIC 20; tightened controls over the VAT collection process in Argentina; increased regulatory compliance costs related to the Dodd-Frank Wall Street Reform and Consumer Protection Act; risks related to some of the Company's directors' and officers' involvement with other natural resource companies; risks related to claims and legal proceedings; potential difficulty in bringing or enforcing actions against the Company or its directors or officers outside the United States; risks related to the terms of the Company's outstanding convertible notes, as well as other factors described in the Company's most recent Form 20-F filed with the U.S. Securities and Exchange Commission and Canadian regulatory authorities.

This list is not exhaustive of the factors that may affect any of the Company's forward-looking statements. The Company's forward-looking statements are based on what the Company's management considers to be reasonable assumptions, beliefs, expectations and opinions based on the information currently available to it. We cannot assure you that actual events, performance or results will be consistent with these forward looking statements, and management's assumptions may prove to be incorrect. Assumptions have been made regarding, among other things, the Company's ability to carry on its exploration and development activities, the Company's ability to meet its obligations under its property agreements, the timing and results of drilling programs, the discovery of mineral resources and mineral reserves on the Company's mineral properties, the timely receipt of required approvals including obtaining the necessary surface rights for the lands required for successful project permitting, construction and operation of the Pitarrilla project, the price of the minerals the Company produces, the costs of operating and exploration expenditures, the Company's ability to operate in a safe, efficient and effective manner and the Company's ability to obtain financing as and when required and on reasonable terms and its ability to continue operating the Pirquitas mine. You are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. The Company's forward-looking statements reflect current expectations regarding future events and operating performance and speak only as of the date hereof and the Company does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. For the reasons set forth above, you should not place undue reliance on forward-looking statements.

Cautionary Note to U.S. Investors.

The disclosure included in this news release uses Mineral Reserves and Mineral Resources classification terms that comply with reporting standards in Canada and the Mineral Reserves and Mineral Resources estimates are made in accordance with Canadian National Instrument 43-101—Standards of Disclosure for Mineral Projects ("NI 43-101").  NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects.  These standards differ significantly from the requirements of the SEC set out in Industry Guide 7.  Consequently, Mineral Reserves and Mineral Resources information included in this news release is not comparable to similar information that would generally be disclosed by domestic U.S. reporting companies subject to the reporting and disclosure requirements of the SEC.  Under SEC standards, mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be economically produced or extracted at the time the reserve determination is made.

Cautionary Note Regarding Non-GAAP Measures:

The Company has included the non-GAAP financial measure, "total cash cost." This measure has been revised from the Company's previous presentation as described in this news release under the heading "Changes to the Presentation of Non-GAAP Financial Measures." Although "total cash cost" is a common financial measure in the mining industry, it is a non-GAAP measure and it does not have a standardized meaning. The Company believes that, in addition to conventional measures prepared in accordance with GAAP, certain investors use this information to evaluate the Company's performance and ability to generate cash flow. Accordingly, it is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP. 

All amounts reported in U.S. dollars.

To receive Silver Standard's news releases by e-mail, please register using the Silver Standard website at www.silverstandard.com.

SOURCE Silver Standard Resources Inc.

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
DevOps tends to focus on the relationship between Dev and Ops, putting an emphasis on the ops and application infrastructure. But that’s changing with microservices architectures. In her session at DevOps Summit, Lori MacVittie, Evangelist for F5 Networks, will focus on how microservices are changing the underlying architectures needed to scale, secure and deliver applications based on highly distributed (micro) services and why that means an expansion into “the network” for DevOps.
Is it possible to migrate 100% of your data ecosystem to the cloud? Join Joe Caserta as he takes you on a complete journey to digital transformation mapping out on-prem data footprint and walking it to the cloud. Joe will also explain how the modern ecosystem supports Artificial Intelligence and will include business use cases to back each of his insights.
With 10 simultaneous tracks, keynotes, general sessions and targeted breakout classes, @CloudEXPO and DXWorldEXPO are two of the most important technology events of the year. Since its launch over eight years ago, @CloudEXPO and DXWorldEXPO have presented a rock star faculty as well as showcased hundreds of sponsors and exhibitors! In this blog post, we provide 7 tips on how, as part of our world-class faculty, you can deliver one of the most popular sessions at our events. But before reading...
René Bostic is the Technical VP of the IBM Cloud Unit in North America. Enjoying her career with IBM during the modern millennial technological era, she is an expert in cloud computing, DevOps and emerging cloud technologies such as Blockchain. Her strengths and core competencies include a proven record of accomplishments in consensus building at all levels to assess, plan, and implement enterprise and cloud computing solutions. René is a member of the Society of Women Engineers (SWE) and a m...
Containers and Kubernetes allow for code portability across on-premise VMs, bare metal, or multiple cloud provider environments. Yet, despite this portability promise, developers may include configuration and application definitions that constrain or even eliminate application portability. In this session we'll describe best practices for "configuration as code" in a Kubernetes environment. We will demonstrate how a properly constructed containerized app can be deployed to both Amazon and Azure ...
Poor data quality and analytics drive down business value. In fact, Gartner estimated that the average financial impact of poor data quality on organizations is $9.7 million per year. But bad data is much more than a cost center. By eroding trust in information, analytics and the business decisions based on these, it is a serious impediment to digital transformation.
Charles Araujo is an industry analyst, internationally recognized authority on the Digital Enterprise and author of The Quantum Age of IT: Why Everything You Know About IT is About to Change. As Principal Analyst with Intellyx, he writes, speaks and advises organizations on how to navigate through this time of disruption. He is also the founder of The Institute for Digital Transformation and a sought after keynote speaker. He has been a regular contributor to both InformationWeek and CIO Insight...
In this presentation, you will learn first hand what works and what doesn't while architecting and deploying OpenStack. Some of the topics will include:- best practices for creating repeatable deployments of OpenStack- multi-site considerations- how to customize OpenStack to integrate with your existing systems and security best practices.
DXWorldEXPO LLC announced today that Kevin Jackson joined the faculty of CloudEXPO's "10-Year Anniversary Event" which will take place on November 11-13, 2018 in New York City. Kevin L. Jackson is a globally recognized cloud computing expert and Founder/Author of the award winning "Cloud Musings" blog. Mr. Jackson has also been recognized as a "Top 100 Cybersecurity Influencer and Brand" by Onalytica (2015), a Huffington Post "Top 100 Cloud Computing Experts on Twitter" (2013) and a "Top 50 C...
Bill Schmarzo, Tech Chair of "Big Data | Analytics" of upcoming CloudEXPO | DXWorldEXPO New York (November 12-13, 2018, New York City) today announced the outline and schedule of the track. "The track has been designed in experience/degree order," said Schmarzo. "So, that folks who attend the entire track can leave the conference with some of the skills necessary to get their work done when they get back to their offices. It actually ties back to some work that I'm doing at the University of ...
The now mainstream platform changes stemming from the first Internet boom brought many changes but didn’t really change the basic relationship between servers and the applications running on them. In fact, that was sort of the point. In his session at 18th Cloud Expo, Gordon Haff, senior cloud strategy marketing and evangelism manager at Red Hat, will discuss how today’s workloads require a new model and a new platform for development and execution. The platform must handle a wide range of rec...
DXWorldEXPO LLC, the producer of the world's most influential technology conferences and trade shows has announced the 22nd International CloudEXPO | DXWorldEXPO "Early Bird Registration" is now open. Register for Full Conference "Gold Pass" ▸ Here (Expo Hall ▸ Here)
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busine...
Enterprises are universally struggling to understand where the new tools and methodologies of DevOps fit into their organizations, and are universally making the same mistakes. These mistakes are not unavoidable, and in fact, avoiding them gifts an organization with sustained competitive advantage, just like it did for Japanese Manufacturing Post WWII.
The revocation of Safe Harbor has radically affected data sovereignty strategy in the cloud. In his session at 17th Cloud Expo, Jeff Miller, Product Management at Cavirin Systems, discussed how to assess these changes across your own cloud strategy, and how you can mitigate risks previously covered under the agreement.