Welcome!

News Feed Item

Mawson West Provides Update and 2013 Outlook and Production Guidance

PERTH, AUSTRALIA -- (Marketwire) -- 01/31/13 -- Mawson West Limited (TSX:MWE) ("Mawson West" or "the Company") announces the following update and guidance on activities at its Dikulushi copper-silver mine and Kapulo copper project located in the Democratic Republic of Congo (DRC).

Highlights:


--  Successful ramp-up of Dikulushi open pit and achievement of steady state
    production of approximately 1,600 tonnes of copper per month 
    
--  Copper production from Dikulushi expected to be 20,000-22,000 tonnes in
    FY2013 
    
--  C1(1) costs at Dikulushi in FY2013 anticipated to be less than US$0.35
    per pound of copper produced 
    
--  Kapulo process plant commissioning targeted to commence in late 2013 
    
--  FY2013 exploration budget of approximately US$11 million across
    Dikulushi satellite deposits, Kapulo and Lufukwe 

Production Update

During Q4 2012, Mawson West completed the ramp-up of the Dikulushi open pit, with steady state production of approximately 1,600 tonnes of copper per month achieved in both December 2012 (1,584 tonnes) and January 2013 (approximately 1,600 tonnes). Mawson West expects to produce between 20,000 and 22,000 tonnes of copper in FY2013, with output of more than 4,500 tonnes of copper during Q1 FY2013. C1(1) costs in FY2013 are anticipated to be less than US$0.35 per pound of copper produced.

Development Update

Dikulushi

With the ramp-up of the Dikulushi open pit now complete, Mawson West has commenced studies of a potential underground mine at Dikulushi, where the high grade deposit remains open at depth, providing an opportunity to increase the life of the project. Phase 1 (mining of the upper levels of the measured resource) of these studies is scheduled to be completed during Q2 2013, with Phase 2 (mining of the deeper levels of the measured and indicated resource) scheduled to be completed during Q4 2013.

Mawson West believes that the Dikulushi underground and known satellite deposits provide opportunities to extend the life of the Dikulushi mine by up to four years.

Kapulo

Construction is continuing on a scaled back rate of expenditure at the Kapulo copper project, funded through a combination of existing cash and cash flow from the Dikulushi operation. Work on site is approximately 35% complete, with process plant commissioning targeted to commence in late 2013.

(1) C1 costs are direct cash operating costs per pound of copper produced, net of silver by-product credits.

The Company is also in the advanced stage of a design review and costing study of the Kapulo copper project, with the aim of optimizing the process flow sheet and capital costs. In addition, the Company has commenced a review of the mine design, cutback design and mine scheduling to include the Safari deposits in the mine plan.

Exploration Update

Exploration spending in FY2013 is budgeted to be approximately US$11 million as Mawson West intends to evaluate multiple near-mine and stand-alone exploration opportunities within its approximate 7,300 km2 license governed by the Dikulushi Mining Convention, including the work at the Dikulushi satellite deposits, Kapulo and Lufukwe.

In addition to work on the Dikulushi underground and Kapulo projects, Mawson West continues to evaluate a number of satellite targets within the areas governed by the Dikulushi Mining Convention that may support an extension of the current mine life. Resource extension drilling is continuing at Kazumbula, with a resource review expected mid-year. Similar work continues at Kabusanje with a maiden resource also anticipated in mid-2013. Drilling will recommence at Lufukwe during April 2013 following the wet season.

Mawson West Chief Executive Officer and Managing Director Bruce McFadzean said: "We continue to make progress towards our goal of establishing Mawson West as a sustainable, low cost copper producer from two operations by the end of 2013. In addition to the successful ramp-up at the Dikulushi open pit, we are continuing to explore the multiple near-mine and stand-alone opportunities that exist within our significant footprint in the DRC.

"With a new, experienced management team in place, and a history of operating successfully in the DRC, we are confident we will deliver on our stated targets."

About Mawson West

Mawson West is a copper and silver-focused resource company listed on the Toronto Stock Exchange (TSX) and based in Perth, Australia.

The Company's approximate 7,300km2 ground position in the Democratic Republic of Congo (DRC) contains Mawson West's two key projects, the Dikulushi copper-silver mine and the Kapulo copper project, as well as multiple near-mine and stand-alone exploration opportunities.

With existing cash and cash flow from the Dikulushi operation, Mawson West has the capacity to advance its exploration and development portfolio. In addition, the Company has assembled a proven management team with a track record of delivering new resources projects, as well as years of experience operating in Africa.

Forward-Looking Information

This press release contains "forward-looking information" that is based on Mawson West's expectations, estimates and projections as of the dates as of which those statements were made. This forward-looking information may include, among other things, statements with respect to the Company's business strategy, plans, outlook, financing plans, projections, targets and expectations as to reserves, resources, results of exploration (including targets) and related expenses, mine development, mine operations, mine production costs, drilling activity, sampling and other data, estimating grade levels, future recovery levels, future production levels, capital costs, costs savings, cash and total costs of production of copper, expenditures for environmental matters, projected life of Mawson West's mines, reclamation and other post closure obligations and estimated future expenditures for those matters, completion dates for the various development stages of mines, future copper prices (including the long-term estimated prices used in calculating Mawson West's mineral reserves), end-use demand for copper, currency exchange rates, timing of expected sales and final pricing of concentrate sales and anticipated timing of production at the Dikulushi mine and Kapulo project. Generally, this forward-looking information can be identified by the use of forward-looking terminology such as "outlook", "anticipate", "project", "target", "believe", "estimate", "expect", "intend", "should", "scheduled", "will", "plan" and similar expressions. Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause Mawson West's actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking information, and developed based on assumptions about such risks, uncertainties and other factors set out herein, including but not limited to:


--  Our ability to successfully bring the Kapulo project into production; 
--  Receipt of all permits required for the Kapulo project; 
--  The ability of our key contractors to perform the services for us in the
    manner contracted for; 
--  The availability and cost of key operating supplies and services; 
--  The production facilities may not achieve the planned desired
    recoveries; 
--  Fluctuations in copper prices; 
--  The ability to expand or replace depleted reserves and the possible
    recalculation or reduction of the reserves and resources; 
--  Actual capital costs, operating costs and expenditures, production
    schedules and economic returns from the Dikulushi mine or Kapulo
    project; 
--  Geotechnical issues; 
--  Inherent hazards and risks associated with mining operations; 
--  Inherent uncertainties associated with mineral exploration; 
--  Being subject to government regulation, including changes in regulation;
--  Being subject to extensive environmental laws and regulations, including
    change in regulation; 
--  Need for governmental licenses and permits; 
--  Political and country risk; 
--  Fluctuations in foreign currency exchange rates; and 
--  Global financial conditions. 

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to no material adverse change in the market price of commodities, that mining development and operations will operate in accordance with Mawson West's public statements and achieve their stated outcomes, and such other assumptions and factors as set out herein. Although Mawson West has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate. Accordingly, readers should not place undue reliance on forward-looking statements. Mawson West disclaims any intent or obligations to update or revise publicly any forward-looking statements whether as a result of new information, estimates or options, future events or results or otherwise, unless required to do so by law.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of the content of this press release.

Contacts:
Mawson West Limited
Bruce McFadzean
Chief Executive Officer and Managing Director
+61 8 9485 9800
+61 8 9486 8857 (FAX)
[email protected]

Mawson West Limited
Anthony Lloyd
Non-Executive Chairman
+1 647 233 7999
[email protected]

Media:
MAGNUS Investor Relations + Corporate Communication
Dudley White
+61 2 8999 1002
[email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Enterprise architects are increasingly adopting multi-cloud strategies as they seek to utilize existing data center assets, leverage the advantages of cloud computing and avoid cloud vendor lock-in. This requires a globally aware traffic management strategy that can monitor infrastructure health across data centers and end-user experience globally, while responding to control changes and system specification at the speed of today’s DevOps teams. In his session at 20th Cloud Expo, Josh Gray, Chie...
To get the most out of their data, successful companies are not focusing on queries and data lakes, they are actively integrating analytics into their operations with a data-first application development approach. Real-time adjustments to improve revenues, reduce costs, or mitigate risk rely on applications that minimize latency on a variety of data sources. Jack Norris reviews best practices to show how companies develop, deploy, and dynamically update these applications and how this data-first...
Intelligent Automation is now one of the key business imperatives for CIOs and CISOs impacting all areas of business today. In his session at 21st Cloud Expo, Brian Boeggeman, VP Alliances & Partnerships at Ayehu, will talk about how business value is created and delivered through intelligent automation to today’s enterprises. The open ecosystem platform approach toward Intelligent Automation that Ayehu delivers to the market is core to enabling the creation of the self-driving enterprise.
"At the keynote this morning we spoke about the value proposition of Nutanix, of having a DevOps culture and a mindset, and the business outcomes of achieving agility and scale, which everybody here is trying to accomplish," noted Mark Lavi, DevOps Solution Architect at Nutanix, in this SYS-CON.tv interview at @DevOpsSummit at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
"We're here to tell the world about our cloud-scale infrastructure that we have at Juniper combined with the world-class security that we put into the cloud," explained Lisa Guess, VP of Systems Engineering at Juniper Networks, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
Historically, some banking activities such as trading have been relying heavily on analytics and cutting edge algorithmic tools. The coming of age of powerful data analytics solutions combined with the development of intelligent algorithms have created new opportunities for financial institutions. In his session at 20th Cloud Expo, Sebastien Meunier, Head of Digital for North America at Chappuis Halder & Co., discussed how these tools can be leveraged to develop a lasting competitive advantage ...
In his session at 20th Cloud Expo, Mike Johnston, an infrastructure engineer at Supergiant.io, discussed how to use Kubernetes to set up a SaaS infrastructure for your business. Mike Johnston is an infrastructure engineer at Supergiant.io with over 12 years of experience designing, deploying, and maintaining server and workstation infrastructure at all scales. He has experience with brick and mortar data centers as well as cloud providers like Digital Ocean, Amazon Web Services, and Rackspace. H...
The question before companies today is not whether to become intelligent, it’s a question of how and how fast. The key is to adopt and deploy an intelligent application strategy while simultaneously preparing to scale that intelligence. In her session at 21st Cloud Expo, Sangeeta Chakraborty, Chief Customer Officer at Ayasdi, will provide a tactical framework to become a truly intelligent enterprise, including how to identify the right applications for AI, how to build a Center of Excellence to ...
You know you need the cloud, but you’re hesitant to simply dump everything at Amazon since you know that not all workloads are suitable for cloud. You know that you want the kind of ease of use and scalability that you get with public cloud, but your applications are architected in a way that makes the public cloud a non-starter. You’re looking at private cloud solutions based on hyperconverged infrastructure, but you’re concerned with the limits inherent in those technologies.
SYS-CON Events announced today that Massive Networks will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Massive Networks mission is simple. To help your business operate seamlessly with fast, reliable, and secure internet and network solutions. Improve your customer's experience with outstanding connections to your cloud.
DevOps is under attack because developers don’t want to mess with infrastructure. They will happily own their code into production, but want to use platforms instead of raw automation. That’s changing the landscape that we understand as DevOps with both architecture concepts (CloudNative) and process redefinition (SRE). Rob Hirschfeld’s recent work in Kubernetes operations has led to the conclusion that containers and related platforms have changed the way we should be thinking about DevOps and...
As businesses adopt functionalities in cloud computing, it’s imperative that IT operations consistently ensure cloud systems work correctly – all of the time, and to their best capabilities. In his session at @BigDataExpo, Bernd Harzog, CEO and founder of OpsDataStore, presented an industry answer to the common question, “Are you running IT operations as efficiently and as cost effectively as you need to?” He then expounded on the industry issues he frequently came up against as an analyst, and ...
All organizations that did not originate this moment have a pre-existing culture as well as legacy technology and processes that can be more or less amenable to DevOps implementation. That organizational culture is influenced by the personalities and management styles of Executive Management, the wider culture in which the organization is situated, and the personalities of key team members at all levels of the organization. This culture and entrenched interests usually throw a wrench in the work...
SYS-CON Events announced today that Datera, that offers a radically new data management architecture, has been named "Exhibitor" of SYS-CON's 21st International Cloud Expo ®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Datera is transforming the traditional datacenter model through modern cloud simplicity. The technology industry is at another major inflection point. The rise of mobile, the Internet of Things, data storage and Big...
Given the popularity of the containers, further investment in the telco/cable industry is needed to transition existing VM-based solutions to containerized cloud native deployments. The networking architecture of the solution isolates the network traffic into different network planes (e.g., management, control, and media). This naturally makes support for multiple interfaces in container orchestration engines an indispensable requirement.