Welcome!

News Feed Item

Mawson West Provides Update and 2013 Outlook and Production Guidance

PERTH, AUSTRALIA -- (Marketwire) -- 01/31/13 -- Mawson West Limited (TSX:MWE) ("Mawson West" or "the Company") announces the following update and guidance on activities at its Dikulushi copper-silver mine and Kapulo copper project located in the Democratic Republic of Congo (DRC).

Highlights:

--  Successful ramp-up of Dikulushi open pit and achievement of steady state
    production of approximately 1,600 tonnes of copper per month 
    
--  Copper production from Dikulushi expected to be 20,000-22,000 tonnes in
    FY2013 
    
--  C1(1) costs at Dikulushi in FY2013 anticipated to be less than US$0.35
    per pound of copper produced 
    
--  Kapulo process plant commissioning targeted to commence in late 2013 
    
--  FY2013 exploration budget of approximately US$11 million across
    Dikulushi satellite deposits, Kapulo and Lufukwe 

Production Update

During Q4 2012, Mawson West completed the ramp-up of the Dikulushi open pit, with steady state production of approximately 1,600 tonnes of copper per month achieved in both December 2012 (1,584 tonnes) and January 2013 (approximately 1,600 tonnes). Mawson West expects to produce between 20,000 and 22,000 tonnes of copper in FY2013, with output of more than 4,500 tonnes of copper during Q1 FY2013. C1(1) costs in FY2013 are anticipated to be less than US$0.35 per pound of copper produced.

Development Update

Dikulushi

With the ramp-up of the Dikulushi open pit now complete, Mawson West has commenced studies of a potential underground mine at Dikulushi, where the high grade deposit remains open at depth, providing an opportunity to increase the life of the project. Phase 1 (mining of the upper levels of the measured resource) of these studies is scheduled to be completed during Q2 2013, with Phase 2 (mining of the deeper levels of the measured and indicated resource) scheduled to be completed during Q4 2013.

Mawson West believes that the Dikulushi underground and known satellite deposits provide opportunities to extend the life of the Dikulushi mine by up to four years.

Kapulo

Construction is continuing on a scaled back rate of expenditure at the Kapulo copper project, funded through a combination of existing cash and cash flow from the Dikulushi operation. Work on site is approximately 35% complete, with process plant commissioning targeted to commence in late 2013.

(1) C1 costs are direct cash operating costs per pound of copper produced, net of silver by-product credits.

The Company is also in the advanced stage of a design review and costing study of the Kapulo copper project, with the aim of optimizing the process flow sheet and capital costs. In addition, the Company has commenced a review of the mine design, cutback design and mine scheduling to include the Safari deposits in the mine plan.

Exploration Update

Exploration spending in FY2013 is budgeted to be approximately US$11 million as Mawson West intends to evaluate multiple near-mine and stand-alone exploration opportunities within its approximate 7,300 km2 license governed by the Dikulushi Mining Convention, including the work at the Dikulushi satellite deposits, Kapulo and Lufukwe.

In addition to work on the Dikulushi underground and Kapulo projects, Mawson West continues to evaluate a number of satellite targets within the areas governed by the Dikulushi Mining Convention that may support an extension of the current mine life. Resource extension drilling is continuing at Kazumbula, with a resource review expected mid-year. Similar work continues at Kabusanje with a maiden resource also anticipated in mid-2013. Drilling will recommence at Lufukwe during April 2013 following the wet season.

Mawson West Chief Executive Officer and Managing Director Bruce McFadzean said: "We continue to make progress towards our goal of establishing Mawson West as a sustainable, low cost copper producer from two operations by the end of 2013. In addition to the successful ramp-up at the Dikulushi open pit, we are continuing to explore the multiple near-mine and stand-alone opportunities that exist within our significant footprint in the DRC.

"With a new, experienced management team in place, and a history of operating successfully in the DRC, we are confident we will deliver on our stated targets."

About Mawson West

Mawson West is a copper and silver-focused resource company listed on the Toronto Stock Exchange (TSX) and based in Perth, Australia.

The Company's approximate 7,300km2 ground position in the Democratic Republic of Congo (DRC) contains Mawson West's two key projects, the Dikulushi copper-silver mine and the Kapulo copper project, as well as multiple near-mine and stand-alone exploration opportunities.

With existing cash and cash flow from the Dikulushi operation, Mawson West has the capacity to advance its exploration and development portfolio. In addition, the Company has assembled a proven management team with a track record of delivering new resources projects, as well as years of experience operating in Africa.

Forward-Looking Information

This press release contains "forward-looking information" that is based on Mawson West's expectations, estimates and projections as of the dates as of which those statements were made. This forward-looking information may include, among other things, statements with respect to the Company's business strategy, plans, outlook, financing plans, projections, targets and expectations as to reserves, resources, results of exploration (including targets) and related expenses, mine development, mine operations, mine production costs, drilling activity, sampling and other data, estimating grade levels, future recovery levels, future production levels, capital costs, costs savings, cash and total costs of production of copper, expenditures for environmental matters, projected life of Mawson West's mines, reclamation and other post closure obligations and estimated future expenditures for those matters, completion dates for the various development stages of mines, future copper prices (including the long-term estimated prices used in calculating Mawson West's mineral reserves), end-use demand for copper, currency exchange rates, timing of expected sales and final pricing of concentrate sales and anticipated timing of production at the Dikulushi mine and Kapulo project. Generally, this forward-looking information can be identified by the use of forward-looking terminology such as "outlook", "anticipate", "project", "target", "believe", "estimate", "expect", "intend", "should", "scheduled", "will", "plan" and similar expressions. Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause Mawson West's actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking information, and developed based on assumptions about such risks, uncertainties and other factors set out herein, including but not limited to:

--  Our ability to successfully bring the Kapulo project into production; 
--  Receipt of all permits required for the Kapulo project; 
--  The ability of our key contractors to perform the services for us in the
    manner contracted for; 
--  The availability and cost of key operating supplies and services; 
--  The production facilities may not achieve the planned desired
    recoveries; 
--  Fluctuations in copper prices; 
--  The ability to expand or replace depleted reserves and the possible
    recalculation or reduction of the reserves and resources; 
--  Actual capital costs, operating costs and expenditures, production
    schedules and economic returns from the Dikulushi mine or Kapulo
    project; 
--  Geotechnical issues; 
--  Inherent hazards and risks associated with mining operations; 
--  Inherent uncertainties associated with mineral exploration; 
--  Being subject to government regulation, including changes in regulation;
--  Being subject to extensive environmental laws and regulations, including
    change in regulation; 
--  Need for governmental licenses and permits; 
--  Political and country risk; 
--  Fluctuations in foreign currency exchange rates; and 
--  Global financial conditions. 

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to no material adverse change in the market price of commodities, that mining development and operations will operate in accordance with Mawson West's public statements and achieve their stated outcomes, and such other assumptions and factors as set out herein. Although Mawson West has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate. Accordingly, readers should not place undue reliance on forward-looking statements. Mawson West disclaims any intent or obligations to update or revise publicly any forward-looking statements whether as a result of new information, estimates or options, future events or results or otherwise, unless required to do so by law.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of the content of this press release.

Contacts:
Mawson West Limited
Bruce McFadzean
Chief Executive Officer and Managing Director
+61 8 9485 9800
+61 8 9486 8857 (FAX)
[email protected]

Mawson West Limited
Anthony Lloyd
Non-Executive Chairman
+1 647 233 7999
[email protected]

Media:
MAGNUS Investor Relations + Corporate Communication
Dudley White
+61 2 8999 1002
[email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Coca-Cola’s Google powered digital signage system lays the groundwork for a more valuable connection between Coke and its customers. Digital signs pair software with high-resolution displays so that a message can be changed instantly based on what the operator wants to communicate or sell. In their Day 3 Keynote at 21st Cloud Expo, Greg Chambers, Global Group Director, Digital Innovation, Coca-Cola, and Vidya Nagarajan, a Senior Product Manager at Google, will discuss how from store operations...
SYS-CON Events announced today that IBM has been named “Diamond Sponsor” of SYS-CON's 21st Cloud Expo, which will take place on October 31 through November 2nd 2017 at the Santa Clara Convention Center in Santa Clara, California.
SYS-CON Events announced today that Ryobi Systems will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Ryobi Systems Co., Ltd., as an information service company, specialized in business support for local governments and medical industry. We are challenging to achive the precision farming with AI. For more information, visit http:...
As you move to the cloud, your network should be efficient, secure, and easy to manage. An enterprise adopting a hybrid or public cloud needs systems and tools that provide: Agility: ability to deliver applications and services faster, even in complex hybrid environments Easier manageability: enable reliable connectivity with complete oversight as the data center network evolves Greater efficiency: eliminate wasted effort while reducing errors and optimize asset utilization Security: imple...
High-velocity engineering teams are applying not only continuous delivery processes, but also lessons in experimentation from established leaders like Amazon, Netflix, and Facebook. These companies have made experimentation a foundation for their release processes, allowing them to try out major feature releases and redesigns within smaller groups before making them broadly available. In his session at 21st Cloud Expo, Brian Lucas, Senior Staff Engineer at Optimizely, will discuss how by using...
The next XaaS is CICDaaS. Why? Because CICD saves developers a huge amount of time. CD is an especially great option for projects that require multiple and frequent contributions to be integrated. But… securing CICD best practices is an emerging, essential, yet little understood practice for DevOps teams and their Cloud Service Providers. The only way to get CICD to work in a highly secure environment takes collaboration, patience and persistence. Building CICD in the cloud requires rigorous ar...
Transforming cloud-based data into a reportable format can be a very expensive, time-intensive and complex operation. As a SaaS platform with more than 30 million global users, Cornerstone OnDemand’s challenge was to create a scalable solution that would improve the time it took customers to access their user data. Our Real-Time Data Warehouse (RTDW) process vastly reduced data time-to-availability from 24 hours to just 10 minutes. In his session at 21st Cloud Expo, Mark Goldin, Chief Technolo...
In this strange new world where more and more power is drawn from business technology, companies are effectively straddling two paths on the road to innovation and transformation into digital enterprises. The first path is the heritage trail – with “legacy” technology forming the background. Here, extant technologies are transformed by core IT teams to provide more API-driven approaches. Legacy systems can restrict companies that are transitioning into digital enterprises. To truly become a lead...
SYS-CON Events announced today that CAST Software will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CAST was founded more than 25 years ago to make the invisible visible. Built around the idea that even the best analytics on the market still leave blind spots for technical teams looking to deliver better software and prevent outages, CAST provides the software intelligence that matter ...
SYS-CON Events announced today that Daiya Industry will exhibit at the Japanese Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Ruby Development Inc. builds new services in short period of time and provides a continuous support of those services based on Ruby on Rails. For more information, please visit https://github.com/RubyDevInc.
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busine...
Is advanced scheduling in Kubernetes achievable? Yes, however, how do you properly accommodate every real-life scenario that a Kubernetes user might encounter? How do you leverage advanced scheduling techniques to shape and describe each scenario in easy-to-use rules and configurations? In his session at @DevOpsSummit at 21st Cloud Expo, Oleg Chunikhin, CTO at Kublr, will answer these questions and demonstrate techniques for implementing advanced scheduling. For example, using spot instances ...
As businesses evolve, they need technology that is simple to help them succeed today and flexible enough to help them build for tomorrow. Chrome is fit for the workplace of the future — providing a secure, consistent user experience across a range of devices that can be used anywhere. In her session at 21st Cloud Expo, Vidya Nagarajan, a Senior Product Manager at Google, will take a look at various options as to how ChromeOS can be leveraged to interact with people on the devices, and formats th...
First generation hyperconverged solutions have taken the data center by storm, rapidly proliferating in pockets everywhere to provide further consolidation of floor space and workloads. These first generation solutions are not without challenges, however. In his session at 21st Cloud Expo, Wes Talbert, a Principal Architect and results-driven enterprise sales leader at NetApp, will discuss how the HCI solution of tomorrow will integrate with the public cloud to deliver a quality hybrid cloud e...
SYS-CON Events announced today that Yuasa System will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Yuasa System is introducing a multi-purpose endurance testing system for flexible displays, OLED devices, flexible substrates, flat cables, and films in smartphones, wearables, automobiles, and healthcare.