McEwen Mining Inc.: Lower Metal Prices and Higher Cost of Capital Drives Decision to Reduce Forecast Production Growth from 290,000 to 225,000 Gold Equivalent Oz in 2016

Capital Requirements Now Significantly Reduced; Los Azules Sale Deferred

TORONTO, ONTARIO -- (Marketwired) -- 06/10/13 -- McEwen Mining Inc. (NYSE:MUX)(TSX:MUX) announces a reduction to its forecasted production growth from 290,000 to 225,000 gold equivalent oz in 2016. Consequently, our capital requirements have been significantly reduced to a point that our cash reserves and cash flow from operations could be sufficient to fund the majority of our revised production growth.

How we have changed our production growth:

El Gallo 1 is being expanded for an estimated capex of $5 million with an expectation of producing 75,000 oz gold in 2016; we expect Gold Bar to be permitted in late 2014/early 2015, built in 2015 and up and running in 2016 at a rate of 50,000 oz gold per year; and our 49% owned San Jose contributing 100,000 oz gold equivalent for total Company production of 225,000 oz gold equivalent in 2016.

We have begun to re-evaluate El Gallo 2 as a heap leach operation rather than a conventional milling situation. Preliminary column testing results on ore recovery are encouraging and if further test work and bulk sampling are conclusive, then El Gallo 2 will be developed as a heap leach operation. The resultant capital cost reduction for El Gallo 2 would be considerable, from an estimated $180 million for a milling process, to $20-$30 million for a heap leach. The impact on IRR is dramatic because we would use less than 20% of the original capital to generate 60% of former forecasted production.

If the El Gallo 2 heap leach process works, then its projected production could add an additional 60,000 gold equivalent oz, and thus increase total Company production to 285,000 in 2016. This revised total production number would be very close to our original forecast of 290,000 oz in 2015. The metallurgical testing of El Gallo 2 ore should be completed by the 4th Quarter of this year and should coincide with the expected receipt of our permits to mine from the Mexican government.

As a result of our lower capital requirements, the rationale for selling Los Azules has effectively been eliminated. As a result, Los Azules has been removed from the sale process, which began in January. Los Azules is a significant copper deposit that we believe will command a better price in the future.

"Lower gold and silver prices have reduced our cash flow and the projected IRRs on our development projects and increased the cost of capital. As a consequence, we had to re-assess our development plans and look at alternatives to avoid excessive dilution at current market prices. Fortunately, we have developed alternatives that our cash reserves and cash flow from operations would allow us to develop and fund largely from internal sources with limited use of very expensive outside capital. Another very positive aspect of this alternative course is the potential for a significant increase in the IRR of El Gallo 2. Clearly, adversity is the mother of invention," said Rob McEwen, Chairman & Chief Owner.

About McEwen Mining (www.mcewenmining.com)

The goal of McEwen Mining is to qualify for inclusion in the S&P 500 by creating a profitable, mid-tier gold producer focused in the Americas. McEwen Mining's principal assets consist of the San Jose Mine in Santa Cruz, Argentina (49% interest); the El Gallo Complex in Sinaloa, Mexico; the Gold Bar Project in Nevada, US and the Los Azules Project in San Juan, Argentina.

McEwen Mining has 297 million shares issued and outstanding. Rob McEwen, Chairman, President and Chief Owner, owns 25% of the shares of the Company (assuming all outstanding Exchangeable Shares are exchanged for an equivalent amount of Common Shares). As of April 30, 2013, McEwen Mining had cash and liquid assets of approximately US$50 million and is debt free.

TECHNICAL INFORMATION AND RISKS

There are significant risks and uncertainty associated with commencing production or changing production plans without a feasibility, pre-feasibility or scoping study. The proposed expansion to El Gallo Phase 1 and the changes to the existing El Gallo 2 production plans have not and may not be explored, developed or analyzed in sufficient detail to complete an independent feasibility or pre-feasibility study and may ultimately be determined to lack one or more geological, engineering, legal, operating, economic, social, environmental, and other relevant factors reasonably required to serve as the basis for a final decision to complete the development of all or part of these projects.

This news release has been reviewed and approved by William Faust, PE, McEwen Mining's Chief Operating Officer, who is a Qualified Person as defined by National Instrument 43-101. For additional information about El Gallo Phase 2 see the technical report titled "El Gallo Complex Phase II project, NI 43-101 Technical Report Feasibility Study, Mocorito Municipality, Sinaloa, Mexico" with an effective date of September 10, 2012, prepared by M3 Engineering along with a team of associates (the "Phase II Report"). The authors of the Phase 2 Report, Stan Timler - M3 Engineering, Mike Hester - Independent Mining Consultants (Reserves), Dawn Garcia - SRK Consulting (Environmental), Richard Kehmeier and Brian Hartman - Pincock Allen & Holt (El Gallo Deposit Resource), John Read - McEwen Mining consultant (Palmarito Insitu, Historic Waste Dumps and Historic tailings Resource), are each qualified persons and all of whom but John Read are independent of McEwen Mining, each as defined by NI 43-101.

CAUTIONARY NOTE TO US INVESTORS

McEwen Mining prepares its resource estimates in accordance with standards of the Canadian Institute of Mining, Metallurgy and Petroleum referred to in Canadian National Instrument 43-101 (NI 43-101). These standards are different from the standards generally permitted in reports filed with the SEC. Under NI 43-101, McEwen Mining reports measured, indicated and inferred resources, measurements which are generally not permitted in filings made with the SEC. The estimation of measured resources and indicated resources involve greater uncertainty as to their existence and economic feasibility than the estimation of proven and probable reserves. U.S. investors are cautioned not to assume that any part of measured or indicated resources will ever be converted into economically mineable reserves. The estimation of inferred resources involves far greater uncertainty as to their existence and economic viability than the estimation of other categories of resources.

CAUTION CONCERNING FORWARD-LOOKING STATEMENTS

This news release contains certain forward-looking statements and information, including "forward-looking statements" within the meaning of the Private Securities Litigation Reform Act of 1995. The forward-looking statements and information expressed, as at the date of this news release, McEwen Mining Inc.'s (the "Company") estimates, forecasts, projections, expectations or beliefs as to future events and results. Forward-looking statements and information are necessarily based upon a number of estimates and assumptions that, while considered reasonable by management, are inherently subject to significant business, technical, economic and competitive uncertainties, risks and contingencies, and there can be no assurance that such statements and information will prove to be accurate. Therefore, actual results and future events could differ materially from those anticipated in such statements and information. Risks and uncertainties that could cause results or future events to differ materially from current expectations expressed or implied by the forward-looking statements and information include, but are not limited to, factors associated with fluctuations in the market price of precious metals, mining industry risks, political, economic, social, technical and security risks associated with foreign operations, risks associated with the construction of mining operations and commencement of production and the projected costs thereof, risks related to litigation, the state of the capital markets, environmental risks and hazards, uncertainty as to calculation of mineral resources and reserves, projected permitting timelines and other risks. Readers should not place undue reliance on forward-looking statements or information included herein, which speak only as of the date hereof. The Company undertakes no obligation to reissue or update forward-looking statements or information as a result of new information or events after the date hereof except as may be required by law. See McEwen Mining's Annual Report on Form 10-K for the fiscal year ended December 31, 2012 and other filings with the Securities and Exchange Commission, under the caption "Risk Factors", for additional information on risks, uncertainties and other factors relating to the forward-looking statements and information regarding the Company. All forward-looking statements and information made in this news release are qualified by this cautionary statement.

The NYSE and TSX have not reviewed and do not accept responsibility for the adequacy or accuracy of the contents of this news release, which has been prepared by management of McEwen Mining Inc.

Contacts:
McEwen Mining Inc.
Jenya Meshcheryakova
Investor Relations
(647) 258-0395 ext 410 or Toll Free: (866) 441-0690
(647) 258-0408 (FAX)

Facebook: www.facebook.com/mcewenrob
Twitter: www.twitter.com/mcewenmining
Store: www.mcewenmining.com/store

Mailing Address
181 Bay Street Suite 4750
Toronto, ON M5J 2T3
PO box 792
[email protected]
www.mcewenmining.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
In his session at 21st Cloud Expo, Raju Shreewastava, founder of Big Data Trunk, provided a fun and simple way to introduce Machine Leaning to anyone and everyone. He solved a machine learning problem and demonstrated an easy way to be able to do machine learning without even coding. Raju Shreewastava is the founder of Big Data Trunk (www.BigDataTrunk.com), a Big Data Training and consulting firm with offices in the United States. He previously led the data warehouse/business intelligence and B...
In his keynote at 18th Cloud Expo, Andrew Keys, Co-Founder of ConsenSys Enterprise, provided an overview of the evolution of the Internet and the Database and the future of their combination – the Blockchain. Andrew Keys is Co-Founder of ConsenSys Enterprise. He comes to ConsenSys Enterprise with capital markets, technology and entrepreneurial experience. Previously, he worked for UBS investment bank in equities analysis. Later, he was responsible for the creation and distribution of life settle...
No hype cycles or predictions of a gazillion things here. IoT is here. You get it. You know your business and have great ideas for a business transformation strategy. What comes next? Time to make it happen. In his session at @ThingsExpo, Jay Mason, an Associate Partner of Analytics, IoT & Cybersecurity at M&S Consulting, presented a step-by-step plan to develop your technology implementation strategy. He also discussed the evaluation of communication standards and IoT messaging protocols, data...
Smart cities have the potential to change our lives at so many levels for citizens: less pollution, reduced parking obstacles, better health, education and more energy savings. Real-time data streaming and the Internet of Things (IoT) possess the power to turn this vision into a reality. However, most organizations today are building their data infrastructure to focus solely on addressing immediate business needs vs. a platform capable of quickly adapting emerging technologies to address future ...
In his general session at 21st Cloud Expo, Greg Dumas, Calligo’s Vice President and G.M. of US operations, discussed the new Global Data Protection Regulation and how Calligo can help business stay compliant in digitally globalized world. Greg Dumas is Calligo's Vice President and G.M. of US operations. Calligo is an established service provider that provides an innovative platform for trusted cloud solutions. Calligo’s customers are typically most concerned about GDPR compliance, application p...
You know you need the cloud, but you’re hesitant to simply dump everything at Amazon since you know that not all workloads are suitable for cloud. You know that you want the kind of ease of use and scalability that you get with public cloud, but your applications are architected in a way that makes the public cloud a non-starter. You’re looking at private cloud solutions based on hyperconverged infrastructure, but you’re concerned with the limits inherent in those technologies.
Is advanced scheduling in Kubernetes achievable?Yes, however, how do you properly accommodate every real-life scenario that a Kubernetes user might encounter? How do you leverage advanced scheduling techniques to shape and describe each scenario in easy-to-use rules and configurations? In his session at @DevOpsSummit at 21st Cloud Expo, Oleg Chunikhin, CTO at Kublr, answered these questions and demonstrated techniques for implementing advanced scheduling. For example, using spot instances and co...
Blockchain. A day doesn’t seem to go by without seeing articles and discussions about the technology. According to PwC executive Seamus Cushley, approximately $1.4B has been invested in blockchain just last year. In Gartner’s recent hype cycle for emerging technologies, blockchain is approaching the peak. It is considered by Gartner as one of the ‘Key platform-enabling technologies to track.’ While there is a lot of ‘hype vs reality’ discussions going on, there is no arguing that blockchain is b...
DevOps is under attack because developers don’t want to mess with infrastructure. They will happily own their code into production, but want to use platforms instead of raw automation. That’s changing the landscape that we understand as DevOps with both architecture concepts (CloudNative) and process redefinition (SRE). Rob Hirschfeld’s recent work in Kubernetes operations has led to the conclusion that containers and related platforms have changed the way we should be thinking about DevOps and...
The need for greater agility and scalability necessitated the digital transformation in the form of following equation: monolithic to microservices to serverless architecture (FaaS). To keep up with the cut-throat competition, the organisations need to update their technology stack to make software development their differentiating factor. Thus microservices architecture emerged as a potential method to provide development teams with greater flexibility and other advantages, such as the abili...
Product connectivity goes hand and hand these days with increased use of personal data. New IoT devices are becoming more personalized than ever before. In his session at 22nd Cloud Expo | DXWorld Expo, Nicolas Fierro, CEO of MIMIR Blockchain Solutions, will discuss how in order to protect your data and privacy, IoT applications need to embrace Blockchain technology for a new level of product security never before seen - or needed.
Leading companies, from the Global Fortune 500 to the smallest companies, are adopting hybrid cloud as the path to business advantage. Hybrid cloud depends on cloud services and on-premises infrastructure working in unison. Successful implementations require new levels of data mobility, enabled by an automated and seamless flow across on-premises and cloud resources. In his general session at 21st Cloud Expo, Greg Tevis, an IBM Storage Software Technical Strategist and Customer Solution Architec...
Coca-Cola’s Google powered digital signage system lays the groundwork for a more valuable connection between Coke and its customers. Digital signs pair software with high-resolution displays so that a message can be changed instantly based on what the operator wants to communicate or sell. In their Day 3 Keynote at 21st Cloud Expo, Greg Chambers, Global Group Director, Digital Innovation, Coca-Cola, and Vidya Nagarajan, a Senior Product Manager at Google, discussed how from store operations and ...
"As we've gone out into the public cloud we've seen that over time we may have lost a few things - we've lost control, we've given up cost to a certain extent, and then security, flexibility," explained Steve Conner, VP of Sales at Cloudistics,in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
Blockchain is a shared, secure record of exchange that establishes trust, accountability and transparency across business networks. Supported by the Linux Foundation's open source, open-standards based Hyperledger Project, Blockchain has the potential to improve regulatory compliance, reduce cost as well as advance trade. Are you curious about how Blockchain is built for business? In her session at 21st Cloud Expo, René Bostic, Technical VP of the IBM Cloud Unit in North America, discussed the b...