Lucara Diamond Provides Operating Outlook for 2014

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 01/13/14 -- (TSX:LUC)(BOTSWANA:LUC)(NASDAQ OMX First North:LUC) Lucara Diamond Corp. ("Lucara" or the "Company") is pleased to provide operating performance and capital expenditure guidance for 2014. Key operational estimates are as follows:


--  Revenue of $150 to $160 million is expected from the sale of 400,000 to
    420,000 carats of diamonds in 2014, including the assumption that the
    Company will have two exceptional stone tenders. 
--  Karowe operating cash costs are expected to be between $31-$33 per tonne
    treated. 
--  Mining is forecast at 3.0-3.5 million tonnes of kimberlite of which it
    is anticipated that 2.2-2.4 million tonnes will be processed through the
    plant with the remainder being stockpiled. 
--  Waste mining is scheduled to be approximately 10.0-11.0 million tonnes. 
--  Building and commissioning of a plant upgrade at Karowe to improve large
    diamond recovery following continued occurrence of exceptional stones
    and to enable sustainable processing of harder ore in the south lobe.
    This is forecast at an expenditure of $45-$50 million.  
--  Sustaining capital expenditure of $3.5 million is expected. 

William Lamb, President and Chief Executive Officer, commented, "Lucara had a strong year in 2013, achieving its production and operating cost targets and exceeding forecast revenues following the recovery of a high proportion of large exceptional quality diamonds during the year.

In 2014 it is expected that the scheduled plant upgrade, largely funded from the Company's 2013 year end cash balance will be completed and brought online to deliver sustainable diamond recovery for production of 2.5 million tonnes per annum for the remainder of the mine life. This upgrade will also include processes to ensure the safe recovery of the value driving large and exceptional diamonds of Karowe.

The Company is focused on building on its strong financial position through operational optimization and focused cost management. "

Production and Cost Outlook:


----------------------------------------------------------------------------
Karowe Mine                                                   Full Year 2014
----------------------------------------------------------------------------
Ore tonnes mined (million)                                         3.0 - 3.5
----------------------------------------------------------------------------
Waste tonnes mined (million)                                     10.0 - 11.0
----------------------------------------------------------------------------
Ore tonnes treated (million)                                       2.2 - 2.4
----------------------------------------------------------------------------
Carats recovered (thousands)                                       400 - 420
----------------------------------------------------------------------------
Ore treated costs ($ per tonne)                                $31.0 - $33.0
----------------------------------------------------------------------------
Ore treated costs excluding waste ($ per tonne)                $22.0 - $23.0
----------------------------------------------------------------------------
Ore mined cash costs ($ per tonne)                             $3.20 - $3.30
----------------------------------------------------------------------------
Waste mined cash costs ($ per tonne)                          $3.15 - $ 3.20
----------------------------------------------------------------------------
Processing cash costs ($ per tonne milled)                       9.00 - 9.20
----------------------------------------------------------------------------
General and Administration Costs ($ per tonne                               
 milled). Costs include (security, health and                               
 safety, engineering, onsite administration).                   $2.9 - $3.10
----------------------------------------------------------------------------
All In cash operating costs ($ per tonne milled)             $31.00 - $33.00
----------------------------------------------------------------------------

Production

The Karowe Mine is forecast to treat between 2.2-2.4 million tonnes of ore, producing over 400,000 carats of diamonds, which is in line with the 2013 forecast production. The plant throughput is constrained as downtime is scheduled to enable integration and commissioning of the new large diamond recovery and crushing circuits. The forecast for tonnes treated per annum returns to 2.5 million in 2015. Financial analysis has indicated that a treatment rate of 2.5 million tonnes per annum is optimal for the remaining mine life.

Karowe is forecast to increase waste mined during 2014, in line with the original feasibility mine plan, as it opens up the full extent of the South lobe. The Karowe mine plan, therefore, expects more that 10 million tonnes of waste will be stripped and stockpiled or used to expand the tailings in 2014.

2014 Cash Costs

Cash costs per tonne of ore treated is forecast to be between $31-$33 per tonne as compared to 2013 forecast of $23 per tonne. The forecast increase in operating cash costs is largely due to the additional 4.5 million tonnes of waste mined during the year.

Processing costs are also forecast to be marginally higher following the change to the process plant facilities to improve large diamond recovery and process harder material from the south lobe.

2014 Capital Expenditure Guidance

The Karowe Mine has been in production since May 2012 and has conducted mining and processing operations broadly in line with the feasibility study. As of December 2013 there have been 5.5 million tonnes of waste removed to allow for the extraction of 3.9 million tonnes of ore, 2.4 million tonnes of which were processed, yielding 441,000 carats of diamonds. A total of 439,000 carats have been sold in 2013 with year end inventory of 67,000 carats of diamonds. The remaining, low-grade ore, has been stockpiled for treatment at the end of mine life.

The early stage mining and processing has been predominantly weathered ore (near the surface) but as the mine gets deeper, harder, more competent primary kimberlite ore is exposed. During 2014 the weathered ore will be depleted and the process plant feed will transition from weathered ore to competent, primary kimberlite ore. As discussed in the AK6 43-101 dated December 31, 2010, and estimated in the life-of-mine financial model, plant modifications (additional crushing capacity) are required to ensure that the annual tonnage treated is maintained, as the primary kimberlite requires more energy to crush or mill to liberate the diamonds.

During 2013 tests were conducted on site and at metallurgical laboratories to verify the ore treatment assumptions from the feasibility study. Subsequently, engineering studies have been completed to identify the most effective and cost efficient solution to process the ore.

A further development during 2013 was the recovery of large, exceptional quality, diamonds - a development which greatly enhanced the value of the Karowe asset. Since these diamonds were not predicted during the evaluation of the project, the initial process plant design at Karowe did not specifically allow for their effective recovery. Some minor, temporary, modifications were conducted during the year but it was highlighted that a sustainable solution was critical to ensure the safe recovery of these large, high value, diamonds. During 2014, as part of the plant modifications, an enhanced large diamond recovery circuit is planned for construction and commissioning.

Construction is scheduled to begin in Q1 2014 with completion scheduled for Q4 at a projected cost of between $45-$50 million.

Sustaining capital expenditure is forecast to be approximately $3.5 million.

These expenditures will be largely funded from the Company's 2013 year end cash balance, with the remainder funded from forecast 2014 cash flows. Net cash position as of 31 December 2013 was approximately $40 million. The Company's Scotiabank $25 million credit facility was undrawn at year end.

Resource Update

As a result of the continued recovery of large and exceptional stones at Karowe, the Company completed, and announced on December 19, 2013, a resource update and is expecting to release a revised NI 43-101 during the first quarter 2014.

CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS

Certain of the statements made and contained herein constitute forward-looking statements as defined in applicable securities laws. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "expects", "anticipates", "believes", "intends", "estimates", "potential", "possible" and similar expressions, or statements that events, conditions or results "will", "may", "could" or "should" occur or be achieved.

Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to a number of known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievement expressed or implied by such forward-looking statements. The Company believes that expectations reflected in this forward-looking information are reasonable but no assurance can be given that these expectations will prove to be correct and such forward-looking information included in this release should not be unduly relied upon. In particular, this release may contain forward looking information pertaining to the following: the estimates of the Company's mineral reserve and resources; estimates of the Company's production and sales volumes for the Karowe Mine;, production costs; expectation of diamond price and changes to foreign currency exchange rate; expectations regarding the need to raise capital; possible impacts of disputes or litigation and other risks and uncertainties described under Risks and Uncertainties disclosed in the Company's Annual Information Form.

There can be no assurance that such statements will prove to be accurate, as the Company's results and future events could differ materially from those anticipated in this forward-looking information as a result of those factors discussed in or referred to under the heading "Risk Factors' in the Company's Annual Information Form dated March 27, 2013 available at http://www.sedar.com, as well as changes in general business and economic conditions, changes in interest and foreign currency rates, the supply and demand for, deliveries of and the level and volatility of prices of rough diamonds, costs of power and diesel, acts of foreign governments and the outcome of legal proceedings, inaccurate geological and recoverability assumptions (including with respect to the size, grade and recoverability of mineral reserves and resources), unanticipated operational difficulties (including failure of plant, equipment or processes to operate in accordance with specifications or expectations, cost escalations, unavailability of materials and equipment, government action or delays in the receipt of government approvals, industrial disturbances or other job actions, adverse weather conditions, and unanticipated events relating to health safety and environmental matters)

Accordingly, readers are cautioned not to place undue reliance on these forward-looking statements which speak only as of the date the statements were made, and the Company does not assume any obligations to update or revise them to reflect new events or circumstances, except as required by law.

Contacts:
Lucara Diamond Corp.
604 689 7842
604 689 4250 (FAX)
lucara@namdo.com
www.lucaradiamond.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that Synametrics Technologies will exhibit at SYS-CON's 22nd International Cloud Expo®, which will take place on June 5-7, 2018, at the Javits Center in New York, NY. Synametrics Technologies is a privately held company based in Plainsboro, New Jersey that has been providing solutions for the developer community since 1997. Based on the success of its initial product offerings such as WinSQL, Xeams, SynaMan and Syncrify, Synametrics continues to create and hone inn...
Cloud Expo | DXWorld Expo have announced the conference tracks for Cloud Expo 2018. Cloud Expo will be held June 5-7, 2018, at the Javits Center in New York City, and November 6-8, 2018, at the Santa Clara Convention Center, Santa Clara, CA. Digital Transformation (DX) is a major focus with the introduction of DX Expo within the program. Successful transformation requires a laser focus on being data-driven and on using all the tools available that enable transformation if they plan to survive ov...
A strange thing is happening along the way to the Internet of Things, namely far too many devices to work with and manage. It has become clear that we'll need much higher efficiency user experiences that can allow us to more easily and scalably work with the thousands of devices that will soon be in each of our lives. Enter the conversational interface revolution, combining bots we can literally talk with, gesture to, and even direct with our thoughts, with embedded artificial intelligence, whic...
To get the most out of their data, successful companies are not focusing on queries and data lakes, they are actively integrating analytics into their operations with a data-first application development approach. Real-time adjustments to improve revenues, reduce costs, or mitigate risk rely on applications that minimize latency on a variety of data sources. In his session at @BigDataExpo, Jack Norris, Senior Vice President, Data and Applications at MapR Technologies, reviewed best practices to ...
Continuous Delivery makes it possible to exploit findings of cognitive psychology and neuroscience to increase the productivity and happiness of our teams. In his session at 22nd Cloud Expo | DXWorld Expo, Daniel Jones, CTO of EngineerBetter, will answer: How can we improve willpower and decrease technical debt? Is the present bias real? How can we turn it to our advantage? Can you increase a team’s effective IQ? How do DevOps & Product Teams increase empathy, and what impact does empath...
DevOps promotes continuous improvement through a culture of collaboration. But in real terms, how do you: Integrate activities across diverse teams and services? Make objective decisions with system-wide visibility? Use feedback loops to enable learning and improvement? With technology insights and real-world examples, in his general session at @DevOpsSummit, at 21st Cloud Expo, Andi Mann, Chief Technology Advocate at Splunk, explored how leading organizations use data-driven DevOps to close th...
As many know, the first generation of Cloud Management Platform (CMP) solutions were designed for managing virtual infrastructure (IaaS) and traditional applications. But that's no longer enough to satisfy evolving and complex business requirements. In his session at 21st Cloud Expo, Scott Davis, Embotics CTO, explored how next-generation CMPs ensure organizations can manage cloud-native and microservice-based application architectures, while also facilitating agile DevOps methodology. He expla...
Smart cities have the potential to change our lives at so many levels for citizens: less pollution, reduced parking obstacles, better health, education and more energy savings. Real-time data streaming and the Internet of Things (IoT) possess the power to turn this vision into a reality. However, most organizations today are building their data infrastructure to focus solely on addressing immediate business needs vs. a platform capable of quickly adapting emerging technologies to address future ...
With tough new regulations coming to Europe on data privacy in May 2018, Calligo will explain why in reality the effect is global and transforms how you consider critical data. EU GDPR fundamentally rewrites the rules for cloud, Big Data and IoT. In his session at 21st Cloud Expo, Adam Ryan, Vice President and General Manager EMEA at Calligo, examined the regulations and provided insight on how it affects technology, challenges the established rules and will usher in new levels of diligence arou...
Most technology leaders, contemporary and from the hardware era, are reshaping their businesses to do software. They hope to capture value from emerging technologies such as IoT, SDN, and AI. Ultimately, irrespective of the vertical, it is about deriving value from independent software applications participating in an ecosystem as one comprehensive solution. In his session at @ThingsExpo, Kausik Sridhar, founder and CTO of Pulzze Systems, discussed how given the magnitude of today's application ...
There is a huge demand for responsive, real-time mobile and web experiences, but current architectural patterns do not easily accommodate applications that respond to events in real time. Common solutions using message queues or HTTP long-polling quickly lead to resiliency, scalability and development velocity challenges. In his session at 21st Cloud Expo, Ryland Degnan, a Senior Software Engineer on the Netflix Edge Platform team, will discuss how by leveraging a reactive stream-based protocol,...
Mobile device usage has increased exponentially during the past several years, as consumers rely on handhelds for everything from news and weather to banking and purchases. What can we expect in the next few years? The way in which we interact with our devices will fundamentally change, as businesses leverage Artificial Intelligence. We already see this taking shape as businesses leverage AI for cost savings and customer responsiveness. This trend will continue, as AI is used for more sophistica...
In his session at 21st Cloud Expo, Raju Shreewastava, founder of Big Data Trunk, provided a fun and simple way to introduce Machine Leaning to anyone and everyone. He solved a machine learning problem and demonstrated an easy way to be able to do machine learning without even coding. Raju Shreewastava is the founder of Big Data Trunk (www.BigDataTrunk.com), a Big Data Training and consulting firm with offices in the United States. He previously led the data warehouse/business intelligence and B...
In his general session at 21st Cloud Expo, Greg Dumas, Calligo’s Vice President and G.M. of US operations, discussed the new Global Data Protection Regulation and how Calligo can help business stay compliant in digitally globalized world. Greg Dumas is Calligo's Vice President and G.M. of US operations. Calligo is an established service provider that provides an innovative platform for trusted cloud solutions. Calligo’s customers are typically most concerned about GDPR compliance, application p...
Digital transformation is about embracing digital technologies into a company's culture to better connect with its customers, automate processes, create better tools, enter new markets, etc. Such a transformation requires continuous orchestration across teams and an environment based on open collaboration and daily experiments. In his session at 21st Cloud Expo, Alex Casalboni, Technical (Cloud) Evangelist at Cloud Academy, explored and discussed the most urgent unsolved challenges to achieve f...