AuRico Gold Announces Preliminary Fourth Quarter Operational Results

TORONTO, January 14, 2014 /PRNewswire/ --

- Reports Sixth Consecutive Quarter of Production Growth

- $ are US

AuRico Gold Inc. (TSX: AUQ) (NYSE: AUQ), ("AuRico" or the "Company") today announces preliminary fourth quarter and annual operational results. All amounts are in U.S. dollars unless otherwise indicated.

AuRico reported its sixth consecutive quarter of production growth, with the Young-Davidson and El Chanate operations continuing to report solid production results that are in-line with expectations.

AuRico Gold Company-wide Production Growth

The shaft hoisting infrastructure at the Young-Davidson underground mine was commissioned in October, which facilitated the declaration of commercial production on October 31. The shaft hoisting system has, and will continue to, facilitate significant increases in underground productivities and corresponding cost efficiency improvements. During the first two months of commercial production, underground unit mining costs were approximately $39 per tonne resulting in underground production cash costs of $663 per ounce.

Preliminary 2013 Fourth Quarter Operational Results

                                                      Year-end
                                                        Dec.
                            Q1     Q2     Q3     Q4    31/13    2013 Guidance
    Young-Davidson
    Gold Ounces
    Produced[3]           28,281 29,252 30,099 33,106 120,738  120,000-140,000
            Underground
            Cash Costs
            per oz.            -      -      -   $663    $663                -
            Open Pit Cash
            Costs per oz.   $694   $716   $666   $983    $757                -
    Total Cash Costs per
    oz.[1],[2]              $694   $716   $666   $850    $744        $575-$675
    El Chanate
    Gold Ounces Produced  17,889 18,751 18,804 16,420  71,864    70,000-80,000
    Total Cash Costs per
    oz.[2]                  $563   $602   $588   $615    $592        $550-$600
    Consolidated Results
    Gold Ounces
    Produced[3]           46,170 48,003 48,903 49,526 192,601  190,000-220,000
    Total Cash Costs per
    oz.[1],[2]              $635   $655   $628   $766    $676        $565-$645


    [1]  Prior to commissioning the underground mine at Young-Davidson, cash
         costs were calculated on ounces produced from the open pit only. All
         underground costs were capitalized, and any revenue related to
         underground ounces sold was credited against capital. Subsequent to
         the declaration of commercial production in the underground mine,
         cash costs are calculated on ounces produced from both the open pit
         and underground mines, and revenue related to the sale of underground
         ounces is recognized in the Company's Statement of Operations as
         revenue.
    [2]  Cash costs are prior to inventory net realizable value adjustments &
         reversals, and are estimates only and subject to change. See the
         Non-GAAP Measures section on page 20 of the Management's Discussion
         and Analysis for the nine months ended September 30, 2013.
         Underground cash costs per ounce and open pit cash costs per ounce do
         not have a standardized meaning prescribed by International Financial
         Reporting Standards ("IFRS" or "GAAP"). They are therefore considered
         to be non-GAAP measures and may not be comparable to similar measures
         presented by other companies. Underground cash costs per ounce and
         open pit cash costs per ounce are determined by allocating production
         and refining costs to the underground and open pit tonnes mined and
         processed, and then dividing by the relevant ounces produced.
    [3]  Includes pre-production gold ounces from the Young-Davidson
         underground mine prior to the declaration of commercial production in
         the underground mine on October 31, 2013.


"We are pleased to report our sixth consecutive quarter of company-wide production growth and annual production results that are in-line with guidance estimates. Young Davidson is well positioned to drive continued growth in company-wide gold production as the underground operations continue to ramp-up productivity levels over the coming years," stated Scott Perry, President and CEO of AuRico. He continued, "Underpinning our asset base is a strong balance sheet and a management team that is focused on creating shareholder value."

Young-Davidson Update

  • Commercial production of the underground mine was declared on October 31, 2013, following the commissioning of the shaft hoisting system, which will facilitate significant increases in underground productivities and ongoing unit operating cost improvements.
  • During the quarter, the Company averaged 2,590 tpd from the underground mine (approx. 3,000 tpd in November and December), exceeding the year-end targeted level of 2,000 tpd with mine grades being in-line with reserve grade estimates. Underground productivity for the first quarter of 2014 is expected to remain in-line with overall fourth quarter levels (approx. 2,500 tpd) and increase steadily throughout the remainder of the year to reach a productivity target of 4,000 tpd by the end of the year. 
  • The paste backfill plant has been commissioned and the first pour was completed in early January. In 2011, the mine plan was re-engineered to utilize paste backfill to allow for significantly improved mining recovery and reduced dilution.
  • During the first two months of commercial production, underground unit mining costs were approximately $39 per tonne resulting in underground production cash costs of $663 per ounce. In the first quarter of 2014, unit mining costs are expected to average approximately $45 per tonne, reflecting the inclusion of paste fill operations following the commissioning of the paste backfill plant in early January. The unit mining costs are then expected to decrease steadily throughout the year, corresponding with planned quarter-over-quarter increases in underground productivity.
  • As at year end, development advance exceeded expectations with 75% of the 2014 mine plan already laterally accessed and 100% vertically accessed. In 2014, the Company will continue to advance underground development to optimize available ore inventory and thereby position the mine for sustainable, period-over-period, productivity increases in 2014 and beyond.
  • Open pit cash costs were $983 per ounce due to the higher operating strip ratio that resulted from waste movement in the quarter being ineligible for capitalization given the open pit mine life of less than one year. The stripping ratio during the quarter was 3.44:1 versus a year-to-date strip ratio 1.49:1 and is scheduled to average 2:1 for the remaining four to six months of open pit operations.
  • Open pit mine productivities remained at targeted levels and averaged 35,299 tpd during the quarter. As anticipated in the mine plan, the open pit will be fully depleted in coming months at which time approximately 3.0 million tonnes of open pit ore will be stockpiled ahead of the mill facility for future processing.
  • The mill facility continued to operate above nameplate capacity and averaged approximately 6,969 tpd during the fourth quarter.

El Chanate Update

  • The El Chanate open pit mine returned to targeted material movement levels, mining an average of 98,487 tpd during the quarter as compared to 87,366 tpd in the prior quarter as contractor equipment availability returned to normal levels.
  • Crushing and stacking rates remained in-line with targeted levels and averaged 17,462 tpd.

Fourth Quarter Dividend Declared

On January 3, 2014, the Board of Directors declared the Company's quarterly dividend payment of $0.04 per share for the fourth quarter ended December 31, 2013, payable on January 29, 2014 to shareholders of record at the close of business on January 14, 2014. Further information on the Company's dividend reinvestment plan (DRIP) is available through the following link: http://www.auricogold.com/DRIP.

Net Realizable Value Adjustment and Impairment Charges

Due to the lower metal price environment currently being experienced, the Company will be conducting net realizable value testing on ore inventories.  These tests may result in the need to recognize a net realizable value adjustment on these inventories at December 31.  In addition, the Company will be performing its annual impairment test utilizing updated economic and operational factors, which may result in the need to record impairment adjustments.

The Company will complete a final assessment by its fourth quarter and annual 2013 results release.

Upcoming News Flow

The Company expects to issue the following updates during the first quarter of 2014:

  • 2014 Operational Guidance (first week of February)
  • 2013 Reserves and Resources (first week of March)
  • Fourth Quarter and Annual Financial results (March 3)

About AuRico Gold

AuRico Gold is a leading Canadian gold producer with mines and projects in North America that have solid production growth and exploration potential. The Company is focused on its core operations including the Young-Davidson gold mine in northern Ontario and the El Chanate mine in Sonora State, Mexico. AuRico's project pipeline also includes advanced development opportunities in Canada and Mexico. AuRico's head office is located in Toronto, Ontario, Canada.

Cautionary Statement

This press release contains forward-looking statements and forward-looking information as defined under Canadian and U.S. securities laws.  All statements, other than statements of historical fact, are forward-looking statements. The words "expect", "believe", "anticipate", "will", "intend", "estimate", "forecast", "budget" and similar expressions identify forward-looking statements. Forward-looking statements include information as to strategy, plans or future financial or operating performance, such as the Company's expansion plans, project timelines, production plans, projected cash flows or capital expenditures, cost estimates, projected exploration results, reserve and resource estimates and other statements that express management's expectations or estimates of future performance.

Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered reasonable by management, are inherently subject to significant uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements, including: uncertainty of production and cost estimates; fluctuations in the price of gold and foreign exchange rates; the uncertainty of replacing depleted reserves; the risk that the Young-Davidson shaft will not perform as planned; the risk that mining operations do not meet expectations; the risk that projects will not be developed accordingly to budgets or timelines, changes in laws in Canada, Mexico and other jurisdictions in which the Company may carry on business; risks of obtaining necessary licenses, permits or approvals for operations or projects such as Kemess; disputes over title to properties; the speculative nature of mineral exploration and development; risks related to aboriginal title claims; compliance risks with respect to current and future environmental regulations; disruptions affecting operations; opportunities that may be pursued by the Company; employee relations; availability and costs of mining inputs and labor; the ability to secure capital to execute business plans; volatility of the Company's share price; continuation of the dividend and dividend reinvestment plan; the effect of future financings; litigation; risk of loss due to sabotage and civil disturbances; the values of assets and liabilities based on projected future cash flows; risks arising from derivative instruments or the absence of hedging; adequacy of internal control over financial reporting; changes in credit rating; and the impact of inflation. Actual results and developments are likely to differ, and may differ materially, from those expressed or implied by the forward-looking statements contained herein. Such statements are based on a number of assumptions which may prove to be incorrect, including assumptions about: business and economic conditions; commodity prices and the price of key inputs such as labour, fuel and electricity; credit market conditions and conditions in financial markets generally; revenue and cash flow estimates, production levels, development schedules and the associated costs; ability to procure equipment and supplies and on a timely basis; the timing of the receipt of permits and other approvals for projects and operations; the ability to attract and retain skilled employees and contractors for the operations; the accuracy of reserve and resource estimates; the impact of changes in currency exchange rates on costs and results; interest rates; taxation; and ongoing relations with employees and business partners. The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.

For further information please visit the AuRico Gold website at http://www.auricogold.com or contact:

Scott Perry
President and Chief Executive Officer
AuRico Gold Inc.
1-647-260-8880


Anne Day
Vice President, Investor Relations and Communications
AuRico Gold Inc.
+1-647-260-8880

SOURCE AuRico Gold Inc.

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
Eighty percent of a data scientist’s time is spent gathering and cleaning up data, and 80% of all data is unstructured and almost never analyzed. Cognitive computing, in combination with Big Data, is changing the equation by creating data reservoirs and using natural language processing to enable analysis of unstructured data sources. This is impacting every aspect of the analytics profession from how data is mined (and by whom) to how it is delivered. This is not some futuristic vision: it's ha...
Let’s face it, embracing new storage technologies, capabilities and upgrading to new hardware often adds complexity and increases costs. In his session at 18th Cloud Expo, Seth Oxenhorn, Vice President of Business Development & Alliances at FalconStor, will discuss how a truly heterogeneous software-defined storage approach can add value to legacy platforms and heterogeneous environments. The result reduces complexity, significantly lowers cost, and provides IT organizations with improved effi...
With the Apple Watch making its way onto wrists all over the world, it’s only a matter of time before it becomes a staple in the workplace. In fact, Forrester reported that 68 percent of technology and business decision-makers characterize wearables as a top priority for 2015. Recognizing their business value early on, FinancialForce.com was the first to bring ERP to wearables, helping streamline communication across front and back office functions. In his session at @ThingsExpo, Kevin Roberts...
Data-as-a-Service is the complete package for the transformation of raw data into meaningful data assets and the delivery of those data assets. In her session at 18th Cloud Expo, Lakshmi Randall, an industry expert, analyst and strategist, will address: What is DaaS (Data-as-a-Service)? Challenges addressed by DaaS Vendors that are enabling DaaS Architecture options for DaaS
One of the bewildering things about DevOps is integrating the massive toolchain including the dozens of new tools that seem to crop up every year. Part of DevOps is Continuous Delivery and having a complex toolchain can add additional integration and setup to your developer environment. In his session at @DevOpsSummit at 18th Cloud Expo, Miko Matsumura, Chief Marketing Officer of Gradle Inc., will discuss which tools to use in a developer stack, how to provision the toolchain to minimize onboa...
Cognitive Computing is becoming the foundation for a new generation of solutions that have the potential to transform business. Unlike traditional approaches to building solutions, a cognitive computing approach allows the data to help determine the way applications are designed. This contrasts with conventional software development that begins with defining logic based on the current way a business operates. In her session at 18th Cloud Expo, Judith S. Hurwitz, President and CEO of Hurwitz & ...
It's easy to assume that your app will run on a fast and reliable network. The reality for your app's users, though, is often a slow, unreliable network with spotty coverage. What happens when the network doesn't work, or when the device is in airplane mode? You get unhappy, frustrated users. An offline-first app is an app that works, without error, when there is no network connection.
The principles behind DevOps are not new - for decades people have been automating system administration and decreasing the time to deploy apps and perform other management tasks. However, only recently did we see the tools and the will necessary to share the benefits and power of automation with a wider circle of people. In his session at DevOps Summit, Bernard Sanders, Chief Technology Officer at CloudBolt Software, explored the latest tools including Puppet, Chef, Docker, and CMPs needed to...
The cloud promises new levels of agility and cost-savings for Big Data, data warehousing and analytics. But it’s challenging to understand all the options – from IaaS and PaaS to newer services like HaaS (Hadoop as a Service) and BDaaS (Big Data as a Service). In her session at @BigDataExpo at @ThingsExpo, Hannah Smalltree, a director at Cazena, will provide an educational overview of emerging “as-a-service” options for Big Data in the cloud. This is critical background for IT and data profes...
Father business cycles and digital consumers are forcing enterprises to respond faster to customer needs and competitive demands. Successful integration of DevOps and Agile development will be key for business success in today’s digital economy. In his session at DevOps Summit, Pradeep Prabhu, Co-Founder & CEO of Cloudmunch, covered the critical practices that enterprises should consider to seamlessly integrate Agile and DevOps processes, barriers to implementing this in the enterprise, and pr...
SYS-CON Events announced today that Men & Mice, the leading global provider of DNS, DHCP and IP address management overlay solutions, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. The Men & Mice Suite overlay solution is already known for its powerful application in heterogeneous operating environments, enabling enterprises to scale without fuss. Building on a solid range of diverse platform support,...
Advances in technology and ubiquitous connectivity have made the utilization of a dispersed workforce more common. Whether that remote team is located across the street or country, management styles/ approaches will have to be adjusted to accommodate this new dynamic. In his session at 17th Cloud Expo, Sagi Brody, Chief Technology Officer at Webair Internet Development Inc., focused on the challenges of managing remote teams, providing real-world examples that demonstrate what works and what do...
As enterprises work to take advantage of Big Data technologies, they frequently become distracted by product-level decisions. In most new Big Data builds this approach is completely counter-productive: it presupposes tools that may not be a fit for development teams, forces IT to take on the burden of evaluating and maintaining unfamiliar technology, and represents a major up-front expense. In his session at @BigDataExpo at @ThingsExpo, Andrew Warfield, CTO and Co-Founder of Coho Data, will dis...
With the proliferation of both SQL and NoSQL databases, organizations can now target specific fit-for-purpose database tools for their different application needs regarding scalability, ease of use, ACID support, etc. Platform as a Service offerings make this even easier now, enabling developers to roll out their own database infrastructure in minutes with minimal management overhead. However, this same amount of flexibility also comes with the challenges of picking the right tool, on the right ...
In most cases, it is convenient to have some human interaction with a web (micro-)service, no matter how small it is. A traditional approach would be to create an HTTP interface, where user requests will be dispatched and HTML/CSS pages must be served. This approach is indeed very traditional for a web site, but not really convenient for a web service, which is not intended to be good looking, 24x7 up and running and UX-optimized. Instead, talking to a web service in a chat-bot mode would be muc...