AuRico Gold Announces Preliminary Fourth Quarter Operational Results

TORONTO, January 14, 2014 /PRNewswire/ --

- Reports Sixth Consecutive Quarter of Production Growth

- $ are US

AuRico Gold Inc. (TSX: AUQ) (NYSE: AUQ), ("AuRico" or the "Company") today announces preliminary fourth quarter and annual operational results. All amounts are in U.S. dollars unless otherwise indicated.

AuRico reported its sixth consecutive quarter of production growth, with the Young-Davidson and El Chanate operations continuing to report solid production results that are in-line with expectations.

AuRico Gold Company-wide Production Growth

The shaft hoisting infrastructure at the Young-Davidson underground mine was commissioned in October, which facilitated the declaration of commercial production on October 31. The shaft hoisting system has, and will continue to, facilitate significant increases in underground productivities and corresponding cost efficiency improvements. During the first two months of commercial production, underground unit mining costs were approximately $39 per tonne resulting in underground production cash costs of $663 per ounce.

Preliminary 2013 Fourth Quarter Operational Results

                                                      Year-end
                                                        Dec.
                            Q1     Q2     Q3     Q4    31/13    2013 Guidance
    Young-Davidson
    Gold Ounces
    Produced[3]           28,281 29,252 30,099 33,106 120,738  120,000-140,000
            Underground
            Cash Costs
            per oz.            -      -      -   $663    $663                -
            Open Pit Cash
            Costs per oz.   $694   $716   $666   $983    $757                -
    Total Cash Costs per
    oz.[1],[2]              $694   $716   $666   $850    $744        $575-$675
    El Chanate
    Gold Ounces Produced  17,889 18,751 18,804 16,420  71,864    70,000-80,000
    Total Cash Costs per
    oz.[2]                  $563   $602   $588   $615    $592        $550-$600
    Consolidated Results
    Gold Ounces
    Produced[3]           46,170 48,003 48,903 49,526 192,601  190,000-220,000
    Total Cash Costs per
    oz.[1],[2]              $635   $655   $628   $766    $676        $565-$645


    [1]  Prior to commissioning the underground mine at Young-Davidson, cash
         costs were calculated on ounces produced from the open pit only. All
         underground costs were capitalized, and any revenue related to
         underground ounces sold was credited against capital. Subsequent to
         the declaration of commercial production in the underground mine,
         cash costs are calculated on ounces produced from both the open pit
         and underground mines, and revenue related to the sale of underground
         ounces is recognized in the Company's Statement of Operations as
         revenue.
    [2]  Cash costs are prior to inventory net realizable value adjustments &
         reversals, and are estimates only and subject to change. See the
         Non-GAAP Measures section on page 20 of the Management's Discussion
         and Analysis for the nine months ended September 30, 2013.
         Underground cash costs per ounce and open pit cash costs per ounce do
         not have a standardized meaning prescribed by International Financial
         Reporting Standards ("IFRS" or "GAAP"). They are therefore considered
         to be non-GAAP measures and may not be comparable to similar measures
         presented by other companies. Underground cash costs per ounce and
         open pit cash costs per ounce are determined by allocating production
         and refining costs to the underground and open pit tonnes mined and
         processed, and then dividing by the relevant ounces produced.
    [3]  Includes pre-production gold ounces from the Young-Davidson
         underground mine prior to the declaration of commercial production in
         the underground mine on October 31, 2013.


"We are pleased to report our sixth consecutive quarter of company-wide production growth and annual production results that are in-line with guidance estimates. Young Davidson is well positioned to drive continued growth in company-wide gold production as the underground operations continue to ramp-up productivity levels over the coming years," stated Scott Perry, President and CEO of AuRico. He continued, "Underpinning our asset base is a strong balance sheet and a management team that is focused on creating shareholder value."

Young-Davidson Update

  • Commercial production of the underground mine was declared on October 31, 2013, following the commissioning of the shaft hoisting system, which will facilitate significant increases in underground productivities and ongoing unit operating cost improvements.
  • During the quarter, the Company averaged 2,590 tpd from the underground mine (approx. 3,000 tpd in November and December), exceeding the year-end targeted level of 2,000 tpd with mine grades being in-line with reserve grade estimates. Underground productivity for the first quarter of 2014 is expected to remain in-line with overall fourth quarter levels (approx. 2,500 tpd) and increase steadily throughout the remainder of the year to reach a productivity target of 4,000 tpd by the end of the year. 
  • The paste backfill plant has been commissioned and the first pour was completed in early January. In 2011, the mine plan was re-engineered to utilize paste backfill to allow for significantly improved mining recovery and reduced dilution.
  • During the first two months of commercial production, underground unit mining costs were approximately $39 per tonne resulting in underground production cash costs of $663 per ounce. In the first quarter of 2014, unit mining costs are expected to average approximately $45 per tonne, reflecting the inclusion of paste fill operations following the commissioning of the paste backfill plant in early January. The unit mining costs are then expected to decrease steadily throughout the year, corresponding with planned quarter-over-quarter increases in underground productivity.
  • As at year end, development advance exceeded expectations with 75% of the 2014 mine plan already laterally accessed and 100% vertically accessed. In 2014, the Company will continue to advance underground development to optimize available ore inventory and thereby position the mine for sustainable, period-over-period, productivity increases in 2014 and beyond.
  • Open pit cash costs were $983 per ounce due to the higher operating strip ratio that resulted from waste movement in the quarter being ineligible for capitalization given the open pit mine life of less than one year. The stripping ratio during the quarter was 3.44:1 versus a year-to-date strip ratio 1.49:1 and is scheduled to average 2:1 for the remaining four to six months of open pit operations.
  • Open pit mine productivities remained at targeted levels and averaged 35,299 tpd during the quarter. As anticipated in the mine plan, the open pit will be fully depleted in coming months at which time approximately 3.0 million tonnes of open pit ore will be stockpiled ahead of the mill facility for future processing.
  • The mill facility continued to operate above nameplate capacity and averaged approximately 6,969 tpd during the fourth quarter.

El Chanate Update

  • The El Chanate open pit mine returned to targeted material movement levels, mining an average of 98,487 tpd during the quarter as compared to 87,366 tpd in the prior quarter as contractor equipment availability returned to normal levels.
  • Crushing and stacking rates remained in-line with targeted levels and averaged 17,462 tpd.

Fourth Quarter Dividend Declared

On January 3, 2014, the Board of Directors declared the Company's quarterly dividend payment of $0.04 per share for the fourth quarter ended December 31, 2013, payable on January 29, 2014 to shareholders of record at the close of business on January 14, 2014. Further information on the Company's dividend reinvestment plan (DRIP) is available through the following link: http://www.auricogold.com/DRIP.

Net Realizable Value Adjustment and Impairment Charges

Due to the lower metal price environment currently being experienced, the Company will be conducting net realizable value testing on ore inventories.  These tests may result in the need to recognize a net realizable value adjustment on these inventories at December 31.  In addition, the Company will be performing its annual impairment test utilizing updated economic and operational factors, which may result in the need to record impairment adjustments.

The Company will complete a final assessment by its fourth quarter and annual 2013 results release.

Upcoming News Flow

The Company expects to issue the following updates during the first quarter of 2014:

  • 2014 Operational Guidance (first week of February)
  • 2013 Reserves and Resources (first week of March)
  • Fourth Quarter and Annual Financial results (March 3)

About AuRico Gold

AuRico Gold is a leading Canadian gold producer with mines and projects in North America that have solid production growth and exploration potential. The Company is focused on its core operations including the Young-Davidson gold mine in northern Ontario and the El Chanate mine in Sonora State, Mexico. AuRico's project pipeline also includes advanced development opportunities in Canada and Mexico. AuRico's head office is located in Toronto, Ontario, Canada.

Cautionary Statement

This press release contains forward-looking statements and forward-looking information as defined under Canadian and U.S. securities laws.  All statements, other than statements of historical fact, are forward-looking statements. The words "expect", "believe", "anticipate", "will", "intend", "estimate", "forecast", "budget" and similar expressions identify forward-looking statements. Forward-looking statements include information as to strategy, plans or future financial or operating performance, such as the Company's expansion plans, project timelines, production plans, projected cash flows or capital expenditures, cost estimates, projected exploration results, reserve and resource estimates and other statements that express management's expectations or estimates of future performance.

Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered reasonable by management, are inherently subject to significant uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements, including: uncertainty of production and cost estimates; fluctuations in the price of gold and foreign exchange rates; the uncertainty of replacing depleted reserves; the risk that the Young-Davidson shaft will not perform as planned; the risk that mining operations do not meet expectations; the risk that projects will not be developed accordingly to budgets or timelines, changes in laws in Canada, Mexico and other jurisdictions in which the Company may carry on business; risks of obtaining necessary licenses, permits or approvals for operations or projects such as Kemess; disputes over title to properties; the speculative nature of mineral exploration and development; risks related to aboriginal title claims; compliance risks with respect to current and future environmental regulations; disruptions affecting operations; opportunities that may be pursued by the Company; employee relations; availability and costs of mining inputs and labor; the ability to secure capital to execute business plans; volatility of the Company's share price; continuation of the dividend and dividend reinvestment plan; the effect of future financings; litigation; risk of loss due to sabotage and civil disturbances; the values of assets and liabilities based on projected future cash flows; risks arising from derivative instruments or the absence of hedging; adequacy of internal control over financial reporting; changes in credit rating; and the impact of inflation. Actual results and developments are likely to differ, and may differ materially, from those expressed or implied by the forward-looking statements contained herein. Such statements are based on a number of assumptions which may prove to be incorrect, including assumptions about: business and economic conditions; commodity prices and the price of key inputs such as labour, fuel and electricity; credit market conditions and conditions in financial markets generally; revenue and cash flow estimates, production levels, development schedules and the associated costs; ability to procure equipment and supplies and on a timely basis; the timing of the receipt of permits and other approvals for projects and operations; the ability to attract and retain skilled employees and contractors for the operations; the accuracy of reserve and resource estimates; the impact of changes in currency exchange rates on costs and results; interest rates; taxation; and ongoing relations with employees and business partners. The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.

For further information please visit the AuRico Gold website at http://www.auricogold.com or contact:

Scott Perry
President and Chief Executive Officer
AuRico Gold Inc.
1-647-260-8880


Anne Day
Vice President, Investor Relations and Communications
AuRico Gold Inc.
+1-647-260-8880

SOURCE AuRico Gold Inc.

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
Blockchain is a shared, secure record of exchange that establishes trust, accountability and transparency across business networks. Supported by the Linux Foundation's open source, open-standards based Hyperledger Project, Blockchain has the potential to improve regulatory compliance, reduce cost as well as advance trade. Are you curious about how Blockchain is built for business? In her session at 21st Cloud Expo, René Bostic, Technical VP of the IBM Cloud Unit in North America, will discuss th...
WebRTC is great technology to build your own communication tools. It will be even more exciting experience it with advanced devices, such as a 360 Camera, 360 microphone, and a depth sensor camera. In his session at @ThingsExpo, Masashi Ganeko, a manager at INFOCOM Corporation, will introduce two experimental projects from his team and what they learned from them. "Shotoku Tamago" uses the robot audition software HARK to track speakers in 360 video of a remote party. "Virtual Teleport" uses a...
While some vendors scramble to create and sell you a fancy solution for monitoring your spanking new Amazon Lambdas, hear how you can do it on the cheap using just built-in Java APIs yourself. By exploiting a little-known fact that Lambdas aren’t exactly single-threaded, you can effectively identify hot spots in your serverless code. In his session at @DevOpsSummit at 21st Cloud Expo, Dave Martin, Product owner at CA Technologies, will give a live demonstration and code walkthrough, showing how ...
Docker containers have brought great opportunities to shorten the deployment process through continuous integration and the delivery of applications and microservices. This applies equally to enterprise data centers as well as the cloud. In his session at 20th Cloud Expo, Jari Kolehmainen, founder and CTO of Kontena, discussed solutions and benefits of a deeply integrated deployment pipeline using technologies such as container management platforms, Docker containers, and the drone.io Cl tool. H...
Translating agile methodology into real-world best practices within the modern software factory has driven widespread DevOps adoption, yet much work remains to expand workflows and tooling across the enterprise. As models evolve from pockets of experimentation into wholescale organizational reinvention, practitioners find themselves challenged to incorporate the culture and architecture necessary to support DevOps at scale.
When shopping for a new data processing platform for IoT solutions, many development teams want to be able to test-drive options before making a choice. Yet when evaluating an IoT solution, it’s simply not feasible to do so at scale with physical devices. Building a sensor simulator is the next best choice; however, generating a realistic simulation at very high TPS with ease of configurability is a formidable challenge. When dealing with multiple application or transport protocols, you would be...
SYS-CON Events announced today that CAST Software will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CAST was founded more than 25 years ago to make the invisible visible. Built around the idea that even the best analytics on the market still leave blind spots for technical teams looking to deliver better software and prevent outages, CAST provides the software intelligence that matter ...
As more and more companies are making the shift from on-premises to public cloud, the standard approach to DevOps is evolving. From encryption, compliance and regulations like GDPR, security in the cloud has become a hot topic. Many DevOps-focused companies have hired dedicated staff to fulfill these requirements, often creating further siloes, complexity and cost. This session aims to highlight existing DevOps cultural approaches, tooling and how security can be wrapped in every facet of the bu...
SYS-CON Events announced today that CA Technologies has been named “Platinum Sponsor” of SYS-CON's 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CA Technologies helps customers succeed in a future where every business – from apparel to energy – is being rewritten by software. From planning to development to management to security, CA creates software that fuels transformation for companies in the applic...
yperConvergence came to market with the objective of being simple, flexible and to help drive down operating expenses. It reduced the footprint by bundling the compute/storage/network into one box. This brought a new set of challenges as the HyperConverged vendors are very focused on their own proprietary building blocks. If you want to scale in a certain way, let’s say you identified a need for more storage and want to add a device that is not sold by the HyperConverged vendor, forget about it....
SYS-CON Events announced today that Pulzze Systems will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Pulzze Systems Inc, provides the software product "The Interactor" that uniquely simplifies building IoT, Web and Smart Enterprise Solutions. It is a Silicon Valley startup funded by US government agencies, NSF and DHS to bring innovative solutions to market.
In his session at @ThingsExpo, Dr. Robert Cohen, an economist and senior fellow at the Economic Strategy Institute, presented the findings of a series of six detailed case studies of how large corporations are implementing IoT. The session explored how IoT has improved their economic performance, had major impacts on business models and resulted in impressive ROIs. The companies covered span manufacturing and services firms. He also explored servicification, how manufacturing firms shift from se...
With Cloud Foundry you can easily deploy and use apps utilizing websocket technology, but not everybody realizes that scaling them out is not that trivial. In his session at 21st Cloud Expo, Roman Swoszowski, CTO and VP, Cloud Foundry Services, at Grape Up, will show you an example of how to deal with this issue. He will demonstrate a cloud-native Spring Boot app running in Cloud Foundry and communicating with clients over websocket protocol that can be easily scaled horizontally and coordinate...
SYS-CON Events announced today that Elastifile will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Elastifile Cloud File System (ECFS) is software-defined data infrastructure designed for seamless and efficient management of dynamic workloads across heterogeneous environments. Elastifile provides the architecture needed to optimize your hybrid cloud environment, by facilitating efficient...
For financial firms, the cloud is going to increasingly become a crucial part of dealing with customers over the next five years and beyond, particularly with the growing use and acceptance of virtual currencies. There are new data storage paradigms on the horizon that will deliver secure solutions for storing and moving sensitive financial data around the world without touching terrestrial networks. In his session at 20th Cloud Expo, Cliff Beek, President of Cloud Constellation Corporation, d...