China Gold International Announces Completion and Positive Results of Jiama's Feasibility Study

Measured and Indicated Resources grow by 41% to 1,486 Mt. Jiama's NPV(9%) increases to over US$1.3 Billion.

VANCOUVER, Jan. 15, 2014 /PRNewswire/ - China Gold International Resources Co. Ltd. (TSX:CGG; HKEx: 2099) ("China Gold International Resources" or the "Company") is pleased to announce the results of an updated NI 43-101 compliant, Independent Feasibility Study for the Phase II Expansion of its Jiama Copper-Polymetallic Mine, ("Jiama" or the "Project") in Tibet Autonomous Region, China. Mining One Pty Ltd, has produced the NI 43-101 compliant report based on the Phase II Expansion Project feasibility study, prepared by the Changchun Gold Design Institute in conjunction with independent consulting engineers and the Company's management.

Project Overview

The Jiama Project is a large scale polymetallic (Cu, Mo, Au, Ag, Pb, Zn) deposit located approximately 68 km east-northeast of Lhasa, the capital city of Tibet Autonomous Region, along the Sichuan-Tibet Highway within the Gangdise Copper Metallogeny Belt in Central Tibet, China and represents one of China's largest copper-gold mines.

Phase I of the Jiama Project commenced commercial production in September 2010 and included the development of the Tongqianshan and Niumatang open pits. These pits currently produce 1.8 million tonnes per annum ("Mtpa") of run-of-mine ("ROM") ore. The ore from these mines is processed via two processing plants with a combined processing capacity of 6,000 tonnes of ore per day ("tpd"). The Company plans to expand the Project production capacity to 50,000 tpd (Phase II plant capacity) with the addition of a new floatation plant (44,000 tpd ore), the development of two additional open-pits (Jiaoyan and South Pits) and the expansion of the underground mining operation. Total production is planned to increase from its current production rate of 1.8 Mtpa to 16.5 Mtpa of ROM ore. Metal concentrate (saleable product), will be sold to smelters within China.

Highlights

(All amounts are presented in US dollars unless otherwise stated)

  • Copper (Cu) Measured and Indicated Mineral Resources increased to 1,486 million tonnes at 0.41% Cu from 1,053 million tonnes at 0.44% Cu;
  • Copper Proved and Probable Mineral Reserves increased to 441 million tonnes at a grade of 0.61% Cu from 363 million tonnes at 0.77% Cu;
  • Contained copper in the resources increased to 6.138 million tonnes from 4.64 million tonnes;
  • Total production rate is expected to grow to 16.5 Mtpa of ROM ore: 9.9 Mtpa from open-pit and 6.6 Mtpa from underground operations:
    • Phase II plant capacity will come online in two stages in 2015 and 2016
    • Ramp up to an annual processing capacity approximating 16.5 Mtpa of ROM ore is expected to happen during 2017 and is expected to continue until 2039 when the reserves from the open pit mines are exhausted
    • After 2039, operations will continue from the underground mine until 2049 at an average annual rate of 5.4 Mtpa of ROM ore
  • At the completion of operations the total recovered metal is estimated to be:
    • 5.3 billion pounds of copper ("Cu")
    • 192.4 million pounds of molybdenum ("Mo")
    • 101.3 million ounces of silver ("Ag")
    • 1.5 million ounces of gold ("Au")
    • 828.2 million pounds of lead ("Pb")
    • 314.0 million pounds of zinc ("Zn")
  • Average annual metal production is estimated to be:
    • 67 thousand tonnes of copper
    • 2.4 thousand tonnes of molybdenum
    • 2.8 million ounces of silver
    • 42 thousand ounces of gold
    • 10.4 thousand tonnes of lead
    • 4.0 thousand tonnes of zinc
  • Contributions by metal to total sales is: 66.5% copper, 12.7% molybdenum, 8.6% silver, 8.3% gold, 3.5% lead and 1.3% zinc.
  • Estimated life of mine is 35 years;
  • Estimated capital expenditure is $716.2 million ($1.59 per tonne of ore);
  • Estimated total operating costs are $23.48 per tonne of ore, of which:
    • Mining costs are $11.50 per tonne of ore
    • Processing costs are $10.06 per tonne of ore
    • Fixed costs are $0.33 per tonne of ore
    • Overhead costs are $1.58 per tonne of ore
  • A Net Present Value (NPV) of over $1.3 billion with nominal cash flow of $5.8 billion after-tax at a discount rate of 9% based on metal prices of:
    • $2.90/lb copper
    • $15.5/lb molybdenum
    • $0.98/lb lead
    • $0.95/lb zinc
    • $1,300/oz gold
    • $20/oz silver
  • After-tax Internal Rates of Return (IRR) of 24.0% with a payback period of 6.72 years

Dr. Xin Song, CEO of the Company, commented, "This feasibility study indicates a significant increase in our resources and reserves. The Project's economics are strong with an NPV (at a discount rate of 9%) of over $1.3 billion and IRR of 24% even when using prudent assumptions about metals prices.  We are planning to grow the project from 6,000 to 50,000 tonnes per day instead of previously announced 40,000 tpd.  We are also planning a longer mine life, close to 35 years. We are very pleased with the results of this study and the long-term outlook for this strategic asset."

Geology

The Project is located in the central-south portion of the Gangdise-Nianqing Tanggula Terrane. Stratigraphy outcropping in the Project area is dominated by passive epicontinental clastic-carbonate rocks. Three types of copper-polymetallic mineralization are observed within the Project, these include skarn, hornfels and porphyry hosted mineralization. All three styles of mineralization are structurally controlled with concentrations occurring along shear/structure zones and mineralization offset by thrust and detachment faults as well as associated with anticlines and synclines.

The zone of mineralization within fault hosted skarn alteration measures kilometers in both strike and dip and remains open at depth to the northeast.

Mining

The Phase II Expansion Project will include two open pits and one underground mine.

The two open pits are designed to mine all three types of mineralization, producing approximately 9.9 million tonnes of ROM ore and removing about 20 million tonnes of waste rock per annum with a life-of-mine (LOM) stripping ratio of 2.16.  The underground mine is designed to mine the high grade portion of the skarn type mineralization and will produce approximately 6.6 million tonnes of ROM ore per annum.

Capex and Cash Flow Analysis

Estimated capital expenditures for the Phase II Expansion of the Project will be approximately $716 million, including $350 million for processing and $366 million for mining.

The long term metal prices used for the Feasibility Study are contained in Table 1 along with sensitivity data. Prices for zinc and lead are $0.98/lb and $0.95/lb respectively.

The after-tax net present value ("NPV") is over $1.3 billion with a discount rate of 9%, giving a payback period of 6.7 years and IRR of 24%. The undiscounted, cumulative net cash flow is approximately $5.8 billion.

Table 1: Jiama Copper-Polymetallic Project - NPV and IRR Summary

Long Term Metal Price   NPV ($ Million) IRR
Cu ($/lb) Mo ($/lb) Au ($/oz) Ag ($/oz) 0%
Disc. rate
7%
Disc, rate
9% Base
Disc. rate
11%
Disc. rate
$2.90 $15.5 $1,300 $20 Pre-Tax $7,406 $2,461 $1,873 $1,438 30%
After-Tax $5,785 $1,795 $1,324 $978 24%

Mineral Resources Estimate

A Mineral Resource estimate, dated November 20, 2013, has been independently completed by Mining One Pty Ltd in accordance with the CIM Definitions Standards under NI 43-101.  The Resource estimate is based on information collected up to November 12, 2012. Assaying and geological logging and testing of the core subsequent to November 2012 including an extensive drill program conducted in 2013 will be included in future updates of the Mineral Resources and Reserves.

During the review of the data Mining One Pty Ltd noted that whilst the mineralization occurs within a single mineralized body, gold and silver mineralization within the ore body had a significantly higher spatial variability than the other elements. As a result Mining One Pty Ltd has classified the Au and Ag resource presented in Table 3 separately; this classification takes into account the proposed large scale mining techniques where Au and Ag will only be credits to the overall products from the operations. Mining One Pty Ltd has assumed that Au and Ag will not be assigned a single cut-off grade for a selected mining block and will be mined in conjunction with the other elements.

The Mineral Resources are summarized in Tables 2 and 3. The Mineral Resources presented in Table 3 for Au and Ag are inclusive and not in addition to the Mineral Resources in Table 2 and occur within the same mineralized body.

Table 2: Jiama Project - Cu, Mo, Pb and Zn Mineral Resources
Reported at a 0.3% Cu Equivalent Cut Off Grade*, as of 20th of November, 2013

                     
Rock
Type
Class Quantity
Mt
Cu % Mo % Pb % Zn % Cu Metal
(kt)
Mo Metal
(kt)
Pb Metal
(kt)
Zn Metal
(kt)
Skarn Measured 42.8 0.66 0.041 0.06 0.04 281 17 28 19
  Indicated 453.0 0.69 0.040 0.15 0.09 3,114 183 676 399
  M+I 495.8 0.68 0.040 0.14 0.08 3,395 200 704 417
  Inferred 125.5 0.46 0.038 0.20 0.10 577 47 248 125
Hornfels Measured 54.9 0.23 0.031 0.03 0.01 127 17 15 5
  Indicated 852.9 0.28 0.030 0.01 0.01 2,368 253 69 64
  M+I 907.8 0.27 0.030 0.01 0.01 2,496 270 84 69
  Inferred 276.6 0.24 0.026 0.02 0.02 660 73 63 49
Porphyry Measured 2.6 0.26 0.049 0.02 0.01 7 1 1 0
  Indicated 79.9 0.30 0.039 0.01 0.01 240 31 6 8
  M+I 82.4 0.30 0.040 0.01 0.01 247 33 6 8
  Inferred 4.0 0.24 0.085 0.01 0.02 10 3 0 1
Total Measured 100.2 0.41 0.035 0.04 0.02 415 36 43 24
  Indicated 1,385.8 0.41 0.034 0.05 0.03 5,772 468 751 470
  M+I 1,486.0 0.41 0.034 0.05 0.03 6,138 503 794 495
  Inferred 406.0 0.31 0.030 0.08 0.04 1,247 124 312 174

Table 3: Jiama Project - Au and Ag Mineral Resources
Reported at a 0.3% Cu Equivalent Cut Off Grade* as of 20th of November, 2013

             
Rock Type Class Quantity (Mt) Au g/t Ag g/t Au Moz Ag Moz
Skarn Measured 42.8 0.22 13.39 0.304 18.429
  Indicated 453.0 0.27 15.59 3.901 227.094
  M+I 495.8 0.26 15.40 4.205 245.523
  Inferred 125.5 0.19 11.90 0.750 47.995
Hornfels Measured 54.9 0.02 1.32 0.041 2.330
  Indicated 852.9 0.03 1.38 0.909 37.733
  M+I 907.8 0.03 1.37 0.950 40.063
  Inferred 276.6 0.06 2.10 0.562 18.644
Porphyry Measured 2.6 0.06 3.42 0.005 0.281
  Indicated 79.9 0.07 2.93 0.174 7.522
  M+I 82.4 0.07 2.94 0.179 7.803
  Inferred 4.0 0.04 2.25 0.006 0.287
Total Measured 100.2 0.11 6.53 0.349 21.040
  Indicated 1,385.8 0.11 6.11 4.985 272.349
  M+I 1,486.0 0.11 6.14 5.334 293.389
  Inferred 406.0 0.10 5.13 1.317 66.926

Note:  Figures reported are rounded which may result in small tabulation errors.

The Copper Equivalent basis for the reporting of resources has been compiled on the following basis:

CuEq Resources:

= (Ag Grade * Ag Price + Au Grade * Au Price + Cu Grade * Cu Price + Pb Grade * Pb Price + Zn Grade * Zn Price + Mo Grade * Mo Price) / Copper Price

Mineral Reserves Estimate

A Mineral Reserve estimate, dated 20th of November, 2013, has been independently verified by Mining One Pty Ltd in accordance with the CIM Definitions Standards under NI 43-101.

The selected mining strategies developed by CGDI (Changchun Gold Design Institute) consider conventional truck shovel mining for the Jiaoyan and South open pits. Various mining methods have been examined for the Phase II Expansion Underground Mine with the primary method being Sub Level Stoping with fill (Primary/Secondary/Tertiary).

The reserve estimate for the Jiama underground mine is based on a combination of Sub Level Open Stoping with Paste fill, Room and Pillar and Cut and Fill. Table 4 presents the Mineral Reserves estimate for the Project (Open pit and underground mines).

Table 4: Jiama Project Statement of NI 43-101 Mineral Reserve Estimate as of 20th of Nov., 2012

                Metal
Type Quantity Mt Cu % Mo % Pb % Zn % Au g/t Ag g/t Cu kt Mo kt Pb kt Zn kt Au Moz Ag Moz
Proven 24.96 0.64 0.04 0.05 0.03 0.19 11.35 160 10 12 8 0.2 9.1
Probable 415.87 0.61 0.03 0.13 0.08 0.19 11.52 2,548 133 551 319 2.5 154.1
                           
Subtotal 440.83 0.61 0.03 0.13 0.07 0.19 11.51 2,708 143 563 327 2.7 163.2

Notes:
 
1.     The Mineral Reserve as of 20th November 2013.
2.     All Mineral Reserves have been estimated in accordance with the JORC code and have been reconciled to CIM standards as prescribed by the National Instrument 43-101.
3.     Mineral Reserves were estimated using the following mining and economic factors:
Open Pits:
      a)  5% dilution factor and 95% recovery were applied to the mining method;
      b)  overall slope angles of 43 degrees;
      c)  a copper price of USD$ 2.9/lbs;
      d)  an overall processing recovery of 88 - 90% for copper
Underground:
      a)  10% dilution added to all Sub-Level Open Stoping;
      b)  Stope recovery is 87% for Sub-Level Open Stoping;
      c)  An overall processing recovery of 88 - 90% for copper.
4.     The cut-off grade for Mineral Reserves has been estimated at copper equivalent grades of 0.3%Cu (NSR) for the open pits and 0.45%Cu (NSR) for the underground mine.
5.     Mineral Reserve Estimates were prepared under the guidance of Anthony R. Cameron who is a sub-consultant to Mining One Pty Ltd. He is a Fellow of the Australasian Institute of Mining and Metallurgy and has over 26 years of relevant engineering experience and is the Qualified Person for Mineral Reserves.

Project Update

As of December 1, 2013, the Company has completed a further infill drilling program to upgrade the resource confidence and help further optimize the mine design and reserves of the Jiama deposit. The program consisted of 104 drill holes for a total of 43,930 meters, including: 85 regular in-fill resource drill holes (34,923 m), 13 geo-technical drill holes (4,835 m), and 6 geo-hydrological holes (4,172 m). Assaying and geological logging and testing of the core from 2013 drill holes is ongoing and this information will be included in the operational mine plans and future updates of the Mineral Resources and Mineral reserves.

The Company is currently completing further metallurgical testing of both skarn and hornfels ores to further optimize the molybdenum and precious metal recoveries especially in lower grade ores. Further testing underway in the South pit area, will be focused on further refining the Cu-Pb-Zn separation.

Based on the above infill drilling and metallurgical program the Company aims to continue to refine the operational mining plans and release an update of the Mineral Resources and Mineral Reserves in the first half of 2014.

National Instrument 43-101 Disclosure

An NI 43-101 Technical Report - Jiama Phase 2 Expansion Project Mineral Resources & Reserves for China Gold International with an effective date of December 20, 2013 has been prepared by Mining One Pty Ltd. The report will be available on SEDAR (www.sedar.com) and on the Company's website within 45 days of this release.

The content of this news release has been reviewed by Bin Guo and Anthony R. Cameron of Mining One Pty Ltd, each of whom is a Qualified Person in accordance with the requirements of NI 43-101.  Bin Guo is a sub-consultant to Mining One Pty Ltd and is the Senior Vice President at CITIC Securities, responsible for valuation, ranking and transaction of mining projects, and has been so employed since 2011. He has 13 years' of industry and academic experience, with specific expertise in exploration management, 3D integrated geological and geophysical modelling / targeting and fulfils the requirements to be a Qualified Person for the purpose of NI 43-101.

Anthony R Cameron is a sub-consultant to Mining One Pty Ltd and is classified as an independent author. He is a Fellow of the Australasian Institute of Mining and Metallurgy and has over 26 years of relevant engineering experience and is the Qualified Person for Mineral Reserves.

About China Gold International Resources

China Gold International Resources Corp. Ltd. is based in Vancouver, BC, Canada and operates both profitable and growing mines, the CSH Gold Mine in Inner Mongolia, and the Jiama Copper-Gold Polymetallic Mine in Tibet Autonomous Region of the People's Republic of China. The Company's objective is to continue to build shareholder value by growing production at its current mining operations, expanding its resource base, and aggressively acquiring and developing new projects internationally. The Company is listed on the Toronto Stock Exchange (TSX: CGG) and the Main Board of The Stock Exchange of Hong Kong Limited (HKEx: 2099).

Cautionary Note about Forward-Looking Statements

Certain information regarding China Gold International Resources contained herein may constitute forward-looking statements within the meaning of applicable securities laws. Forward-looking statements may include estimates, plans, expectations, opinions, forecasts, projections, guidance or other statements that are not statements of fact. Although China Gold International Resources believes that the expectations reflected in such forward-looking statements are reasonable, it can give no assurance that such expectations will prove to have been correct. China Gold International Resources cautions that actual performance will be affected by a number of factors, most of which are beyond its control, and that future events and results may vary substantially from what China Gold International Resources currently foresees. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices, exploitation and exploration results, continued availability of capital and financing and general economic, market or business conditions. The forward-looking statements are expressly qualified in their entirety by this cautionary statement. The information contained herein is stated as of the current date and subject to change after that date.

SOURCE China Gold International Resources Corp. Ltd.

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
With more than 30 Kubernetes solutions in the marketplace, it's tempting to think Kubernetes and the vendor ecosystem has solved the problem of operationalizing containers at scale or of automatically managing the elasticity of the underlying infrastructure that these solutions need to be truly scalable. Far from it. There are at least six major pain points that companies experience when they try to deploy and run Kubernetes in their complex environments. In this presentation, the speaker will d...
While DevOps most critically and famously fosters collaboration, communication, and integration through cultural change, culture is more of an output than an input. In order to actively drive cultural evolution, organizations must make substantial organizational and process changes, and adopt new technologies, to encourage a DevOps culture. Moderated by Andi Mann, panelists discussed how to balance these three pillars of DevOps, where to focus attention (and resources), where organizations might...
The deluge of IoT sensor data collected from connected devices and the powerful AI required to make that data actionable are giving rise to a hybrid ecosystem in which cloud, on-prem and edge processes become interweaved. Attendees will learn how emerging composable infrastructure solutions deliver the adaptive architecture needed to manage this new data reality. Machine learning algorithms can better anticipate data storms and automate resources to support surges, including fully scalable GPU-c...
When building large, cloud-based applications that operate at a high scale, it's important to maintain a high availability and resilience to failures. In order to do that, you must be tolerant of failures, even in light of failures in other areas of your application. "Fly two mistakes high" is an old adage in the radio control airplane hobby. It means, fly high enough so that if you make a mistake, you can continue flying with room to still make mistakes. In his session at 18th Cloud Expo, Le...
Machine learning has taken residence at our cities' cores and now we can finally have "smart cities." Cities are a collection of buildings made to provide the structure and safety necessary for people to function, create and survive. Buildings are a pool of ever-changing performance data from large automated systems such as heating and cooling to the people that live and work within them. Through machine learning, buildings can optimize performance, reduce costs, and improve occupant comfort by ...
As Cybric's Chief Technology Officer, Mike D. Kail is responsible for the strategic vision and technical direction of the platform. Prior to founding Cybric, Mike was Yahoo's CIO and SVP of Infrastructure, where he led the IT and Data Center functions for the company. He has more than 24 years of IT Operations experience with a focus on highly-scalable architectures.
The explosion of new web/cloud/IoT-based applications and the data they generate are transforming our world right before our eyes. In this rush to adopt these new technologies, organizations are often ignoring fundamental questions concerning who owns the data and failing to ask for permission to conduct invasive surveillance of their customers. Organizations that are not transparent about how their systems gather data telemetry without offering shared data ownership risk product rejection, regu...
CI/CD is conceptually straightforward, yet often technically intricate to implement since it requires time and opportunities to develop intimate understanding on not only DevOps processes and operations, but likely product integrations with multiple platforms. This session intends to bridge the gap by offering an intense learning experience while witnessing the processes and operations to build from zero to a simple, yet functional CI/CD pipeline integrated with Jenkins, Github, Docker and Azure...
René Bostic is the Technical VP of the IBM Cloud Unit in North America. Enjoying her career with IBM during the modern millennial technological era, she is an expert in cloud computing, DevOps and emerging cloud technologies such as Blockchain. Her strengths and core competencies include a proven record of accomplishments in consensus building at all levels to assess, plan, and implement enterprise and cloud computing solutions. René is a member of the Society of Women Engineers (SWE) and a m...
Dhiraj Sehgal works in Delphix's product and solution organization. His focus has been DevOps, DataOps, private cloud and datacenters customers, technologies and products. He has wealth of experience in cloud focused and virtualized technologies ranging from compute, networking to storage. He has spoken at Cloud Expo for last 3 years now in New York and Santa Clara.
Enterprises are striving to become digital businesses for differentiated innovation and customer-centricity. Traditionally, they focused on digitizing processes and paper workflow. To be a disruptor and compete against new players, they need to gain insight into business data and innovate at scale. Cloud and cognitive technologies can help them leverage hidden data in SAP/ERP systems to fuel their businesses to accelerate digital transformation success.
Containers and Kubernetes allow for code portability across on-premise VMs, bare metal, or multiple cloud provider environments. Yet, despite this portability promise, developers may include configuration and application definitions that constrain or even eliminate application portability. In this session we'll describe best practices for "configuration as code" in a Kubernetes environment. We will demonstrate how a properly constructed containerized app can be deployed to both Amazon and Azure ...
Poor data quality and analytics drive down business value. In fact, Gartner estimated that the average financial impact of poor data quality on organizations is $9.7 million per year. But bad data is much more than a cost center. By eroding trust in information, analytics and the business decisions based on these, it is a serious impediment to digital transformation.
Digital Transformation: Preparing Cloud & IoT Security for the Age of Artificial Intelligence. As automation and artificial intelligence (AI) power solution development and delivery, many businesses need to build backend cloud capabilities. Well-poised organizations, marketing smart devices with AI and BlockChain capabilities prepare to refine compliance and regulatory capabilities in 2018. Volumes of health, financial, technical and privacy data, along with tightening compliance requirements by...
Predicting the future has never been more challenging - not because of the lack of data but because of the flood of ungoverned and risk laden information. Microsoft states that 2.5 exabytes of data are created every day. Expectations and reliance on data are being pushed to the limits, as demands around hybrid options continue to grow.