Welcome!

News Feed Item

EPM Mining Issues Summary of 2013 Results and 2014 Projections for Its Sevier Lake Playa Sulphate of Potash Project

TORONTO, ONTARIO -- (Marketwired) -- 01/16/14 -- EPM Mining Ventures Inc. (TSX VENTURE:EPK)(OTCQX:EPKMF) ("EPM" or the "Company"), today issued a review of advancements accomplished during 2013 at its Sevier Lake Playa Sulphate of Potash Project located in southwestern Utah and offered guidance about what is planned for 2014.

"As C.E.O., I am very pleased with everything we achieved this past year and look forward to all that we will accomplish this year," said Lance D'Ambrosio, Chief Executive Officer of EPM. "Looking back, I have to say that without a doubt, our biggest success was completing our Preliminary Feasibility Study. So let me start by sharing a few highlights from that."

Preliminary Feasibility Study Highlights


--  The PFS forecasts average annual SOP production of 300,000 metric tonnes
    (t) with an estimated Net Present Value ("NPV") of $629 million (after
    tax, inflated, 8% discount rate) and an estimated Internal Rate of
    Return ("IRR") of 20% (after tax, inflated). 
--  The PFS includes an updated Mineral Resource Estimate that includes
    31.486 million tonnes of SOP in the Measured and Indicated categories, a
    7% increase from previously published estimates, due primarily to
    results of recent drilling. 
--  Economic Highlights: 

----------------------------------------------------------------------------
Economic Indicators                                                         
----------------------------------------------------------------------------
NPV (pretax, 8%)                                                     $ 957 M
----------------------------------------------------------------------------
NPV (after tax, 8%)                                                  $ 629 M
----------------------------------------------------------------------------
IRR (pretax)                                                             24%
----------------------------------------------------------------------------
IRR (after tax)                                                          20%
----------------------------------------------------------------------------
Average Annual SOP Production                                      300,000 t
----------------------------------------------------------------------------
Mine Life                                                           30 years
----------------------------------------------------------------------------
Initial Direct Capital Costs                                         $ 292 M
----------------------------------------------------------------------------
Initial Indirect Capital Costs                                        $ 50 M
----------------------------------------------------------------------------
Initial Capital Contingency                                           $ 36 M
----------------------------------------------------------------------------
Operating Cost                                                    $ 180.91/t
----------------------------------------------------------------------------
Production Royalties (% of gross revenues)                             5.61%
----------------------------------------------------------------------------
Year 3 EBITDA (nameplate production)                                 $ 143 M
----------------------------------------------------------------------------
Payback Period (from commencement of production)                   5.5 years
----------------------------------------------------------------------------
Measured & Indicated SOP Resource                                  31.486 Mt
----------------------------------------------------------------------------

--  The economic analysis in the PFS is based upon the following
    assumptions: 
    --  100% Equity 
    --  Production Ramp-Up over two years, reaching full production in Year
        3 
        --  50,000 tonnes in Year 1; 100,000 tonnes in Year 2; and 300,000
            tonnes in Year 3 
    --  Construction on playa beginning in Preproduction Year 3 ("PP-3") 
    --  Effective tax rate of approximately 29% 
--  The economic analysis was based upon Measured and Indicated Mineral
    Resources only. No Inferred Resources were included in the analysis.
    Mineral Resources that are not Mineral Reserves do not have demonstrated
    economic viability. 
--  Capital Costs - the total direct capital costs of the Project are
    estimated to be $292 M, not including indirect costs and contingency, as
    of 2013. All capital costs in the economic model are inflated by 2%
    annually beginning in year PP-3. Contingency is 12% of direct capital
    costs. The capital cost estimate has an accuracy of +25%/-20%. 
--  Operating Costs - the total cash operating costs of the Project are
    estimated to be $180.91/t as of 2013. All operating costs in the
    economic model are inflated by 2% annually beginning in year PP-3. 

"In 2013 as part of the PFS, we conducted a comprehensive study of the playa and made significant progress with our engineering," said Lance. "These efforts provided us with important insights and a detailed path forward. The highlights include:"

Hydrology Highlights


--  A comprehensive groundwater modeling effort was completed that included
    two- and three-dimensional models of the playa system. The models
    incorporated layer elevations derived from intercepts logged from over
    400 boreholes and wells drilled during the exploration programs. 
--  Field data incorporated into the models included estimates of hydraulic
    conductivity and storage coefficients based on hydrophysical and aquifer
    stress tests employing both wells and trenches. Site-specific estimates
    of the vertical infiltration rate and evapotranspiration were also
    obtained. 
    --  In the latest program, five single-hole pump tests were performed;
        four well-to-trench tests; nine well-to-well tests; and one trench-
        to-trench test. These studies yielded substantial new data that
        significantly improved our understanding of playa hydrology. 
--  Initial modeling determined that the target production rate of 300,000
    tpy could be achieved based upon the hydro-physical characteristics of
    the deposit. Multiple simulations incorporating trench spacing, well
    layouts, and flow rates were carried out to prototype designs. 
    --  Results showed that acceptable brine production could be extracted
        from two trench phases, based on 1,000 meter spacing, followed by
        well extraction with individual shafts set about 400 meters. 

Engineering Highlights


--  Developed an optimized process flow sheet anticipated to provide
    improved operating benefits and flexibility while maintaining a balance
    between production, expense, and potential additional mineral
    production. 
--  Completed thermodynamic modeling and pilot-plant testing of pond
    crystallization. In addition, conducted bench-scale testing with Hazen
    Research and Swenson Technologies for the flotation and multiple effect
    crystallizer circuits. The thermodynamic modeling and subsequent bench-
    scale test-work confirmed projected plant recoveries of 78%. 
--  Developed civil construction designs for the plant and rail load-out
    facility as well as all playa infrastructure. The capital cost estimate
    in the PFS included budgetary quotes on 93% of all plant mechanical
    equipment costs. 

"As I briefly mentioned before, we successfully expanded our resource estimates by about seven percent," Lance added. "While we expect to release mineral reserves with our feasibility study, we are very pleased to provide a summary of the basis for the resource estimate expansion."

Resource Estimate Expansion Highlights


--  Norwest completed an updated Mineral Resource Estimate based upon data
    collected from the original drilling and exploration program conducted
    in 2011-2012 as well as a second drilling and exploration program
    conducted in 2013. 
--  The total Measured and Indicated Resource for SOP increased from 29.485
    Mt in the May 2012 Technical Report, to 31.486 Mt in the PFS, an
    increase of approximately 7%, primarily due to the results of the 2013
    drilling program. 
--  No claim for Mineral Reserves has been made at this time pending further
    verification of the hydrologic models via longer-term pilot testing
    planned during the Feasibility Study phase. 

"We received several important approvals this past year," Lance stated. "And our environmental and permitting programs continue to progress. Highlights from these include:"

Environmental, Permitting, & Regulatory Highlights


--  The Company met with the Utah Division of Air Quality ("UDAQ") in August
    2013. In that meeting, UDAQ determined that the company could proceed
    along a "dual permit" approach. This means that a Minor Source permit is
    all that is required for initial work on the playa to begin while a
    Major Source Permit could be added later when construction of the
    processing plant is required. 
    --  An Air Approval order for the Minor Source Permit was submitted to
        UDAQ in October 2013. An approval is expected shortly. 
    --  In July of 2013, the company started an on-site monitoring program
        for Prevention of Significant Deterioration (PSD), or the Major
        Source Permit. 
--  The BLM's Fillmore Field Office continued progress with the EIS and
    selected a third-party contractor to write the EIS document in August
    2013. Technical resource reports were prepared by CH2M Hill and
    submitted to BLM for their review and approval in November 2013. BLM
    selection of the third-party contractor is an important step to moving
    the EIS process forward. 
--  The BLM Plan of Operations and DOGM Large Mine Permit, historically two
    separate documents, are being consolidated into a single mine plan
    document (the "Mine Plan") agreed to by both agencies. The BLM has
    reviewed the Mine Plan and determined it was "Sufficiently Complete" in
    July 2013. A consolidated Mine Plan will allow for the Company to have
    one all-encompassing document that meets the requirement for the two
    agencies. 
--  A key decision in June 2013 by the Environmental Protection Agency and
    the United States Army Corps of Engineers ("USACE") determined that
    there are no Waters of the United States on the Sevier Lake Playa. 
    --  USACE determined that the Sevier Lake Playa is not a regulated
        feature under Section 404 of the Clean Water Act ("Act") and as such
        is exempt from permitting requirements under the Act. 
    --  Therefore, certain federal permits relating to water will not be
        required. This decision simplifies the permitting process and
        results in significant savings of time and money. 
--  In 2013, the Company submitted all water rights applications to the
    State Engineer, for which there were only four protestants. 
    --  In August 2013, the Company along with Holland and Hart and CH2M
        Hill discussed EPM's water rights presentation with the State
        Engineer in Delta, Utah. The hearing went very well and the Company
        anticipates that all water right applications will be approved by
        the third quarter 2014. 

Outlook for 2014

"2014 should be a banner year for us. We expect to complete most of the pre-construction milestones, nearly complete our EIS, and conclude all other necessary permitting," Lance indicated. "And soon, we will be kicking-off our Feasibility Study. While the PFS only considered SOP production, we anticipate that the Feasibility Study will consider the production of specialty products in addition to SOP including, magnesium sulphate, magnesium chloride, sodium sulphate, and possibly lithium," Lance said. "Given the presence of the other known constituents in our brine resource, we expect these minerals to provide the Company with a significant source of additional value if such minerals prove to be economic as the result of further studies."

About EPM Mining Ventures

EPM Mining Ventures Inc. is a development-stage company focused on specialty fertilizers. Through Peak Minerals Inc., its indirect wholly-owned subsidiary, EPM controls directly or through agreement mineral leases on more than 124,000 acres on its Sevier Lake Playa property in Millard County, Utah. With a brine resource known to contain potassium, magnesium, sulphate, lithium and a suite of other beneficial minerals, EPM is targeting the development and production of specialty fertilizers, including SOP, through the use of a cost-effective solar evaporation process. SOP and other specialty fertilizers are used in the production of high value, chloride-sensitive crops such as fruits, vegetables, and tree nuts. With the recent completion of a Preliminary Feasibility Study, the Company is currently engaged in engineering and analysis designed to support a feasibility study, environmental permitting, and ultimately mineral production.

For more information, please visit our web site at www.epmmining.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
EPM Mining Ventures Inc.
Lance D'Ambrosio
Chief Executive Officer
(801) 485-0223
www.epmmining.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that Peak 10, Inc., a national IT infrastructure and cloud services provider, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Peak 10 provides reliable, tailored data center and network services, cloud and managed services. Its solutions are designed to scale and adapt to customers’ changing business needs, enabling them to lower costs, improve performance and focus inter...
You think you know what’s in your data. But do you? Most organizations are now aware of the business intelligence represented by their data. Data science stands to take this to a level you never thought of – literally. The techniques of data science, when used with the capabilities of Big Data technologies, can make connections you had not yet imagined, helping you discover new insights and ask new questions of your data. In his session at @ThingsExpo, Sarbjit Sarkaria, data science team lead ...
So, you bought into the current machine learning craze and went on to collect millions/billions of records from this promising new data source. Now, what do you do with them? Too often, the abundance of data quickly turns into an abundance of problems. How do you extract that "magic essence" from your data without falling into the common pitfalls? In her session at @ThingsExpo, Natalia Ponomareva, Software Engineer at Google, will provide tips on how to be successful in large scale machine lear...
If there is anything we have learned by now, is that every business paves their own unique path for releasing software- every pipeline, implementation and practices are a bit different, and DevOps comes in all shapes and sizes. Software delivery practices are often comprised of set of several complementing (or even competing) methodologies – such as leveraging Agile, DevOps and even a mix of ITIL, to create the combination that’s most suitable for your organization and that maximize your busines...
Struggling to keep up with increasing application demand? Learn how Platform as a Service (PaaS) can streamline application development processes and make resource management easy.
In his session at @ThingsExpo, Chris Klein, CEO and Co-founder of Rachio, will discuss next generation communities that are using IoT to create more sustainable, intelligent communities. One example is Sterling Ranch, a 10,000 home development that – with the help of Siemens – will integrate IoT technology into the community to provide residents with energy and water savings as well as intelligent security. Everything from stop lights to sprinkler systems to building infrastructures will run ef...
Whether your IoT service is connecting cars, homes, appliances, wearable, cameras or other devices, one question hangs in the balance – how do you actually make money from this service? The ability to turn your IoT service into profit requires the ability to create a monetization strategy that is flexible, scalable and working for you in real-time. It must be a transparent, smoothly implemented strategy that all stakeholders – from customers to the board – will be able to understand and comprehe...
Machine Learning helps make complex systems more efficient. By applying advanced Machine Learning techniques such as Cognitive Fingerprinting, wind project operators can utilize these tools to learn from collected data, detect regular patterns, and optimize their own operations. In his session at 18th Cloud Expo, Stuart Gillen, Director of Business Development at SparkCognition, will discuss how research has demonstrated the value of Machine Learning in delivering next generation analytics to im...
In the world of DevOps there are ‘known good practices’ – aka ‘patterns’ – and ‘known bad practices’ – aka ‘anti-patterns.' Many of these patterns and anti-patterns have been developed from real world experience, especially by the early adopters of DevOps theory; but many are more feasible in theory than in practice, especially for more recent entrants to the DevOps scene. In this power panel at @DevOpsSummit at 18th Cloud Expo, moderated by DevOps Conference Chair Andi Mann, panelists will dis...
See storage differently! Storage performance problems have only gotten worse and harder to solve as applications have become largely virtualized and moved to a cloud-based infrastructure. Storage performance in a virtualized environment is not just about IOPS, it is about how well that potential performance is guaranteed to individual VMs for these apps as the number of VMs keep going up real time. In his session at 18th Cloud Expo, Dhiraj Sehgal, in product and marketing at Tintri, will discu...
Unless you don’t use the internet, don’t live in California, or haven’t been paying attention to the recent news… you should be aware that self-driving cars are on their way to becoming a reality. I have seen them – they are real. If you believe in the future reality of self-driving cars, then continue reading on. If you don’t believe in the future possibilities, then I am not sure what to do to convince you other than discuss the very real changes that will roll out with the consumer producti...
Up until last year, enterprises that were looking into cloud services usually undertook a long-term pilot with one of the large cloud providers, running test and dev workloads in the cloud. With cloud’s transition to mainstream adoption in 2015, and with enterprises migrating more and more workloads into the cloud and in between public and private environments, the single-provider approach must be revisited. In his session at 18th Cloud Expo, Yoav Mor, multi-cloud solution evangelist at Cloudy...
There is an ever-growing explosion of new devices that are connected to the Internet using “cloud” solutions. This rapid growth is creating a massive new demand for efficient access to data. And it’s not just about connecting to that data anymore. This new demand is bringing new issues and challenges and it is important for companies to scale for the coming growth. And with that scaling comes the need for greater security, gathering and data analysis, storage, connectivity and, of course, the...
This is not a small hotel event. It is also not a big vendor party where politicians and entertainers are more important than real content. This is Cloud Expo, the world's longest-running conference and exhibition focused on Cloud Computing and all that it entails. If you want serious presentations and valuable insight about Cloud Computing for three straight days, then register now for Cloud Expo.
IoT device adoption is growing at staggering rates, and with it comes opportunity for developers to meet consumer demand for an ever more connected world. Wireless communication is the key part of the encompassing components of any IoT device. Wireless connectivity enhances the device utility at the expense of ease of use and deployment challenges. Since connectivity is fundamental for IoT device development, engineers must understand how to overcome the hurdles inherent in incorporating multipl...