Welcome!

News Feed Item

EPM Mining Issues Summary of 2013 Results and 2014 Projections for Its Sevier Lake Playa Sulphate of Potash Project

TORONTO, ONTARIO -- (Marketwired) -- 01/16/14 -- EPM Mining Ventures Inc. (TSX VENTURE:EPK)(OTCQX:EPKMF) ("EPM" or the "Company"), today issued a review of advancements accomplished during 2013 at its Sevier Lake Playa Sulphate of Potash Project located in southwestern Utah and offered guidance about what is planned for 2014.

"As C.E.O., I am very pleased with everything we achieved this past year and look forward to all that we will accomplish this year," said Lance D'Ambrosio, Chief Executive Officer of EPM. "Looking back, I have to say that without a doubt, our biggest success was completing our Preliminary Feasibility Study. So let me start by sharing a few highlights from that."

Preliminary Feasibility Study Highlights

--  The PFS forecasts average annual SOP production of 300,000 metric tonnes
    (t) with an estimated Net Present Value ("NPV") of $629 million (after
    tax, inflated, 8% discount rate) and an estimated Internal Rate of
    Return ("IRR") of 20% (after tax, inflated). 
--  The PFS includes an updated Mineral Resource Estimate that includes
    31.486 million tonnes of SOP in the Measured and Indicated categories, a
    7% increase from previously published estimates, due primarily to
    results of recent drilling. 
--  Economic Highlights: 

----------------------------------------------------------------------------
Economic Indicators                                                         
----------------------------------------------------------------------------
NPV (pretax, 8%)                                                     $ 957 M
----------------------------------------------------------------------------
NPV (after tax, 8%)                                                  $ 629 M
----------------------------------------------------------------------------
IRR (pretax)                                                             24%
----------------------------------------------------------------------------
IRR (after tax)                                                          20%
----------------------------------------------------------------------------
Average Annual SOP Production                                      300,000 t
----------------------------------------------------------------------------
Mine Life                                                           30 years
----------------------------------------------------------------------------
Initial Direct Capital Costs                                         $ 292 M
----------------------------------------------------------------------------
Initial Indirect Capital Costs                                        $ 50 M
----------------------------------------------------------------------------
Initial Capital Contingency                                           $ 36 M
----------------------------------------------------------------------------
Operating Cost                                                    $ 180.91/t
----------------------------------------------------------------------------
Production Royalties (% of gross revenues)                             5.61%
----------------------------------------------------------------------------
Year 3 EBITDA (nameplate production)                                 $ 143 M
----------------------------------------------------------------------------
Payback Period (from commencement of production)                   5.5 years
----------------------------------------------------------------------------
Measured & Indicated SOP Resource                                  31.486 Mt
----------------------------------------------------------------------------

--  The economic analysis in the PFS is based upon the following
    assumptions: 
    --  100% Equity 
    --  Production Ramp-Up over two years, reaching full production in Year
        3 
        --  50,000 tonnes in Year 1; 100,000 tonnes in Year 2; and 300,000
            tonnes in Year 3 
    --  Construction on playa beginning in Preproduction Year 3 ("PP-3") 
    --  Effective tax rate of approximately 29% 
--  The economic analysis was based upon Measured and Indicated Mineral
    Resources only. No Inferred Resources were included in the analysis.
    Mineral Resources that are not Mineral Reserves do not have demonstrated
    economic viability. 
--  Capital Costs - the total direct capital costs of the Project are
    estimated to be $292 M, not including indirect costs and contingency, as
    of 2013. All capital costs in the economic model are inflated by 2%
    annually beginning in year PP-3. Contingency is 12% of direct capital
    costs. The capital cost estimate has an accuracy of +25%/-20%. 
--  Operating Costs - the total cash operating costs of the Project are
    estimated to be $180.91/t as of 2013. All operating costs in the
    economic model are inflated by 2% annually beginning in year PP-3. 

"In 2013 as part of the PFS, we conducted a comprehensive study of the playa and made significant progress with our engineering," said Lance. "These efforts provided us with important insights and a detailed path forward. The highlights include:"

Hydrology Highlights

--  A comprehensive groundwater modeling effort was completed that included
    two- and three-dimensional models of the playa system. The models
    incorporated layer elevations derived from intercepts logged from over
    400 boreholes and wells drilled during the exploration programs. 
--  Field data incorporated into the models included estimates of hydraulic
    conductivity and storage coefficients based on hydrophysical and aquifer
    stress tests employing both wells and trenches. Site-specific estimates
    of the vertical infiltration rate and evapotranspiration were also
    obtained. 
    --  In the latest program, five single-hole pump tests were performed;
        four well-to-trench tests; nine well-to-well tests; and one trench-
        to-trench test. These studies yielded substantial new data that
        significantly improved our understanding of playa hydrology. 
--  Initial modeling determined that the target production rate of 300,000
    tpy could be achieved based upon the hydro-physical characteristics of
    the deposit. Multiple simulations incorporating trench spacing, well
    layouts, and flow rates were carried out to prototype designs. 
    --  Results showed that acceptable brine production could be extracted
        from two trench phases, based on 1,000 meter spacing, followed by
        well extraction with individual shafts set about 400 meters. 

Engineering Highlights

--  Developed an optimized process flow sheet anticipated to provide
    improved operating benefits and flexibility while maintaining a balance
    between production, expense, and potential additional mineral
    production. 
--  Completed thermodynamic modeling and pilot-plant testing of pond
    crystallization. In addition, conducted bench-scale testing with Hazen
    Research and Swenson Technologies for the flotation and multiple effect
    crystallizer circuits. The thermodynamic modeling and subsequent bench-
    scale test-work confirmed projected plant recoveries of 78%. 
--  Developed civil construction designs for the plant and rail load-out
    facility as well as all playa infrastructure. The capital cost estimate
    in the PFS included budgetary quotes on 93% of all plant mechanical
    equipment costs. 

"As I briefly mentioned before, we successfully expanded our resource estimates by about seven percent," Lance added. "While we expect to release mineral reserves with our feasibility study, we are very pleased to provide a summary of the basis for the resource estimate expansion."

Resource Estimate Expansion Highlights

--  Norwest completed an updated Mineral Resource Estimate based upon data
    collected from the original drilling and exploration program conducted
    in 2011-2012 as well as a second drilling and exploration program
    conducted in 2013. 
--  The total Measured and Indicated Resource for SOP increased from 29.485
    Mt in the May 2012 Technical Report, to 31.486 Mt in the PFS, an
    increase of approximately 7%, primarily due to the results of the 2013
    drilling program. 
--  No claim for Mineral Reserves has been made at this time pending further
    verification of the hydrologic models via longer-term pilot testing
    planned during the Feasibility Study phase. 

"We received several important approvals this past year," Lance stated. "And our environmental and permitting programs continue to progress. Highlights from these include:"

Environmental, Permitting, & Regulatory Highlights

--  The Company met with the Utah Division of Air Quality ("UDAQ") in August
    2013. In that meeting, UDAQ determined that the company could proceed
    along a "dual permit" approach. This means that a Minor Source permit is
    all that is required for initial work on the playa to begin while a
    Major Source Permit could be added later when construction of the
    processing plant is required. 
    --  An Air Approval order for the Minor Source Permit was submitted to
        UDAQ in October 2013. An approval is expected shortly. 
    --  In July of 2013, the company started an on-site monitoring program
        for Prevention of Significant Deterioration (PSD), or the Major
        Source Permit. 
--  The BLM's Fillmore Field Office continued progress with the EIS and
    selected a third-party contractor to write the EIS document in August
    2013. Technical resource reports were prepared by CH2M Hill and
    submitted to BLM for their review and approval in November 2013. BLM
    selection of the third-party contractor is an important step to moving
    the EIS process forward. 
--  The BLM Plan of Operations and DOGM Large Mine Permit, historically two
    separate documents, are being consolidated into a single mine plan
    document (the "Mine Plan") agreed to by both agencies. The BLM has
    reviewed the Mine Plan and determined it was "Sufficiently Complete" in
    July 2013. A consolidated Mine Plan will allow for the Company to have
    one all-encompassing document that meets the requirement for the two
    agencies. 
--  A key decision in June 2013 by the Environmental Protection Agency and
    the United States Army Corps of Engineers ("USACE") determined that
    there are no Waters of the United States on the Sevier Lake Playa. 
    --  USACE determined that the Sevier Lake Playa is not a regulated
        feature under Section 404 of the Clean Water Act ("Act") and as such
        is exempt from permitting requirements under the Act. 
    --  Therefore, certain federal permits relating to water will not be
        required. This decision simplifies the permitting process and
        results in significant savings of time and money. 
--  In 2013, the Company submitted all water rights applications to the
    State Engineer, for which there were only four protestants. 
    --  In August 2013, the Company along with Holland and Hart and CH2M
        Hill discussed EPM's water rights presentation with the State
        Engineer in Delta, Utah. The hearing went very well and the Company
        anticipates that all water right applications will be approved by
        the third quarter 2014. 

Outlook for 2014

"2014 should be a banner year for us. We expect to complete most of the pre-construction milestones, nearly complete our EIS, and conclude all other necessary permitting," Lance indicated. "And soon, we will be kicking-off our Feasibility Study. While the PFS only considered SOP production, we anticipate that the Feasibility Study will consider the production of specialty products in addition to SOP including, magnesium sulphate, magnesium chloride, sodium sulphate, and possibly lithium," Lance said. "Given the presence of the other known constituents in our brine resource, we expect these minerals to provide the Company with a significant source of additional value if such minerals prove to be economic as the result of further studies."

About EPM Mining Ventures

EPM Mining Ventures Inc. is a development-stage company focused on specialty fertilizers. Through Peak Minerals Inc., its indirect wholly-owned subsidiary, EPM controls directly or through agreement mineral leases on more than 124,000 acres on its Sevier Lake Playa property in Millard County, Utah. With a brine resource known to contain potassium, magnesium, sulphate, lithium and a suite of other beneficial minerals, EPM is targeting the development and production of specialty fertilizers, including SOP, through the use of a cost-effective solar evaporation process. SOP and other specialty fertilizers are used in the production of high value, chloride-sensitive crops such as fruits, vegetables, and tree nuts. With the recent completion of a Preliminary Feasibility Study, the Company is currently engaged in engineering and analysis designed to support a feasibility study, environmental permitting, and ultimately mineral production.

For more information, please visit our web site at www.epmmining.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
EPM Mining Ventures Inc.
Lance D'Ambrosio
Chief Executive Officer
(801) 485-0223
www.epmmining.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Everyone wants the rainbow - reduced IT costs, scalability, continuity, flexibility, manageability, and innovation. But in order to get to that collaboration rainbow, you need the cloud! In this presentation, we'll cover three areas: First - the rainbow of benefits from cloud collaboration. There are many different reasons why more and more companies and institutions are moving to the cloud. Benefits include: cost savings (reducing on-prem infrastructure, reducing data center foot print, r...
They say multi-cloud is coming, but organizations are leveraging multiple clouds already. According to a study by 451 Research, only 21% of organizations were using a single cloud. If you've found yourself unprepared for the barrage of cloud services introduced in your organization, you will need to change your approach to engaging with the business and engaging with vendors. Look at technologies that are on the way and work with the internal players involved to have a plan in place when the ine...
Excitement and interest in APIs has skyrocketed in recent years. However, if you ask a room full of IT professionals "What is an API", you will get a wide array of answers. There exists a wide knowledge gap between API experts and those that have a general idea of what they are, but are unsure of what they have been for in the past, what they look like now, and how they can be used to expand your business in the future. In this session John will cover what the history of APIs, what an API looks ...
DXWorldEXPO LLC, the producer of the world's most influential technology conferences and trade shows has announced the 22nd International CloudEXPO | DXWorldEXPO "Early Bird Registration" is now open. Register for Full Conference "Gold Pass" ▸ Here (Expo Hall ▸ Here)
Bill Schmarzo, Tech Chair of "Big Data | Analytics" of upcoming CloudEXPO | DXWorldEXPO New York (November 12-13, 2018, New York City) today announced the outline and schedule of the track. "The track has been designed in experience/degree order," said Schmarzo. "So, that folks who attend the entire track can leave the conference with some of the skills necessary to get their work done when they get back to their offices. It actually ties back to some work that I'm doing at the University of ...
The now mainstream platform changes stemming from the first Internet boom brought many changes but didn’t really change the basic relationship between servers and the applications running on them. In fact, that was sort of the point. In his session at 18th Cloud Expo, Gordon Haff, senior cloud strategy marketing and evangelism manager at Red Hat, will discuss how today’s workloads require a new model and a new platform for development and execution. The platform must handle a wide range of rec...
@DevOpsSummit at Cloud Expo, taking place November 12-13 in New York City, NY, is co-located with 22nd international CloudEXPO | first international DXWorldEXPO and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time t...
The Internet of Things will challenge the status quo of how IT and development organizations operate. Or will it? Certainly the fog layer of IoT requires special insights about data ontology, security and transactional integrity. But the developmental challenges are the same: People, Process and Platform and how we integrate our thinking to solve complicated problems. In his session at 19th Cloud Expo, Craig Sproule, CEO of Metavine, demonstrated how to move beyond today's coding paradigm and sh...
DevOps with IBMz? You heard right. Maybe you're wondering what a developer can do to speed up the entire development cycle--coding, testing, source code management, and deployment-? In this session you will learn about how to integrate z application assets into a DevOps pipeline using familiar tools like Jenkins and UrbanCode Deploy, plus z/OSMF workflows, all of which can increase deployment speeds while simultaneously improving reliability. You will also learn how to provision mainframe syste...
CloudEXPO New York 2018, colocated with DXWorldEXPO New York 2018 will be held November 11-13, 2018, in New York City and will bring together Cloud Computing, FinTech and Blockchain, Digital Transformation, Big Data, Internet of Things, DevOps, AI, Machine Learning and WebRTC to one location.
The best way to leverage your Cloud Expo presence as a sponsor and exhibitor is to plan your news announcements around our events. The press covering Cloud Expo and @ThingsExpo will have access to these releases and will amplify your news announcements. More than two dozen Cloud companies either set deals at our shows or have announced their mergers and acquisitions at Cloud Expo. Product announcements during our show provide your company with the most reach through our targeted audiences.
Cell networks have the advantage of long-range communications, reaching an estimated 90% of the world. But cell networks such as 2G, 3G and LTE consume lots of power and were designed for connecting people. They are not optimized for low- or battery-powered devices or for IoT applications with infrequently transmitted data. Cell IoT modules that support narrow-band IoT and 4G cell networks will enable cell connectivity, device management, and app enablement for low-power wide-area network IoT. B...
DevOpsSummit New York 2018, colocated with CloudEXPO | DXWorldEXPO New York 2018 will be held November 11-13, 2018, in New York City. Digital Transformation (DX) is a major focus with the introduction of DXWorldEXPO within the program. Successful transformation requires a laser focus on being data-driven and on using all the tools available that enable transformation if they plan to survive over the long term.
What are the new priorities for the connected business? First: businesses need to think differently about the types of connections they will need to make – these span well beyond the traditional app to app into more modern forms of integration including SaaS integrations, mobile integrations, APIs, device integration and Big Data integration. It’s important these are unified together vs. doing them all piecemeal. Second, these types of connections need to be simple to design, adapt and configure...
Traditional on-premises data centers have long been the domain of modern data platforms like Apache Hadoop, meaning companies who build their business on public cloud were challenged to run Big Data processing and analytics at scale. But recent advancements in Hadoop performance, security, and most importantly cloud-native integrations, are giving organizations the ability to truly gain value from all their data. In his session at 19th Cloud Expo, David Tishgart, Director of Product Marketing ...