Welcome!

News Feed Item

EPM Mining Issues Summary of 2013 Results and 2014 Projections for Its Sevier Lake Playa Sulphate of Potash Project

TORONTO, ONTARIO -- (Marketwired) -- 01/16/14 -- EPM Mining Ventures Inc. (TSX VENTURE:EPK)(OTCQX:EPKMF) ("EPM" or the "Company"), today issued a review of advancements accomplished during 2013 at its Sevier Lake Playa Sulphate of Potash Project located in southwestern Utah and offered guidance about what is planned for 2014.

"As C.E.O., I am very pleased with everything we achieved this past year and look forward to all that we will accomplish this year," said Lance D'Ambrosio, Chief Executive Officer of EPM. "Looking back, I have to say that without a doubt, our biggest success was completing our Preliminary Feasibility Study. So let me start by sharing a few highlights from that."

Preliminary Feasibility Study Highlights

--  The PFS forecasts average annual SOP production of 300,000 metric tonnes
    (t) with an estimated Net Present Value ("NPV") of $629 million (after
    tax, inflated, 8% discount rate) and an estimated Internal Rate of
    Return ("IRR") of 20% (after tax, inflated). 
--  The PFS includes an updated Mineral Resource Estimate that includes
    31.486 million tonnes of SOP in the Measured and Indicated categories, a
    7% increase from previously published estimates, due primarily to
    results of recent drilling. 
--  Economic Highlights: 

----------------------------------------------------------------------------
Economic Indicators                                                         
----------------------------------------------------------------------------
NPV (pretax, 8%)                                                     $ 957 M
----------------------------------------------------------------------------
NPV (after tax, 8%)                                                  $ 629 M
----------------------------------------------------------------------------
IRR (pretax)                                                             24%
----------------------------------------------------------------------------
IRR (after tax)                                                          20%
----------------------------------------------------------------------------
Average Annual SOP Production                                      300,000 t
----------------------------------------------------------------------------
Mine Life                                                           30 years
----------------------------------------------------------------------------
Initial Direct Capital Costs                                         $ 292 M
----------------------------------------------------------------------------
Initial Indirect Capital Costs                                        $ 50 M
----------------------------------------------------------------------------
Initial Capital Contingency                                           $ 36 M
----------------------------------------------------------------------------
Operating Cost                                                    $ 180.91/t
----------------------------------------------------------------------------
Production Royalties (% of gross revenues)                             5.61%
----------------------------------------------------------------------------
Year 3 EBITDA (nameplate production)                                 $ 143 M
----------------------------------------------------------------------------
Payback Period (from commencement of production)                   5.5 years
----------------------------------------------------------------------------
Measured & Indicated SOP Resource                                  31.486 Mt
----------------------------------------------------------------------------

--  The economic analysis in the PFS is based upon the following
    assumptions: 
    --  100% Equity 
    --  Production Ramp-Up over two years, reaching full production in Year
        3 
        --  50,000 tonnes in Year 1; 100,000 tonnes in Year 2; and 300,000
            tonnes in Year 3 
    --  Construction on playa beginning in Preproduction Year 3 ("PP-3") 
    --  Effective tax rate of approximately 29% 
--  The economic analysis was based upon Measured and Indicated Mineral
    Resources only. No Inferred Resources were included in the analysis.
    Mineral Resources that are not Mineral Reserves do not have demonstrated
    economic viability. 
--  Capital Costs - the total direct capital costs of the Project are
    estimated to be $292 M, not including indirect costs and contingency, as
    of 2013. All capital costs in the economic model are inflated by 2%
    annually beginning in year PP-3. Contingency is 12% of direct capital
    costs. The capital cost estimate has an accuracy of +25%/-20%. 
--  Operating Costs - the total cash operating costs of the Project are
    estimated to be $180.91/t as of 2013. All operating costs in the
    economic model are inflated by 2% annually beginning in year PP-3. 

"In 2013 as part of the PFS, we conducted a comprehensive study of the playa and made significant progress with our engineering," said Lance. "These efforts provided us with important insights and a detailed path forward. The highlights include:"

Hydrology Highlights

--  A comprehensive groundwater modeling effort was completed that included
    two- and three-dimensional models of the playa system. The models
    incorporated layer elevations derived from intercepts logged from over
    400 boreholes and wells drilled during the exploration programs. 
--  Field data incorporated into the models included estimates of hydraulic
    conductivity and storage coefficients based on hydrophysical and aquifer
    stress tests employing both wells and trenches. Site-specific estimates
    of the vertical infiltration rate and evapotranspiration were also
    obtained. 
    --  In the latest program, five single-hole pump tests were performed;
        four well-to-trench tests; nine well-to-well tests; and one trench-
        to-trench test. These studies yielded substantial new data that
        significantly improved our understanding of playa hydrology. 
--  Initial modeling determined that the target production rate of 300,000
    tpy could be achieved based upon the hydro-physical characteristics of
    the deposit. Multiple simulations incorporating trench spacing, well
    layouts, and flow rates were carried out to prototype designs. 
    --  Results showed that acceptable brine production could be extracted
        from two trench phases, based on 1,000 meter spacing, followed by
        well extraction with individual shafts set about 400 meters. 

Engineering Highlights

--  Developed an optimized process flow sheet anticipated to provide
    improved operating benefits and flexibility while maintaining a balance
    between production, expense, and potential additional mineral
    production. 
--  Completed thermodynamic modeling and pilot-plant testing of pond
    crystallization. In addition, conducted bench-scale testing with Hazen
    Research and Swenson Technologies for the flotation and multiple effect
    crystallizer circuits. The thermodynamic modeling and subsequent bench-
    scale test-work confirmed projected plant recoveries of 78%. 
--  Developed civil construction designs for the plant and rail load-out
    facility as well as all playa infrastructure. The capital cost estimate
    in the PFS included budgetary quotes on 93% of all plant mechanical
    equipment costs. 

"As I briefly mentioned before, we successfully expanded our resource estimates by about seven percent," Lance added. "While we expect to release mineral reserves with our feasibility study, we are very pleased to provide a summary of the basis for the resource estimate expansion."

Resource Estimate Expansion Highlights

--  Norwest completed an updated Mineral Resource Estimate based upon data
    collected from the original drilling and exploration program conducted
    in 2011-2012 as well as a second drilling and exploration program
    conducted in 2013. 
--  The total Measured and Indicated Resource for SOP increased from 29.485
    Mt in the May 2012 Technical Report, to 31.486 Mt in the PFS, an
    increase of approximately 7%, primarily due to the results of the 2013
    drilling program. 
--  No claim for Mineral Reserves has been made at this time pending further
    verification of the hydrologic models via longer-term pilot testing
    planned during the Feasibility Study phase. 

"We received several important approvals this past year," Lance stated. "And our environmental and permitting programs continue to progress. Highlights from these include:"

Environmental, Permitting, & Regulatory Highlights

--  The Company met with the Utah Division of Air Quality ("UDAQ") in August
    2013. In that meeting, UDAQ determined that the company could proceed
    along a "dual permit" approach. This means that a Minor Source permit is
    all that is required for initial work on the playa to begin while a
    Major Source Permit could be added later when construction of the
    processing plant is required. 
    --  An Air Approval order for the Minor Source Permit was submitted to
        UDAQ in October 2013. An approval is expected shortly. 
    --  In July of 2013, the company started an on-site monitoring program
        for Prevention of Significant Deterioration (PSD), or the Major
        Source Permit. 
--  The BLM's Fillmore Field Office continued progress with the EIS and
    selected a third-party contractor to write the EIS document in August
    2013. Technical resource reports were prepared by CH2M Hill and
    submitted to BLM for their review and approval in November 2013. BLM
    selection of the third-party contractor is an important step to moving
    the EIS process forward. 
--  The BLM Plan of Operations and DOGM Large Mine Permit, historically two
    separate documents, are being consolidated into a single mine plan
    document (the "Mine Plan") agreed to by both agencies. The BLM has
    reviewed the Mine Plan and determined it was "Sufficiently Complete" in
    July 2013. A consolidated Mine Plan will allow for the Company to have
    one all-encompassing document that meets the requirement for the two
    agencies. 
--  A key decision in June 2013 by the Environmental Protection Agency and
    the United States Army Corps of Engineers ("USACE") determined that
    there are no Waters of the United States on the Sevier Lake Playa. 
    --  USACE determined that the Sevier Lake Playa is not a regulated
        feature under Section 404 of the Clean Water Act ("Act") and as such
        is exempt from permitting requirements under the Act. 
    --  Therefore, certain federal permits relating to water will not be
        required. This decision simplifies the permitting process and
        results in significant savings of time and money. 
--  In 2013, the Company submitted all water rights applications to the
    State Engineer, for which there were only four protestants. 
    --  In August 2013, the Company along with Holland and Hart and CH2M
        Hill discussed EPM's water rights presentation with the State
        Engineer in Delta, Utah. The hearing went very well and the Company
        anticipates that all water right applications will be approved by
        the third quarter 2014. 

Outlook for 2014

"2014 should be a banner year for us. We expect to complete most of the pre-construction milestones, nearly complete our EIS, and conclude all other necessary permitting," Lance indicated. "And soon, we will be kicking-off our Feasibility Study. While the PFS only considered SOP production, we anticipate that the Feasibility Study will consider the production of specialty products in addition to SOP including, magnesium sulphate, magnesium chloride, sodium sulphate, and possibly lithium," Lance said. "Given the presence of the other known constituents in our brine resource, we expect these minerals to provide the Company with a significant source of additional value if such minerals prove to be economic as the result of further studies."

About EPM Mining Ventures

EPM Mining Ventures Inc. is a development-stage company focused on specialty fertilizers. Through Peak Minerals Inc., its indirect wholly-owned subsidiary, EPM controls directly or through agreement mineral leases on more than 124,000 acres on its Sevier Lake Playa property in Millard County, Utah. With a brine resource known to contain potassium, magnesium, sulphate, lithium and a suite of other beneficial minerals, EPM is targeting the development and production of specialty fertilizers, including SOP, through the use of a cost-effective solar evaporation process. SOP and other specialty fertilizers are used in the production of high value, chloride-sensitive crops such as fruits, vegetables, and tree nuts. With the recent completion of a Preliminary Feasibility Study, the Company is currently engaged in engineering and analysis designed to support a feasibility study, environmental permitting, and ultimately mineral production.

For more information, please visit our web site at www.epmmining.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
EPM Mining Ventures Inc.
Lance D'Ambrosio
Chief Executive Officer
(801) 485-0223
www.epmmining.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Microsoft Azure Container Services can be used for container deployment in a variety of ways including support for Orchestrators like Kubernetes, Docker Swarm and Mesos. However, the abstraction for app development that support application self-healing, scaling and so on may not be at the right level. Helm and Draft makes this a lot easier. In this primarily demo-driven session at @DevOpsSummit at 21st Cloud Expo, Raghavan "Rags" Srinivas, a Cloud Solutions Architect/Evangelist at Microsoft, wi...
The next XaaS is CICDaaS. Why? Because CICD saves developers a huge amount of time. CD is an especially great option for projects that require multiple and frequent contributions to be integrated. But… securing CICD best practices is an emerging, essential, yet little understood practice for DevOps teams and their Cloud Service Providers. The only way to get CICD to work in a highly secure environment takes collaboration, patience and persistence. Building CICD in the cloud requires rigorous ar...
Containers are rapidly finding their way into enterprise data centers, but change is difficult. How do enterprises transform their architecture with technologies like containers without losing the reliable components of their current solutions? In his session at @DevOpsSummit at 21st Cloud Expo, Tony Campbell, Director, Educational Services at CoreOS, will explore the challenges organizations are facing today as they move to containers and go over how Kubernetes applications can deploy with lega...
In his session at 21st Cloud Expo, Raju Shreewastava, founder of Big Data Trunk, will provide a fun and simple way to introduce Machine Leaning to anyone and everyone. Together we will solve a machine learning problem and find an easy way to be able to do machine learning without even coding. Raju Shreewastava is the founder of Big Data Trunk (www.BigDataTrunk.com), a Big Data Training and consulting firm with offices in the United States. He previously led the data warehouse/business intellige...
Today most companies are adopting or evaluating container technology - Docker in particular - to speed up application deployment, drive down cost, ease management and make application delivery more flexible overall. As with most new architectures, this dream takes significant work to become a reality. Even when you do get your application componentized enough and packaged properly, there are still challenges for DevOps teams to making the shift to continuous delivery and achieving that reducti...
We all know that end users experience the Internet primarily with mobile devices. From an app development perspective, we know that successfully responding to the needs of mobile customers depends on rapid DevOps – failing fast, in short, until the right solution evolves in your customers' relationship to your business. Whether you’re decomposing an SOA monolith, or developing a new application cloud natively, it’s not a question of using microservices – not doing so will be a path to eventual b...
In a recent survey, Sumo Logic surveyed 1,500 customers who employ cloud services such as Amazon Web Services (AWS), Microsoft Azure, and Google Cloud Platform (GCP). According to the survey, a quarter of the respondents have already deployed Docker containers and nearly as many (23 percent) are employing the AWS Lambda serverless computing framework. It’s clear: serverless is here to stay. The adoption does come with some needed changes, within both application development and operations. Tha...
As hybrid cloud becomes the de-facto standard mode of operation for most enterprises, new challenges arise on how to efficiently and economically share data across environments. In his session at 21st Cloud Expo, Dr. Allon Cohen, VP of Product at Elastifile, will explore new techniques and best practices that help enterprise IT benefit from the advantages of hybrid cloud environments by enabling data availability for both legacy enterprise and cloud-native mission critical applications. By rev...
In his Opening Keynote at 21st Cloud Expo, John Considine, General Manager of IBM Cloud Infrastructure, will lead you through the exciting evolution of the cloud. He'll look at this major disruption from the perspective of technology, business models, and what this means for enterprises of all sizes. John Considine is General Manager of Cloud Infrastructure Services at IBM. In that role he is responsible for leading IBM’s public cloud infrastructure including strategy, development, and offering ...
SYS-CON Events announced today that Ryobi Systems will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Ryobi Systems Co., Ltd., as an information service company, specialized in business support for local governments and medical industry. We are challenging to achive the precision farming with AI. For more information, visit http:...
Amazon is pursuing new markets and disrupting industries at an incredible pace. Almost every industry seems to be in its crosshairs. Companies and industries that once thought they were safe are now worried about being “Amazoned.”. The new watch word should be “Be afraid. Be very afraid.” In his session 21st Cloud Expo, Chris Kocher, a co-founder of Grey Heron, will address questions such as: What new areas is Amazon disrupting? How are they doing this? Where are they likely to go? What are th...
As you move to the cloud, your network should be efficient, secure, and easy to manage. An enterprise adopting a hybrid or public cloud needs systems and tools that provide: Agility: ability to deliver applications and services faster, even in complex hybrid environments Easier manageability: enable reliable connectivity with complete oversight as the data center network evolves Greater efficiency: eliminate wasted effort while reducing errors and optimize asset utilization Security: imple...
High-velocity engineering teams are applying not only continuous delivery processes, but also lessons in experimentation from established leaders like Amazon, Netflix, and Facebook. These companies have made experimentation a foundation for their release processes, allowing them to try out major feature releases and redesigns within smaller groups before making them broadly available. In his session at 21st Cloud Expo, Brian Lucas, Senior Staff Engineer at Optimizely, will discuss how by using...
In this strange new world where more and more power is drawn from business technology, companies are effectively straddling two paths on the road to innovation and transformation into digital enterprises. The first path is the heritage trail – with “legacy” technology forming the background. Here, extant technologies are transformed by core IT teams to provide more API-driven approaches. Legacy systems can restrict companies that are transitioning into digital enterprises. To truly become a lead...
Companies are harnessing data in ways we once associated with science fiction. Analysts have access to a plethora of visualization and reporting tools, but considering the vast amount of data businesses collect and limitations of CPUs, end users are forced to design their structures and systems with limitations. Until now. As the cloud toolkit to analyze data has evolved, GPUs have stepped in to massively parallel SQL, visualization and machine learning.