Click here to close now.


News Feed Item

EPM Mining Issues Summary of 2013 Results and 2014 Projections for Its Sevier Lake Playa Sulphate of Potash Project

TORONTO, ONTARIO -- (Marketwired) -- 01/16/14 -- EPM Mining Ventures Inc. (TSX VENTURE:EPK)(OTCQX:EPKMF) ("EPM" or the "Company"), today issued a review of advancements accomplished during 2013 at its Sevier Lake Playa Sulphate of Potash Project located in southwestern Utah and offered guidance about what is planned for 2014.

"As C.E.O., I am very pleased with everything we achieved this past year and look forward to all that we will accomplish this year," said Lance D'Ambrosio, Chief Executive Officer of EPM. "Looking back, I have to say that without a doubt, our biggest success was completing our Preliminary Feasibility Study. So let me start by sharing a few highlights from that."

Preliminary Feasibility Study Highlights

--  The PFS forecasts average annual SOP production of 300,000 metric tonnes
    (t) with an estimated Net Present Value ("NPV") of $629 million (after
    tax, inflated, 8% discount rate) and an estimated Internal Rate of
    Return ("IRR") of 20% (after tax, inflated). 
--  The PFS includes an updated Mineral Resource Estimate that includes
    31.486 million tonnes of SOP in the Measured and Indicated categories, a
    7% increase from previously published estimates, due primarily to
    results of recent drilling. 
--  Economic Highlights: 

Economic Indicators                                                         
NPV (pretax, 8%)                                                     $ 957 M
NPV (after tax, 8%)                                                  $ 629 M
IRR (pretax)                                                             24%
IRR (after tax)                                                          20%
Average Annual SOP Production                                      300,000 t
Mine Life                                                           30 years
Initial Direct Capital Costs                                         $ 292 M
Initial Indirect Capital Costs                                        $ 50 M
Initial Capital Contingency                                           $ 36 M
Operating Cost                                                    $ 180.91/t
Production Royalties (% of gross revenues)                             5.61%
Year 3 EBITDA (nameplate production)                                 $ 143 M
Payback Period (from commencement of production)                   5.5 years
Measured & Indicated SOP Resource                                  31.486 Mt

--  The economic analysis in the PFS is based upon the following
    --  100% Equity 
    --  Production Ramp-Up over two years, reaching full production in Year
        --  50,000 tonnes in Year 1; 100,000 tonnes in Year 2; and 300,000
            tonnes in Year 3 
    --  Construction on playa beginning in Preproduction Year 3 ("PP-3") 
    --  Effective tax rate of approximately 29% 
--  The economic analysis was based upon Measured and Indicated Mineral
    Resources only. No Inferred Resources were included in the analysis.
    Mineral Resources that are not Mineral Reserves do not have demonstrated
    economic viability. 
--  Capital Costs - the total direct capital costs of the Project are
    estimated to be $292 M, not including indirect costs and contingency, as
    of 2013. All capital costs in the economic model are inflated by 2%
    annually beginning in year PP-3. Contingency is 12% of direct capital
    costs. The capital cost estimate has an accuracy of +25%/-20%. 
--  Operating Costs - the total cash operating costs of the Project are
    estimated to be $180.91/t as of 2013. All operating costs in the
    economic model are inflated by 2% annually beginning in year PP-3. 

"In 2013 as part of the PFS, we conducted a comprehensive study of the playa and made significant progress with our engineering," said Lance. "These efforts provided us with important insights and a detailed path forward. The highlights include:"

Hydrology Highlights

--  A comprehensive groundwater modeling effort was completed that included
    two- and three-dimensional models of the playa system. The models
    incorporated layer elevations derived from intercepts logged from over
    400 boreholes and wells drilled during the exploration programs. 
--  Field data incorporated into the models included estimates of hydraulic
    conductivity and storage coefficients based on hydrophysical and aquifer
    stress tests employing both wells and trenches. Site-specific estimates
    of the vertical infiltration rate and evapotranspiration were also
    --  In the latest program, five single-hole pump tests were performed;
        four well-to-trench tests; nine well-to-well tests; and one trench-
        to-trench test. These studies yielded substantial new data that
        significantly improved our understanding of playa hydrology. 
--  Initial modeling determined that the target production rate of 300,000
    tpy could be achieved based upon the hydro-physical characteristics of
    the deposit. Multiple simulations incorporating trench spacing, well
    layouts, and flow rates were carried out to prototype designs. 
    --  Results showed that acceptable brine production could be extracted
        from two trench phases, based on 1,000 meter spacing, followed by
        well extraction with individual shafts set about 400 meters. 

Engineering Highlights

--  Developed an optimized process flow sheet anticipated to provide
    improved operating benefits and flexibility while maintaining a balance
    between production, expense, and potential additional mineral
--  Completed thermodynamic modeling and pilot-plant testing of pond
    crystallization. In addition, conducted bench-scale testing with Hazen
    Research and Swenson Technologies for the flotation and multiple effect
    crystallizer circuits. The thermodynamic modeling and subsequent bench-
    scale test-work confirmed projected plant recoveries of 78%. 
--  Developed civil construction designs for the plant and rail load-out
    facility as well as all playa infrastructure. The capital cost estimate
    in the PFS included budgetary quotes on 93% of all plant mechanical
    equipment costs. 

"As I briefly mentioned before, we successfully expanded our resource estimates by about seven percent," Lance added. "While we expect to release mineral reserves with our feasibility study, we are very pleased to provide a summary of the basis for the resource estimate expansion."

Resource Estimate Expansion Highlights

--  Norwest completed an updated Mineral Resource Estimate based upon data
    collected from the original drilling and exploration program conducted
    in 2011-2012 as well as a second drilling and exploration program
    conducted in 2013. 
--  The total Measured and Indicated Resource for SOP increased from 29.485
    Mt in the May 2012 Technical Report, to 31.486 Mt in the PFS, an
    increase of approximately 7%, primarily due to the results of the 2013
    drilling program. 
--  No claim for Mineral Reserves has been made at this time pending further
    verification of the hydrologic models via longer-term pilot testing
    planned during the Feasibility Study phase. 

"We received several important approvals this past year," Lance stated. "And our environmental and permitting programs continue to progress. Highlights from these include:"

Environmental, Permitting, & Regulatory Highlights

--  The Company met with the Utah Division of Air Quality ("UDAQ") in August
    2013. In that meeting, UDAQ determined that the company could proceed
    along a "dual permit" approach. This means that a Minor Source permit is
    all that is required for initial work on the playa to begin while a
    Major Source Permit could be added later when construction of the
    processing plant is required. 
    --  An Air Approval order for the Minor Source Permit was submitted to
        UDAQ in October 2013. An approval is expected shortly. 
    --  In July of 2013, the company started an on-site monitoring program
        for Prevention of Significant Deterioration (PSD), or the Major
        Source Permit. 
--  The BLM's Fillmore Field Office continued progress with the EIS and
    selected a third-party contractor to write the EIS document in August
    2013. Technical resource reports were prepared by CH2M Hill and
    submitted to BLM for their review and approval in November 2013. BLM
    selection of the third-party contractor is an important step to moving
    the EIS process forward. 
--  The BLM Plan of Operations and DOGM Large Mine Permit, historically two
    separate documents, are being consolidated into a single mine plan
    document (the "Mine Plan") agreed to by both agencies. The BLM has
    reviewed the Mine Plan and determined it was "Sufficiently Complete" in
    July 2013. A consolidated Mine Plan will allow for the Company to have
    one all-encompassing document that meets the requirement for the two
--  A key decision in June 2013 by the Environmental Protection Agency and
    the United States Army Corps of Engineers ("USACE") determined that
    there are no Waters of the United States on the Sevier Lake Playa. 
    --  USACE determined that the Sevier Lake Playa is not a regulated
        feature under Section 404 of the Clean Water Act ("Act") and as such
        is exempt from permitting requirements under the Act. 
    --  Therefore, certain federal permits relating to water will not be
        required. This decision simplifies the permitting process and
        results in significant savings of time and money. 
--  In 2013, the Company submitted all water rights applications to the
    State Engineer, for which there were only four protestants. 
    --  In August 2013, the Company along with Holland and Hart and CH2M
        Hill discussed EPM's water rights presentation with the State
        Engineer in Delta, Utah. The hearing went very well and the Company
        anticipates that all water right applications will be approved by
        the third quarter 2014. 

Outlook for 2014

"2014 should be a banner year for us. We expect to complete most of the pre-construction milestones, nearly complete our EIS, and conclude all other necessary permitting," Lance indicated. "And soon, we will be kicking-off our Feasibility Study. While the PFS only considered SOP production, we anticipate that the Feasibility Study will consider the production of specialty products in addition to SOP including, magnesium sulphate, magnesium chloride, sodium sulphate, and possibly lithium," Lance said. "Given the presence of the other known constituents in our brine resource, we expect these minerals to provide the Company with a significant source of additional value if such minerals prove to be economic as the result of further studies."

About EPM Mining Ventures

EPM Mining Ventures Inc. is a development-stage company focused on specialty fertilizers. Through Peak Minerals Inc., its indirect wholly-owned subsidiary, EPM controls directly or through agreement mineral leases on more than 124,000 acres on its Sevier Lake Playa property in Millard County, Utah. With a brine resource known to contain potassium, magnesium, sulphate, lithium and a suite of other beneficial minerals, EPM is targeting the development and production of specialty fertilizers, including SOP, through the use of a cost-effective solar evaporation process. SOP and other specialty fertilizers are used in the production of high value, chloride-sensitive crops such as fruits, vegetables, and tree nuts. With the recent completion of a Preliminary Feasibility Study, the Company is currently engaged in engineering and analysis designed to support a feasibility study, environmental permitting, and ultimately mineral production.

For more information, please visit our web site at

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

EPM Mining Ventures Inc.
Lance D'Ambrosio
Chief Executive Officer
(801) 485-0223

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Containers are all the rage among developers and web companies, but they also represent two very substantial benefits to larger organizations. First, they have the potential to dramatically accelerate the application lifecycle from software builds and testing to deployment and upgrades. Second they represent the first truly hybrid-approach to consuming infrastructure, allowing organizations to run the same workloads on any cloud, virtual machine or physical server. Together, they represent a ver...
SYS-CON Events announced today the Containers & Microservices Bootcamp, being held November 3-4, 2015, in conjunction with 17th Cloud Expo, @ThingsExpo, and @DevOpsSummit at the Santa Clara Convention Center in Santa Clara, CA. This is your chance to get started with the latest technology in the industry. Combined with real-world scenarios and use cases, the Containers and Microservices Bootcamp, led by Janakiram MSV, a Microsoft Regional Director, will include presentations as well as hands-on...
As more intelligent IoT applications shift into gear, they’re merging into the ever-increasing traffic flow of the Internet. It won’t be long before we experience bottlenecks, as IoT traffic peaks during rush hours. Organizations that are unprepared will find themselves by the side of the road unable to cross back into the fast lane. As billions of new devices begin to communicate and exchange data – will your infrastructure be scalable enough to handle this new interconnected world?
As operational failure becomes more acceptable to discuss within the software industry, the necessity for holding constructive, actionable postmortems increases. But most of what we know about postmortems from "pop culture" isn't actually relevant for the software systems we work on and within. In his session at DevOps Summit, J. Paul Reed will look at postmortem pitfalls, techniques, and tools you'll be able to take back to your own environment so they will be able to lay the foundations for h...
DevOps Summit, taking place at the Santa Clara Convention Center in Santa Clara, CA, and Javits Center in New York City, is co-located with 17th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait...
As a company adopts a DevOps approach to software development, what are key things that both the Dev and Ops side of the business must keep in mind to ensure effective continuous delivery? In his session at DevOps Summit, Mark Hydar, Head of DevOps, Ericsson TV Platforms, will share best practices and provide helpful tips for Ops teams to adopt an open line of communication with the development side of the house to ensure success between the two sides.
The enterprise is being consumerized, and the consumer is being enterprised. Moore's Law does not matter anymore, the future belongs to business virtualization powered by invisible service architecture, powered by hyperscale and hyperconvergence, and facilitated by vertical streaming and horizontal scaling and consolidation. Both buyers and sellers want instant results, and from paperwork to paperless to mindless is the ultimate goal for any seamless transaction. The sweetest sweet spot in innov...
The IoT is upon us, but today’s databases, built on 30-year-old math, require multiple platforms to create a single solution. Data demands of the IoT require Big Data systems that can handle ingest, transactions and analytics concurrently adapting to varied situations as they occur, with speed at scale. In his session at @ThingsExpo, Chad Jones, chief strategy officer at Deep Information Sciences, will look differently at IoT data so enterprises can fully leverage their IoT potential. He’ll sha...
Developing software for the Internet of Things (IoT) comes with its own set of challenges. Security, privacy, and unified standards are a few key issues. In addition, each IoT product is comprised of at least three separate application components: the software embedded in the device, the backend big-data service, and the mobile application for the end user's controls. Each component is developed by a different team, using different technologies and practices, and deployed to a different stack/...
Chris Van Tuin, Chief Technologist for the Western US at Red Hat, has over 20 years of experience in IT and Software. Since joining Red Hat in 2005, he has been architecting solutions for strategic customers and partners with a focus on emerging technologies including IaaS, PaaS, and DevOps. He started his career at Intel in IT and Managed Hosting followed by leadership roles in services and sales engineering at Loudcloud and Linux startups.
Containers have changed the mind of IT in DevOps. They enable developers to work with dev, test, stage and production environments identically. Containers provide the right abstraction for microservices and many cloud platforms have integrated them into deployment pipelines. DevOps and Containers together help companies to achieve their business goals faster and more effectively.
With major technology companies and startups seriously embracing IoT strategies, now is the perfect time to attend @ThingsExpo in Silicon Valley. Learn what is going on, contribute to the discussions, and ensure that your enterprise is as "IoT-Ready" as it can be! Internet of @ThingsExpo, taking place Nov 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 17th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading in...
There will be 20 billion IoT devices connected to the Internet soon. What if we could control these devices with our voice, mind, or gestures? What if we could teach these devices how to talk to each other? What if these devices could learn how to interact with us (and each other) to make our lives better? What if Jarvis was real? How can I gain these super powers? In his session at 17th Cloud Expo, Chris Matthieu, co-founder and CTO of Octoblu, will show you!
Today air travel is a minefield of delays, hassles and customer disappointment. Airlines struggle to revitalize the experience. GE and M2Mi will demonstrate practical examples of how IoT solutions are helping airlines bring back personalization, reduce trip time and improve reliability. In their session at @ThingsExpo, Shyam Varan Nath, Principal Architect with GE, and Dr. Sarah Cooper, M2Mi's VP Business Development and Engineering, will explore the IoT cloud-based platform technologies driv...
The Internet of Everything is re-shaping technology trends–moving away from “request/response” architecture to an “always-on” Streaming Web where data is in constant motion and secure, reliable communication is an absolute necessity. As more and more THINGS go online, the challenges that developers will need to address will only increase exponentially. In his session at @ThingsExpo, Todd Greene, Founder & CEO of PubNub, will explore the current state of IoT connectivity and review key trends an...