Welcome!

News Feed Item

EPM Mining Issues Summary of 2013 Results and 2014 Projections for Its Sevier Lake Playa Sulphate of Potash Project

TORONTO, ONTARIO -- (Marketwired) -- 01/16/14 -- EPM Mining Ventures Inc. (TSX VENTURE: EPK)(OTCQX: EPKMF) ("EPM" or the "Company"), today issued a review of advancements accomplished during 2013 at its Sevier Lake Playa Sulphate of Potash Project located in southwestern Utah and offered guidance about what is planned for 2014.

"As C.E.O., I am very pleased with everything we achieved this past year and look forward to all that we will accomplish this year," said Lance D'Ambrosio, Chief Executive Officer of EPM. "Looking back, I have to say that without a doubt, our biggest success was completing our Preliminary Feasibility Study. So let me start by sharing a few highlights from that."

Preliminary Feasibility Study Highlights


--  The PFS forecasts average annual SOP production of 300,000 metric tonnes
    (t) with an estimated Net Present Value ("NPV") of $629 million (after
    tax, inflated, 8% discount rate) and an estimated Internal Rate of
    Return ("IRR") of 20% (after tax, inflated).
--  The PFS includes an updated Mineral Resource Estimate that includes
    31.486 million tonnes of SOP in the Measured and Indicated categories, a
    7% increase from previously published estimates, due primarily to
    results of recent drilling.
--  Economic Highlights:

----------------------------------------------------------------------------
Economic Indicators
----------------------------------------------------------------------------
NPV (pretax, 8%)                                                     $ 957 M
----------------------------------------------------------------------------
NPV (after tax, 8%)                                                  $ 629 M
----------------------------------------------------------------------------
IRR (pretax)                                                             24%
----------------------------------------------------------------------------
IRR (after tax)                                                          20%
----------------------------------------------------------------------------
Average Annual SOP Production                                      300,000 t
----------------------------------------------------------------------------
Mine Life                                                           30 years
----------------------------------------------------------------------------
Initial Direct Capital Costs                                         $ 292 M
----------------------------------------------------------------------------
Initial Indirect Capital Costs                                        $ 50 M
----------------------------------------------------------------------------
Initial Capital Contingency                                           $ 36 M
----------------------------------------------------------------------------
Operating Cost                                                    $ 180.91/t
----------------------------------------------------------------------------
Production Royalties (% of gross revenues)                             5.61%
----------------------------------------------------------------------------
Year 3 EBITDA (nameplate production)                                 $ 143 M
----------------------------------------------------------------------------
Payback Period (from commencement of production)                   5.5 years
----------------------------------------------------------------------------
Measured & Indicated SOP Resource                                  31.486 Mt
----------------------------------------------------------------------------

--  The economic analysis in the PFS is based upon the following
    assumptions:
    --  100% Equity
    --  Production Ramp-Up over two years, reaching full production in Year
        3
        --  50,000 tonnes in Year 1; 100,000 tonnes in Year 2; and 300,000
            tonnes in Year 3
    --  Construction on playa beginning in Preproduction Year 3 ("PP-3")
    --  Effective tax rate of approximately 29%
--  The economic analysis was based upon Measured and Indicated Mineral
    Resources only. No Inferred Resources were included in the analysis.
    Mineral Resources that are not Mineral Reserves do not have demonstrated
    economic viability.
--  Capital Costs - the total direct capital costs of the Project are
    estimated to be $292 M, not including indirect costs and contingency, as
    of 2013. All capital costs in the economic model are inflated by 2%
    annually beginning in year PP-3. Contingency is 12% of direct capital
    costs. The capital cost estimate has an accuracy of +25%/-20%.
--  Operating Costs - the total cash operating costs of the Project are
    estimated to be $180.91/t as of 2013. All operating costs in the
    economic model are inflated by 2% annually beginning in year PP-3.

"In 2013 as part of the PFS, we conducted a comprehensive study of the playa and made significant progress with our engineering," said Lance. "These efforts provided us with important insights and a detailed path forward. The highlights include:"

Hydrology Highlights


--  A comprehensive groundwater modeling effort was completed that included
    two- and three-dimensional models of the playa system. The models
    incorporated layer elevations derived from intercepts logged from over
    400 boreholes and wells drilled during the exploration programs.
--  Field data incorporated into the models included estimates of hydraulic
    conductivity and storage coefficients based on hydrophysical and aquifer
    stress tests employing both wells and trenches. Site-specific estimates
    of the vertical infiltration rate and evapotranspiration were also
    obtained.
    --  In the latest program, five single-hole pump tests were performed;
        four well-to-trench tests; nine well-to-well tests; and one trench-
        to-trench test. These studies yielded substantial new data that
        significantly improved our understanding of playa hydrology.
--  Initial modeling determined that the target production rate of 300,000
    tpy could be achieved based upon the hydro-physical characteristics of
    the deposit. Multiple simulations incorporating trench spacing, well
    layouts, and flow rates were carried out to prototype designs.
    --  Results showed that acceptable brine production could be extracted
        from two trench phases, based on 1,000 meter spacing, followed by
        well extraction with individual shafts set about 400 meters.

Engineering Highlights


--  Developed an optimized process flow sheet anticipated to provide
    improved operating benefits and flexibility while maintaining a balance
    between production, expense, and potential additional mineral
    production.
--  Completed thermodynamic modeling and pilot-plant testing of pond
    crystallization. In addition, conducted bench-scale testing with Hazen
    Research and Swenson Technologies for the flotation and multiple effect
    crystallizer circuits. The thermodynamic modeling and subsequent bench-
    scale test-work confirmed projected plant recoveries of 78%.
--  Developed civil construction designs for the plant and rail load-out
    facility as well as all playa infrastructure. The capital cost estimate
    in the PFS included budgetary quotes on 93% of all plant mechanical
    equipment costs.

"As I briefly mentioned before, we successfully expanded our resource estimates by about seven percent," Lance added. "While we expect to release mineral reserves with our feasibility study, we are very pleased to provide a summary of the basis for the resource estimate expansion."

Resource Estimate Expansion Highlights


--  Norwest completed an updated Mineral Resource Estimate based upon data
    collected from the original drilling and exploration program conducted
    in 2011-2012 as well as a second drilling and exploration program
    conducted in 2013.
--  The total Measured and Indicated Resource for SOP increased from 29.485
    Mt in the May 2012 Technical Report, to 31.486 Mt in the PFS, an
    increase of approximately 7%, primarily due to the results of the 2013
    drilling program.
--  No claim for Mineral Reserves has been made at this time pending further
    verification of the hydrologic models via longer-term pilot testing
    planned during the Feasibility Study phase.

"We received several important approvals this past year," Lance stated. "And our environmental and permitting programs continue to progress. Highlights from these include:"

Environmental, Permitting, & Regulatory Highlights


--  The Company met with the Utah Division of Air Quality ("UDAQ") in August
    2013. In that meeting, UDAQ determined that the company could proceed
    along a "dual permit" approach. This means that a Minor Source permit is
    all that is required for initial work on the playa to begin while a
    Major Source Permit could be added later when construction of the
    processing plant is required.
    --  An Air Approval order for the Minor Source Permit was submitted to
        UDAQ in October 2013. An approval is expected shortly.
    --  In July of 2013, the company started an on-site monitoring program
        for Prevention of Significant Deterioration (PSD), or the Major
        Source Permit.
--  The BLM's Fillmore Field Office continued progress with the EIS and
    selected a third-party contractor to write the EIS document in August
    2013. Technical resource reports were prepared by CH2M Hill and
    submitted to BLM for their review and approval in November 2013. BLM
    selection of the third-party contractor is an important step to moving
    the EIS process forward.
--  The BLM Plan of Operations and DOGM Large Mine Permit, historically two
    separate documents, are being consolidated into a single mine plan
    document (the "Mine Plan") agreed to by both agencies. The BLM has
    reviewed the Mine Plan and determined it was "Sufficiently Complete" in
    July 2013. A consolidated Mine Plan will allow for the Company to have
    one all-encompassing document that meets the requirement for the two
    agencies.
--  A key decision in June 2013 by the Environmental Protection Agency and
    the United States Army Corps of Engineers ("USACE") determined that
    there are no Waters of the United States on the Sevier Lake Playa.
    --  USACE determined that the Sevier Lake Playa is not a regulated
        feature under Section 404 of the Clean Water Act ("Act") and as such
        is exempt from permitting requirements under the Act.
    --  Therefore, certain federal permits relating to water will not be
        required. This decision simplifies the permitting process and
        results in significant savings of time and money.
--  In 2013, the Company submitted all water rights applications to the
    State Engineer, for which there were only four protestants.
    --  In August 2013, the Company along with Holland and Hart and CH2M
        Hill discussed EPM's water rights presentation with the State
        Engineer in Delta, Utah. The hearing went very well and the Company
        anticipates that all water right applications will be approved by
        the third quarter 2014.

Outlook for 2014

"2014 should be a banner year for us. We expect to complete most of the pre-construction milestones, nearly complete our EIS, and conclude all other necessary permitting," Lance indicated. "And soon, we will be kicking-off our Feasibility Study. While the PFS only considered SOP production, we anticipate that the Feasibility Study will consider the production of specialty products in addition to SOP including, magnesium sulphate, magnesium chloride, sodium sulphate, and possibly lithium," Lance said. "Given the presence of the other known constituents in our brine resource, we expect these minerals to provide the Company with a significant source of additional value if such minerals prove to be economic as the result of further studies."

About EPM Mining Ventures

EPM Mining Ventures Inc. is a development-stage company focused on specialty fertilizers. Through Peak Minerals Inc., its indirect wholly-owned subsidiary, EPM controls directly or through agreement mineral leases on more than 124,000 acres on its Sevier Lake Playa property in Millard County, Utah. With a brine resource known to contain potassium, magnesium, sulphate, lithium and a suite of other beneficial minerals, EPM is targeting the development and production of specialty fertilizers, including SOP, through the use of a cost-effective solar evaporation process. SOP and other specialty fertilizers are used in the production of high value, chloride-sensitive crops such as fruits, vegetables, and tree nuts. With the recent completion of a Preliminary Feasibility Study, the Company is currently engaged in engineering and analysis designed to support a feasibility study, environmental permitting, and ultimately mineral production.

For more information, please visit our web site at www.epmmining.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
EPM Mining Ventures Inc.
Lance D'Ambrosio
Chief Executive Officer
(801) 485-0223
www.epmmining.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Organizations planning enterprise data center consolidation and modernization projects are faced with a challenging, costly reality. Requirements to deploy modern, cloud-native applications simultaneously with traditional client/server applications are almost impossible to achieve with hardware-centric enterprise infrastructure. Compute and network infrastructure are fast moving down a software-defined path, but storage has been a laggard. Until now.
We're entering the post-smartphone era, where wearable gadgets from watches and fitness bands to glasses and health aids will power the next technological revolution. With mass adoption of wearable devices comes a new data ecosystem that must be protected. Wearables open new pathways that facilitate the tracking, sharing and storing of consumers’ personal health, location and daily activity data. Consumers have some idea of the data these devices capture, but most don’t realize how revealing and...
Kubernetes is a new and revolutionary open-sourced system for managing containers across multiple hosts in a cluster. Ansible is a simple IT automation tool for just about any requirement for reproducible environments. In his session at @DevOpsSummit at 18th Cloud Expo, Patrick Galbraith, a principal engineer at HPE, discussed how to build a fully functional Kubernetes cluster on a number of virtual machines or bare-metal hosts. Also included will be a brief demonstration of running a Galera M...
Unless your company can spend a lot of money on new technology, re-engineering your environment and hiring a comprehensive cybersecurity team, you will most likely move to the cloud or seek external service partnerships. In his session at 18th Cloud Expo, Darren Guccione, CEO of Keeper Security, revealed what you need to know when it comes to encryption in the cloud.
"We build IoT infrastructure products - when you have to integrate different devices, different systems and cloud you have to build an application to do that but we eliminate the need to build an application. Our products can integrate any device, any system, any cloud regardless of protocol," explained Peter Jung, Chief Product Officer at Pulzze Systems, in this SYS-CON.tv interview at @ThingsExpo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
"We are an all-flash array storage provider but our focus has been on VM-aware storage specifically for virtualized applications," stated Dhiraj Sehgal of Tintri in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
In his general session at 19th Cloud Expo, Manish Dixit, VP of Product and Engineering at Dice, discussed how Dice leverages data insights and tools to help both tech professionals and recruiters better understand how skills relate to each other and which skills are in high demand using interactive visualizations and salary indicator tools to maximize earning potential. Manish Dixit is VP of Product and Engineering at Dice. As the leader of the Product, Engineering and Data Sciences team at D...
It's easy to assume that your app will run on a fast and reliable network. The reality for your app's users, though, is often a slow, unreliable network with spotty coverage. What happens when the network doesn't work, or when the device is in airplane mode? You get unhappy, frustrated users. An offline-first app is an app that works, without error, when there is no network connection. In his session at 18th Cloud Expo, Bradley Holt, a Developer Advocate with IBM Cloud Data Services, discussed...
Data is the fuel that drives the machine learning algorithmic engines and ultimately provides the business value. In his session at 20th Cloud Expo, Ed Featherston, director/senior enterprise architect at Collaborative Consulting, will discuss the key considerations around quality, volume, timeliness, and pedigree that must be dealt with in order to properly fuel that engine.
Between 2005 and 2020, data volumes will grow by a factor of 300 – enough data to stack CDs from the earth to the moon 162 times. This has come to be known as the ‘big data’ phenomenon. Unfortunately, traditional approaches to handling, storing and analyzing data aren’t adequate at this scale: they’re too costly, slow and physically cumbersome to keep up. Fortunately, in response a new breed of technology has emerged that is cheaper, faster and more scalable. Yet, in meeting these new needs they...
In addition to all the benefits, IoT is also bringing new kind of customer experience challenges - cars that unlock themselves, thermostats turning houses into saunas and baby video monitors broadcasting over the internet. This list can only increase because while IoT services should be intuitive and simple to use, the delivery ecosystem is a myriad of potential problems as IoT explodes complexity. So finding a performance issue is like finding the proverbial needle in the haystack.
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busin...
According to Forrester Research, every business will become either a digital predator or digital prey by 2020. To avoid demise, organizations must rapidly create new sources of value in their end-to-end customer experiences. True digital predators also must break down information and process silos and extend digital transformation initiatives to empower employees with the digital resources needed to win, serve, and retain customers.
"We are the public cloud providers. We are currently providing 50% of the resources they need for doing e-commerce business in China and we are hosting about 60% of mobile gaming in China," explained Yi Zheng, CPO and VP of Engineering at CDS Global Cloud, in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
Fact is, enterprises have significant legacy voice infrastructure that’s costly to replace with pure IP solutions. How can we bring this analog infrastructure into our shiny new cloud applications? There are proven methods to bind both legacy voice applications and traditional PSTN audio into cloud-based applications and services at a carrier scale. Some of the most successful implementations leverage WebRTC, WebSockets, SIP and other open source technologies. In his session at @ThingsExpo, Da...