Besra Releases Stage One Feasibility Study for Bau Gold Project in East Malaysia

TORONTO, ONTARIO -- (Marketwired) -- 01/20/14 -- Besra (TSX: BEZ)(ASX: BEZ)(OTCQX: BSRAF)(FRANKFURT: OP6) today filed its feasibility study for Stage One of its Bau project in Sarawak, East Malaysia. The feasibility study specifically covers the proposed open pit development at Jugan Hill to the northeastern end of the Bau Central gold trend and proposes average annual production of 116,000 oz per year from late 2015.


----------------------------------------------------------------------------
----------------------------------------------------------------------------
Key Results
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total Capital                                                $   134,878,000
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Initial Capital                                              $    92,119,690
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Ongoing Capital                                              $    42,758,310
----------------------------------------------------------------------------
----------------------------------------------------------------------------
@ Gold Price                                                 $         1,300
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Operating Cost/Ore Tonne                                     $         36.84
----------------------------------------------------------------------------
----------------------------------------------------------------------------
All-in Sustaining Cost per Ounce                             $      1,159.18
----------------------------------------------------------------------------
----------------------------------------------------------------------------
All-in Cost per Ounce (incl. Resale)                         $      1,101.71
----------------------------------------------------------------------------
----------------------------------------------------------------------------
NPV @ 8%                                                     $    48,323,190
----------------------------------------------------------------------------
----------------------------------------------------------------------------
IRR                                                                    25.4%
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Besra CEO, John Seton, said, "The release of the Stage One feasibility study confirms that this is an exciting and economically viable project. I'd also like to make it clear that this is only Stage One of a sizable multi-mine project with significant potential for expansion for many years to come. We have already commenced pre-feasibility studies on adjacent deposits to increase mine life to 10-years. The fifteen kilometer long Bau gold field is open along strike and at depth at almost every deposit." Bau is a historic goldfield, which has been intermittently mined at surface for the past 150 years. Past production from these shallow pits is estimated to be around 3 million ounces.

Since 2006, Besra has been consolidating mining tenure over approximately 350 sq km of the most prospective parts of the goldfield and systematically exploring multiple gold deposits and prospective zones. Current JORC/NI 43-101 resources stand at 21,285,300 tonnes @ 1.64 g/t Au for 1,124,900 ounces (measured + indicated) and 51,329,000 tonnes @ 1.32 g/t Au for 2,181,600 ounces (inferred). These resources reflect a low discovery cost of US$6.00 per ounce.


----------------------------------------------------------------------------
----------------------------------------------------------------------------
Resource Category                                  Tonnes (t)    Grade (g/t)
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Measured                                            3,405,600           1.52
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Indicated                                          17,879,700           1.67
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Measured + Indicated                               21,285,300           1.64
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Inferred                                           51,329,000           1.32
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Exploration

Seton said, "Exploration remains at relatively early stage, with multiple deposits at various stages of exploration development and many prospective zones as yet entirely unexplored. Geological potential for substantially higher-grade mineralisation has also been identified at depth. The exploration success rate suggests that continued exploration has the potential to progressively expand resources and reserves over decades to come; with the potential to establish Bau as one of the major goldfields of Asia."

To view accompanying map, visit the following link: http://media3.marketwire.com/docs/BEZmap.jpg

Jugan Hill has been well defined through drilling to the current depths, the depth extent is less well defined and there remains open-ended potential to increase the resource beyond the current depth. Geophysical surveys and soil sampling campaigns have identified some nearby anomalies that will require further work and exploration/resource drilling.

The remainder of the Bau goldfield contains thirty-six prospects or known deposits which are at the Inferred level or have suitable geological potential requiring an extensive amount of follow up work and exploration or resource drilling. The goldfield also needs to be tested at depth below these deposits/prospects to fully understand the significant depth potential in line with the Carlin similarity model and concept.

Metallurgy and Process

Both the historical and recent Besra metallurgical test work on the Jugan ore deposit have demonstrated that the majority of the gold is associated with arsenopyrite and pyrite with the remaining gold present in silicious gangue material. The recovery of gold from the ore requires a gold pre-concentration step in a treatment flow sheet comprising crushing, grinding, desliming, and flotation to produce a high gold grade concentrate. For the base case and preferred option the flotation concentrate will be filtered to about 10% moisture, packaged and sent to an outside smelting or gold refining operation.

The sale of a flotation concentrates offers the lowest capital expenditure, and the lowest operating expenditure as well as the highest return on investment compared with treating concentrates on site.

As a result, significant savings will be made on capital costs and financing of the development should be attainable on more attractive terms. Besra is in discussions with Asian companies for a smelter off-take agreement, several of which have tested and confirmed their ability to process the concentrate. An indicative offer has already been received from one of the four smelters with more expected in the coming weeks.

Sarawak, Malaysia

East Malaysia provides an encouraging environment for mining and foreign investment with a 0% gold royalty and 24% corporate income tax rate. Additionally, the Bau project is located 40 km via good roads from a deep-water port in the Sarawak state capital of Kuching, and within 30 km of Kuching International Airport. High quality infrastructure and services already exist and there is a supportive and skilled English-speaking workforce with good education levels and significant mining or quarrying experience.

Once in production, the Bau project is estimated to be one of the top fifteen gold producing properties in Asia (ranked according to JORC/NI43-101 resources). By moving into production now, Besra can generate significant cash flow to further improve the gold field resources and reserves and take advantage of the opportunity for growth alongside the development of site infrastructure. Besra expects the property will ultimately assume a more prominent position as exploration continues to convert large-scale geological potential into resources.

A copy of the feasibility study may be downloaded from www.besra.com/bau.

Besra Gold Inc.

John A G Seton, Chief Executive Officer

Besra -www.besra.com

Besra is a diversified gold mining company focused on the exploration, development and mining of mineral properties in South East Asia. The Company has four key properties; the Bau Goldfield in East Malaysia, Bong Mieu and Phuoc Son in Central Vietnam, and Capcapo in the Philippines. Besra expects to expand existing gold capacity in Vietnam over the next two years and is projecting new production capacity from Bau Central during late 2015.

Cautionary Note Regarding Forward-Looking Statements

Certain of the statements made and information contained herein is "looking information"" within the meaning of applicable securities laws, including statements concerning our plans at our producing mines and exploration projects, which involve known and unknown risks, uncertainties, and other factors which may cause the actual results, performance or achievements of the Company, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking information. Forward-looking information is subject to a variety of risks and uncertainties that could cause actual events or results to differ from those reflected in the forward-looking information, including, without limitation, failure to establish estimated resources or to convert resources to mineable reserves; the grade and recovery of ore which is mined varying from estimates; capital and operating costs varying significantly from estimates; delays in obtaining or failure to obtain required governmental, environmental, or other project approvals; changes in national and local government legislation or regulations regarding environmental factors, royalties, taxation or foreign investment; political or economic instability; terrorism; inflation; changes in currency exchange rates; fluctuations in commodity prices; delays in the development of projects; shortage of personnel with the requisite knowledge and skills to design and execute exploration and development programs; difficulties in arranging contracts for drilling and other exploration and development services; dependency on equity market financings to fund programs and maintain and develop mineral properties; and risks associated with title to resource properties due to the difficulties of determining the validity of certain claims and other risks and uncertainties, including those described in each management's discussion and analysis released by the Company. In addition, forward-looking information is based on various assumptions including, without limitation, the expectations and beliefs of management; the assumed long-term price of gold; the availability of permits and surface rights; access to financing, equipment and labour and that the political environment in the jurisdictions within which the Company operates will continue to support the development of environmentally safe mining projects. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Accordingly, readers are advised not to place undue reliance on forward-looking statements, which speak only as of the date they are made. Except as required under applicable securities legislation, the Company undertakes no obligation to publicly update or revise forward-looking information, whether as a result of new information, future events or otherwise.

Technical Information

The technical information in this press release has been prepared under the supervision of Mr Graeme Fulton who is a Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM), a "Competent Person", as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserve" and a "Qualified Person" as defined in National Instrument 43-101 Standards of Disclosure for Mineral Projects of the Canadian Securities Administrators. Mr Fulton is a full-time consultant to the Company and is not "independent" within the meaning of National Instrument 43-101. Mr Fulton consents to the inclusion in this press release of the technical information, in the form, and context in which it appears.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
"We've just seen a huge influx of new partners coming into our ecosystem, and partners building unique offerings on top of our API set," explained Seth Bostock, Chief Executive Officer at IndependenceIT, in this SYS-CON.tv interview at 16th Cloud Expo, held June 9-11, 2015, at the Javits Center in New York City.
Mobile, social, Big Data, and cloud have fundamentally changed the way we live. “Anytime, anywhere” access to data and information is no longer a luxury; it’s a requirement, in both our personal and professional lives. For IT organizations, this means pressure has never been greater to deliver meaningful services to the business and customers.
Digital Transformation is the ultimate goal of cloud computing and related initiatives. The phrase is certainly not a precise one, and as subject to hand-waving and distortion as any high-falutin' terminology in the world of information technology. Yet it is an excellent choice of words to describe what enterprise IT—and by extension, organizations in general—should be working to achieve. Digital Transformation means: handling all the data types being found and created in the organizat...
SYS-CON Events announced today that HPM Networks will exhibit at the 17th International Cloud Expo®, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. For 20 years, HPM Networks has been integrating technology solutions that solve complex business challenges. HPM Networks has designed solutions for both SMB and enterprise customers throughout the San Francisco Bay Area.
Chuck Piluso presented a study of cloud adoption trends and the power and flexibility of IBM Power and Pureflex cloud solutions. Prior to Secure Infrastructure and Services, Mr. Piluso founded North American Telecommunication Corporation, a facilities-based Competitive Local Exchange Carrier licensed by the Public Service Commission in 10 states, serving as the company's chairman and president from 1997 to 2000. Between 1990 and 1997, Mr. Piluso served as chairman & founder of International Te...
The Software Defined Data Center (SDDC), which enables organizations to seamlessly run in a hybrid cloud model (public + private cloud), is here to stay. IDC estimates that the software-defined networking market will be valued at $3.7 billion by 2016. Security is a key component and benefit of the SDDC, and offers an opportunity to build security 'from the ground up' and weave it into the environment from day one. In his session at 16th Cloud Expo, Reuven Harrison, CTO and Co-Founder of Tufin,...
Container technology is sending shock waves through the world of cloud computing. Heralded as the 'next big thing,' containers provide software owners a consistent way to package their software and dependencies while infrastructure operators benefit from a standard way to deploy and run them. Containers present new challenges for tracking usage due to their dynamic nature. They can also be deployed to bare metal, virtual machines and various cloud platforms. How do software owners track the usag...
SYS-CON Events announced today that MobiDev, a software development company, will exhibit at the 17th International Cloud Expo®, which will take place November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. MobiDev is a software development company with representative offices in Atlanta (US), Sheffield (UK) and Würzburg (Germany); and development centers in Ukraine. Since 2009 it has grown from a small group of passionate engineers and business managers to a full-scale mobi...
With SaaS use rampant across organizations, how can IT departments track company data and maintain security? More and more departments are commissioning their own solutions and bypassing IT. A cloud environment is amorphous and powerful, allowing you to set up solutions for all of your user needs: document sharing and collaboration, mobile access, e-mail, even industry-specific applications. In his session at 16th Cloud Expo, Shawn Mills, President and a founder of Green House Data, discussed h...
For IoT to grow as quickly as analyst firms’ project, a lot is going to fall on developers to quickly bring applications to market. But the lack of a standard development platform threatens to slow growth and make application development more time consuming and costly, much like we’ve seen in the mobile space. In his session at @ThingsExpo, Mike Weiner, Product Manager of the Omega DevCloud with KORE Telematics Inc., discussed the evolving requirements for developers as IoT matures and conducte...
There are many considerations when moving applications from on-premise to cloud. It is critical to understand the benefits and also challenges of this migration. A successful migration will result in lower Total Cost of Ownership, yet offer the same or higher level of robustness. In his session at 15th Cloud Expo, Michael Meiner, an Engineering Director at Oracle, Corporation, analyzed a range of cloud offerings (IaaS, PaaS, SaaS) and discussed the benefits/challenges of migrating to each offe...
One of the hottest areas in cloud right now is DRaaS and related offerings. In his session at 16th Cloud Expo, Dale Levesque, Disaster Recovery Product Manager with Windstream's Cloud and Data Center Marketing team, will discuss the benefits of the cloud model, which far outweigh the traditional approach, and how enterprises need to ensure that their needs are properly being met.
In their session at 17th Cloud Expo, Hal Schwartz, CEO of Secure Infrastructure & Services (SIAS), and Chuck Paolillo, CTO of Secure Infrastructure & Services (SIAS), provide a study of cloud adoption trends and the power and flexibility of IBM Power and Pureflex cloud solutions. In his role as CEO of Secure Infrastructure & Services (SIAS), Hal Schwartz provides leadership and direction for the company.
In a recent research, analyst firm IDC found that the average cost of a critical application failure is $500,000 to $1 million per hour and the average total cost of unplanned application downtime is $1.25 billion to $2.5 billion per year for Fortune 1000 companies. In addition to the findings on the cost of the downtime, the research also highlighted best practices for development, testing, application support, infrastructure, and operations teams.
The Internet of Everything (IoE) brings together people, process, data and things to make networked connections more relevant and valuable than ever before – transforming information into knowledge and knowledge into wisdom. IoE creates new capabilities, richer experiences, and unprecedented opportunities to improve business and government operations, decision making and mission support capabilities.