Besra Releases Stage One Feasibility Study for Bau Gold Project in East Malaysia

TORONTO, ONTARIO -- (Marketwired) -- 01/20/14 -- Besra (TSX: BEZ)(ASX: BEZ)(OTCQX: BSRAF)(FRANKFURT: OP6) today filed its feasibility study for Stage One of its Bau project in Sarawak, East Malaysia. The feasibility study specifically covers the proposed open pit development at Jugan Hill to the northeastern end of the Bau Central gold trend and proposes average annual production of 116,000 oz per year from late 2015.


----------------------------------------------------------------------------
----------------------------------------------------------------------------
Key Results
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total Capital                                                $   134,878,000
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Initial Capital                                              $    92,119,690
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Ongoing Capital                                              $    42,758,310
----------------------------------------------------------------------------
----------------------------------------------------------------------------
@ Gold Price                                                 $         1,300
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Operating Cost/Ore Tonne                                     $         36.84
----------------------------------------------------------------------------
----------------------------------------------------------------------------
All-in Sustaining Cost per Ounce                             $      1,159.18
----------------------------------------------------------------------------
----------------------------------------------------------------------------
All-in Cost per Ounce (incl. Resale)                         $      1,101.71
----------------------------------------------------------------------------
----------------------------------------------------------------------------
NPV @ 8%                                                     $    48,323,190
----------------------------------------------------------------------------
----------------------------------------------------------------------------
IRR                                                                    25.4%
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Besra CEO, John Seton, said, "The release of the Stage One feasibility study confirms that this is an exciting and economically viable project. I'd also like to make it clear that this is only Stage One of a sizable multi-mine project with significant potential for expansion for many years to come. We have already commenced pre-feasibility studies on adjacent deposits to increase mine life to 10-years. The fifteen kilometer long Bau gold field is open along strike and at depth at almost every deposit." Bau is a historic goldfield, which has been intermittently mined at surface for the past 150 years. Past production from these shallow pits is estimated to be around 3 million ounces.

Since 2006, Besra has been consolidating mining tenure over approximately 350 sq km of the most prospective parts of the goldfield and systematically exploring multiple gold deposits and prospective zones. Current JORC/NI 43-101 resources stand at 21,285,300 tonnes @ 1.64 g/t Au for 1,124,900 ounces (measured + indicated) and 51,329,000 tonnes @ 1.32 g/t Au for 2,181,600 ounces (inferred). These resources reflect a low discovery cost of US$6.00 per ounce.


----------------------------------------------------------------------------
----------------------------------------------------------------------------
Resource Category                                  Tonnes (t)    Grade (g/t)
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Measured                                            3,405,600           1.52
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Indicated                                          17,879,700           1.67
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Measured + Indicated                               21,285,300           1.64
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Inferred                                           51,329,000           1.32
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Exploration

Seton said, "Exploration remains at relatively early stage, with multiple deposits at various stages of exploration development and many prospective zones as yet entirely unexplored. Geological potential for substantially higher-grade mineralisation has also been identified at depth. The exploration success rate suggests that continued exploration has the potential to progressively expand resources and reserves over decades to come; with the potential to establish Bau as one of the major goldfields of Asia."

To view accompanying map, visit the following link: http://media3.marketwire.com/docs/BEZmap.jpg

Jugan Hill has been well defined through drilling to the current depths, the depth extent is less well defined and there remains open-ended potential to increase the resource beyond the current depth. Geophysical surveys and soil sampling campaigns have identified some nearby anomalies that will require further work and exploration/resource drilling.

The remainder of the Bau goldfield contains thirty-six prospects or known deposits which are at the Inferred level or have suitable geological potential requiring an extensive amount of follow up work and exploration or resource drilling. The goldfield also needs to be tested at depth below these deposits/prospects to fully understand the significant depth potential in line with the Carlin similarity model and concept.

Metallurgy and Process

Both the historical and recent Besra metallurgical test work on the Jugan ore deposit have demonstrated that the majority of the gold is associated with arsenopyrite and pyrite with the remaining gold present in silicious gangue material. The recovery of gold from the ore requires a gold pre-concentration step in a treatment flow sheet comprising crushing, grinding, desliming, and flotation to produce a high gold grade concentrate. For the base case and preferred option the flotation concentrate will be filtered to about 10% moisture, packaged and sent to an outside smelting or gold refining operation.

The sale of a flotation concentrates offers the lowest capital expenditure, and the lowest operating expenditure as well as the highest return on investment compared with treating concentrates on site.

As a result, significant savings will be made on capital costs and financing of the development should be attainable on more attractive terms. Besra is in discussions with Asian companies for a smelter off-take agreement, several of which have tested and confirmed their ability to process the concentrate. An indicative offer has already been received from one of the four smelters with more expected in the coming weeks.

Sarawak, Malaysia

East Malaysia provides an encouraging environment for mining and foreign investment with a 0% gold royalty and 24% corporate income tax rate. Additionally, the Bau project is located 40 km via good roads from a deep-water port in the Sarawak state capital of Kuching, and within 30 km of Kuching International Airport. High quality infrastructure and services already exist and there is a supportive and skilled English-speaking workforce with good education levels and significant mining or quarrying experience.

Once in production, the Bau project is estimated to be one of the top fifteen gold producing properties in Asia (ranked according to JORC/NI43-101 resources). By moving into production now, Besra can generate significant cash flow to further improve the gold field resources and reserves and take advantage of the opportunity for growth alongside the development of site infrastructure. Besra expects the property will ultimately assume a more prominent position as exploration continues to convert large-scale geological potential into resources.

A copy of the feasibility study may be downloaded from www.besra.com/bau.

Besra Gold Inc.

John A G Seton, Chief Executive Officer

Besra -www.besra.com

Besra is a diversified gold mining company focused on the exploration, development and mining of mineral properties in South East Asia. The Company has four key properties; the Bau Goldfield in East Malaysia, Bong Mieu and Phuoc Son in Central Vietnam, and Capcapo in the Philippines. Besra expects to expand existing gold capacity in Vietnam over the next two years and is projecting new production capacity from Bau Central during late 2015.

Cautionary Note Regarding Forward-Looking Statements

Certain of the statements made and information contained herein is "looking information"" within the meaning of applicable securities laws, including statements concerning our plans at our producing mines and exploration projects, which involve known and unknown risks, uncertainties, and other factors which may cause the actual results, performance or achievements of the Company, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking information. Forward-looking information is subject to a variety of risks and uncertainties that could cause actual events or results to differ from those reflected in the forward-looking information, including, without limitation, failure to establish estimated resources or to convert resources to mineable reserves; the grade and recovery of ore which is mined varying from estimates; capital and operating costs varying significantly from estimates; delays in obtaining or failure to obtain required governmental, environmental, or other project approvals; changes in national and local government legislation or regulations regarding environmental factors, royalties, taxation or foreign investment; political or economic instability; terrorism; inflation; changes in currency exchange rates; fluctuations in commodity prices; delays in the development of projects; shortage of personnel with the requisite knowledge and skills to design and execute exploration and development programs; difficulties in arranging contracts for drilling and other exploration and development services; dependency on equity market financings to fund programs and maintain and develop mineral properties; and risks associated with title to resource properties due to the difficulties of determining the validity of certain claims and other risks and uncertainties, including those described in each management's discussion and analysis released by the Company. In addition, forward-looking information is based on various assumptions including, without limitation, the expectations and beliefs of management; the assumed long-term price of gold; the availability of permits and surface rights; access to financing, equipment and labour and that the political environment in the jurisdictions within which the Company operates will continue to support the development of environmentally safe mining projects. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Accordingly, readers are advised not to place undue reliance on forward-looking statements, which speak only as of the date they are made. Except as required under applicable securities legislation, the Company undertakes no obligation to publicly update or revise forward-looking information, whether as a result of new information, future events or otherwise.

Technical Information

The technical information in this press release has been prepared under the supervision of Mr Graeme Fulton who is a Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM), a "Competent Person", as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserve" and a "Qualified Person" as defined in National Instrument 43-101 Standards of Disclosure for Mineral Projects of the Canadian Securities Administrators. Mr Fulton is a full-time consultant to the Company and is not "independent" within the meaning of National Instrument 43-101. Mr Fulton consents to the inclusion in this press release of the technical information, in the form, and context in which it appears.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Rapid innovation, changing business landscapes, and new IT demands force businesses to make changes quickly. In the eyes of many, containers are at the brink of becoming a pervasive technology in enterprise IT to accelerate application delivery. In this presentation, attendees learned about the: The transformation of IT to a DevOps, microservices, and container-based architecture What are containers and how DevOps practices can operate in a container-based environment A demonstration of how ...
Cloud Expo, Inc. has announced today that Andi Mann returns to 'DevOps at Cloud Expo 2017' as Conference Chair The @DevOpsSummit at Cloud Expo will take place on June 6-8, 2017, at the Javits Center in New York City, NY. "DevOps is set to be one of the most profound disruptions to hit IT in decades," said Andi Mann. "It is a natural extension of cloud computing, and I have seen both firsthand and in independent research the fantastic results DevOps delivers. So I am excited to help the great t...
SYS-CON Events announced today that Fusion, a leading provider of cloud services, will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Fusion, a leading provider of integrated cloud solutions to small, medium and large businesses, is the industry’s single source for the cloud. Fusion’s advanced, proprietary cloud service platform enables the integration of leading edge solutions in the cloud, including clou...
Fact: storage performance problems have only gotten more complicated, as applications not only have become largely virtualized, but also have moved to cloud-based infrastructures. Storage performance in virtualized environments isn’t just about IOPS anymore. Instead, you need to guarantee performance for individual VMs, helping applications maintain performance as the number of VMs continues to go up in real time. In his session at Cloud Expo, Dhiraj Sehgal, Product and Marketing at Tintri, sha...
Without lifecycle traceability and visibility across the tool chain, stakeholders from Planning-to-Ops have limited insight and answers to who, what, when, why and how across the DevOps lifecycle. This impacts the ability to deliver high quality software at the needed velocity to drive positive business outcomes. In his general session at @DevOpsSummit at 19th Cloud Expo, Phil Hombledal, Solution Architect at CollabNet, discussed how customers are able to achieve a level of transparency that e...
WebRTC is the future of browser-to-browser communications, and continues to make inroads into the traditional, difficult, plug-in web communications world. The 6th WebRTC Summit continues our tradition of delivering the latest and greatest presentations within the world of WebRTC. Topics include voice calling, video chat, P2P file sharing, and use cases that have already leveraged the power and convenience of WebRTC.
"Venafi has a platform that allows you to manage, centralize and automate the complete life cycle of keys and certificates within the organization," explained Gina Osmond, Sr. Field Marketing Manager at Venafi, in this SYS-CON.tv interview at DevOps at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
Get deep visibility into the performance of your databases and expert advice for performance optimization and tuning. You can't get application performance without database performance. Give everyone on the team a comprehensive view of how every aspect of the system affects performance across SQL database operations, host server and OS, virtualization resources and storage I/O. Quickly find bottlenecks and troubleshoot complex problems.
The many IoT deployments around the world are busy integrating smart devices and sensors into their enterprise IT infrastructures. Yet all of this technology – and there are an amazing number of choices – is of no use without the software to gather, communicate, and analyze the new data flows. Without software, there is no IT. In this power panel at @ThingsExpo, moderated by Conference Chair Roger Strukhoff, Dave McCarthy, Director of Products at Bsquare Corporation; Alan Williamson, Principal...
20th Cloud Expo, taking place June 6-8, 2017, at the Javits Center in New York City, NY, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy.
"This is specifically designed to accommodate some of the needs for high availability and failover in a network managed system for the major Korean corporations," stated Thomas Masters, Managing Director at InfranicsUSA, in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
"Qosmos has launched L7Viewer, a network traffic analysis tool, so it analyzes all the traffic between the virtual machine and the data center and the virtual machine and the external world," stated Sebastien Synold, Product Line Manager at Qosmos, in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
"Coalfire is a cyber-risk, security and compliance assessment and advisory services firm. We do a lot of work with the cloud service provider community," explained Ryan McGowan, Vice President, Sales (West) at Coalfire Systems, Inc., in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
In his keynote at 18th Cloud Expo, Andrew Keys, Co-Founder of ConsenSys Enterprise, provided an overview of the evolution of the Internet and the Database and the future of their combination – the Blockchain. Andrew Keys is Co-Founder of ConsenSys Enterprise. He comes to ConsenSys Enterprise with capital markets, technology and entrepreneurial experience. Previously, he worked for UBS investment bank in equities analysis. Later, he was responsible for the creation and distribution of life sett...
An IoT product’s log files speak volumes about what’s happening with your products in the field, pinpointing current and potential issues, and enabling you to predict failures and save millions of dollars in inventory. But until recently, no one knew how to listen. In his session at @ThingsExpo, Dan Gettens, Chief Research Officer at OnProcess, discussed recent research by Massachusetts Institute of Technology and OnProcess Technology, where MIT created a new, breakthrough analytics model for ...