Besra Releases Stage One Feasibility Study for Bau Gold Project in East Malaysia

TORONTO, ONTARIO -- (Marketwired) -- 01/20/14 -- Besra (TSX: BEZ)(ASX: BEZ)(OTCQX: BSRAF)(FRANKFURT: OP6) today filed its feasibility study for Stage One of its Bau project in Sarawak, East Malaysia. The feasibility study specifically covers the proposed open pit development at Jugan Hill to the northeastern end of the Bau Central gold trend and proposes average annual production of 116,000 oz per year from late 2015.

----------------------------------------------------------------------------
----------------------------------------------------------------------------
Key Results
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total Capital                                                $   134,878,000
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Initial Capital                                              $    92,119,690
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Ongoing Capital                                              $    42,758,310
----------------------------------------------------------------------------
----------------------------------------------------------------------------
@ Gold Price                                                 $         1,300
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Operating Cost/Ore Tonne                                     $         36.84
----------------------------------------------------------------------------
----------------------------------------------------------------------------
All-in Sustaining Cost per Ounce                             $      1,159.18
----------------------------------------------------------------------------
----------------------------------------------------------------------------
All-in Cost per Ounce (incl. Resale)                         $      1,101.71
----------------------------------------------------------------------------
----------------------------------------------------------------------------
NPV @ 8%                                                     $    48,323,190
----------------------------------------------------------------------------
----------------------------------------------------------------------------
IRR                                                                    25.4%
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Besra CEO, John Seton, said, "The release of the Stage One feasibility study confirms that this is an exciting and economically viable project. I'd also like to make it clear that this is only Stage One of a sizable multi-mine project with significant potential for expansion for many years to come. We have already commenced pre-feasibility studies on adjacent deposits to increase mine life to 10-years. The fifteen kilometer long Bau gold field is open along strike and at depth at almost every deposit." Bau is a historic goldfield, which has been intermittently mined at surface for the past 150 years. Past production from these shallow pits is estimated to be around 3 million ounces.

Since 2006, Besra has been consolidating mining tenure over approximately 350 sq km of the most prospective parts of the goldfield and systematically exploring multiple gold deposits and prospective zones. Current JORC/NI 43-101 resources stand at 21,285,300 tonnes @ 1.64 g/t Au for 1,124,900 ounces (measured + indicated) and 51,329,000 tonnes @ 1.32 g/t Au for 2,181,600 ounces (inferred). These resources reflect a low discovery cost of US$6.00 per ounce.

----------------------------------------------------------------------------
----------------------------------------------------------------------------
Resource Category                                  Tonnes (t)    Grade (g/t)
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Measured                                            3,405,600           1.52
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Indicated                                          17,879,700           1.67
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Measured + Indicated                               21,285,300           1.64
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Inferred                                           51,329,000           1.32
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Exploration

Seton said, "Exploration remains at relatively early stage, with multiple deposits at various stages of exploration development and many prospective zones as yet entirely unexplored. Geological potential for substantially higher-grade mineralisation has also been identified at depth. The exploration success rate suggests that continued exploration has the potential to progressively expand resources and reserves over decades to come; with the potential to establish Bau as one of the major goldfields of Asia."

To view accompanying map, visit the following link: http://media3.marketwire.com/docs/BEZmap.jpg

Jugan Hill has been well defined through drilling to the current depths, the depth extent is less well defined and there remains open-ended potential to increase the resource beyond the current depth. Geophysical surveys and soil sampling campaigns have identified some nearby anomalies that will require further work and exploration/resource drilling.

The remainder of the Bau goldfield contains thirty-six prospects or known deposits which are at the Inferred level or have suitable geological potential requiring an extensive amount of follow up work and exploration or resource drilling. The goldfield also needs to be tested at depth below these deposits/prospects to fully understand the significant depth potential in line with the Carlin similarity model and concept.

Metallurgy and Process

Both the historical and recent Besra metallurgical test work on the Jugan ore deposit have demonstrated that the majority of the gold is associated with arsenopyrite and pyrite with the remaining gold present in silicious gangue material. The recovery of gold from the ore requires a gold pre-concentration step in a treatment flow sheet comprising crushing, grinding, desliming, and flotation to produce a high gold grade concentrate. For the base case and preferred option the flotation concentrate will be filtered to about 10% moisture, packaged and sent to an outside smelting or gold refining operation.

The sale of a flotation concentrates offers the lowest capital expenditure, and the lowest operating expenditure as well as the highest return on investment compared with treating concentrates on site.

As a result, significant savings will be made on capital costs and financing of the development should be attainable on more attractive terms. Besra is in discussions with Asian companies for a smelter off-take agreement, several of which have tested and confirmed their ability to process the concentrate. An indicative offer has already been received from one of the four smelters with more expected in the coming weeks.

Sarawak, Malaysia

East Malaysia provides an encouraging environment for mining and foreign investment with a 0% gold royalty and 24% corporate income tax rate. Additionally, the Bau project is located 40 km via good roads from a deep-water port in the Sarawak state capital of Kuching, and within 30 km of Kuching International Airport. High quality infrastructure and services already exist and there is a supportive and skilled English-speaking workforce with good education levels and significant mining or quarrying experience.

Once in production, the Bau project is estimated to be one of the top fifteen gold producing properties in Asia (ranked according to JORC/NI43-101 resources). By moving into production now, Besra can generate significant cash flow to further improve the gold field resources and reserves and take advantage of the opportunity for growth alongside the development of site infrastructure. Besra expects the property will ultimately assume a more prominent position as exploration continues to convert large-scale geological potential into resources.

A copy of the feasibility study may be downloaded from www.besra.com/bau.

Besra Gold Inc.

John A G Seton, Chief Executive Officer

Besra -www.besra.com

Besra is a diversified gold mining company focused on the exploration, development and mining of mineral properties in South East Asia. The Company has four key properties; the Bau Goldfield in East Malaysia, Bong Mieu and Phuoc Son in Central Vietnam, and Capcapo in the Philippines. Besra expects to expand existing gold capacity in Vietnam over the next two years and is projecting new production capacity from Bau Central during late 2015.

Cautionary Note Regarding Forward-Looking Statements

Certain of the statements made and information contained herein is "looking information"" within the meaning of applicable securities laws, including statements concerning our plans at our producing mines and exploration projects, which involve known and unknown risks, uncertainties, and other factors which may cause the actual results, performance or achievements of the Company, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking information. Forward-looking information is subject to a variety of risks and uncertainties that could cause actual events or results to differ from those reflected in the forward-looking information, including, without limitation, failure to establish estimated resources or to convert resources to mineable reserves; the grade and recovery of ore which is mined varying from estimates; capital and operating costs varying significantly from estimates; delays in obtaining or failure to obtain required governmental, environmental, or other project approvals; changes in national and local government legislation or regulations regarding environmental factors, royalties, taxation or foreign investment; political or economic instability; terrorism; inflation; changes in currency exchange rates; fluctuations in commodity prices; delays in the development of projects; shortage of personnel with the requisite knowledge and skills to design and execute exploration and development programs; difficulties in arranging contracts for drilling and other exploration and development services; dependency on equity market financings to fund programs and maintain and develop mineral properties; and risks associated with title to resource properties due to the difficulties of determining the validity of certain claims and other risks and uncertainties, including those described in each management's discussion and analysis released by the Company. In addition, forward-looking information is based on various assumptions including, without limitation, the expectations and beliefs of management; the assumed long-term price of gold; the availability of permits and surface rights; access to financing, equipment and labour and that the political environment in the jurisdictions within which the Company operates will continue to support the development of environmentally safe mining projects. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Accordingly, readers are advised not to place undue reliance on forward-looking statements, which speak only as of the date they are made. Except as required under applicable securities legislation, the Company undertakes no obligation to publicly update or revise forward-looking information, whether as a result of new information, future events or otherwise.

Technical Information

The technical information in this press release has been prepared under the supervision of Mr Graeme Fulton who is a Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM), a "Competent Person", as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserve" and a "Qualified Person" as defined in National Instrument 43-101 Standards of Disclosure for Mineral Projects of the Canadian Securities Administrators. Mr Fulton is a full-time consultant to the Company and is not "independent" within the meaning of National Instrument 43-101. Mr Fulton consents to the inclusion in this press release of the technical information, in the form, and context in which it appears.

Contacts:
Besra Gold Inc.
James W Hamilton
Investor Relations
+1 (416) 572 2525 or TF: 1 888 902 5522 (North America)
[email protected]

Besra Gold Inc.
Steve Wilson
Corporate Communications
+64 9 9121765 or M: +64 21675660
TF: 800 308 602 (Australia)
[email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
yperConvergence came to market with the objective of being simple, flexible and to help drive down operating expenses. It reduced the footprint by bundling the compute/storage/network into one box. This brought a new set of challenges as the HyperConverged vendors are very focused on their own proprietary building blocks. If you want to scale in a certain way, let’s say you identified a need for more storage and want to add a device that is not sold by the HyperConverged vendor, forget about it....
SYS-CON Events announced today that Pulzze Systems will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Pulzze Systems Inc, provides the software product "The Interactor" that uniquely simplifies building IoT, Web and Smart Enterprise Solutions. It is a Silicon Valley startup funded by US government agencies, NSF and DHS to bring innovative solutions to market.
In his session at @ThingsExpo, Dr. Robert Cohen, an economist and senior fellow at the Economic Strategy Institute, presented the findings of a series of six detailed case studies of how large corporations are implementing IoT. The session explored how IoT has improved their economic performance, had major impacts on business models and resulted in impressive ROIs. The companies covered span manufacturing and services firms. He also explored servicification, how manufacturing firms shift from se...
With Cloud Foundry you can easily deploy and use apps utilizing websocket technology, but not everybody realizes that scaling them out is not that trivial. In his session at 21st Cloud Expo, Roman Swoszowski, CTO and VP, Cloud Foundry Services, at Grape Up, will show you an example of how to deal with this issue. He will demonstrate a cloud-native Spring Boot app running in Cloud Foundry and communicating with clients over websocket protocol that can be easily scaled horizontally and coordinate...
SYS-CON Events announced today that Elastifile will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Elastifile Cloud File System (ECFS) is software-defined data infrastructure designed for seamless and efficient management of dynamic workloads across heterogeneous environments. Elastifile provides the architecture needed to optimize your hybrid cloud environment, by facilitating efficient...
For financial firms, the cloud is going to increasingly become a crucial part of dealing with customers over the next five years and beyond, particularly with the growing use and acceptance of virtual currencies. There are new data storage paradigms on the horizon that will deliver secure solutions for storing and moving sensitive financial data around the world without touching terrestrial networks. In his session at 20th Cloud Expo, Cliff Beek, President of Cloud Constellation Corporation, d...
As more and more companies are making the shift from on-premises to public cloud, the standard approach to DevOps is evolving. From encryption, compliance and regulations like GDPR, security in the cloud has become a hot topic. Many DevOps-focused companies have hired dedicated staff to fulfill these requirements, often creating further siloes, complexity and cost. This session aims to highlight existing DevOps cultural approaches, tooling and how security can be wrapped in every facet of the bu...
Businesses and business units of all sizes can benefit from cloud computing, but many don't want the cost, performance and security concerns of public cloud nor the complexity of building their own private clouds. Today, some cloud vendors are using artificial intelligence (AI) to simplify cloud deployment and management. In his session at 20th Cloud Expo, Ajay Gulati, Co-founder and CEO of ZeroStack, discussed how AI can simplify cloud operations. He covered the following topics: why cloud mana...
DevOps at Cloud Expo, taking place October 31 - November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 21st Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to w...
SYS-CON Events announced today that CAST Software will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CAST was founded more than 25 years ago to make the invisible visible. Built around the idea that even the best analytics on the market still leave blind spots for technical teams looking to deliver better software and prevent outages, CAST provides the software intelligence that matter ...
SYS-CON Events announced today that Golden Gate University will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Since 1901, non-profit Golden Gate University (GGU) has been helping adults achieve their professional goals by providing high quality, practice-based undergraduate and graduate educational programs in law, taxation, business and related professions. Many of its courses are taug...
Vulnerability management is vital for large companies that need to secure containers across thousands of hosts, but many struggle to understand how exposed they are when they discover a new high security vulnerability. In his session at 21st Cloud Expo, John Morello, CTO of Twistlock, will address this pressing concern by introducing the concept of the “Vulnerability Risk Tree API,” which brings all the data together in a simple REST endpoint, allowing companies to easily grasp the severity of t...
Recently, WebRTC has a lot of eyes from market. The use cases of WebRTC are expanding - video chat, online education, online health care etc. Not only for human-to-human communication, but also IoT use cases such as machine to human use cases can be seen recently. One of the typical use-case is remote camera monitoring. With WebRTC, people can have interoperability and flexibility for deploying monitoring service. However, the benefit of WebRTC for IoT is not only its convenience and interopera...
Translating agile methodology into real-world best practices within the modern software factory has driven widespread DevOps adoption, yet much work remains to expand workflows and tooling across the enterprise. As models evolve from pockets of experimentation into wholescale organizational reinvention, practitioners find themselves challenged to incorporate the culture and architecture necessary to support DevOps at scale.
SYS-CON Events announced today that CA Technologies has been named “Platinum Sponsor” of SYS-CON's 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CA Technologies helps customers succeed in a future where every business – from apparel to energy – is being rewritten by software. From planning to development to management to security, CA creates software that fuels transformation for companies in the applic...