First Quantum Minerals Provides Update on Its Cobre Panama Copper Project and Funding Arrangements

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 01/28/14 -- (In United States dollars, except where noted otherwise)

First Quantum Minerals Ltd. ("First Quantum" or the "Company") (TSX: FM)(LSE: FQM) is pleased to provide the following update on the development of its Cobre Panama copper project and progress in the optimization of the Company's capital structure.

The Company will be hosting a conference call and webcast on January 28, 2014 at 8:00 AM Eastern Standard Time to further discuss the update.

KEY POINTS

Since First Quantum's acquisition of Inmet Mining Corporation ("Inmet") in March 2013, the prime focus has been to critically review and stabilize all activities and focus on the key elements of the Cobre Panama project development, construction and contracting plan, and implementation of practical site infrastructure.

This update on the project covers mainly the planned operating parameters, capital estimate and development timeframe. The Company intends to disclose in due course outcomes of the reviews currently underway of other aspects of the project, including the potential sale of excess power, and validation of the Measured and Indicated Resources estimate reported and filed in May, 2010 by Inmet.

Planned Operating Parameters

--  The review has used Measured and Indicated Resources estimate of 3,271
    million tonnes, inclusive of Reserves and on a 100% basis as reported
    and filed in May, 2010 by Inmet.

--  The revised project will have installed capacity of about 70 million
    tonnes per annum ("Mtpa") for the first 10 years; approximately 17%
    higher than the Inmet plan. Further expansion up to 100 Mtpa beyond Year
    10.

--  On the basis of the current Resource estimate and the planned installed
    capacity of about 70 Mtpa, the project would produce an average of
    approximately 320,000 tonnes of copper annually on a life-of-mine basis;
    approximately 20% higher than the Inmet plan.

--  Average annual life-of-mine by-product production of 100,000 ounces
    gold; 1,800,000 ounces silver and 3,500 tonnes molybdenum.

--  Average copper grade of 0.5% total copper for first 10 years and 0.37%
    for remaining mine life.

--  Average life-of-mine strip ratio of 0.7:1.

--  Mine life of 34 years.

Capital Cost Estimate

--  Capital estimate of $6.4 billion inclusive of $913 million incurred
    prior to acquisition; $1,465 million incurred at November 30, 2013;
    $1,578 million committed at November 30, 2013.

--  Capital per installed tonne of capacity of approximately $17,125.

 --------------------------------------------------------------------------
                                       Incurred        Incurred
                                           Pre-             at        Total
                                    Acquisition    Nov 30, 2013       Capex
 --------------------------------------------------------------------------
                                         (US$M)          (US$M)      (US$M)
 Mine, Port & Infrastructure                480             867       3,034
 Power Plant                                209             276         664
 Owners Cost                                162             223         567
 Process Plant                               62              99       1,739
 Contingency                                  -               -         421
                                 ------------------------------------------
 Total Project                              913           1,465       6,425
                                 ------------------------------------------
                                 ------------------------------------------

Progress to Date

--  The project has transformed from an out-sourced approach to a complete
    in-house, self-perform arrangement where third-party engineers and
    contractors are now utilized only for identified specific tasks, and
    work within the Company's preferred project execution model.

    The earthworks have been the subject of critical review, as has the
    methodology of subsequent excavation and construction. Significant
    quantities of on-site equipment have been purchased by First Quantum
    from contractors whose contracts have been either cancelled or modified.
    This enables First Quantum to fully control all site development
    activities which provides for greater flexibility and significantly
    reduced risk. Site accommodation, road access, communications and
    management are now all fully functional and allowing the major
    activities to advance efficiently.

    The locations of key site infrastructure including the processing
    facilities have been reviewed and an alternate, more practical plant
    site has been selected which should be more cost effective to construct
    and allow for better access to the proposed in-pit crushing and conveyor
    systems for life-of-mine pits, and to the main access road.

Development Timeframe

--  The re-engineered and larger project is scheduled for construction
    completion and commissioning in the second half of 2017.

--------------------------------------------------------------------------
Activity                                                  Target Timeframe
--------------------------------------------------------------------------
Coast road available for use                                       Q1 2014
230KV overland power line complete                                 Q4 2015
300MW power station complete                                       Q1 2017
Tailings management facility complete                              Q2 2017
Process plant construction complete                                Q3 2017
Process commissioning and first concentrate production             Q4 2017
--------------------------------------------------------------------------

John Gregory, First Quantum's Group Consulting Engineer and a Qualified
Person as defined by National Instrument 43-101, has supervised the
preparation of the scientific and technical information (other than the
Cobre Panama Resource estimate) contained herein and has approved its
disclosure.

Funding Update

--  The Company advanced its objective to optimize its capital structure and
    financial flexibility and to achieve pari passu ranking and credit
    support among all classes of its capital markets indebtedness to
    appropriately suit its future growth and investment plans.

--  Inmet Bonds
    The Company and a subsidiary company are making an exchange offer to
    Inmet note holders. As part of this offer, existing 2020 and 2021 Notes
    which were issued by Inmet will be exchanged for New Notes which will be
    issued by the Company. As part of the consideration for the exchange,
    the Company is soliciting customary consents from Eligible Holders of
    Existing Notes. Highlights of the offer are as follows:

        --  Offer to exchange Inmet Notes as follows:
            --  US$1.5 billion Notes maturing 2020 with 8.75% coupon
            --  US$500 million Notes maturing 2021 with 7.5% coupon
            --  Exchanged into two Notes of US$1.14 billion each
                --  6.75% coupon maturing 2020
                --  7.00% coupon maturing 2021

--  Signed term sheet to refinance US$2.5 billion
        --  US$2.5 billion refinanced and announced in a separate news
            release on January 27, 2014
            --  Facility at the Company level
            --  Current Facility expiring June 30, 2014
            --  To be replaced by new five-year facilities:
                --  US$1 billion Term Loan (amortizing to start in 2 1/2
                    years' time)
                --  US$1.5 billion Revolving Credit Financing
                --  Interest calculated at a rate equal to LIBOR plus 2.75%

--  Kevitsa facility will be terminated (US$215 million available)

--  Kansanshi US$1 billion facility
    --  Work in progress to replace this with an US$350 million unsecured
        facility at the Kansanshi level

--  Korea Panama Mining Corporation
    --  Contributing and part of future funding plan

--  Franco Nevada
    --  Discussions to effect changes to the existing security and reporting
        requirements

CONFERENCE CALL & WEBCAST

Conference call and webcast details are as follows:

Date:         January 28, 2014

Time:         8:00 am (EST); 1:00 pm (GMT); 5:00 am (PST)

Webcast:      www.first-quantum.com

Dial in:      North America: 800 786 7015 (toll free)
              International and North America: 1 647 722 6879
              United Kingdom: 0800 528 0280 (toll free) or 44 2081962146

Replay:       Canada and international: 1 416 626 4100
              OR
              Toll free North America: 800 558 5253

Passcode:     21705806

The conference call replay will be available from 11:00 am (EST) until 11:59 pm (EST) on February 4, 2014.

ABOUT THE COBRE PANAMA PROJECT

Cobre Panama is a large open-pit copper development project in Panama. The concession is located 120 kilometres west of Panama City and 20 kilometres from the Caribbean Sea coast, in the district of Donoso, Colon province, in the Republic of Panama. The concession consists of four zones totalling 13,600 hectares.

Following the completion of First Quantum's acquisition of Inmet Mining in April 2013, it assumed an 80% equity interest in Minera Panama, S.A. ("MPSA"), the Panamanian company that holds the Cobre Panama concession. MPSA was incorporated under the laws of the Republic of Panama in January 1997 and has a mineral concession to explore and exploit the Cobre Panama property.

Access to the project area is via the Pan-American Highway system from Panama City to Penonome, surfaced all-weather roads to Llano Grande, and gravel roads via the town of Coclecito. The topography in the concession area is low elevation (less than 300 metres) but rugged with considerable local relief covered by dense rainforest. Climatic conditions are tropical with high precipitation levels, high humidity and relatively high temperatures of 25 degrees C to 30 degrees C year-round.

FORWARD LOOKING INFORMATION

Certain statements and information in this press release, including all statements that are not historical facts, contain forward-looking statements and forward-looking information within the meaning of applicable securities laws. Such forward-looking statements or information include but are not limited to statements or information with respect to the anticipated completion of the proposed Offer and the anticipated strategic and operational benefits of the Offer. Often, but not always, forward-looking statements or information can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "projects", "anticipates" or "does not anticipate" or "believes" or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

With respect to forward-looking statements and information contained in this press release, First Quantum has made numerous assumptions including, among other things, assumptions about the price of copper, gold, cobalt, nickel, PGE, and sulphuric acid, and other anticipated costs and expenditures. Although management of First Quantum believes that the assumptions made and the expectations represented by such statements or information are reasonable, there can be no assurance that any forward-looking statement or information herein will prove to be accurate. Forward-looking statements and information by their nature involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. These risks, uncertainties and other factors include, but are not limited to; availability of financing and access to capital, financing costs, operating cash flows, future production volumes and costs, costs for inputs, including oil, power and sulphur, retaining key personal, political stability in Zambia and Panama, adverse weather conditions, labour costs and disruptions, mechanical failures, water supply, procurement and delivery of parts and supplies to the project sites and operations, inherent uncertainty in estimating mineral reserves and resources, discrepancies between actual and estimated mineral reserves and resources, unanticipated grade, geological, metallurgical or processing problems, and other financial, construction, mining and production risks.

See First Quantum's annual information form for additional information on risks, uncertainties and other factors relating to the forward-looking statements and information. Although we have attempted to identify factors that would cause actual actions, events or results to differ materially from those disclosed in the forward-looking statements or information, there may be other factors, many of which are beyond the control of First Quantum, which might cause actual results, performances, achievements or events to differ from those anticipated, estimated or intended. Accordingly, readers should not place undue reliance on forward-looking statements or information.

While First Quantum may elect to update the forward-looking statements at any time, First Quantum does not undertake to update them at any particular time or in response to any particular event, other than as may be required by applicable securities laws. Investors and others should not assume that any forward-looking statement in this press release represent management's estimate as of any date other than the date of this press release

On Behalf of the Board of Directors of First Quantum Minerals Ltd.

G. Clive Newall, President

12g3-2b-82-4461

Listed in Standard and Poor's

Contacts:
North American contact:
Sharon Loung
Director, Investor Relations
(647) 346-3934 or Toll Free: 1 (888) 688-6577
(604) 688-3818 (FAX)
[email protected]

United Kingdom contact:
Clive Newall
President
+44 140 327 3484
+44 140 327 3494 (FAX)
[email protected]
www.first-quantum.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
With more than 30 Kubernetes solutions in the marketplace, it's tempting to think Kubernetes and the vendor ecosystem has solved the problem of operationalizing containers at scale or of automatically managing the elasticity of the underlying infrastructure that these solutions need to be truly scalable. Far from it. There are at least six major pain points that companies experience when they try to deploy and run Kubernetes in their complex environments. In this presentation, the speaker will d...
While DevOps most critically and famously fosters collaboration, communication, and integration through cultural change, culture is more of an output than an input. In order to actively drive cultural evolution, organizations must make substantial organizational and process changes, and adopt new technologies, to encourage a DevOps culture. Moderated by Andi Mann, panelists discussed how to balance these three pillars of DevOps, where to focus attention (and resources), where organizations might...
The deluge of IoT sensor data collected from connected devices and the powerful AI required to make that data actionable are giving rise to a hybrid ecosystem in which cloud, on-prem and edge processes become interweaved. Attendees will learn how emerging composable infrastructure solutions deliver the adaptive architecture needed to manage this new data reality. Machine learning algorithms can better anticipate data storms and automate resources to support surges, including fully scalable GPU-c...
When building large, cloud-based applications that operate at a high scale, it's important to maintain a high availability and resilience to failures. In order to do that, you must be tolerant of failures, even in light of failures in other areas of your application. "Fly two mistakes high" is an old adage in the radio control airplane hobby. It means, fly high enough so that if you make a mistake, you can continue flying with room to still make mistakes. In his session at 18th Cloud Expo, Le...
Machine learning has taken residence at our cities' cores and now we can finally have "smart cities." Cities are a collection of buildings made to provide the structure and safety necessary for people to function, create and survive. Buildings are a pool of ever-changing performance data from large automated systems such as heating and cooling to the people that live and work within them. Through machine learning, buildings can optimize performance, reduce costs, and improve occupant comfort by ...
As Cybric's Chief Technology Officer, Mike D. Kail is responsible for the strategic vision and technical direction of the platform. Prior to founding Cybric, Mike was Yahoo's CIO and SVP of Infrastructure, where he led the IT and Data Center functions for the company. He has more than 24 years of IT Operations experience with a focus on highly-scalable architectures.
The explosion of new web/cloud/IoT-based applications and the data they generate are transforming our world right before our eyes. In this rush to adopt these new technologies, organizations are often ignoring fundamental questions concerning who owns the data and failing to ask for permission to conduct invasive surveillance of their customers. Organizations that are not transparent about how their systems gather data telemetry without offering shared data ownership risk product rejection, regu...
CI/CD is conceptually straightforward, yet often technically intricate to implement since it requires time and opportunities to develop intimate understanding on not only DevOps processes and operations, but likely product integrations with multiple platforms. This session intends to bridge the gap by offering an intense learning experience while witnessing the processes and operations to build from zero to a simple, yet functional CI/CD pipeline integrated with Jenkins, Github, Docker and Azure...
René Bostic is the Technical VP of the IBM Cloud Unit in North America. Enjoying her career with IBM during the modern millennial technological era, she is an expert in cloud computing, DevOps and emerging cloud technologies such as Blockchain. Her strengths and core competencies include a proven record of accomplishments in consensus building at all levels to assess, plan, and implement enterprise and cloud computing solutions. René is a member of the Society of Women Engineers (SWE) and a m...
Dhiraj Sehgal works in Delphix's product and solution organization. His focus has been DevOps, DataOps, private cloud and datacenters customers, technologies and products. He has wealth of experience in cloud focused and virtualized technologies ranging from compute, networking to storage. He has spoken at Cloud Expo for last 3 years now in New York and Santa Clara.
Enterprises are striving to become digital businesses for differentiated innovation and customer-centricity. Traditionally, they focused on digitizing processes and paper workflow. To be a disruptor and compete against new players, they need to gain insight into business data and innovate at scale. Cloud and cognitive technologies can help them leverage hidden data in SAP/ERP systems to fuel their businesses to accelerate digital transformation success.
Containers and Kubernetes allow for code portability across on-premise VMs, bare metal, or multiple cloud provider environments. Yet, despite this portability promise, developers may include configuration and application definitions that constrain or even eliminate application portability. In this session we'll describe best practices for "configuration as code" in a Kubernetes environment. We will demonstrate how a properly constructed containerized app can be deployed to both Amazon and Azure ...
Poor data quality and analytics drive down business value. In fact, Gartner estimated that the average financial impact of poor data quality on organizations is $9.7 million per year. But bad data is much more than a cost center. By eroding trust in information, analytics and the business decisions based on these, it is a serious impediment to digital transformation.
Digital Transformation: Preparing Cloud & IoT Security for the Age of Artificial Intelligence. As automation and artificial intelligence (AI) power solution development and delivery, many businesses need to build backend cloud capabilities. Well-poised organizations, marketing smart devices with AI and BlockChain capabilities prepare to refine compliance and regulatory capabilities in 2018. Volumes of health, financial, technical and privacy data, along with tightening compliance requirements by...
Predicting the future has never been more challenging - not because of the lack of data but because of the flood of ungoverned and risk laden information. Microsoft states that 2.5 exabytes of data are created every day. Expectations and reliance on data are being pushed to the limits, as demands around hybrid options continue to grow.