Revett Updates Troy Mine Reserves and Resources Indicating a Twelve Year Life-of-Mine and Provides Development Update

SPOKANE VALLEY, WASHINGTON FEBRUARY -- (Marketwired) -- 02/03/14 -- Revett Minerals Inc. (TSX: RVM)(NYSE MKT: RVM) ("Revett" or the "Company") is pleased to provide updated reserve and resource estimates as at year end 2013 suggesting a twelve year Life of Mine. The Company is also pleased to provide an update on underground development activities at the Troy Mine in northwestern Montana.

Troy Reserves & Resources

Ongoing exploration efforts, along with confirmation of existing data at the Troy Mine, have successfully illustrated reserves and resources which will extend the life-of-mine to twelve years. These reserves fully replace the ore mined in 2012 and the approximately 1 million tons of ore reserves adversely impacted by restricted access due to known structural issues; and, by reduced metal pricing. The Company's primary focus during 2014 and early 2015 will be on development of the North and South C Bed and I Bed orebodies. Exploration efforts will recommence in late 2015 which will further define I Bed mineralization east and south of current I Bed reserves and will focus on continuity and extension of the I Beds to the south.

Estimated Mineral Reserves and Resources as of December 31, 2013 are as shown in the following tables:


----------------------------------------------------------------------------
----------------------------------------------------------------------------
Troy Reserves (Dec. 31, 2013)              Grades           Contained Metals
----------------------------------------------------------------------------
Classification(1)        Tons  Silver
                   (Mst)(2,3)   (opt)  Copper (%) Silver (Moz) Copper (Mlbs)
----------------------------------------------------------------------------
Proven                   1.54    1.42        0.70         2.18         21.45
Probable                15.03    1.00        0.33        14.99         99.48
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total                   16.57    1.04        0.36        17.17        120.92
----------------------------------------------------------------------------
1.  Mineral Reserves have been categorized in accordance with the
    classifications defined by the Canadian Institute of Mining, Metallurgy,
    and Petroleum ("CIMM").
2.  Does not include resources contained in planned pillars. Only material
    scheduled to be extracted and milled included.
3.  The estimated mineral reserves were calculated by Mr. Larry Erickson, P
    Eng., a Qualified Person ("QP") in accordance with Canadian National
    Instrument 43-101 ("NI 43-101"). Key factors in determining reserves are
    stated using cut-off grade of US$29.99 net smelter return calculated at
    US$25.06/oz Ag and US$3.32/lb Cu, mining recovery of 100% and 0%
    dilution. Metallurgical recoveries for life of mine average are 85.43%
    Ag. and 83.76% Cu.
----------------------------------------------------------------------------
----------------------------------------------------------------------------

----------------------------------------------------------------------------
----------------------------------------------------------------------------

Troy Resources (Dec. 31, 2013)                      Grades  Contained Metals
Classification(1)                     Tons  Silver  Copper   Silver   Copper
                                (Mst)(2,3)   (opt)     (%)    (Moz)   (Mlbs)
----------------------------------------------------------------------------
Measured                             50.69    1.33    0.65    67.65   661.38
Indicated                            25.08    1.02    0.34    25.59   172.71
----------------------------------------------------------------------------
Total Measured &
 Indicated(i)                        75.77    1.23    0.55    93.24   834.09
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Inferred                              1.50    0.71    0.30     1.06     8.86
----------------------------------------------------------------------------
----------------------------------------------------------------------------

----------------------------------------------------------------------------
----------------------------------------------------------------------------
(i)Pillars Incl. in
 Meas. & Ind.                        49.91    1.33    0.65    66.39   650.15
----------------------------------------------------------------------------
----------------------------------------------------------------------------
1.  Mineral Resources have been categorized in accordance with the
    classifications defined by the CIMM.
2.  Includes Proven & Probable Reserves and resources contained in existing
    pillars The estimated mineral resources were calculated by Mr. Larry
    Erickson, P Eng., a QP in accordance with NI 43-101. They are stated
    using a cut-off grade of US$29.99 net smelter return per ton calculated
    at US$25.06/oz Ag and US$3.32/lb Cu. Mr. Erickson is an employee of
    Revett and is not considered independent.
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Larry Erickson, P. Eng., an employee of Revett and a QP, has reviewed the technical information in this new release.

Troy Mine Update

Underground development at Troy continues on schedule and within budget. Since commencing the I Bed development drift in early November 2013, the Company has advanced approximately 2,250 feet in total as at January 31st, 2014. Preparations are now being made for the installation of the first borehole which will serve as secondary egress and ventilation for development and production of the C Beds. Development has now moved to dual drifting and will continue at an average grade of 12.5% until reaching the North C Bed which is anticipated to be in the third quarter of 2014. The mill is scheduled to be restarted for limited commercial production in the fourth quarter of 2014.

The planned total of the development drifts to the North C Bed is approximately 7,500 feet (including muck bays and cross-overs). Continued development to access the I Beds requires an additional 5,900 feet of single decline with an accompanying borehole for secondary egress and ventilation. This development is expected to take six to nine months after the North C Bed orebody has been accessed. Once completed, we anticipate returning to full production capabilities at the Troy Mine. The total cost of the decline development is currently estimated to be approximately $12 million.

John Shanahan, Revett's President and CEO stated "Our current underground development efforts continue to progress on schedule. We are particularly pleased with the structural integrity and competency of the development drift which will support our current twelve year mine life. With continued exploration, we remain confident that we will continue to extend mine life at Troy. Being an efficient and safe operator at Troy is an important component of our development plans at Rock Creek. Being in operation at Troy in tandem with Rock Creek will enable us to fully utilize our operational experiences and attain the high level of responsible development that we are committed to."

About Revett

Revett, through its subsidiaries, owns and operates the Troy Mine in Lincoln County, Montana and development-stage Rock Creek Project located in Sanders County, Montana, USA. Its goal is to resume commercial production at the Troy Mine and develop the significant resources at the Rock Creek project, and thereby become a premier mid-tier base and precious metals producer.

John Shanahan, President & CEO

Except for the statements of historical fact contained herein, the information presented in this news release may contain "forward-looking statements" within the meaning of applicable Canadian securities legislation and The Private Securities Litigation Reform Act of 1995. Generally, these forward looking statements can be identified by the use of forward-looking terminology such as "plans", "expects", or "does not expect", "is expected", "is not expected", "budget", "schedule", "estimates", "forecasts", "intends", "anticipates", "or does not anticipate" or "believes" or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking statements contained in this news release include estimated reserves and resources as well as estimated life of mine, the Company's plans to complete the construction of declines and the Company's expectation that limited commercial production will resume in the fourth quarter of 2014, including having the financial capability to do so. Actual results will depend upon our ability to obtain financing, the views of MSHA, actual tonnage and grade and economic feasibility of the deposits as well as decisions made my management having regard to the nature of the geotechnical conditions and the safety of Revett's employees. (NTD: set out any other factors that could affect future outcome) Forward looking statements, including future-oriented financial information, are necessarily based upon a number of estimates and assumptions that, while considered reasonable by management, are inherently subject to significant business and economic uncertainties, risks and contingencies and those factors discussed in the section entitled "Risk Factors" in the Form 10-K filed on SEDAR at www.sedar.com and with the SEC on EDGAR. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Revett Minerals does not undertake to update any forward-looking statements except as required by applicable securities laws.

Contacts:
Revett Minerals Inc.
Monique Hayes
Corporate Secretary / Director of Investor Relations
(509) 921-2294
www.revettminerals.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Discussions about cloud computing are evolving into discussions about enterprise IT in general. As enterprises increasingly migrate toward their own unique clouds, new issues such as the use of containers and microservices emerge to keep things interesting. In this Power Panel at 16th Cloud Expo, moderated by Conference Chair Roger Strukhoff, panelists addressed the state of cloud computing today, and what enterprise IT professionals need to know about how the latest topics and trends affect t...
The essence of cloud computing is that all consumable IT resources are delivered as services. In his session at 15th Cloud Expo, Yung Chou, Technology Evangelist at Microsoft, demonstrated the concepts and implementations of two important cloud computing deliveries: Infrastructure as a Service (IaaS) and Platform as a Service (PaaS). He discussed from business and technical viewpoints what exactly they are, why we care, how they are different and in what ways, and the strategies for IT to tran...
Containers are changing the security landscape for software development and deployment. As with any security solutions, security approaches that work for developers, operations personnel and security professionals is a requirement. In his session at DevOps Summit, Kevin Gilpin, CTO and Co-Founder of Conjur, will discuss various security considerations for container-based infrastructure and related DevOps workflows.
Countless business models have spawned from the IaaS industry. Resell Web hosting, blogs, public cloud, and on and on. With the overwhelming amount of tools available to us, it's sometimes easy to overlook that many of them are just new skins of resources we've had for a long time. In his General Session at 16th Cloud Expo, Phil Jackson, Lead Technology Evangelist at SoftLayer, broke down what we've got to work with and discuss the benefits and pitfalls to discover how we can best use them to d...
Puppet Labs has announced the next major update to its flagship product: Puppet Enterprise 2015.2. This release includes new features providing DevOps teams with clarity, simplicity and additional management capabilities, including an all-new user interface, an interactive graph for visualizing infrastructure code, a new unified agent and broader infrastructure support.
SYS-CON Events announced today that HPM Networks will exhibit at the 17th International Cloud Expo®, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. For 20 years, HPM Networks has been integrating technology solutions that solve complex business challenges. HPM Networks has designed solutions for both SMB and enterprise customers throughout the San Francisco Bay Area.
SYS-CON Events announced today that Agema Systems will exhibit at the 17th International Cloud Expo®, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. Agema Systems is the leading provider of critical white-box rack solutions to data centers through the major integrators and value added distribution channels.
For IoT to grow as quickly as analyst firms’ project, a lot is going to fall on developers to quickly bring applications to market. But the lack of a standard development platform threatens to slow growth and make application development more time consuming and costly, much like we’ve seen in the mobile space. In his session at @ThingsExpo, Mike Weiner, Product Manager of the Omega DevCloud with KORE Telematics Inc., discussed the evolving requirements for developers as IoT matures and conducte...
"Our biggest growth area has been the security services, the managed services - the things that differentiate us in the market that there is no client that's too small and there's no client that's too big," explained Paul Mazzucco, Chief Security Officer at TierPoint, in this SYS-CON.tv interview at 16th Cloud Expo, held June 9-11, 2015, at the Javits Center in New York City.
Converging digital disruptions is creating a major sea change - Cisco calls this the Internet of Everything (IoE). IoE is the network connection of People, Process, Data and Things, fueled by Cloud, Mobile, Social, Analytics and Security, and it represents a $19Trillion value-at-stake over the next 10 years. In her keynote at @ThingsExpo, Manjula Talreja, VP of Cisco Consulting Services, discussed IoE and the enormous opportunities it provides to public and private firms alike. She will share w...
"Alert Logic is a managed security service provider that basically deploys technologies, but we support those technologies with the people and process behind it," stated Stephen Coty, Chief Security Evangelist at Alert Logic, in this SYS-CON.tv interview at 16th Cloud Expo, held June 9-11, 2015, at the Javits Center in New York City.
"We specialize in testing. DevOps is all about continuous delivery and accelerating the delivery pipeline and there is no continuous delivery without testing," noted Marc Hornbeek, Sr. Solutions Architect at Spirent Communications, in this SYS-CON.tv interview at @DevOpsSummit, held June 9-11, 2015, at the Javits Center in New York City.
"ProfitBricks was founded in 2010 and we are the painless cloud - and we are also the Infrastructure as a Service 2.0 company," noted Achim Weiss, Chief Executive Officer and Co-Founder of ProfitBricks, in this SYS-CON.tv interview at 16th Cloud Expo, held June 9-11, 2015, at the Javits Center in New York City.
With SaaS use rampant across organizations, how can IT departments track company data and maintain security? More and more departments are commissioning their own solutions and bypassing IT. A cloud environment is amorphous and powerful, allowing you to set up solutions for all of your user needs: document sharing and collaboration, mobile access, e-mail, even industry-specific applications. In his session at 16th Cloud Expo, Shawn Mills, President and a founder of Green House Data, discussed h...
"We do data integration for B2B also application to application, and we do data management and enable Big Data," explained Pat Adamiak, Vice President, Product Marketing at Liaison Technologies, in this SYS-CON.tv interview at 16th Cloud Expo, held June 9-11, 2015, at the Javits Center in New York City.