Revett Updates Troy Mine Reserves and Resources Indicating a Twelve Year Life-of-Mine and Provides Development Update

SPOKANE VALLEY, WASHINGTON FEBRUARY -- (Marketwired) -- 02/03/14 -- Revett Minerals Inc. (TSX: RVM)(NYSE MKT: RVM) ("Revett" or the "Company") is pleased to provide updated reserve and resource estimates as at year end 2013 suggesting a twelve year Life of Mine. The Company is also pleased to provide an update on underground development activities at the Troy Mine in northwestern Montana.

Troy Reserves & Resources

Ongoing exploration efforts, along with confirmation of existing data at the Troy Mine, have successfully illustrated reserves and resources which will extend the life-of-mine to twelve years. These reserves fully replace the ore mined in 2012 and the approximately 1 million tons of ore reserves adversely impacted by restricted access due to known structural issues; and, by reduced metal pricing. The Company's primary focus during 2014 and early 2015 will be on development of the North and South C Bed and I Bed orebodies. Exploration efforts will recommence in late 2015 which will further define I Bed mineralization east and south of current I Bed reserves and will focus on continuity and extension of the I Beds to the south.

Estimated Mineral Reserves and Resources as of December 31, 2013 are as shown in the following tables:

----------------------------------------------------------------------------
----------------------------------------------------------------------------
Troy Reserves (Dec. 31, 2013)              Grades           Contained Metals
----------------------------------------------------------------------------
Classification(1)        Tons  Silver
                   (Mst)(2,3)   (opt)  Copper (%) Silver (Moz) Copper (Mlbs)
----------------------------------------------------------------------------
Proven                   1.54    1.42        0.70         2.18         21.45
Probable                15.03    1.00        0.33        14.99         99.48
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total                   16.57    1.04        0.36        17.17        120.92
----------------------------------------------------------------------------
1.  Mineral Reserves have been categorized in accordance with the
    classifications defined by the Canadian Institute of Mining, Metallurgy,
    and Petroleum ("CIMM").
2.  Does not include resources contained in planned pillars. Only material
    scheduled to be extracted and milled included.
3.  The estimated mineral reserves were calculated by Mr. Larry Erickson, P
    Eng., a Qualified Person ("QP") in accordance with Canadian National
    Instrument 43-101 ("NI 43-101"). Key factors in determining reserves are
    stated using cut-off grade of US$29.99 net smelter return calculated at
    US$25.06/oz Ag and US$3.32/lb Cu, mining recovery of 100% and 0%
    dilution. Metallurgical recoveries for life of mine average are 85.43%
    Ag. and 83.76% Cu.
----------------------------------------------------------------------------
----------------------------------------------------------------------------

----------------------------------------------------------------------------
----------------------------------------------------------------------------

Troy Resources (Dec. 31, 2013)                      Grades  Contained Metals
Classification(1)                     Tons  Silver  Copper   Silver   Copper
                                (Mst)(2,3)   (opt)     (%)    (Moz)   (Mlbs)
----------------------------------------------------------------------------
Measured                             50.69    1.33    0.65    67.65   661.38
Indicated                            25.08    1.02    0.34    25.59   172.71
----------------------------------------------------------------------------
Total Measured &
 Indicated(i)                        75.77    1.23    0.55    93.24   834.09
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Inferred                              1.50    0.71    0.30     1.06     8.86
----------------------------------------------------------------------------
----------------------------------------------------------------------------

----------------------------------------------------------------------------
----------------------------------------------------------------------------
(i)Pillars Incl. in
 Meas. & Ind.                        49.91    1.33    0.65    66.39   650.15
----------------------------------------------------------------------------
----------------------------------------------------------------------------
1.  Mineral Resources have been categorized in accordance with the
    classifications defined by the CIMM.
2.  Includes Proven & Probable Reserves and resources contained in existing
    pillars The estimated mineral resources were calculated by Mr. Larry
    Erickson, P Eng., a QP in accordance with NI 43-101. They are stated
    using a cut-off grade of US$29.99 net smelter return per ton calculated
    at US$25.06/oz Ag and US$3.32/lb Cu. Mr. Erickson is an employee of
    Revett and is not considered independent.
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Larry Erickson, P. Eng., an employee of Revett and a QP, has reviewed the technical information in this new release.

Troy Mine Update

Underground development at Troy continues on schedule and within budget. Since commencing the I Bed development drift in early November 2013, the Company has advanced approximately 2,250 feet in total as at January 31st, 2014. Preparations are now being made for the installation of the first borehole which will serve as secondary egress and ventilation for development and production of the C Beds. Development has now moved to dual drifting and will continue at an average grade of 12.5% until reaching the North C Bed which is anticipated to be in the third quarter of 2014. The mill is scheduled to be restarted for limited commercial production in the fourth quarter of 2014.

The planned total of the development drifts to the North C Bed is approximately 7,500 feet (including muck bays and cross-overs). Continued development to access the I Beds requires an additional 5,900 feet of single decline with an accompanying borehole for secondary egress and ventilation. This development is expected to take six to nine months after the North C Bed orebody has been accessed. Once completed, we anticipate returning to full production capabilities at the Troy Mine. The total cost of the decline development is currently estimated to be approximately $12 million.

John Shanahan, Revett's President and CEO stated "Our current underground development efforts continue to progress on schedule. We are particularly pleased with the structural integrity and competency of the development drift which will support our current twelve year mine life. With continued exploration, we remain confident that we will continue to extend mine life at Troy. Being an efficient and safe operator at Troy is an important component of our development plans at Rock Creek. Being in operation at Troy in tandem with Rock Creek will enable us to fully utilize our operational experiences and attain the high level of responsible development that we are committed to."

About Revett

Revett, through its subsidiaries, owns and operates the Troy Mine in Lincoln County, Montana and development-stage Rock Creek Project located in Sanders County, Montana, USA. Its goal is to resume commercial production at the Troy Mine and develop the significant resources at the Rock Creek project, and thereby become a premier mid-tier base and precious metals producer.

John Shanahan, President & CEO

Except for the statements of historical fact contained herein, the information presented in this news release may contain "forward-looking statements" within the meaning of applicable Canadian securities legislation and The Private Securities Litigation Reform Act of 1995. Generally, these forward looking statements can be identified by the use of forward-looking terminology such as "plans", "expects", or "does not expect", "is expected", "is not expected", "budget", "schedule", "estimates", "forecasts", "intends", "anticipates", "or does not anticipate" or "believes" or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking statements contained in this news release include estimated reserves and resources as well as estimated life of mine, the Company's plans to complete the construction of declines and the Company's expectation that limited commercial production will resume in the fourth quarter of 2014, including having the financial capability to do so. Actual results will depend upon our ability to obtain financing, the views of MSHA, actual tonnage and grade and economic feasibility of the deposits as well as decisions made my management having regard to the nature of the geotechnical conditions and the safety of Revett's employees. (NTD: set out any other factors that could affect future outcome) Forward looking statements, including future-oriented financial information, are necessarily based upon a number of estimates and assumptions that, while considered reasonable by management, are inherently subject to significant business and economic uncertainties, risks and contingencies and those factors discussed in the section entitled "Risk Factors" in the Form 10-K filed on SEDAR at www.sedar.com and with the SEC on EDGAR. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Revett Minerals does not undertake to update any forward-looking statements except as required by applicable securities laws.

Contacts:
Revett Minerals Inc.
Monique Hayes
Corporate Secretary / Director of Investor Relations
(509) 921-2294
www.revettminerals.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
DX World EXPO, LLC, a Lighthouse Point, Florida-based startup trade show producer and the creator of "DXWorldEXPO® - Digital Transformation Conference & Expo" has announced its executive management team. The team is headed by Levent Selamoglu, who has been named CEO. "Now is the time for a truly global DX event, to bring together the leading minds from the technology world in a conversation about Digital Transformation," he said in making the announcement.
"Space Monkey by Vivent Smart Home is a product that is a distributed cloud-based edge storage network. Vivent Smart Home, our parent company, is a smart home provider that places a lot of hard drives across homes in North America," explained JT Olds, Director of Engineering, and Brandon Crowfeather, Product Manager, at Vivint Smart Home, in this SYS-CON.tv interview at @ThingsExpo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today that Conference Guru has been named “Media Sponsor” of the 22nd International Cloud Expo, which will take place on June 5-7, 2018, at the Javits Center in New York, NY. A valuable conference experience generates new contacts, sales leads, potential strategic partners and potential investors; helps gather competitive intelligence and even provides inspiration for new products and services. Conference Guru works with conference organizers to pass great deals to gre...
DevOps is under attack because developers don’t want to mess with infrastructure. They will happily own their code into production, but want to use platforms instead of raw automation. That’s changing the landscape that we understand as DevOps with both architecture concepts (CloudNative) and process redefinition (SRE). Rob Hirschfeld’s recent work in Kubernetes operations has led to the conclusion that containers and related platforms have changed the way we should be thinking about DevOps and...
The Internet of Things will challenge the status quo of how IT and development organizations operate. Or will it? Certainly the fog layer of IoT requires special insights about data ontology, security and transactional integrity. But the developmental challenges are the same: People, Process and Platform. In his session at @ThingsExpo, Craig Sproule, CEO of Metavine, demonstrated how to move beyond today's coding paradigm and shared the must-have mindsets for removing complexity from the develop...
In his Opening Keynote at 21st Cloud Expo, John Considine, General Manager of IBM Cloud Infrastructure, led attendees through the exciting evolution of the cloud. He looked at this major disruption from the perspective of technology, business models, and what this means for enterprises of all sizes. John Considine is General Manager of Cloud Infrastructure Services at IBM. In that role he is responsible for leading IBM’s public cloud infrastructure including strategy, development, and offering m...
The next XaaS is CICDaaS. Why? Because CICD saves developers a huge amount of time. CD is an especially great option for projects that require multiple and frequent contributions to be integrated. But… securing CICD best practices is an emerging, essential, yet little understood practice for DevOps teams and their Cloud Service Providers. The only way to get CICD to work in a highly secure environment takes collaboration, patience and persistence. Building CICD in the cloud requires rigorous ar...
Companies are harnessing data in ways we once associated with science fiction. Analysts have access to a plethora of visualization and reporting tools, but considering the vast amount of data businesses collect and limitations of CPUs, end users are forced to design their structures and systems with limitations. Until now. As the cloud toolkit to analyze data has evolved, GPUs have stepped in to massively parallel SQL, visualization and machine learning.
"Evatronix provides design services to companies that need to integrate the IoT technology in their products but they don't necessarily have the expertise, knowledge and design team to do so," explained Adam Morawiec, VP of Business Development at Evatronix, in this SYS-CON.tv interview at @ThingsExpo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
To get the most out of their data, successful companies are not focusing on queries and data lakes, they are actively integrating analytics into their operations with a data-first application development approach. Real-time adjustments to improve revenues, reduce costs, or mitigate risk rely on applications that minimize latency on a variety of data sources. In his session at @BigDataExpo, Jack Norris, Senior Vice President, Data and Applications at MapR Technologies, reviewed best practices to ...
Widespread fragmentation is stalling the growth of the IIoT and making it difficult for partners to work together. The number of software platforms, apps, hardware and connectivity standards is creating paralysis among businesses that are afraid of being locked into a solution. EdgeX Foundry is unifying the community around a common IoT edge framework and an ecosystem of interoperable components.
"ZeroStack is a startup in Silicon Valley. We're solving a very interesting problem around bringing public cloud convenience with private cloud control for enterprises and mid-size companies," explained Kamesh Pemmaraju, VP of Product Management at ZeroStack, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
Large industrial manufacturing organizations are adopting the agile principles of cloud software companies. The industrial manufacturing development process has not scaled over time. Now that design CAD teams are geographically distributed, centralizing their work is key. With large multi-gigabyte projects, outdated tools have stifled industrial team agility, time-to-market milestones, and impacted P&L stakeholders.
"Akvelon is a software development company and we also provide consultancy services to folks who are looking to scale or accelerate their engineering roadmaps," explained Jeremiah Mothersell, Marketing Manager at Akvelon, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
Enterprises are adopting Kubernetes to accelerate the development and the delivery of cloud-native applications. However, sharing a Kubernetes cluster between members of the same team can be challenging. And, sharing clusters across multiple teams is even harder. Kubernetes offers several constructs to help implement segmentation and isolation. However, these primitives can be complex to understand and apply. As a result, it’s becoming common for enterprises to end up with several clusters. Thi...