Revett Updates Troy Mine Reserves and Resources Indicating a Twelve Year Life-of-Mine and Provides Development Update

SPOKANE VALLEY, WASHINGTON FEBRUARY -- (Marketwired) -- 02/03/14 -- Revett Minerals Inc. (TSX: RVM)(NYSE MKT: RVM) ("Revett" or the "Company") is pleased to provide updated reserve and resource estimates as at year end 2013 suggesting a twelve year Life of Mine. The Company is also pleased to provide an update on underground development activities at the Troy Mine in northwestern Montana.

Troy Reserves & Resources

Ongoing exploration efforts, along with confirmation of existing data at the Troy Mine, have successfully illustrated reserves and resources which will extend the life-of-mine to twelve years. These reserves fully replace the ore mined in 2012 and the approximately 1 million tons of ore reserves adversely impacted by restricted access due to known structural issues; and, by reduced metal pricing. The Company's primary focus during 2014 and early 2015 will be on development of the North and South C Bed and I Bed orebodies. Exploration efforts will recommence in late 2015 which will further define I Bed mineralization east and south of current I Bed reserves and will focus on continuity and extension of the I Beds to the south.

Estimated Mineral Reserves and Resources as of December 31, 2013 are as shown in the following tables:


----------------------------------------------------------------------------
----------------------------------------------------------------------------
Troy Reserves (Dec. 31, 2013)              Grades           Contained Metals
----------------------------------------------------------------------------
Classification(1)        Tons  Silver
                   (Mst)(2,3)   (opt)  Copper (%) Silver (Moz) Copper (Mlbs)
----------------------------------------------------------------------------
Proven                   1.54    1.42        0.70         2.18         21.45
Probable                15.03    1.00        0.33        14.99         99.48
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total                   16.57    1.04        0.36        17.17        120.92
----------------------------------------------------------------------------
1.  Mineral Reserves have been categorized in accordance with the
    classifications defined by the Canadian Institute of Mining, Metallurgy,
    and Petroleum ("CIMM").
2.  Does not include resources contained in planned pillars. Only material
    scheduled to be extracted and milled included.
3.  The estimated mineral reserves were calculated by Mr. Larry Erickson, P
    Eng., a Qualified Person ("QP") in accordance with Canadian National
    Instrument 43-101 ("NI 43-101"). Key factors in determining reserves are
    stated using cut-off grade of US$29.99 net smelter return calculated at
    US$25.06/oz Ag and US$3.32/lb Cu, mining recovery of 100% and 0%
    dilution. Metallurgical recoveries for life of mine average are 85.43%
    Ag. and 83.76% Cu.
----------------------------------------------------------------------------
----------------------------------------------------------------------------

----------------------------------------------------------------------------
----------------------------------------------------------------------------

Troy Resources (Dec. 31, 2013)                      Grades  Contained Metals
Classification(1)                     Tons  Silver  Copper   Silver   Copper
                                (Mst)(2,3)   (opt)     (%)    (Moz)   (Mlbs)
----------------------------------------------------------------------------
Measured                             50.69    1.33    0.65    67.65   661.38
Indicated                            25.08    1.02    0.34    25.59   172.71
----------------------------------------------------------------------------
Total Measured &
 Indicated(i)                        75.77    1.23    0.55    93.24   834.09
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Inferred                              1.50    0.71    0.30     1.06     8.86
----------------------------------------------------------------------------
----------------------------------------------------------------------------

----------------------------------------------------------------------------
----------------------------------------------------------------------------
(i)Pillars Incl. in
 Meas. & Ind.                        49.91    1.33    0.65    66.39   650.15
----------------------------------------------------------------------------
----------------------------------------------------------------------------
1.  Mineral Resources have been categorized in accordance with the
    classifications defined by the CIMM.
2.  Includes Proven & Probable Reserves and resources contained in existing
    pillars The estimated mineral resources were calculated by Mr. Larry
    Erickson, P Eng., a QP in accordance with NI 43-101. They are stated
    using a cut-off grade of US$29.99 net smelter return per ton calculated
    at US$25.06/oz Ag and US$3.32/lb Cu. Mr. Erickson is an employee of
    Revett and is not considered independent.
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Larry Erickson, P. Eng., an employee of Revett and a QP, has reviewed the technical information in this new release.

Troy Mine Update

Underground development at Troy continues on schedule and within budget. Since commencing the I Bed development drift in early November 2013, the Company has advanced approximately 2,250 feet in total as at January 31st, 2014. Preparations are now being made for the installation of the first borehole which will serve as secondary egress and ventilation for development and production of the C Beds. Development has now moved to dual drifting and will continue at an average grade of 12.5% until reaching the North C Bed which is anticipated to be in the third quarter of 2014. The mill is scheduled to be restarted for limited commercial production in the fourth quarter of 2014.

The planned total of the development drifts to the North C Bed is approximately 7,500 feet (including muck bays and cross-overs). Continued development to access the I Beds requires an additional 5,900 feet of single decline with an accompanying borehole for secondary egress and ventilation. This development is expected to take six to nine months after the North C Bed orebody has been accessed. Once completed, we anticipate returning to full production capabilities at the Troy Mine. The total cost of the decline development is currently estimated to be approximately $12 million.

John Shanahan, Revett's President and CEO stated "Our current underground development efforts continue to progress on schedule. We are particularly pleased with the structural integrity and competency of the development drift which will support our current twelve year mine life. With continued exploration, we remain confident that we will continue to extend mine life at Troy. Being an efficient and safe operator at Troy is an important component of our development plans at Rock Creek. Being in operation at Troy in tandem with Rock Creek will enable us to fully utilize our operational experiences and attain the high level of responsible development that we are committed to."

About Revett

Revett, through its subsidiaries, owns and operates the Troy Mine in Lincoln County, Montana and development-stage Rock Creek Project located in Sanders County, Montana, USA. Its goal is to resume commercial production at the Troy Mine and develop the significant resources at the Rock Creek project, and thereby become a premier mid-tier base and precious metals producer.

John Shanahan, President & CEO

Except for the statements of historical fact contained herein, the information presented in this news release may contain "forward-looking statements" within the meaning of applicable Canadian securities legislation and The Private Securities Litigation Reform Act of 1995. Generally, these forward looking statements can be identified by the use of forward-looking terminology such as "plans", "expects", or "does not expect", "is expected", "is not expected", "budget", "schedule", "estimates", "forecasts", "intends", "anticipates", "or does not anticipate" or "believes" or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking statements contained in this news release include estimated reserves and resources as well as estimated life of mine, the Company's plans to complete the construction of declines and the Company's expectation that limited commercial production will resume in the fourth quarter of 2014, including having the financial capability to do so. Actual results will depend upon our ability to obtain financing, the views of MSHA, actual tonnage and grade and economic feasibility of the deposits as well as decisions made my management having regard to the nature of the geotechnical conditions and the safety of Revett's employees. (NTD: set out any other factors that could affect future outcome) Forward looking statements, including future-oriented financial information, are necessarily based upon a number of estimates and assumptions that, while considered reasonable by management, are inherently subject to significant business and economic uncertainties, risks and contingencies and those factors discussed in the section entitled "Risk Factors" in the Form 10-K filed on SEDAR at www.sedar.com and with the SEC on EDGAR. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Revett Minerals does not undertake to update any forward-looking statements except as required by applicable securities laws.

Contacts:
Revett Minerals Inc.
Monique Hayes
Corporate Secretary / Director of Investor Relations
(509) 921-2294
www.revettminerals.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that LeaseWeb USA, a cloud Infrastructure-as-a-Service (IaaS) provider, will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. LeaseWeb is one of the world's largest hosting brands. The company helps customers define, develop and deploy IT infrastructure tailored to their exact business needs, by combining various kinds cloud solutions.
Using new techniques of information modeling, indexing, and processing, new cloud-based systems can support cloud-based workloads previously not possible for high-throughput insurance, banking, and case-based applications. In his session at 18th Cloud Expo, John Newton, CTO, Founder and Chairman of Alfresco, described how to scale cloud-based content management repositories to store, manage, and retrieve billions of documents and related information with fast and linear scalability. He addres...
The cloud market growth today is largely in public clouds. While there is a lot of spend in IT departments in virtualization, these aren’t yet translating into a true “cloud” experience within the enterprise. What is stopping the growth of the “private cloud” market? In his general session at 18th Cloud Expo, Nara Rajagopalan, CEO of Accelerite, explored the challenges in deploying, managing, and getting adoption for a private cloud within an enterprise. What are the key differences between wh...
Adding public cloud resources to an existing application can be a daunting process. The tools that you currently use to manage the software and hardware outside the cloud aren’t always the best tools to efficiently grow into the cloud. All of the major configuration management tools have cloud orchestration plugins that can be leveraged, but there are also cloud-native tools that can dramatically improve the efficiency of managing your application lifecycle. In his session at 18th Cloud Expo, ...
It’s 2016: buildings are smart, connected and the IoT is fundamentally altering how control and operating systems work and speak to each other. Platforms across the enterprise are networked via inexpensive sensors to collect massive amounts of data for analytics, information management, and insights that can be used to continuously improve operations. In his session at @ThingsExpo, Brian Chemel, Co-Founder and CTO of Digital Lumens, will explore: The benefits sensor-networked systems bring to ...
Much of IT terminology is often misused and misapplied. Modernization and transformation are two such terms. They are often used interchangeably even though they mean different things and have very different connotations. Indeed, it is somewhat safe to assume that in IT any transformative effort is likely to also have a modernizing effect, and thus, we can see these as levels of improvement efforts. However, many businesses are being led to believe if they don’t transform now they risk becoming ...
SYS-CON Events announced today the Enterprise IoT Bootcamp, being held November 1-2, 2016, in conjunction with 19th Cloud Expo | @ThingsExpo at the Santa Clara Convention Center in Santa Clara, CA. Combined with real-world scenarios and use cases, the Enterprise IoT Bootcamp is not just based on presentations but with hands-on demos and detailed walkthroughs. We will introduce you to a variety of real world use cases prototyped using Arduino, Raspberry Pi, BeagleBone, Spark, and Intel Edison. Y...
When building large, cloud-based applications that operate at a high scale, it’s important to maintain a high availability and resilience to failures. In order to do that, you must be tolerant of failures, even in light of failures in other areas of your application. “Fly two mistakes high” is an old adage in the radio control airplane hobby. It means, fly high enough so that if you make a mistake, you can continue flying with room to still make mistakes. In his session at 18th Cloud Expo, Lee...
Large scale deployments present unique planning challenges, system commissioning hurdles between IT and OT and demand careful system hand-off orchestration. In his session at @ThingsExpo, Jeff Smith, Senior Director and a founding member of Incenergy, will discuss some of the key tactics to ensure delivery success based on his experience of the last two years deploying Industrial IoT systems across four continents.
SYS-CON Events announced today that Venafi, the Immune System for the Internet™ and the leading provider of Next Generation Trust Protection, will exhibit at @DevOpsSummit at 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Venafi is the Immune System for the Internet™ that protects the foundation of all cybersecurity – cryptographic keys and digital certificates – so they can’t be misused by bad guys in attacks...
Identity is in everything and customers are looking to their providers to ensure the security of their identities, transactions and data. With the increased reliance on cloud-based services, service providers must build security and trust into their offerings, adding value to customers and improving the user experience. Making identity, security and privacy easy for customers provides a unique advantage over the competition.
Whether your IoT service is connecting cars, homes, appliances, wearable, cameras or other devices, one question hangs in the balance – how do you actually make money from this service? The ability to turn your IoT service into profit requires the ability to create a monetization strategy that is flexible, scalable and working for you in real-time. It must be a transparent, smoothly implemented strategy that all stakeholders – from customers to the board – will be able to understand and comprehe...
"There's a growing demand from users for things to be faster. When you think about all the transactions or interactions users will have with your product and everything that is between those transactions and interactions - what drives us at Catchpoint Systems is the idea to measure that and to analyze it," explained Leo Vasiliou, Director of Web Performance Engineering at Catchpoint Systems, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York Ci...
"Tintri was started in 2008 with the express purpose of building a storage appliance that is ideal for virtualized environments. We support a lot of different hypervisor platforms from VMware to OpenStack to Hyper-V," explained Dan Florea, Director of Product Management at Tintri, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.
"Avere Systems is a hybrid cloud solution provider. We have customers that want to use cloud storage and we have customers that want to take advantage of cloud compute," explained Rebecca Thompson, VP of Marketing at Avere Systems, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.