Welcome!

News Feed Item

Paladin Energy Ltd: Suspension of Production at Kayelekera Mine, Malawi

PERTH, WESTERN AUSTRALIA -- (Marketwired) -- 02/07/14 -- Paladin Energy Ltd (TSX:PDN)(ASX:PDN) ("Paladin" or the "Company") advises that its subsidiary company, Paladin (Africa) Limited (PAL), is suspending production at its Kayelekera Mine (KM or the Operation) in Malawi. The suspension will involve placing the Operation on care and maintenance until the price of uranium recovers. This decision will preserve the remaining ore body until a sustained price recovery occurs and Paladin determines that production may be resumed on a profitable basis.

The Government of Malawi (GoM), which has a 15% interest in PAL, has been notified of this decision and PAL will be working with the relevant GoM authorities on implementation of the suspension of operations.

Reasons for Decision

The decision to suspend production at KM was based on two factors, both beyond the control of PAL and the Company:


1.  The continuing depressed price for uranium oxide, which has been
    severely negatively impacted since March 2011 following the nuclear
    reactor damage caused by the Fukushima earthquake and tsunami; and
    
    

2.  The unsustainable cash demand to maintain the loss-making Operation at
    KM.

The Managing Director/CEO of Paladin, Mr John Borshoff, said that the decision to place KM on care and maintenance would be in the best long-term interest of all stakeholders, as the Operation would resume only when it was profitable to do so.

"The Kayelekera Mine has performed exceptionally well technically, with production levels recorded at or near nameplate capacity over the past 12 months and significant achievements made in PAL's cost reduction programme. That is a credit to all the staff at KM and something of which they can be very proud. Nevertheless, despite these considerable efforts, KM continues to operate at a loss due to the low prevailing uranium price. Paladin is unable to continue to provide the level of financial support that PAL has required in recent years, hence the decision at this time."

"By placing Kayelekera on care and maintenance now, we are preserving the remaining value of the ore body until it can be mined profitably to make a positive contribution to the Paladin Group. This is in the best interest of all PAL stakeholders, including the Government of Malawi," Mr Borshoff said.

Impact of Low Prices

PAL has maintained operations at KM since the Fukushima earthquake and tsunami of March 2011 at considerable financial cost to Paladin. During this period, the spot uranium price has more than halved from its pre-Fukushima level of US$72.63/lb to a current price of US$35.50/lb. While PAL has achieved successive cost reductions quarter by quarter, these efforts have not been sufficient to achieve cash break-even at KM. For example, during financial year 2012-13, PAL reduced KM's year-on-year direct cost of production (C1) by 24% to US$39.20/lb, while maintaining uranium production at optimal, near-nameplate levels. In the same period, the uranium spot price declined by 32% - from US$50.75/lb in June 2012 to US$34.50/lb in July 2013.

While PAL has successfully installed and commissioned one of two major cost-reduction initiatives at KM for FY 2013-14 - the Nano-filtration acid recovery plant; the second measure - aimed at significantly reducing KM's cost of power by connecting the Operation to Malawi's national power distribution grid - has not been achieved to date. During the 18-month negotiating period, uranium prices have continued to fall, making grid power - even if available at this time - ineffectual in achieving profitability at KM.

Since Fukushima, the negative impact on KM of the very low uranium spot price was partially offset initially by several higher-priced term sales contracts put in place before March 2011; however, KM delivered its last product under these contracts in September 2013. Subsequent uranium produced from KM is now fully exposed to the depressed uranium spot market. The very low continuing uranium spot price, together with the Operation's cash cost of production, which remains above the spot price, makes continued operation at KM unsustainable in both current market conditions and in conditions projected in the medium term.

Production Rundown

While mining operations at KM are being suspended, processing of ore will continue during a transitional rundown phase until reagents and consumables on site have been depleted and the production circuit has been emptied and cleaned. At this time, the plant will be sterilised, shut down and placed on care and maintenance. This rundown/sterilisation phase is expected to be completed by April/May of this year.

PAL is committed to maintaining the mine and infrastructure at KM in good working order to facilitate a rapid resumption of production when market conditions dictate that it is possible to profitably do so. For this reason, PAL will retain some 194 Malawi national employees and 27 expatriate staff to maintain the site, including staff to strengthen physical security measures at the Operation.

Generous Redundancy Package

This decision will result in a significant level of redundancy at KM and the process has commenced to retrench employees not required during the period of care and maintenance. In appreciation of their endeavours to drive down costs and improve efficiency, retrenched national employees will receive generous redundancy packages that exceed Malawi's minimum legal requirements. Based on length of service, allowances and entitlements and an ex-gratia payment, the average payout for national employees will be the equivalent of 10.7 months' salary. It is the Company's hope that this gesture will assist employees in their transition from employment at KM. In addition, national employees will be offered financial planning advice and training in business skills.

Financial and Guidance Impact on Paladin

Supporting KM has been a substantial drain on Paladin's cash resources during the past three years. Based on a uranium price of U$35/lb, Paladin would have had to inject a further US$20M-US$25M in cash for each of the next two calendar years to maintain the Operation.

Placing KM on care and maintenance will improve Paladin's forecast cash flow position by US$7-10M in calendar year 2014 and US$20-25M in calendar year 2015. Paladin anticipates that the ongoing cost of maintaining KM on care and maintenance of approximately US$12M per annum will be funded from proceeds to be received from the sale of uranium oxide on hand and produced during the rundown phase. The previously announced repayment of PAL's Project Financing Facility has saved an additional US$30M cash requirement in 2014.

Production and cost guidance at Paladin's Langer Heinrich Mine in Namibia, which has a significantly lower cost profile than KM, will not be affected by this move.

Following the decision to place KM on care and maintenance, Paladin is revising its FY14 production guidance from 8.3-8.7Mlb U3O8 to 7.8-8.0Mlb U3O8.

Commitment to Malawi

Paladin remains committed to its vision of the long-term viability and strength of the nuclear sector and to its presence in Malawi. Paladin intends to maintain its presence in Malawi and to continue exploration activities in the country, with the objective of identifying and delineating additional uranium resources in order to assure the long-term future of KM.

The Company will also sustain its commitment to PAL's Corporate Social Responsibility programme in Malawi, albeit at a reduced expenditure level in line with KM's non-producing status.

PAL will also maintain its strict environmental management of the Operation.

Impact on Supply Side

Paladin has consistently stated that current pricing levels for uranium oxide are unsustainable. KM is one of numerous uranium mines currently operating at or below break-even. PAL's decision to place KM on care and maintenance is the latest in a sequence of closures, production suspensions and deferrals of major planned greenfield and brownfield expansions in the uranium sector, including Paladin's decision in 2012 to suspend evaluation of a major Stage 4 expansion of the Langer Heinrich Mine in Namibia.

Mr Borshoff stated: "We will not contemplate any such an expansion until uranium prices reach at least US$75/lb and are sustainable at or above this level." He added that, consistent with that decision, Paladin would invest in future production only when it made economic sense to do so - and this included recommencement of production in Malawi, as well as expansion in Namibia.

"This unfortunate but necessary curtailment of world uranium production will have impacts well into the future. Even when uranium prices improve, it is inevitable that the lead-time to return mothballed operations to production and re-evaluate the development timeframe for deferred brownfield and greenfield projects will exacerbate the uranium supply-demand imbalance that will become increasingly evident in the course of this decade."

Positioning for the Future

During its dynamic period of growth and expansion, Paladin has demonstrated that it could simultaneously develop and commission two state-of-the-art uranium projects utilising technological innovations. During its consolidation phase, Paladin demonstrated that its operations units could perform consistently near or better than nameplate capacity in an African environment, while attaining commendable safety standards. Paladin retains its installed capacity of 8.5Mlb pa, including the 3.3Mlb pa at KM that will be available for the future.

"Electing to take Kayelekera "off-line" at this time is a prudent and sensible step to preserve shareholder value and position Paladin to take best advantage of the opportunities that will present to the Company when the uranium sector enters its next exciting phase of growth and profitability," Mr Borshoff said.

Appendix 1: ASX Determination Required under Chapter 11 of the Listing Rules

Paladin does not intend to seek the approval of shareholders to the suspension of operations at KM unless ASX requires it under Listing Rule 11.1.2 or 11.2.

Paladin intends to apply to ASX for a determination as to whether shareholder approval is required under Chapter 11 of the Listing Rules. After ASX has made its determination in respect of Paladin's application, Paladin will update the market accordingly. In the event that ASX determines that the approval of shareholders is required under Listing Rules 11.1.2 or 11.2, Paladin will provide further details regarding the process and timetable for seeking such approval.

Details of the Assets subject to the Suspension

As indicated above, the suspension will involve placing the Kayelekera Mine (KM) operation on care and maintenance until a recovery in the price of uranium enables production to resume on a profitable basis. Production at Paladin's Langer Heinrich Mine in Namibia will not be affected.

KM is Paladin's producing uranium mine in Malawi, southern Africa. The Mining Licence (ML 152) was granted in April 2007 for a period of 15 years following the signing of a Development Agreement (DA) with the Government of Malawi. Construction commenced in June 2007 and was completed in April 2009.

KM is wholly-owned by Paladin (Africa) Limited (PAL), a subsidiary of Paladin incorporated in Malawi. Paladin's wholly owned subsidiary, Paladin Energy Minerals NL, holds an 85% interest in PAL. The remaining 15% interest is held by the GoM, pursuant to the terms of the DA.

The mining method used at KM is conventional open pit and the Operation's resin-in-pulp processing plant has operated at or near its design capacity of 3.3Mlb pa. Details of the Kayelekera project's Mineral Resources and Ore Reserves are detailed below.


                                                                            
----------------------------------------------------------------------------
Mineral Resource at 300ppm U3O8 cut-off                                     
----------------------------------------------------------------------------
----------------------------------------------------------------------------
                            Mt     Grade ppm U3O8      t U3O8       Mlb U3O8
----------------------------------------------------------------------------
Measured                                                                    
 Resources                0.87              1,071         931           2.05
----------------------------------------------------------------------------
Indicated                                                                   
 Resources               13.43                722       9,694          21.37
----------------------------------------------------------------------------
Total Measured                                                              
 and Indicated           14.30                743      10,625          23.42
----------------------------------------------------------------------------
Stockpiles                1.54                945       1,454           3.21
----------------------------------------------------------------------------
Inferred                                                                    
 Resources                 5.4                623       3,336            7.4
----------------------------------------------------------------------------
Note: Figures may not add due to rounding and are quoted inclusive of any   
Ore Reserves and are depleted for mining to end of June 2013.               

As noted in Paladin's 2013 Annual Report, the Mineral Resource is unchanged from that previously reported except for depletion due to mining activities to 30 June 2013. The Mineral Resource estimate is based on Multi Indicator Kriging techniques with a specific adjustment based on parameters derived from the mining process.


                                                                            
----------------------------------------------------------------------------
Ore Reserve at 400ppm U3O8 cut-off                                          
----------------------------------------------------------------------------
----------------------------------------------------------------------------
                              Mt   Grade ppm U3O8      t U3O8       Mlb U3O8
----------------------------------------------------------------------------
Proved Reserve              0.49            1,230         605           1.33
----------------------------------------------------------------------------
Probable Reserve            5.98              907       5,423          11.96
----------------------------------------------------------------------------
Stockpiles                  1.54              945       1,454           3.21
----------------------------------------------------------------------------
Total Ore Reserve           8.01              934       7,483          16.50
----------------------------------------------------------------------------
Note: Figures may not add due to rounding and are depleted for mining to end
of June 2013.                                                               

As noted in the 2013 Annual Report, the underlying Ore Reserve is unchanged from the one announced in 2008 and has only been depleted for mining until 30 June 2013. With the exception of the prevailing uranium price the parameters and assumption used to estimate the reported Minerals and Ore Reserves have not materially changed since the estimations were undertaken.

This information in the tables above relating to KM was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with the JORC Code 2012 on the basis that the information that the estimates are derived from has not materially changed since it was last reported.

Financial Impact

The financial impact on Paladin's balance sheet will be immaterial, given that the value of the KM asset has already been written down to zero. The suspension of operations will result in an impairment of inventory, stores and consumables of approximately US$32M.

As noted earlier, Paladin has revised its production guidance for FY14 from 8.3-8.7Mlb U3O8 to 7.8-8.0Mlb U3O8.

There will be no effect on Paladin's capital structure as a result of the suspension of mining activities at KM.

Indicative timetable

As noted above, PAL is currently in the process of suspending operations at KM, but processing of ore will continue until early in the June 2014 quarter when reagents and consumables on site will have been depleted. All remaining in-circuit inventory will then be recovered and the plant cleaned in preparation for care and maintenance which will commence by the end of the June quarter.

Declaration

The information in this Announcement relating to exploration and mineral resources and ore reserves is, except where stated, based on information compiled by David Princep B.Sc and Andrew Hutson B.E. who are both Fellows of the AusIMM. Messrs Princep and Hutson have sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity that they are undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves", and as a Qualified Person as defined in Canadian National Instrument 43-101. Messrs Princep and Hutson are full-time employees of Paladin Energy Ltd and consent to the inclusion of this information in the form and context in which it appears.

ACN 061 681 098

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Early adopters of IoT viewed it mainly as a different term for machine-to-machine connectivity or M2M. This is understandable since a prerequisite for any IoT solution is the ability to collect and aggregate device data, which is most often presented in a dashboard. The problem is that viewing data in a dashboard requires a human to interpret the results and take manual action, which doesn’t scale to the needs of IoT.
SYS-CON Events announced today the Kubernetes and Google Container Engine Workshop, being held November 3, 2016, in conjunction with @DevOpsSummit at 19th Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA. This workshop led by Sebastian Scheele introduces participants to Kubernetes and Google Container Engine (GKE). Through a combination of instructor-led presentations, demonstrations, and hands-on labs, students learn the key concepts and practices for deploying and maintainin...
Cloud analytics is dramatically altering business intelligence. Some businesses will capitalize on these promising new technologies and gain key insights that’ll help them gain competitive advantage. And others won’t. Whether you’re a business leader, an IT manager, or an analyst, we want to help you and the people you need to influence with a free copy of “Cloud Analytics for Dummies,” the essential guide to this explosive new space for business intelligence.
So, you bought into the current machine learning craze and went on to collect millions/billions of records from this promising new data source. Now, what do you do with them? Too often, the abundance of data quickly turns into an abundance of problems. How do you extract that "magic essence" from your data without falling into the common pitfalls? In her session at @ThingsExpo, Natalia Ponomareva, Software Engineer at Google, provided tips on how to be successful in large scale machine learning...
What does it look like when you have access to cloud infrastructure and platform under the same roof? Let’s talk about the different layers of Technology as a Service: who cares, what runs where, and how does it all fit together. In his session at 18th Cloud Expo, Phil Jackson, Lead Technology Evangelist at SoftLayer, an IBM company, spoke about the picture being painted by IBM Cloud and how the tools being crafted can help fill the gaps in your IT infrastructure.
"delaPlex is a software development company. We do team-based outsourcing development," explained Mark Rivers, COO and Co-founder of delaPlex Software, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.
"C2M is our digital transformation and IoT platform. We've had C2M on the market for almost three years now and it has a comprehensive set of functionalities that it brings to the market," explained Mahesh Ramu, Vice President, IoT Strategy and Operations at Plasma, in this SYS-CON.tv interview at @ThingsExpo, held June 7-9, 2016, at the Javits Center in New York City, NY.
Traditional IT, great for stable systems of record, is struggling to cope with newer, agile systems of engagement requirements coming straight from the business. In his session at 18th Cloud Expo, William Morrish, General Manager of Product Sales at Interoute, outlined ways of exploiting new architectures to enable both systems and building them to support your existing platforms, with an eye for the future. Technologies such as Docker and the hyper-convergence of computing, networking and sto...
Whether your IoT service is connecting cars, homes, appliances, wearable, cameras or other devices, one question hangs in the balance – how do you actually make money from this service? The ability to turn your IoT service into profit requires the ability to create a monetization strategy that is flexible, scalable and working for you in real-time. It must be a transparent, smoothly implemented strategy that all stakeholders – from customers to the board – will be able to understand and comprehe...
SYS-CON Events announced today that LeaseWeb USA, a cloud Infrastructure-as-a-Service (IaaS) provider, will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. LeaseWeb is one of the world's largest hosting brands. The company helps customers define, develop and deploy IT infrastructure tailored to their exact business needs, by combining various kinds cloud solutions.
Using new techniques of information modeling, indexing, and processing, new cloud-based systems can support cloud-based workloads previously not possible for high-throughput insurance, banking, and case-based applications. In his session at 18th Cloud Expo, John Newton, CTO, Founder and Chairman of Alfresco, described how to scale cloud-based content management repositories to store, manage, and retrieve billions of documents and related information with fast and linear scalability. He addres...
The cloud market growth today is largely in public clouds. While there is a lot of spend in IT departments in virtualization, these aren’t yet translating into a true “cloud” experience within the enterprise. What is stopping the growth of the “private cloud” market? In his general session at 18th Cloud Expo, Nara Rajagopalan, CEO of Accelerite, explored the challenges in deploying, managing, and getting adoption for a private cloud within an enterprise. What are the key differences between wh...
Adding public cloud resources to an existing application can be a daunting process. The tools that you currently use to manage the software and hardware outside the cloud aren’t always the best tools to efficiently grow into the cloud. All of the major configuration management tools have cloud orchestration plugins that can be leveraged, but there are also cloud-native tools that can dramatically improve the efficiency of managing your application lifecycle. In his session at 18th Cloud Expo, ...
It’s 2016: buildings are smart, connected and the IoT is fundamentally altering how control and operating systems work and speak to each other. Platforms across the enterprise are networked via inexpensive sensors to collect massive amounts of data for analytics, information management, and insights that can be used to continuously improve operations. In his session at @ThingsExpo, Brian Chemel, Co-Founder and CTO of Digital Lumens, will explore: The benefits sensor-networked systems bring to ...
When building large, cloud-based applications that operate at a high scale, it’s important to maintain a high availability and resilience to failures. In order to do that, you must be tolerant of failures, even in light of failures in other areas of your application. “Fly two mistakes high” is an old adage in the radio control airplane hobby. It means, fly high enough so that if you make a mistake, you can continue flying with room to still make mistakes. In his session at 18th Cloud Expo, Lee...