TORONTO, ONTARIO -- (Marketwired) -- 02/11/14 -- Rubicon Minerals Corporation (TSX: RMX)(NYSE MKT: RBY) ("Rubicon" or the "Company") provides an update on the development of the Phoenix Gold Project ("Project"). Rubicon has recently completed sinking the shaft, initial development of the tailings facility, construction of the mill building, earthworks, and 200-person camp. Underground development is underway. The Company has also entered into a US$75 million gold stream agreement to assist in financing the Project construction.

The Phoenix Gold Project Development and Construction Update

Shaft Sinking Completed

Rubicon completed shaft sinking in mid-December 2013. The total shaft depth is 730 metres ("m") from the surface. The installation of a loading pocket on the 337-metre level from surface is completed and the surface skip dump is nearing completion. This allows the Company to expedite underground lateral development on the 122-metre, 244-metre, and 305-metre levels. Two 10-tonne skips and two cages for personnel transport have been installed. The Company will be installing a 10-tonne loading pocket at the 685-metre depth and is planning lateral development at the 610-metre level.

Underground Project Development

Lateral development has been initiated on the 244-metre level for diamond drilling. Vertical development on the 122-metre and 305-metre levels has commenced and this will provide access for the ventilation system expansion.

Tailings Management Facility ("TMF") and Remaining Earthworks

The Company has completed the majority of the TMF development necessary for the first 2 years of operation.

Mill Construction

The main components of the semi-autogenous ("SAG") and ball mill were delivered and received on site in 2013. The Company has poured most of the required outdoor concrete slabs. The mill building is completed and the internal cranes are fully operational. The mill thickener tank foundations are completed. Management has deferred some activities in the mill construction to preserve the Company's strong balance sheet.

Surface Infrastructure Completed

The Company has commissioned a 2,500 horsepower hoist and extended headframe. In addition, Rubicon has completed the construction of the required roads, a 200-person camp, a new power line and substation, the mill building, and the SAG and ball mill foundations.

Timeline to Projected Production

Rubicon believes that the main elements required to complete the Phoenix Gold Project are the completion of the mill construction, as well as the underground lateral and vertical development. The completion of the mill construction is the critical path. Management has deferred mill construction to preserve the Company's balance sheet until it has secured the remaining financing to complete the Project. Rubicon has entered into a US$75 million gold stream agreement with Royal Gold and the Company estimates it will need to raise an additional US$100 million to complete the Project to potential production. Rubicon is currently evaluating financing alternatives with a strong focus on minimizing the Company's cost of capital. We estimate projected gold production in approximately 12-14 months following the completion of additional financing.

"We are extremely pleased with the key construction milestones that we have achieved to-date," stated Michael A. Lalonde, President and Chief Executive Officer of Rubicon. "The Company has completed a substantial amount of the required construction, further de-risking the Project."

Conference Call Details

Rubicon's senior management team will host a conference call today, Tuesday, February 11, 2014 at 10:00 am ET (7:00am PT) to discuss the gold streaming deal and Project update.

Participants in Canada and the United States may join the conference call by dialing toll free +1 (800) 319-4610 or +1 (604) 638-5340 for calls outside Canada and the United States or via webcast on the Company's website at www.rubiconminerals.com.

A recorded playback of the conference call can be accessed after the event by dialing +1 (800) 319-6413 or +1 (604) 638-9010 for calls outside Canada and the United States. The pass code for the conference call playback is 7856#. The archived audio webcast will also be available on the Company's website at www.rubiconminerals.com.

About Rubicon Minerals Corporation

Rubicon Minerals Corporation is an advanced stage gold development company. The Company is focused on responsible and environmentally sustainable development of its Phoenix Gold Project in Red Lake, Ontario. Gold production is projected to commence 12-14 months following the completion of the remaining financing. The Phoenix Gold Project is fully permitted for initial production at 1,250 tonnes per day. In addition, Rubicon controls over 100 square miles of prime exploration ground in the prolific Red Lake gold district which hosts Goldcorp's high-grade, world class Red Lake Mine. Rubicon's shares are listed on the NYSE.MKT (RBY) and the TSX (RMX) Exchanges.


Mike Lalonde, President and Chief Executive Officer

Qualified Persons

The content of this news release has been read and approved by Daniel Labine, P.Eng., Vice President of Operations and Mark Ross, B.Sc., P.Geo., Chief Mine Geologist, for Rubicon. Both are Qualified Persons as defined by NI 43-101.

Forward Looking Statements

This news release contains statements that constitute "forward-looking statements" within the meaning of Section 21E of the United States Securities Exchange Act of 1934 and "forward looking information" within the meaning of applicable Canadian provincial securities legislation (collectively, "forward-looking statements"). Forward-looking statements often, but not always, are identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect", "targeting", "look forward" and "intend" and statements that an event or result "may", "will", "would", "should", "could", or "might" occur or be achieved and other similar expressions.

Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and represent management's best judgment based on facts and assumptions that management considers reasonable. The material assumptions upon which such forward-looking statements are based include, among others; that the aspects of the transition will progress on a satisfactory basis; that the demand for gold and base metal deposits will develop as anticipated; that the price of gold will remain at levels that will render the Phoenix Gold Project economic; that operating and capital plans will not be disrupted by issues such as mechanical failure, unavailability of parts and supplies, labour disturbances, interruption in transportation or utilities, or adverse weather conditions; that Rubicon will meet its estimated timeline for the development of the Phoenix Gold Project; that Rubicon will continue to have the ability to attract and retain skilled staff; that the mineral resource estimate as disclosed in the New Preliminary Economic Assessment dated June 25, 2013 ("New PEA") will be realized; and that there are no material unanticipated variations in the cost of energy or supplies, or in the pre-production capital and operating cost estimate as disclosed in the New PEA. Rubicon makes no representation that reasonable business people in possession of the same information would reach the same conclusions.

Capital expenditures and time required to develop new mines are considerable and changes in cost or construction schedules can significantly increase both the time and capital required to build and complete a development project. Additional capital costs may be to be incurred in respect of the Phoenix Gold Project.

The New PEA is preliminary in nature as it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the New PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources referred to in the New PEA are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource category.

Forward-looking statements in this news release include, but are not limited to statements regarding projected production, projected completion of the perimeter ditch and estimates of additional financing.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Rubicon to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others: future prices of gold and other metals; possible variations in mineralization, grade or recovery rates; actual results of current exploration activities; actual results of reclamation activities; conclusions of future economic evaluations; changes in project parameters as plans continue to be refined; failure of equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays and other risks related to joint venture operations; timing and receipt of regulatory approvals of operations; the ability of Rubicon and other relevant parties to satisfy regulatory requirements; the availability of financing for proposed transactions and programs on reasonable terms; the ability of third-party service providers to deliver services on reasonable terms and in a timely manner; and delays in the completion of development or construction activities. Other factors that could cause the actual results to differ include market prices, results of exploration, availability of capital and financing on acceptable terms, inability to obtain required regulatory approvals, unanticipated difficulties or costs in any rehabilitation which may be necessary, market conditions and general business, economic, competitive, political and social conditions.

It is important to note that the information provided in this news release is preliminary in nature. There is no certainty that a potential mine will be realized. A mine production decision that is made without a bankable feasibility study carries additional potential risks which include, but are not limited to, the inclusion of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mine design and mining schedules, metallurgical flow sheets and process plant designs may require additional detailed work to ensure satisfactory operational conditions.

Forward-looking statements contained herein are made as of the date of this news release and Rubicon disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
For basic one-to-one voice or video calling solutions, WebRTC has proven to be a very powerful technology. Although WebRTC’s core functionality is to provide secure, real-time p2p media streaming, leveraging native platform features and server-side components brings up new communication capabilities for web and native mobile applications, allowing for advanced multi-user use cases such as video broadcasting, conferencing, and media recording.
Without lifecycle traceability and visibility across the tool chain, stakeholders from Planning-to-Ops have limited insight and answers to who, what, when, why and how across the DevOps lifecycle. This impacts the ability to deliver high quality software at the needed velocity to drive positive business outcomes. In his general session at @DevOpsSummit at 19th Cloud Expo, Eric Robertson, General Manager at CollabNet, will discuss how customers are able to achieve a level of transparency that e...
Fifty billion connected devices and still no winning protocols standards. HTTP, WebSockets, MQTT, and CoAP seem to be leading in the IoT protocol race at the moment but many more protocols are getting introduced on a regular basis. Each protocol has its pros and cons depending on the nature of the communications. Does there really need to be only one protocol to rule them all? Of course not. In his session at @ThingsExpo, Chris Matthieu, co-founder and CTO of Octoblu, walk you through how Oct...
DevOps is speeding towards the IT world like a freight train and the hype around it is deafening. There is no reason to be afraid of this change as it is the natural reaction to the agile movement that revolutionized development just a few years ago. By definition, DevOps is the natural alignment of IT performance to business profitability. The relevance of this has yet to be quantified but it has been suggested that the route to the CEO’s chair will come from the IT leaders that successfully ma...
Major trends and emerging technologies – from virtual reality and IoT, to Big Data and algorithms – are helping organizations innovate in the digital era. However, to create real business value, IT must think beyond the ‘what’ of digital transformation to the ‘how’ to harness emerging trends, innovation and disruption. Architecture is the key that underpins and ties all these efforts together. In the digital age, it’s important to invest in architecture, extend the enterprise footprint to the cl...
Almost everyone sees the potential of Internet of Things but how can businesses truly unlock that potential. The key will be in the ability to discover business insight in the midst of an ocean of Big Data generated from billions of embedded devices via Systems of Discover. Businesses will also need to ensure that they can sustain that insight by leveraging the cloud for global reach, scale and elasticity.
@DevOpsSummit has been named the ‘Top DevOps Influencer' by iTrend. iTrend processes millions of conversations, tweets, interactions, news articles, press releases, blog posts - and extract meaning form them and analyzes mobile and desktop software platforms used to communicate, various metadata (such as geo location), and automation tools. In overall placement, @DevOpsSummit ranked as the number one ‘DevOps Influencer' followed by @CloudExpo at third, and @MicroservicesE at 24th.
A critical component of any IoT project is what to do with all the data being generated. This data needs to be captured, processed, structured, and stored in a way to facilitate different kinds of queries. Traditional data warehouse and analytical systems are mature technologies that can be used to handle certain kinds of queries, but they are not always well suited to many problems, particularly when there is a need for real-time insights.
One of biggest questions about Big Data is “How do we harness all that information for business use quickly and effectively?” Geographic Information Systems (GIS) or spatial technology is about more than making maps, but adding critical context and meaning to data of all types, coming from all different channels – even sensors. In his session at @ThingsExpo, William (Bill) Meehan, director of utility solutions for Esri, will take a closer look at the current state of spatial technology and ar...
Without lifecycle traceability and visibility across the tool chain, stakeholders from Planning-to-Ops have limited insight and answers to who, what, when, why and how across the DevOps lifecycle. This impacts the ability to deliver high quality software at the needed velocity to drive positive business outcomes. In his session at @DevOpsSummit 19th Cloud Expo, Eric Robertson, General Manager at CollabNet, will show how customers are able to achieve a level of transparency that enables everyon...
Explosive growth in connected devices. Enormous amounts of data for collection and analysis. Critical use of data for split-second decision making and actionable information. All three are factors in making the Internet of Things a reality. Yet, any one factor would have an IT organization pondering its infrastructure strategy. How should your organization enhance its IT framework to enable an Internet of Things implementation? In his session at @ThingsExpo, James Kirkland, Red Hat's Chief Arch...
SYS-CON Events announced today that Interface Masters Technologies, a leader in Network Visibility and Uptime Solutions, will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Interface Masters Technologies is a leading vendor in the network monitoring and high speed networking markets. Based in the heart of Silicon Valley, Interface Masters' expertise lies in Gigabit, 10 Gigabit and 40 Gigabit Eth...
The IoT industry is now at a crossroads, between the fast-paced innovation of technologies and the pending mass adoption by global enterprises. The complexity of combining rapidly evolving technologies and the need to establish practices for market acceleration pose a strong challenge to global enterprises as well as IoT vendors. In his session at @ThingsExpo, Clark Smith, senior product manager for Numerex, will discuss how Numerex, as an experienced, established IoT provider, has embraced a ...
As software becomes more and more complex, we, as software developers, have been splitting up our code into smaller and smaller components. This is also true for the environment in which we run our code: going from bare metal, to VMs to the modern-day Cloud Native world of containers, schedulers and microservices. While we have figured out how to run containerized applications in the cloud using schedulers, we've yet to come up with a good solution to bridge the gap between getting your conta...
Everyone knows that truly innovative companies learn as they go along, pushing boundaries in response to market changes and demands. What's more of a mystery is how to balance innovation on a fresh platform built from scratch with the legacy tech stack, product suite and customers that continue to serve as the business' foundation. In his General Session at 19th Cloud Expo, Michael Chambliss, Head of Engineering at ReadyTalk, will discuss why and how ReadyTalk diverted from healthy revenue an...