Rubicon Achieves Construction and Financing Milestones Towards the Completion of the Phoenix Gold Project

TORONTO, ONTARIO -- (Marketwired) -- 02/11/14 -- Rubicon Minerals Corporation (TSX: RMX)(NYSE MKT: RBY) ("Rubicon" or the "Company") provides an update on the development of the Phoenix Gold Project ("Project"). Rubicon has recently completed sinking the shaft, initial development of the tailings facility, construction of the mill building, earthworks, and 200-person camp. Underground development is underway. The Company has also entered into a US$75 million gold stream agreement to assist in financing the Project construction.

The Phoenix Gold Project Development and Construction Update

Shaft Sinking Completed

Rubicon completed shaft sinking in mid-December 2013. The total shaft depth is 730 metres ("m") from the surface. The installation of a loading pocket on the 337-metre level from surface is completed and the surface skip dump is nearing completion. This allows the Company to expedite underground lateral development on the 122-metre, 244-metre, and 305-metre levels. Two 10-tonne skips and two cages for personnel transport have been installed. The Company will be installing a 10-tonne loading pocket at the 685-metre depth and is planning lateral development at the 610-metre level.

Underground Project Development

Lateral development has been initiated on the 244-metre level for diamond drilling. Vertical development on the 122-metre and 305-metre levels has commenced and this will provide access for the ventilation system expansion.

Tailings Management Facility ("TMF") and Remaining Earthworks

The Company has completed the majority of the TMF development necessary for the first 2 years of operation.

Mill Construction

The main components of the semi-autogenous ("SAG") and ball mill were delivered and received on site in 2013. The Company has poured most of the required outdoor concrete slabs. The mill building is completed and the internal cranes are fully operational. The mill thickener tank foundations are completed. Management has deferred some activities in the mill construction to preserve the Company's strong balance sheet.

Surface Infrastructure Completed

The Company has commissioned a 2,500 horsepower hoist and extended headframe. In addition, Rubicon has completed the construction of the required roads, a 200-person camp, a new power line and substation, the mill building, and the SAG and ball mill foundations.

Timeline to Projected Production

Rubicon believes that the main elements required to complete the Phoenix Gold Project are the completion of the mill construction, as well as the underground lateral and vertical development. The completion of the mill construction is the critical path. Management has deferred mill construction to preserve the Company's balance sheet until it has secured the remaining financing to complete the Project. Rubicon has entered into a US$75 million gold stream agreement with Royal Gold and the Company estimates it will need to raise an additional US$100 million to complete the Project to potential production. Rubicon is currently evaluating financing alternatives with a strong focus on minimizing the Company's cost of capital. We estimate projected gold production in approximately 12-14 months following the completion of additional financing.

"We are extremely pleased with the key construction milestones that we have achieved to-date," stated Michael A. Lalonde, President and Chief Executive Officer of Rubicon. "The Company has completed a substantial amount of the required construction, further de-risking the Project."

Conference Call Details

Rubicon's senior management team will host a conference call today, Tuesday, February 11, 2014 at 10:00 am ET (7:00am PT) to discuss the gold streaming deal and Project update.

Participants in Canada and the United States may join the conference call by dialing toll free +1 (800) 319-4610 or +1 (604) 638-5340 for calls outside Canada and the United States or via webcast on the Company's website at www.rubiconminerals.com.

A recorded playback of the conference call can be accessed after the event by dialing +1 (800) 319-6413 or +1 (604) 638-9010 for calls outside Canada and the United States. The pass code for the conference call playback is 7856#. The archived audio webcast will also be available on the Company's website at www.rubiconminerals.com.

About Rubicon Minerals Corporation

Rubicon Minerals Corporation is an advanced stage gold development company. The Company is focused on responsible and environmentally sustainable development of its Phoenix Gold Project in Red Lake, Ontario. Gold production is projected to commence 12-14 months following the completion of the remaining financing. The Phoenix Gold Project is fully permitted for initial production at 1,250 tonnes per day. In addition, Rubicon controls over 100 square miles of prime exploration ground in the prolific Red Lake gold district which hosts Goldcorp's high-grade, world class Red Lake Mine. Rubicon's shares are listed on the NYSE.MKT (RBY) and the TSX (RMX) Exchanges.

RUBICON MINERALS CORPORATION

Mike Lalonde, President and Chief Executive Officer

Qualified Persons

The content of this news release has been read and approved by Daniel Labine, P.Eng., Vice President of Operations and Mark Ross, B.Sc., P.Geo., Chief Mine Geologist, for Rubicon. Both are Qualified Persons as defined by NI 43-101.

Forward Looking Statements

This news release contains statements that constitute "forward-looking statements" within the meaning of Section 21E of the United States Securities Exchange Act of 1934 and "forward looking information" within the meaning of applicable Canadian provincial securities legislation (collectively, "forward-looking statements"). Forward-looking statements often, but not always, are identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect", "targeting", "look forward" and "intend" and statements that an event or result "may", "will", "would", "should", "could", or "might" occur or be achieved and other similar expressions.

Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and represent management's best judgment based on facts and assumptions that management considers reasonable. The material assumptions upon which such forward-looking statements are based include, among others; that the aspects of the transition will progress on a satisfactory basis; that the demand for gold and base metal deposits will develop as anticipated; that the price of gold will remain at levels that will render the Phoenix Gold Project economic; that operating and capital plans will not be disrupted by issues such as mechanical failure, unavailability of parts and supplies, labour disturbances, interruption in transportation or utilities, or adverse weather conditions; that Rubicon will meet its estimated timeline for the development of the Phoenix Gold Project; that Rubicon will continue to have the ability to attract and retain skilled staff; that the mineral resource estimate as disclosed in the New Preliminary Economic Assessment dated June 25, 2013 ("New PEA") will be realized; and that there are no material unanticipated variations in the cost of energy or supplies, or in the pre-production capital and operating cost estimate as disclosed in the New PEA. Rubicon makes no representation that reasonable business people in possession of the same information would reach the same conclusions.

Capital expenditures and time required to develop new mines are considerable and changes in cost or construction schedules can significantly increase both the time and capital required to build and complete a development project. Additional capital costs may be to be incurred in respect of the Phoenix Gold Project.

The New PEA is preliminary in nature as it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the New PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources referred to in the New PEA are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource category.

Forward-looking statements in this news release include, but are not limited to statements regarding projected production, projected completion of the perimeter ditch and estimates of additional financing.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Rubicon to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others: future prices of gold and other metals; possible variations in mineralization, grade or recovery rates; actual results of current exploration activities; actual results of reclamation activities; conclusions of future economic evaluations; changes in project parameters as plans continue to be refined; failure of equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays and other risks related to joint venture operations; timing and receipt of regulatory approvals of operations; the ability of Rubicon and other relevant parties to satisfy regulatory requirements; the availability of financing for proposed transactions and programs on reasonable terms; the ability of third-party service providers to deliver services on reasonable terms and in a timely manner; and delays in the completion of development or construction activities. Other factors that could cause the actual results to differ include market prices, results of exploration, availability of capital and financing on acceptable terms, inability to obtain required regulatory approvals, unanticipated difficulties or costs in any rehabilitation which may be necessary, market conditions and general business, economic, competitive, political and social conditions.

It is important to note that the information provided in this news release is preliminary in nature. There is no certainty that a potential mine will be realized. A mine production decision that is made without a bankable feasibility study carries additional potential risks which include, but are not limited to, the inclusion of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mine design and mining schedules, metallurgical flow sheets and process plant designs may require additional detailed work to ensure satisfactory operational conditions.

Forward-looking statements contained herein are made as of the date of this news release and Rubicon disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
The principles behind DevOps are not new - for decades people have been automating system administration and decreasing the time to deploy apps and perform other management tasks. However, only recently did we see the tools and the will necessary to share the benefits and power of automation with a wider circle of people. In his session at DevOps Summit, Bernard Sanders, Chief Technology Officer at CloudBolt Software, explored the latest tools including Puppet, Chef, Docker, and CMPs needed to...
SYS-CON Events announced today that AppNeta, the leader in performance insight for business-critical web applications, will exhibit and present at SYS-CON's @DevOpsSummit at Cloud Expo New York, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. AppNeta is the only application performance monitoring (APM) company to provide solutions for all applications – applications you develop internally, business-critical SaaS applications you use and the networks that deli...
Fortunately, meaningful and tangible business cases for IoT are plentiful in a broad array of industries and vertical markets. These range from simple warranty cost reduction for capital intensive assets, to minimizing downtime for vital business tools, to creating feedback loops improving product design, to improving and enhancing enterprise customer experiences. All of these business cases, which will be briefly explored in this session, hinge on cost effectively extracting relevant data from ...
Advances in technology and ubiquitous connectivity have made the utilization of a dispersed workforce more common. Whether that remote team is located across the street or country, management styles/ approaches will have to be adjusted to accommodate this new dynamic. In his session at 17th Cloud Expo, Sagi Brody, Chief Technology Officer at Webair Internet Development Inc., focused on the challenges of managing remote teams, providing real-world examples that demonstrate what works and what do...
It's easy to assume that your app will run on a fast and reliable network. The reality for your app's users, though, is often a slow, unreliable network with spotty coverage. What happens when the network doesn't work, or when the device is in airplane mode? You get unhappy, frustrated users. An offline-first app is an app that works, without error, when there is no network connection.
Father business cycles and digital consumers are forcing enterprises to respond faster to customer needs and competitive demands. Successful integration of DevOps and Agile development will be key for business success in today’s digital economy. In his session at DevOps Summit, Pradeep Prabhu, Co-Founder & CEO of Cloudmunch, covered the critical practices that enterprises should consider to seamlessly integrate Agile and DevOps processes, barriers to implementing this in the enterprise, and pr...
In most cases, it is convenient to have some human interaction with a web (micro-)service, no matter how small it is. A traditional approach would be to create an HTTP interface, where user requests will be dispatched and HTML/CSS pages must be served. This approach is indeed very traditional for a web site, but not really convenient for a web service, which is not intended to be good looking, 24x7 up and running and UX-optimized. Instead, talking to a web service in a chat-bot mode would be muc...
More and more companies are looking to microservices as an architectural pattern for breaking apart applications into more manageable pieces so that agile teams can deliver new features quicker and more effectively. What this pattern has done more than anything to date is spark organizational transformations, setting the foundation for future application development. In practice, however, there are a number of considerations to make that go beyond simply “build, ship, and run,” which changes ho...
SYS-CON Events announced today that Interoute, owner-operator of one of Europe's largest networks and a global cloud services platform, has been named “Bronze Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2015 at the Javits Center in New York, New York. Interoute is the owner-operator of one of Europe's largest networks and a global cloud services platform which encompasses 12 data centers, 14 virtual data centers and 31 colocation centers, with connections to 195 ad...
Most people haven’t heard the word, “gamification,” even though they probably, and perhaps unwittingly, participate in it every day. Gamification is “the process of adding games or game-like elements to something (as a task) so as to encourage participation.” Further, gamification is about bringing game mechanics – rules, constructs, processes, and methods – into the real world in an effort to engage people. In his session at @ThingsExpo, Robert Endo, owner and engagement manager of Intrepid D...
SYS-CON Events announced today that Pythian, a global IT services company specializing in helping companies adopt disruptive technologies to optimize revenue-generating systems, has been named “Bronze Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2015 at the Javits Center in New York, New York. Founded in 1997, Pythian is a global IT services company that helps companies compete by adopting disruptive technologies such as cloud, Big Data, advanced analytics, and DevO...
One of the bewildering things about DevOps is integrating the massive toolchain including the dozens of new tools that seem to crop up every year. Part of DevOps is Continuous Delivery and having a complex toolchain can add additional integration and setup to your developer environment. In his session at @DevOpsSummit at 18th Cloud Expo, Miko Matsumura, Chief Marketing Officer of Gradle Inc., will discuss which tools to use in a developer stack, how to provision the toolchain to minimize onboa...
With microservices, SOA and distributed architectures becoming more popular, it is becoming increasingly harder to keep track of where time is spent in a distributed application when trying to diagnose performance problems. Distributed tracing systems attempt to address this problem by following application requests across service boundaries, persisting metadata along the way that provide context for fine-grained performance monitoring.
With an estimated 50 billion devices connected to the Internet by 2020, several industries will begin to expand their capabilities for retaining end point data at the edge to better utilize the range of data types and sheer volume of M2M data generated by the Internet of Things. In his session at @ThingsExpo, Don DeLoach, CEO and President of Infobright, will discuss the infrastructures businesses will need to implement to handle this explosion of data by providing specific use cases for filte...
SYS-CON Events announced today that Men & Mice, the leading global provider of DNS, DHCP and IP address management overlay solutions, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. The Men & Mice Suite overlay solution is already known for its powerful application in heterogeneous operating environments, enabling enterprises to scale without fuss. Building on a solid range of diverse platform support,...