Centerra Gold Completes Preliminary Economic Assessment of the Oksut Project

TORONTO, ONTARIO -- (Marketwired) -- 02/20/14 --

All figures are in United States dollars

Centerra Gold Inc. (TSX:CG) announces the completion of a preliminary economic assessment study (PEA) on its 100% owned Oksut project located in south-central Turkey, about 295 kilometres southeast of the capital city of Ankara. The Oksut project is currently comprised of the Keltepe deposit and the smaller Guneytepe deposit.

The resource estimate used as the basis for the PEA was made as of December 31, 2013 using a cut-off grade of 0.2 grams per tonne of gold and a gold price of $1,300 per ounce and was announced in a news release dated February 5, 2014. The resource estimate consists of: (i) indicated mineral resources from the Keltepe deposit, estimated at 29 million tonnes grading 1.2 grams per tonne of gold for 1.1 million contained ounces of gold; and (ii) inferred mineral resources located at the Guneytepe deposit, estimated at 4.7 million tonnes grading 0.9 grams per tonne of gold for 134,000 contained ounces of gold.

The PEA envisions a conventional open-pit and heap leach facility with an expected 34 million tonnes of ore to be stacked at a maximum rate of 11,000 tonnes per day.

Highlights of the PEA study (using a $1,300 per ounce gold price) include:

--  11 year mine life (2016 to 2027), 
--  Life of mine gold production of 893,000 ounces, average annual gold
    production of 125,000 ounces in years 4 through 6, 
--  Total construction capital and preproduction costs of $166 million, 
--  Total sustaining capital of $9 million, 
--  All-in costs(1) for the project of $849 per ounce, 
--  All-in costs including taxes(1) for the project of $914 per ounce, 
--  After tax net present value (NPV) of $117 million at an 8% discount rate
    with a 19% project internal rate of return, 
--  Payback on construction capital and pre-production costs is expected to
    be 4.5 years after production begins.

(1)  Non-GAAP measure. Centerra has adopted the World Gold Council's (WGC)  
     guidelines regarding "all-in-costs". These financial measures do not   
     have any standardized meaning prescribed by GAAP and are therefore     
     unlikely to be comparable to similar measures presented by other       
     issuers, even issuers applying the WGC's guidelines. See description of
     "Non-GAAP Measures" in the Company's Management Discussion & Analysis  
     dated February 19, 2014 and filed on SEDAR.                            

The PEA is preliminary in nature and includes the use of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Thus, there is no certainty that the PEA will be realized. Actual results may vary, perhaps materially. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The PEA is subject to a number of assumptions, including, among others, that an environmental impact assessment will be completed within the required timelines, all required permits will be obtained in a timely manner, the Company will continue to have the support of local communities, a constant regulatory environment and no material increase occurs to the estimated costs. A full list of the relevant assumptions will be set out in the PEA.

Ian Atkinson, President and CEO of Centerra Gold stated, "We are very pleased with the positive results of the PEA study which confirmed our expectations based on the known resources. The Keltepe deposit is still open to the south in the direction of the Guneytepe deposit and we have additional exploration targets on our land package which we will continue to follow-up on through exploration and drilling. Now we will move forward with a feasibility study for the project with the target of achieving initial gold production sometime in late 2016."

The PEA study envisions a conventional open pit and heap leach facility with the mining of the two pits completed by a local mining contractor. The heap leach pad design is based on an expected 34 million tonnes of ore to be stacked at a maximum rate of 11,000 tonnes per day, with a nominal crush size of 80% less than 37.5 mm.

Over the life of mine, mining costs are estimated to average $2.77 per tonne mined, processing costs are estimated to average $4.00 per tonne processed and administrative costs will average about $9 million per operating year.

To account for mining dilution and losses during the mining process, the mineral resources have had a 95% factor applied to the gold grades in the production schedule and are constrained by an optimized pit shell defined using optimization software, a gold price of $1,300 per ounce, an overall metallurgical recovery of 77%, and estimated average mining, processing and administrative costs. Overall pit-slope angles range from 38 degrees to 42 degrees depending on the location in the pit and result in a low overall stripping ratio of 2.0 over the mine life.

Using a gold price of $1,300 per ounce and a discount rate of 8%, the Oksut open pit LOM outlined in the PEA has an estimated project NPV (after tax) of approximately $117 million and a project internal rate of return of 19% after accounting for all operating costs and capital expenditures related to the open pit operation as well as required tax and royalty payments. Additional exploration costs going forward have not been included in the financial analysis.

Sensitivities of the project NPV to the gold price, discount rate and other project variables are as follows:

 Sensitivities of Oksut Project Net Present Value to Gold Price and Discount
                            (millions of dollars)                           
                                      Discount Rate                         
                 Gold Price                                                 
                  ($/ounce)          5%        8%       10%                 
                 $1,100        $   81.0  $   36.7  $   14.5                 
                 $1,200        $  131.8  $   77.7  $   50.3                 
                 $1,300        $  181.1  $  117.7  $   85.2                 
                 $1,400        $  224.7  $  153.4  $  116.7                 
                 $1,500        $  267.8  $  188.6  $  147.6                 
   Sensitivities of Oksut Project Net Present Value to other Variables at   
                 $1,300 per ounce gold and 8% discount rate                 
                            (millions of dollars)                           
Variable                     Operating Costs   Capital Costs      Gold Grade
+15%                          $         75.4  $         99.9  $        181.3
Base Case                     $        117.7  $        117.7  $        117.7
-15%                          $        156.1  $        131.2  $         45.4

The inferred mineral resources located at the Guneytepe deposit have a great amount of uncertainty as to their existence and as to whether they can be mined legally or economically. It cannot be assumed that all or any part of inferred mineral resources will ever be upgraded to a higher category.

The PEA will be available on the Company's website in middle of March, 2014.

Qualified Person & QA/QC

The PEA report was undertaken by Centerra staff with the assistance of several external consultants. Resource estimates, life-of-mine plan and other scientific and technical information in this news release and on Centerra's website were prepared in accordance with the standards of the Canadian Institute of Mining, Metallurgy and Petroleum and National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and were reviewed, verified and compiled by Centerra's geological and mining staff under the supervision of Dan Redmond, Ontario Professional Geoscientist, Centerra's Director, Technical Services - Mining, who is the qualified person for the purpose of NI 43-101. Sample preparation, analytical techniques, laboratories used and quality assurance-quality control protocols used during the exploration drilling programs on the Oksut project have been done consistent with industry standards and independent certified assay labs have been used. Available quality control data indicates that the gold assay data used for resource estimation are reliable.

Cautionary Note Regarding Forward-looking Information

Information contained in this news release and the documents referred to herein which are not statements of historical facts, may be "forward-looking information" for the purposes of Canadian securities laws. Such forward looking information involves risks, uncertainties and other factors that could cause actual results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward looking information. The words "believe", "expect", "envision", "target", "intends", "estimate", "may", "will", and similar expressions identify forward-looking information. These forward-looking statements relate to, among other things, mineral resource estimates and Centerra's plans to conduct additional exploration and drilling work and to commence a feasibility study for its Oksut property in 2014.

Forward-looking information is necessarily based upon a number of estimates and assumptions that, while considered reasonable by Centerra, are inherently subject to significant political, business, economic and competitive uncertainties and contingencies. There may be factors that cause results, assumptions, performance, achievements, prospects or opportunities in future periods not to be as anticipated, estimated or intended. These factors include: (i) tight time lines for the completion of an environmental impact assessment and permitting, since the project has to receive all necessary permits prior to January 2016 and the possibility of forfeiting the operating license as a result of any delays in such timelines; (ii) delays in recent years in the issuance of permits, particularly for State Forestry Land which covers part of the Oksut project area and on which the two open pits and part of the waste dump are located; (iii) the absence of condemnation drilling of the heap-leach and waste-dump sites, which may result in those sites being poorly located or requiring additional capital costs; (iv) potential opposition to the project by local communities or civil groups related to concerns over water usage in competition with agriculture, water quality, environmental impact from cyanide use in gold leaching, visual impacts, acoustic impacts, ambient air impacts or failure of the company to agree to local demands; (v) potential material increases in project development or operation costs due to increases in key consumables, inflation, imposed demands for infrastructure development or regulatory changes; (vi) further column tests being required to determine the variability of the metallurgical parameters and response of the Oksut oxide ore; (vii) the planning, design and costing of the key project infrastructure such as power, water and access being at a high level conceptual stage in the PEA; (viii) closure costs to cap waste rock and heap leach dumps; (ix) mine design, mining schedules, metallurgical flow sheets and process designs will require additional detailed work and economic analysis; and (x) internal studies to ensure satisfactory operational conditions and decisions regarding future targeted production must be carried out. See also "Risks that can affect our business" in the Company's Annual Information Form for the year ended December 31, 2012, available on SEDAR at

There can be no assurances that forward-looking information and statements will prove to be accurate, as many factors and future events, both known and unknown could cause actual results, performance or achievements to vary or differ materially, from the results, performance or achievements that are or may be expressed or implied by such forward looking statements contained herein or incorporated by reference. Accordingly, all such factors should be considered carefully when making decisions with respect to Centerra, and prospective investors should not place undue reliance on forward-looking information. Forward looking information is as of February 19, 2014. Centerra assumes no obligation to update or revise forward-looking information to reflect changes in assumptions, changes in circumstances or any other events affecting such forward looking information, except as required by applicable law.

About Centerra

Centerra Gold Inc. is a gold mining company focused on operating, developing, exploring and acquiring gold properties primarily in Asia, the former Soviet Union and other emerging markets worldwide. Centerra is the largest Western-based gold producer in Central Asia. Centerra's shares trade on the Toronto Stock Exchange (TSX) under the symbol CG. The Company is based in Toronto, Ontario, Canada.

Additional information on Centerra is available on the Company's web site at and at SEDAR at

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that Alert Logic, Inc., the leading provider of Security-as-a-Service solutions for the cloud, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Alert Logic, Inc., provides Security-as-a-Service for on-premises, cloud, and hybrid infrastructures, delivering deep security insight and continuous protection for customers at a lower cost than traditional security solutions. Ful...
Just over a week ago I received a long and loud sustained applause for a presentation I delivered at this year’s Cloud Expo in Santa Clara. I was extremely pleased with the turnout and had some very good conversations with many of the attendees. Over the next few days I had many more meaningful conversations and was not only happy with the results but also learned a few new things. Here is everything I learned in those three days distilled into three short points.
As organizations realize the scope of the Internet of Things, gaining key insights from Big Data, through the use of advanced analytics, becomes crucial. However, IoT also creates the need for petabyte scale storage of data from millions of devices. A new type of Storage is required which seamlessly integrates robust data analytics with massive scale. These storage systems will act as “smart systems” provide in-place analytics that speed discovery and enable businesses to quickly derive meaningf...
DevOps is about increasing efficiency, but nothing is more inefficient than building the same application twice. However, this is a routine occurrence with enterprise applications that need both a rich desktop web interface and strong mobile support. With recent technological advances from Isomorphic Software and others, rich desktop and tuned mobile experiences can now be created with a single codebase – without compromising functionality, performance or usability. In his session at DevOps Su...
In his General Session at 17th Cloud Expo, Bruce Swann, Senior Product Marketing Manager for Adobe Campaign, explored the key ingredients of cross-channel marketing in a digital world. Learn how the Adobe Marketing Cloud can help marketers embrace opportunities for personalized, relevant and real-time customer engagement across offline (direct mail, point of sale, call center) and digital (email, website, SMS, mobile apps, social networks, connected objects).
The buzz continues for cloud, data analytics and the Internet of Things (IoT) and their collective impact across all industries. But a new conversation is emerging - how do companies use industry disruption and technology enablers to lead in markets undergoing change, uncertainty and ambiguity? Organizations of all sizes need to evolve and transform, often under massive pressure, as industry lines blur and merge and traditional business models are assaulted and turned upside down. In this new da...
In his General Session at DevOps Summit, Asaf Yigal, Co-Founder & VP of Product at, explored the value of Kibana 4 for log analysis and provided a hands-on tutorial on how to set up Kibana 4 and get the most out of Apache log files. He examined three use cases: IT operations, business intelligence, and security and compliance. Asaf Yigal is co-founder and VP of Product at log analytics software company In the past, he was co-founder of social-trading platform Currensee, which...
The Internet of Everything is re-shaping technology trends–moving away from “request/response” architecture to an “always-on” Streaming Web where data is in constant motion and secure, reliable communication is an absolute necessity. As more and more THINGS go online, the challenges that developers will need to address will only increase exponentially. In his session at @ThingsExpo, Todd Greene, Founder & CEO of PubNub, exploreed the current state of IoT connectivity and review key trends and t...
Two weeks ago (November 3-5), I attended the Cloud Expo Silicon Valley as a speaker, where I presented on the security and privacy due diligence requirements for cloud solutions. Cloud security is a topical issue for every CIO, CISO, and technology buyer. Decision-makers are always looking for insights on how to mitigate the security risks of implementing and using cloud solutions. Based on the presentation topics covered at the conference, as well as the general discussions heard between sessi...
Continuous processes around the development and deployment of applications are both impacted by -- and a benefit to -- the Internet of Things trend. To help better understand the relationship between DevOps and a plethora of new end-devices and data please welcome Gary Gruver, consultant, author and a former IT executive who has led many large-scale IT transformation projects, and John Jeremiah, Technology Evangelist at Hewlett Packard Enterprise (HPE), on Twitter at @j_jeremiah. The discussion...
Too often with compelling new technologies market participants become overly enamored with that attractiveness of the technology and neglect underlying business drivers. This tendency, what some call the “newest shiny object syndrome” is understandable given that virtually all of us are heavily engaged in technology. But it is also mistaken. Without concrete business cases driving its deployment, IoT, like many other technologies before it, will fade into obscurity.
In today's enterprise, digital transformation represents organizational change even more so than technology change, as customer preferences and behavior drive end-to-end transformation across lines of business as well as IT. To capitalize on the ubiquitous disruption driving this transformation, companies must be able to innovate at an increasingly rapid pace. Traditional approaches for driving innovation are now woefully inadequate for keeping up with the breadth of disruption and change facin...
The Internet of Things is clearly many things: data collection and analytics, wearables, Smart Grids and Smart Cities, the Industrial Internet, and more. Cool platforms like Arduino, Raspberry Pi, Intel's Galileo and Edison, and a diverse world of sensors are making the IoT a great toy box for developers in all these areas. In this Power Panel at @ThingsExpo, moderated by Conference Chair Roger Strukhoff, panelists discussed what things are the most important, which will have the most profound...
With all the incredible momentum behind the Internet of Things (IoT) industry, it is easy to forget that not a single CEO wakes up and wonders if “my IoT is broken.” What they wonder is if they are making the right decisions to do all they can to increase revenue, decrease costs, and improve customer experience – effectively the same challenges they have always had in growing their business. The exciting thing about the IoT industry is now these decisions can be better, faster, and smarter. Now ...
PubNub has announced the release of BLOCKS, a set of customizable microservices that give developers a simple way to add code and deploy features for realtime apps.PubNub BLOCKS executes business logic directly on the data streaming through PubNub’s network without splitting it off to an intermediary server controlled by the customer. This revolutionary approach streamlines app development, reduces endpoint-to-endpoint latency, and allows apps to better leverage the enormous scalability of PubNu...