QMX Gold Produces Over 22,000 Ounces of Gold in 2013 from Lac Herbin Mine

Company expects production of 16,500 to 19,000 in 2014

TORONTO, ONTARIO -- (Marketwired) -- 02/25/14 -- QMX GOLD CORPORATION (TSX VENTURE: QMX) ("QMX Gold" or the "Company") produced approximately 7,260 ounces of gold from its Lac Herbin Mine in Val D'Or, Quebec in the fourth quarter of 2013. This brings total production for 2013 to over 22,200 ounces of gold, in line with Company guidance. Full financial details will be released in March 2014.

----------------------------------------------------------------------------
                        Production Summary for 2013
----------------------------------------------------------------------------
Quarter                  Q1          Q2          Q3           Q4 Total 2013
----------------------------------------------------------------------------
Tons Milled (mt)     33,866      39,667      40,403       59,791    173,727
----------------------------------------------------------------------------
Grade (g/mt)           4.09        4.42        4.62         4.03       4.27
----------------------------------------------------------------------------
Average Recovery
 Rate                  93.0%       93.5%       92.6%        93.7       93.2%
----------------------------------------------------------------------------
Recovered Gold
 (oz)                 4,141       5,275       5,549        7,260     22,225
----------------------------------------------------------------------------

2013 Production Results

The Aurbel Mill continued to generate positive and consistent results in 2013 with an overall annual average recovery rate of 93.2% and was achieved with a significant increase in the mill throughput quarter over quarter. Over the course of 2013, the mill processed a total of 173,727 tonnes of ore at an average grade of 4.27 g/t to produce 22,225 ounces of gold. The production figures do not include an additional 10,000 tonnes of ore that were custom milled under the milling agreement with Armistice Resources (now renamed Kerr Mines Inc.) in the third quarter.

Fourth Quarter Production Results

In the fourth quarter of 2013, mill throughput was 77% higher than in the first quarter of the same year, processing 59,791 tonnes of ore at an average grade of 4.03 g/t Au with recoveries of 93.7% to produce 7,260 ounces of gold. The mill throughput increase was a result of producing from larger zones, which were developed by the operating team over the last year, at slightly lower than average grades.

Operational Outlook

QMX Gold continues to mine out the Lac Herbin mine above the 42 Level as a suspension of development and exploration activities remains in place. The Company plans to to process ore at the Aurbel Mill for Kerr Mines Inc. under the custom milling agreement signed in June 2013. QMX Gold intends to process at least an additional 20,000 tonnes of ore under the agreement. The Company continues to search for additional feed to maintain operation at its Aurbel mill.

Also, the Company is continuing to evaluate several projects within a 150 kilometer radius from Aurbel mill which could be put in production in the short to medium term.

The sale of QMX Gold's Snow Lake property to Northern Sun Mining Corp. remains pending and is expected to close on or before March 31, 2014.

Brett New, President and CEO of QMX Gold, commented "I am pleased to report that our year-end results are in line with 2013 budgeted figures as we produced between 20,500 and 23,500 ounces of gold at the Aurbel Mill. The team at Lac Herbin and the Aurbel Mill have done an excellent job at keeping operations running smoothly and efficiently, despite a number of cost-reduction measures that were necessary over the course of 2013. This can be seen as our mill recovery rates have remained very consistent throughout 2013. The Company plans to continue to mine out the mineralized lenses above the 42 Level in 2014 and expects production to be 16,500 to 19,000 ounces of gold in 2014."

Qualified Person

Technical programs and information included in this release have been reviewed and approved by Patrick Sevigny, eng., Vice President of Quebec Operations and a Qualified Person as defined under NI 43-101.

Cautionary Note Regarding Forward-Looking Information and Mineral Resources:

This press release contains or may be deemed to contain "forward-looking information" within the meaning of applicable Canadian securities legislation. Forward-looking information includes, but is not limited to, statements (express or implied) relating to financial results, production results and/or the impact of such production results with respect to the mine at Lac Herbin, the timing, cost and/or amount of future exploration and development of the property, if any, the closing of the Snow Lake sale transaction, the processing of more custom mill feed, the timing, cost and/or amount of future production, the future price of gold or other minerals, the mineral resource estimates, the successful implementation of development plans at any of the Company's properties and/or the future financial or operating performance of QMX Gold, its properties and/or its projects. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company, its properties and/or its projects to be materially different from those expressed or implied by such forward-looking information, including but not limited to those risks described in the annual information form of the Company, which is available under the profile of the Company on SEDAR. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking information. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws. It should also be noted that mineral resources that are not mineral reserves do not have demonstrated economic viability.

Contacts:
QMX Gold Corporation
Brett New
President and CEO
(416) 861-5904

QMX Gold Corporation
Louis Baribeau
Public Relations
(514) 667-2304

QMX Gold Corporation
Rob Hopkins
Investor Relations
(416) 861-5899

QMX Gold Corporation
Toll free: +1 877-717-3027
[email protected]
www.qmxgold.ca

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that MIRAI Inc. will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. MIRAI Inc. are IT consultants from the public sector whose mission is to solve social issues by technology and innovation and to create a meaningful future for people.
Transforming cloud-based data into a reportable format can be a very expensive, time-intensive and complex operation. As a SaaS platform with more than 30 million global users, Cornerstone OnDemand’s challenge was to create a scalable solution that would improve the time it took customers to access their user data. Our Real-Time Data Warehouse (RTDW) process vastly reduced data time-to-availability from 24 hours to just 10 minutes. In his session at 21st Cloud Expo, Mark Goldin, Chief Technolo...
SYS-CON Events announced today that IBM has been named “Diamond Sponsor” of SYS-CON's 21st Cloud Expo, which will take place on October 31 through November 2nd 2017 at the Santa Clara Convention Center in Santa Clara, California.
SYS-CON Events announced today that TidalScale will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. TidalScale is the leading provider of Software-Defined Servers that bring flexibility to modern data centers by right-sizing servers on the fly to fit any data set or workload. TidalScale’s award-winning inverse hypervisor technology combines multiple commodity servers (including their ass...
In the fast-paced advances and popularity in cloud technology, one of the most critical factors revolves around concerns for security of your critical data. How to assure both your company and your customers they can confidently trust and utilize your cloud environment is most often top on the list. There is a method to evaluating and providing security that exceeds conventional modes of protecting data both within the cloud as well externally on mobile and other devices. With the public failure...
Join IBM November 1 at 21st Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA, and learn how IBM Watson can bring cognitive services and AI to intelligent, unmanned systems. Cognitive analysis impacts today’s systems with unparalleled ability that were previously available only to manned, back-end operations. Thanks to cloud processing, IBM Watson can bring cognitive services and AI to intelligent, unmanned systems. Imagine a robot vacuum that becomes your personal assistant tha...
Widespread fragmentation is stalling the growth of the IIoT and making it difficult for partners to work together. The number of software platforms, apps, hardware and connectivity standards is creating paralysis among businesses that are afraid of being locked into a solution. EdgeX Foundry is unifying the community around a common IoT edge framework and an ecosystem of interoperable components.
In his session at 21st Cloud Expo, Raju Shreewastava, founder of Big Data Trunk, will provide a fun and simple way to introduce Machine Leaning to anyone and everyone. Together we will solve a machine learning problem and find an easy way to be able to do machine learning without even coding. Raju Shreewastava is the founder of Big Data Trunk (www.BigDataTrunk.com), a Big Data Training and consulting firm with offices in the United States. He previously led the data warehouse/business intellige...
Gemini is Yahoo’s native and search advertising platform. To ensure the quality of a complex distributed system that spans multiple products and components and across various desktop websites and mobile app and web experiences – both Yahoo owned and operated and third-party syndication (supply), with complex interaction with more than a billion users and numerous advertisers globally (demand) – it becomes imperative to automate a set of end-to-end tests 24x7 to detect bugs and regression. In th...
As popularity of the smart home is growing and continues to go mainstream, technological factors play a greater role. The IoT protocol houses the interoperability battery consumption, security, and configuration of a smart home device, and it can be difficult for companies to choose the right kind for their product. For both DIY and professionally installed smart homes, developers need to consider each of these elements for their product to be successful in the market and current smart homes.
Infoblox delivers Actionable Network Intelligence to enterprise, government, and service provider customers around the world. They are the industry leader in DNS, DHCP, and IP address management, the category known as DDI. We empower thousands of organizations to control and secure their networks from the core-enabling them to increase efficiency and visibility, improve customer service, and meet compliance requirements.
In his session at 21st Cloud Expo, Michael Burley, a Senior Business Development Executive in IT Services at NetApp, will describe how NetApp designed a three-year program of work to migrate 25PB of a major telco's enterprise data to a new STaaS platform, and then secured a long-term contract to manage and operate the platform. This significant program blended the best of NetApp’s solutions and services capabilities to enable this telco’s successful adoption of private cloud storage and launchi...
The session is centered around the tracing of systems on cloud using technologies like ebpf. The goal is to talk about what this technology is all about and what purpose it serves. In his session at 21st Cloud Expo, Shashank Jain, Development Architect at SAP, will touch upon concepts of observability in the cloud and also some of the challenges we have. Generally most cloud-based monitoring tools capture details at a very granular level. To troubleshoot problems this might not be good enough.
DevOps is often described as a combination of technology and culture. Without both, DevOps isn't complete. However, applying the culture to outdated technology is a recipe for disaster; as response times grow and connections between teams are delayed by technology, the culture will die. A Nutanix Enterprise Cloud has many benefits that provide the needed base for a true DevOps paradigm. In their Day 3 Keynote at 20th Cloud Expo, Chris Brown, a Solutions Marketing Manager at Nutanix, and Mark Lav...
With major technology companies and startups seriously embracing Cloud strategies, now is the perfect time to attend 21st Cloud Expo October 31 - November 2, 2017, at the Santa Clara Convention Center, CA, and June 12-14, 2018, at the Javits Center in New York City, NY, and learn what is going on, contribute to the discussions, and ensure that your enterprise is on the right path to Digital Transformation.