Lupaka Gold to Begin Permitting and Commence Small-Scale Production at the Invicta Gold Project by Q1-2015

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 03/17/14 -- Lupaka Gold Corp ("Lupaka Gold" or the "Company") (TSX: LPK)(LMA: LPK)(FRANKFURT: LQP) is pleased to announce that it intends to initiate a small-scale mining operation at the Invicta Gold Project at a rate of 300 tonnes per day ("t/d") by Q1-2015.

The Company intends to commence production by using the existing 1.2 km of tunnels, utilizing contracted third-party mining, development and haulage, and sell the mineralized rock to a local mill for processing. This contract-mining strategy will significantly minimize required capital, surface disturbance, while reducing the impact on the local community. The Company forecasts that production can be commenced at a total cost of less than $2.0 million. Production is planned to initially target some of the highest grade gold and copper mineralization within the Atenea Vein, which contains the majority of the current Invicta gold resource.

Invicta Gold Project production plan highlights:

--  Mine permitting, engineering, development and infrastructure costs of
   less than $2.0 million, funded from the Company's treasury and/or
    alternative financing sources;
--  Preparing and submitting an operating permit under the small miner
    exemption in Peru, which is available for operations of up to 350 t/d;
--  Securing necessary permits within 7 months by modifying/utilizing the
    Company's existing Environmental Impact Assessment for Mine Operations,
    Archeological Certificate, Water License and Community Agreement;
--  Contractor pre-production mine development would commence after
    receiving required permits and be completed within three months;
--  Utilize the existing 1.2 km of tunnels, drifts, and cross cuts that
    access the Measured resource mineralization;
--  Construction of mine safety, alternate escapes, and ventilation upgrades
    as part of the pre-production development;
--  Utilizing a low-cost and scalable sub-level open stoping mining method;
--  Commencing initial production by March 2015;
--  Over the first 12 months, producing approximiately 100,000 tonnes of
    mineralized rock from the areas containing the Measured resource; and
--  Shipping and selling mineralized rock directly to local custom toll
    mills, thereby avoiding capital cost and permit delays associated with
    plant construction, tailings and water impacts.

Eric Edwards, Lupaka Gold's CEO, commented that "the historical development work already provides us with access to an area containing some of the highest grade rock within the current resource. The considerable investment made by Invicta's previous owners has provided most of the infrastructure required for this proposed small-scale mining operation."

The current Invicta resource estimate shows a Measured resource of 131,000 tonnes grading 6.65 grams per tonne ("g/t") gold equivalent for 28,000 contained ounces of gold available from the in-situ development. As well, the current Invicta resource shows an Indicated resource of 8,513,000 tonnes grading 3.43 g/t gold equivalent for 939,000 contained ounces of gold and an Inferred resource of 2,534,000 tonnes grading 2.90 g/t gold equivalent for 236,000 contained ounces of gold. See Table 1 below and the technical report dated April 16, 2012, titled "Technical Report on Resources, Invicta Gold Project, Huaura Province, Peru", and prepared by SRK Consulting (U.S.) Inc. ("SRK Technical Report"), which is available at www.sedar.com under Lupaka Gold Corp's profile.

A portion of the Measured resource mineralization will initially be targeted by the planned production. The Company also intends to pursue further drilling from underground, concurrent with production, with the objective of upgrading inferred resources and providing additional data to inform mining direction and control decisions.

Table 1: Invicta Project: Summarized extract from the SRK Technical Report, detailing the above-mentioned resource estimate

       Resource       Tonnes
Zone   Category      (000's)                   Metal Grade
                               (g/t)Au (g/t)Ag (g/t)  Cu (%)  Pb (%)  Zn (%)
Total -Measured          131    6.65    4.29   31.71    0.73    0.39    0.38
 All   Indicated       8,513    3.43    2.09   15.65    0.42    0.24    0.28
 Zones M + I           8,644    3.48    2.13   15.90    0.43    0.24    0.29
       Inferred        2,534    2.90    1.61   12.02    0.46    0.27    0.18

Zone   Category                 Contained Metal (000's)
                    AuEq Oz   Au Oz   Ag Oz  Cu Lbs  Pb Lbs  Zn Lbs
Total -Measured          28      18     133   2,119   1,110   1,105
 All   Indicated        939     573   4,285  79,048  45,171  53,482
 Zones M + I            967     591   4,418  81,167  46,281  54,587
       Inferred         236     131     979  25,879  14,891   9,854


--  Mineral Resources are not Mineral Reserves and do not have demonstrated
    economic viability. There is no certainty that all or any part of the
    Mineral Resources estimate will be converted into a Mineral Reserves
--  Resources stated as contained within potentially economically mineable
    underground solids stated above a 1.3g/t Au Equivalent cut-off;
--  The resource is stated at a 1.30 g/t gold equivalent cut-off contained
    within potentially economically mineable mineralized solids. Metal
    prices assumed for the gold equivalent calculation are US$1,500/oz for
    gold, US$32.50/oz for silver, US$3.90/lb for copper, US$1.05/lb for lead
    and US$1.00/lb for zinc. The gold equivalent calculation assumes 100%
    metallurgical recovery, and does not account for any smelting,
    transportation or refining charges;
--  Mineral resource tonnage and contained metal have been rounded to
    reflect the accuracy of the estimate, and numbers may not add due to
    rounding; and
--  Mineral resource tonnage and grade are reported as diluted to reflect a
    potentially minable underground selective mining unit of 3.0m.

The Company will prepare and apply for a small mine operations permit in Peru that provides for mining operations of up to 350 tonne per day. The small mine permit approval process is administered through the local jurisdiction in the Department of Lima, and requires two public workshops for comment and local involvement. The permit application process requires similar studies as large-scale permits, i.e. environmental baseline, flora and fauna, archeological assessment, hydrology, hydrogeology, and others, but recognizes that the project has a much smaller surface and environmental disturbance and impact. Small mine permits can typically be prepared and approved within seven months.

The Company is in discussions and negotiations with a number of Peruvian mining contractors. A team to prepare the necessary small mine permits will be formed and contracted within the next month and should have the permit applications completed within 5 months. Community workshops will take place within the required timeframe.

Over the next several months and during the permit preparation/review process, the Company will complete mine engineering, contractor selections, staffing, training, road improvements, water system upgrades, and other activities leading toward operations. Critical to the contractor selection will be not only cost, but safety, environmental awareness, community and cultural sensitivity, permit compliance, references and experience, as well as other factors.

Mr. Edwards further commented that "Invicta remains a project with considerable unrecognized value, and with a successful implementation of an Invicta mining operation we believe that we will be able to interest an established miner in expanding to a larger-scale operation where Lupaka would hold a continuing carried interest."

Previous owners of the Invicta Gold property completed a number of technical studies including metallurgy, rock mechanics, structural geology on the mine area, hydrology, hydrogeology, power line from Andahuasi, and other engineering analysis.

The decision to commence production at the Invicta Gold property was based on economic models prepared by the Company in conjunction with management's knowledge of the property and the existing preliminary estimate of measured and inferred mineral resources on the property. The decision was not based on a preliminary economic assessment, a pre-feasibility study or a feasibility study of mineral reserves demonstrating economic and technical viability. Accordingly, there is increased uncertainty and economic and technical risks of failure associated with this production decision, in particular the risk that mineral grades will be lower than expected, the risk that construction or ongoing mining operations are more difficult or more expensive than expected, the risk that the Company will not be able to transport or sell the mineralized rock it produces to local custom toll mills on the terms it expects, or at all; production and economic variables may vary considerably, due to the absence of a detailed economic and technical analysis according to and in accordance with NI 43-101. Inferred mineral resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves.

To view Figure 1, "Invicta Project: Three dimensional view showing surface topography, underground projection of the main mineralized vein, and existing underground tunnels from surface to main vein," please visit the following link: http://media3.marketwire.com/docs/LPKfig1.pdf.

About Lupaka Gold

Lupaka Gold is a Peru-focused gold explorer and developer with geographic diversification and balance through its interest in asset-based resource projects spread across three regions of Peru.

As of December 31, 2013 Lupaka Gold had cash reserves of $3.85 million, sufficient to conduct planned exploration work and fund its operations during 2014.

Lupaka Gold currently has three projects occupying different stages of exploration and development.

The Company's 100% owned Invicta Gold Project (central Peru) has near-term underground gold and poly-metallic production potential. The Company plans to implement a small-scale mining operation and complete permitting, development and engineering with production to commence by Q1-2015.

Lupaka Gold's flagship exploration project is the Crucero Gold Project, its 5,500 hectare gold property located in southern Peru. Crucero has a growing indicated and inferred gold resource, and the Company is actively exploring the property to identify future drill targets.

In November 2013, the Company optioned the Josnitoro Gold Project from Hochschild Mining PLC. The project is located approximately 600 kilometres by road southeast of Lima in the Department of Apurimac, southern Peru. Historical work on the disseminated gold zones includes over 170 shallow drill holes and extensive surface trenching.

As a result of the Company's 2012 acquisition of Andean American Gold Corp., the Company also holds a strategic 17% stake in Southern Legacy Minerals Inc., owner of the AntaKori copper-gold deposit located in northern Peru.

Qualified Person

The technical information in this document has been reviewed and approved by Julio Castaneda, MAIG, the President of Lupaka Peru, a Peruvian subsidiary of the Company, and a Qualified Person as defined by National Instrument 43-101.

Forward-Looking Information and Regulatory Endnotes

This news release contains "forward-looking statements" and "forward-looking information" within the meaning of applicable securities regulations in Canada and the United States (collectively, "forward-looking information"). The forward-looking information contained in this news release is made as of the date of this news release. Except as required under applicable securities legislation, the Company does not intend, and does not assume any obligation, to update this forward-looking information. Forward-looking information in this news release includes all of the plans and expectations described above regarding initiating mining operations at the Invicta Gold Project (the "planned production"), including but is not limited to: the timing and cost of completing pre-production mine development; the method of funding mine development and infrastructure costs; the mineralizations to be targeted; the existence of high-grade mineralizations and the depth of any such mineralization from the existing tunnels on the project; the Company's plans for shipping and selling mineralized rock from the planned production; all statements regarding the permits necessary for the planned production and the timing and conditions of receiving those permits; mining methods to be used for the planned production and the costs thereof; the date by which the Company expects the planned production to commence; and all quantities and rates of production.

Forward-looking information also includes statements as to the sufficiency of current cash reserves to pay for planned exploration and fund future operations, as well as estimates of mineral resources. Often, but not always, forward-looking information can be identified by the use of words such as "plans", "expects, "is expected", "budget", "scheduled", "projects", "estimates", forecasts", "intends", "anticipates", or "believes", or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might", or "will" be taken, occur or be achieved. The forward-looking information contained in this news release is based on certain assumptions that the Company believes are reasonable, including, with respect to the planned production: that pre-production mine development can be completed in the time and for the cost projected; that the Company will be able to fund expenses of the planned production from its current cash reserves; that mineralizations on the project will be of the grades and in the locations expected; that the Company will be able to extract and transport mineralized rock efficiently and sell the mineralized rock at the prices and in the manner and quantities expected; that permits will be received on the terms and timeline expected and that other regulatory or permitting issues will not arise; that mining methods can be employed in the manner and at the costs expected and that such methods yield the results the Company expects them to; that supplies, equipment, personnel, permits and local community approvals required to develop and conduct the planned production will be available on reasonable term; that the Company will not experience any material accident, labour dispute, or failure of equipment.

The Company's assumptions with respect to mineral resource estimates include all of the key assumptions and parameters on which such estimates are based, as described in the technical report referred to in this news release. However, forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such risks, uncertainties and other factors include, among others: all of the risks described in this news release; the risk that actual results of exploration activities will be different than anticipated; that cost of labour, equipment or materials will increase more than expected; that the future price of gold will decline; that the Canadian dollar will strengthen against the U.S. dollar; that mineral resources are not as estimated; unexpected variations in mineral resources, grade or recovery rates; risks related to shipping mineralized rock; the risk that local mills cannot or will not buy or process mineralized rock from the planned production for the prices expected or at all; risk of accidents, labour disputes and other risks generally associated with mineral exploration; unanticipated delays in obtaining or failure to obtain community, governmental or regulatory approvals or financing; and all of the risks generally associated with the development of mining facilities and the operation of a producing mine; as well as the risks described in the Company's annual information form, which is available on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results to not be as anticipated, estimated or intended. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Readers are cautioned not to place undue reliance on forward-looking information due to the inherent uncertainty thereof.

This announcement contains certain forward looking statements, including such statements within the meaning of Section 27A of the US Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. In particular, such forward looking statements may relate to matters such as the business, strategy, investments, production, major projects and their contribution to expected production and other plans of Hochschild Mining plc and its current goals, assumptions and expectations relating to its future financial condition, performance and results.

Forward-looking statements include, without limitation, statements typically containing words such as "intends", "expects", "anticipates", "targets", "plans", "estimates" and words of similar import. By their nature, forward looking statements involve risks and uncertainties because they relate to events and depend on circumstances that will or may occur in the future. Actual results, performance or achievements of Hochschild Mining plc may be materially different from any future results, performance or achievements expressed or implied by such forward looking statements. Factors that could cause or contribute to differences between the actual results, performance or achievements of Hochschild Mining plc and current expectations include, but are not limited to, legislative, fiscal and regulatory developments, competitive conditions, technological developments, exchange rate fluctuations and general economic conditions. Past performance is no guide to future performance and persons needing advice should consult an independent financial adviser.

The forward looking statements reflect knowledge and information available at the date of preparation of this announcement. Except as required by the Listing Rules and applicable law, Hochschild Mining plc does not undertake any obligation to update or change any forward looking statements to reflect events occurring after the date of this announcement. Nothing in this announcement should be construed as a profit forecast.

Lupaka Gold Corp.
Investor Relations
+1 (604) 681-5900

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
@DevOpsSummit has been named the ‘Top DevOps Influencer' by iTrend. iTrend processes millions of conversations, tweets, interactions, news articles, press releases, blog posts - and extract meaning form them and analyzes mobile and desktop software platforms used to communicate, various metadata (such as geo location), and automation tools. In overall placement, @DevOpsSummit ranked as the number one ‘DevOps Influencer' followed by @CloudExpo at third, and @MicroservicesE at 24th.
One of biggest questions about Big Data is “How do we harness all that information for business use quickly and effectively?” Geographic Information Systems (GIS) or spatial technology is about more than making maps, but adding critical context and meaning to data of all types, coming from all different channels – even sensors. In his session at @ThingsExpo, William (Bill) Meehan, director of utility solutions for Esri, will take a closer look at the current state of spatial technology and ar...
SYS-CON Events announced today that Interface Masters Technologies, a leader in Network Visibility and Uptime Solutions, will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Interface Masters Technologies is a leading vendor in the network monitoring and high speed networking markets. Based in the heart of Silicon Valley, Interface Masters' expertise lies in Gigabit, 10 Gigabit and 40 Gigabit Eth...
Everyone knows that truly innovative companies learn as they go along, pushing boundaries in response to market changes and demands. What's more of a mystery is how to balance innovation on a fresh platform built from scratch with the legacy tech stack, product suite and customers that continue to serve as the business' foundation. In his General Session at 19th Cloud Expo, Michael Chambliss, Head of Engineering at ReadyTalk, will discuss why and how ReadyTalk diverted from healthy revenue an...
As software becomes more and more complex, we, as software developers, have been splitting up our code into smaller and smaller components. This is also true for the environment in which we run our code: going from bare metal, to VMs to the modern-day Cloud Native world of containers, schedulers and microservices. While we have figured out how to run containerized applications in the cloud using schedulers, we've yet to come up with a good solution to bridge the gap between getting your conta...
Without lifecycle traceability and visibility across the tool chain, stakeholders from Planning-to-Ops have limited insight and answers to who, what, when, why and how across the DevOps lifecycle. This impacts the ability to deliver high quality software at the needed velocity to drive positive business outcomes. In his session at @DevOpsSummit 19th Cloud Expo, Eric Robertson, General Manager at CollabNet, will show how customers are able to achieve a level of transparency that enables everyon...
SYS-CON Events announced today that Streamlyzer will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Streamlyzer is a powerful analytics for video streaming service that enables video streaming providers to monitor and analyze QoE (Quality-of-Experience) from end-user devices in real time.
SYS-CON Media announced today that @WebRTCSummit Blog, the largest WebRTC resource in the world, has been launched. @WebRTCSummit Blog offers top articles, news stories, and blog posts from the world's well-known experts and guarantees better exposure for its authors than any other publication. @WebRTCSummit Blog can be bookmarked ▸ Here @WebRTCSummit conference site can be bookmarked ▸ Here
You have great SaaS business app ideas. You want to turn your idea quickly into a functional and engaging proof of concept. You need to be able to modify it to meet customers' needs, and you need to deliver a complete and secure SaaS application. How could you achieve all the above and yet avoid unforeseen IT requirements that add unnecessary cost and complexity? You also want your app to be responsive in any device at any time. In his session at 19th Cloud Expo, Mark Allen, General Manager of...
In past @ThingsExpo presentations, Joseph di Paolantonio has explored how various Internet of Things (IoT) and data management and analytics (DMA) solution spaces will come together as sensor analytics ecosystems. This year, in his session at @ThingsExpo, Joseph di Paolantonio from DataArchon, will be adding the numerous Transportation areas, from autonomous vehicles to “Uber for containers.” While IoT data in any one area of Transportation will have a huge impact in that area, combining sensor...
DevOps theory promotes a culture of continuous improvement built on collaboration, empowerment, systems thinking, and feedback loops. But how do you collaborate effectively across the traditional silos? How can you make decisions without system-wide visibility? How can you see the whole system when it is spread across teams and locations? How do you close feedback loops across teams and activities delivering complex multi-tier, cloud, container, serverless, and/or API-based services?
Almost everyone sees the potential of Internet of Things but how can businesses truly unlock that potential. The key will be in the ability to discover business insight in the midst of an ocean of Big Data generated from billions of embedded devices via Systems of Discover. Businesses will also need to ensure that they can sustain that insight by leveraging the cloud for global reach, scale and elasticity.
So you think you are a DevOps warrior, huh? Put your money (not really, it’s free) where your metrics are and prove it by taking The Ultimate DevOps Geek Quiz Challenge, sponsored by DevOps Summit. Battle through the set of tough questions created by industry thought leaders to earn your bragging rights and win some cool prizes.
Today every business relies on software to drive the innovation necessary for a competitive edge in the Application Economy. This is why collaboration between development and operations, or DevOps, has become IT’s number one priority. Whether you are in Dev or Ops, understanding how to implement a DevOps strategy can deliver faster development cycles, improved software quality, reduced deployment times and overall better experiences for your customers.
Cloud based infrastructure deployment is becoming more and more appealing to customers, from Fortune 500 companies to SMEs due to its pay-as-you-go model. Enterprise storage vendors are able to reach out to these customers by integrating in cloud based deployments; this needs adaptability and interoperability of the products confirming to cloud standards such as OpenStack, CloudStack, or Azure. As compared to off the shelf commodity storage, enterprise storages by its reliability, high-availabil...