Golden Queen provides a construction update and updates its capital cost estimates

New Total Capital Expenditure Estimate of $141 Million Including $7 Million Spent to Date

VANCOUVER, March 27, 2014 /PRNewswire/ - Golden Queen Mining Co.  Ltd.  (TSX:GQM) (OTCQX:GQMNF) (the "Company") is pleased to provide an update on the construction underway on its Soledad Mountain Project (the "Project") and its expected capital costs for the construction of the Project. (Amounts are shown in U.S. dollars).

Costs incurred on construction of the Project since July 2013 to date, including access roads and site preparation are largely in-line with the feasibility study cost estimates provided in a news release dated October 25, 2012; a copy of which is available on the Company's website and on SEDAR.

One of the Company's priorities in Q4 2013 and Q1 2014 has been to complete detailed engineering designs for construction and update cost estimates for the major turn-key projects. The feasibility study capital cost estimates were prepared in 2012 and were therefore out of date by around 18 months by the end of 2013. These detailed designs are either well under way or have essentially been completed, and the Company has now received updated cost estimates for all of the turn-key projects.

The typical increase in cost estimates for the turn-key projects is mostly a result of design changes from the feasibility study.  "The time between the feasibility study and the start of construction has provided us with the opportunity to re-evaluate the designs and we have made a number of improvements which we believe will enhance the efficiency and reliability of the processing operation" said H. Lutz Klingmann, President.

Workshop-Warehouse: The Company received a proposal for the construction of the workshop-warehouse from a local contractor in late-2013.  This was the first of the turn-key projects and the contract price was in line with the feasibility study cost estimate.

Crushing-Screening Plant: The contractor has just completed the design for the crushing-screening plant as a turn-key project with numerous adjustments to the feasibility-level design, to improve the operability of the plant both from an operating and a maintenance point of view.  The plant now includes an agglomeration drum and provision has been made for a possible future increase in plant throughput and this has added to the cost of the plant.

Stacking and Conveying System: The feasibility study employed a stacking and conveying system design completed in 2005. The current design has evolved substantially over the past year to a fully-automated system with a significant increase in the reliability of the overall system.  Especially the power distribution along the system has evolved with a separate transformer and motor control package for each unit of the system.  Each of the grass hopper conveyors now includes dust control covers over the conveyors and all functions of the stacker are now controlled by radio remote control.

Phase 1 Heap Leach Pad: The Phase 1 heap leach pad has been designed as a permanent, single-use pad with external solution collection and management systems.  Crushed and agglomerated ore will be conveyed to the heap and stacked with a radial stacker.  The Company has received an updated cost estimate for the construction of the Phase 1, Stage 1 pad and this, after allowance for the construction of the overland conveyor system and peripheral roads in 2013, is lower than the feasibility study cost estimate.

Merrill-Crowe Plant: The current design includes an increase in solution flow rates of 50% decided upon as part of an overall design review for the Project.  The increase in solution flow rates has been accommodated in the original Merrill-Crowe plant footprint. Costs are elevated due to an increase in the size of the equipment in the plant.

Assay Laboratory: The assay laboratory has been changed from a laboratory assembled from three pre-fabricated modules to a laboratory constructed on site.

Water Supply (Supply from Production Wells & Distribution): Both the design and the cost estimates for the water supply from two production wells were re-done from first principles by a consulting engineering firm based in Bakersfield.  The design for the feasibility study was inadequate and this was reflected in a cost estimate that was significantly lower than the current cost estimate.

The construction period will also be longer than the 12 months assumed in the feasibility study. As a result, the Company increased its EPCM (engineering, procurement and construction management), pre-production overhead and general site support cost estimates.

The key cost increases from the feasibility study estimates are shown in the table below:

   
Turn-Key Project Cost Increase from
2012 Feasibility Study
Workshop-Warehouse $0.1 million
Crushing-Screening Plant $2.7 million
Stacking and Conveying System $3.9 million
Phase 1 / Stage 1 Heap Leach Pad ($1.0 million)
Merrill-Crowe Plant $1.8 million
Assay Laboratory $0.4 million
Water Supply (Supply from Production Wells & Distribution) $2.3 million
Total Impact of Turn-Key Projects Revised Cost Estimates $10.2 million

Approximately 50% of capital expenditures are comprised of turn-key projects that will be awarded as fixed-price contracts. These contracts will therefore provide price protection during the construction period. The Company has selected and is working with contractors with significant experience and excellent reputations.

The updated designs and other cost updates have raised the total estimated capital cost to build the Project to $114 million. This includes a contingency of 15% of estimated construction costs, or approximately $15 million. The 2012 feasibility study had a cost estimate of $79 million and unallocated costs of $12 million for a total of $91 million.

In addition to the construction capital expenditures, the Company anticipates to require $10.5 million for working capital and approximately $17 million for mobile mining equipment. These estimates have not changed from the feasibility study. The Company's new estimate for the total capital required to bring the Project to production is $141 million (from $119 million in the feasibility study), of which $7 million has been spent to date.

CONSTRUCTION UPDATE

Phase 1 Construction

Work on the Phase 1 earthmoving projects was essentially completed in December 2013 with some final touch-up completed in January 2014. This included the pad where the workshop-warehouse is being constructed, the interconnecting roads including the main haul road between the area where the crushing-screening plant will be constructed and the east waste rock storage pad and the construction of safety berms as required by MSHA.

The Company awarded a contract for the construction of the workshop-warehouse and wash slab to a local contractor in late-2013.  A key milestone was achieved when the prepared pad was formally handed over to the contractor in mid-January to commence construction of the footings as illustrated in Photograph 1.

In addition, the Company has awarded contracts for the construction of the Phase 1 water supply and a guard shack and gate.

Phase 2 Construction

Phase 2 construction has commenced and will continue concurrently with the ongoing Phase 1 construction.

The Company anticipates completion of site preparation where the crushing-screening plant and the assay laboratory will be constructed in April.

The Company has awarded contracts for the construction of the septic system and leach field and a fuel storage facility.

A second key turn-key project is the assay laboratory.  Detailed designs have been completed and it is expected that a contract for the procurement and construction of the assay laboratory will be awarded in Q2 2014.

About Golden Queen Mining Co. Ltd.

The Company is developing its wholly-owned, gold-silver, open pit, heap leach operation on its fully-permitted Soledad Mountain property, located just outside the town of Mojave in Kern County in southern California. The Project will use conventional open pit mining methods and the cyanide heap leach and Merrill-Crowe processes to recover gold and silver from crushed, agglomerated ore.

H. Lutz Klingmann, P.Eng., the President of the Company, is a qualified person for the purposes of National Instrument 43-101 and has reviewed and approved the technical content of this press release.

Caution With Respect To Forward-looking Statements

The information in this news release includes certain "forward-looking statements".  All statements in this news release, other than statements of historical fact, including, without limitation, plans for and intentions with respect to construction and other development activities on the Soledad Mountain Project, capital cost estimates, and future mining operations on the Project, are forward-looking statements. There can be no assurance that such statements will prove to be accurate, and actual capital costs, results of our development plans, and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from statements in this news release regarding our intentions include the uncertainties involving the availability of project financing in the debt and capital markets; changes in capital cost estimates or actual costs due to delays in construction or for other reasons, risks of construction and mining such as accidents, equipment breakdowns, non-compliance with environmental and permit requirements, and other risks and uncertainties disclosed in the section entitled "Risk Factors" contained in our Annual Report on Form 10-K for the year ended December 31, 2013.  Investors are cautioned that forward-looking statements are not guarantees of future performance and, accordingly, should not to put undue reliance on forward-looking statements.  Any forward-looking statement made by us in this release is based only on information currently available to us and speaks only as of the date on which it is made. 

SOURCE Golden Queen Mining Co. Ltd.

Image with caption: "Photograph 1 - Concrete pouring near completion at warehouse area (CNW Group/Golden Queen Mining Co. Ltd.)". Image available at: http://photos.newswire.ca/images/download/20140327_C7543_PHOTO_EN_38442.jpg

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
Aspose.Total for .NET is the most complete package of all file format APIs for .NET as offered by Aspose. It empowers developers to create, edit, render, print and convert between a wide range of popular document formats within any .NET, C#, ASP.NET and VB.NET applications. Aspose compiles all .NET APIs on a daily basis to ensure that it contains the most up to date versions of each of Aspose .NET APIs. If a new .NET API or a new version of existing APIs is released during the subscription peri...
Organizations planning enterprise data center consolidation and modernization projects are faced with a challenging, costly reality. Requirements to deploy modern, cloud-native applications simultaneously with traditional client/server applications are almost impossible to achieve with hardware-centric enterprise infrastructure. Compute and network infrastructure are fast moving down a software-defined path, but storage has been a laggard. Until now.
"My role is working with customers, helping them go through this digital transformation. I spend a lot of time talking to banks, big industries, manufacturers working through how they are integrating and transforming their IT platforms and moving them forward," explained William Morrish, General Manager Product Sales at Interoute, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.
To leverage Continuous Delivery, enterprises must consider impacts that span functional silos, as well as applications that touch older, slower moving components. Managing the many dependencies can cause slowdowns. See how to achieve continuous delivery in the enterprise.
You think you know what’s in your data. But do you? Most organizations are now aware of the business intelligence represented by their data. Data science stands to take this to a level you never thought of – literally. The techniques of data science, when used with the capabilities of Big Data technologies, can make connections you had not yet imagined, helping you discover new insights and ask new questions of your data. In his session at @ThingsExpo, Sarbjit Sarkaria, data science team lead ...
SYS-CON Events announced today the Kubernetes and Google Container Engine Workshop, being held November 3, 2016, in conjunction with @DevOpsSummit at 19th Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA. This workshop led by Sebastian Scheele introduces participants to Kubernetes and Google Container Engine (GKE). Through a combination of instructor-led presentations, demonstrations, and hands-on labs, students learn the key concepts and practices for deploying and maintainin...
Security, data privacy, reliability, and regulatory compliance are critical factors when evaluating whether to move business applications from in-house, client-hosted environments to a cloud platform. Quality assurance plays a vital role in ensuring that the appropriate level of risk assessment, verification, and validation takes place to ensure business continuity during the migration to a new cloud platform.
Extracting business value from Internet of Things (IoT) data doesn’t happen overnight. There are several requirements that must be satisfied, including IoT device enablement, data analysis, real-time detection of complex events and automated orchestration of actions. Unfortunately, too many companies fall short in achieving their business goals by implementing incomplete solutions or not focusing on tangible use cases. In his general session at @ThingsExpo, Dave McCarthy, Director of Products...
Security, data privacy, reliability and regulatory compliance are critical factors when evaluating whether to move business applications from in-house client hosted environments to a cloud platform. In her session at 18th Cloud Expo, Vandana Viswanathan, Associate Director at Cognizant, In this session, will provide an orientation to the five stages required to implement a cloud hosted solution validation strategy.
WebRTC is bringing significant change to the communications landscape that will bridge the worlds of web and telephony, making the Internet the new standard for communications. Cloud9 took the road less traveled and used WebRTC to create a downloadable enterprise-grade communications platform that is changing the communication dynamic in the financial sector. In his session at @ThingsExpo, Leo Papadopoulos, CTO of Cloud9, discussed the importance of WebRTC and how it enables companies to focus...
Up until last year, enterprises that were looking into cloud services usually undertook a long-term pilot with one of the large cloud providers, running test and dev workloads in the cloud. With cloud’s transition to mainstream adoption in 2015, and with enterprises migrating more and more workloads into the cloud and in between public and private environments, the single-provider approach must be revisited. In his session at 18th Cloud Expo, Yoav Mor, multi-cloud solution evangelist at Cloudy...
UpGuard has become a member of the Center for Internet Security (CIS), and will continue to help businesses expand visibility into their cyber risk by providing hardening benchmarks to all customers. By incorporating these benchmarks, UpGuard's CSTAR solution builds on its lead in providing the most complete assessment of both internal and external cyber risk. CIS benchmarks are a widely accepted set of hardening guidelines that have been publicly available for years. Numerous solutions exist t...
A critical component of any IoT project is what to do with all the data being generated. This data needs to be captured, processed, structured, and stored in a way to facilitate different kinds of queries. Traditional data warehouse and analytical systems are mature technologies that can be used to handle certain kinds of queries, but they are not always well suited to many problems, particularly when there is a need for real-time insights.
Verizon Communications Inc. (NYSE, Nasdaq: VZ) and Yahoo! Inc. (Nasdaq: YHOO) have entered into a definitive agreement under which Verizon will acquire Yahoo's operating business for approximately $4.83 billion in cash, subject to customary closing adjustments. Yahoo informs, connects and entertains a global audience of more than 1 billion monthly active users** -- including 600 million monthly active mobile users*** through its search, communications and digital content products. Yahoo also co...
"Software-defined storage is a big problem in this industry because so many people have different definitions as they see fit to use it," stated Peter McCallum, VP of Datacenter Solutions at FalconStor Software, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.