Dundee Precious Metals Extends Mine Life at Chelopech With Updated Mineral Reserve and Resource Estimate

TORONTO, ONTARIO -- (Marketwired) -- 03/31/14 -- (All amounts have been expressed in US Dollars except where otherwise indicated)

Dundee Precious Metals Inc. (TSX: DPM) (TSX: DPM.WT.A) ("DPM" or "the Company") announces the results of the updated Mineral Reserve and Mineral Resource for its Chelopech mine in Bulgaria.

Highlights:

--  Life of mine ("LOM") extended from 2023 to 2025
--  Measured tonnes increased 13%, or 2.2 million tonnes ("Mt"), from
    September 2011 estimate
--  Pyrite recoveries incorporated into Mineral Reserve estimation
--  LOM assumptions maintain gold price of $1,250 per ounce
--  Pyrite recovery circuit commissioned in Q1 with an annual gold capacity
    in pyrite production of up to 80,000 oz of gold; concentrate contracts
    in 2014 for 240,000 tonnes and 40,000 oz contained gold
--  First shipment of pyrite concentrate to Xiangguang Copper Co. completed
    in March
--  18 months of stable operation at the 2 million tonnes per year rate,
    combined with the newly introduced pyrite recovery circuit, allows
    incremental tonnage, recovery and profitability optimization steps in
    keeping with DPM's continuous improvement core value

"The addition of a further two years to the LOM of our flagship asset is an encouraging outcome from our reserve and resource update, which now incorporates pyrite recovery as a result of our newly constructed capability to treat all pyrite feeds rather than discard pyrites to tailings," stated Rick Howes, President and CEO. "We have recently completed our first shipment of pyrite concentrate and expect to be able to meet our 2014 contractual obligations."

The 2005 metallurgical testwork characterized the hardness and flotation parameters of each mineralized block, and confirmed that the process flowsheet currently in operation was optimum for the production of copper/gold concentrates. An additional test program was completed in 2012, covering current and future ores, which confirmed the current flowsheet performance for the copper circuit, and developed the optimum conditions for the future recovery of pyrite from the current process plant ore feed.

The expanded ore treatment process was completed in early 2012. Further plant upgrades have been completed since the original expansion, including the replacement circuit for the second and third cleaners of the copper circuit in mid-2013, and a new pyrite circuit that commenced operation in the first quarter of 2014.

Mineral Reserves have been estimated as at December 31, 2013, and are based on, and inclusive of, Mineral Resources, and include approximately 71,000 tonnes of broken stocks and stockpiles. Mineral Reserves are reported using a gold equivalent (Au + Cu(i)2.06) cut-off of 3 g/t and a Net Smelter Return ("NSR") methodology.

----------------------------------------------------------------------------
MINERAL RESERVES                   GOLD           SILVER          COPPER
----------------------------------------------------------------------------
                        Tons   Grade      Oz   Grade      Oz   Grade  Pounds
                           M     g/t       M     g/t       M       %       M
----------------------------------------------------------------------------
Proven                  10.6    3.30   1.128    9.93   3.395    1.21     284
----------------------------------------------------------------------------
Probable                13.3    3.24   1.384    5.33   2.279    0.82     240
----------------------------------------------------------------------------
Proven and Probable     23.9    3.26   2.512    7.37   5.674    0.99     524
----------------------------------------------------------------------------

Mineral Reserves have been estimated by including a number of technical, economic and other factors. A change to any of the inputs would therefore have some effect on the overall results. Concerning mining and metallurgical factors, it is the belief of CSA Global (UK) Ltd. ("CSA") that sufficient work has been done by DPM to ensure that these are not likely to have any significant or material effect on Mineral Reserves. The quality of the ore reserves means that a high level of mine planning can be instituted and complied with.

Mineral Resources have been classified as Measured, Indicated and Inferred, following the guidelines specified by the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") and adopted for technical reports complying with National Instrument 43-101 ("NI 43-101"). Mineral Resources have been estimated as at December 31, 2013, and reported using a gold equivalent (Au + Cu(i)2.06) cut-off of 3 g/t and a breakeven NSR methodology.

----------------------------------------------------------------------------
MINERAL RESOURCES                  GOLD           SILVER          COPPER
----------------------------------------------------------------------------
                        Tons   Grade      Oz   Grade      Oz   Grade  Pounds
                           M     g/t       M     g/t       M       %       M
----------------------------------------------------------------------------
Measured                18.6    4.07   2.431    9.72   5.808    1.35     553
----------------------------------------------------------------------------
Indicated               10.2    3.96   1.293    8.39   2.742    1.06     237
----------------------------------------------------------------------------
Measured and
 Indicated              28.7    4.03   3.724    9.25   8.550    1.25     791
----------------------------------------------------------------------------
Inferred                 8.2    2.71   0.712   11.22   2.952    0.92     166
----------------------------------------------------------------------------

Compared to the September 2011 Mineral Resources estimate, for combined Measured and Indicated material, the updated estimate for Measured tonnes has increased by 13% (or 2.2Mt). Inferred material has 15% fewer tonnes with a 12% increase in copper, 7% increase in gold and 11% increase in silver. The primary reason for these changes are tonnage losses due to production of 2.5 Mt of ore treated during the period October 1, 2012 to December 31, 2013, offset by increases in resources from development drilling success.

It is CSA's opinion that the Mineral Resources estimate has a very low to negligible risk of being affected by factors such as geological understanding, data mismanagement, poor estimation methodology or poor classification strategy. The deposit geology is well understood, has been appropriately modeled in 3D and has adequate sampling data to support the grade and tonnage estimates. Recent reconciliation with production has verified the quality of the Mineral Resources estimate.

Mineral Resources and Reserves are based on the 2014 ore production schedule, operating costs through to 2013, with current projected metal prices of $1,250 per troy ounce price for gold, $2.75 per pound for copper, and $23 per troy ounce for silver.

Technical Information

The Mineral Resource and Mineral Reserve estimates and other scientific and technical information contained in this news release was prepared by CSA Global (UK) Ltd. ("CSA"), in accordance with Canadian regulatory requirements set out in National Instrument 43-101 Standards of Disclosure for Mineral Projects, and has been reviewed and approved by, as it relates to Mineral Resources, Malcolm Titley BSc, MAIG, Director and Principal Geologist, of CSA, and Julian Bennett, BSc ARSM FIMMM CEng, Mining Consultant, as it relates to Mineral Reserves. Both Malcolm Titley and Julian Bennett are independent Qualified Persons ("QP"), as defined under NI 43-101. The NI 43-101 technical report entitled "NI 43-101 Technical Report, Mineral Resource and Mineral Reserve Update, Chelopech Project, Chelopech, Bulgaria" dated March 21, 2014, in respect of the Mineral Resource and Mineral Reserves estimates disclosed herein (the "Technical Report"), is being filed today on SEDAR at www.sedar.com. Simon Meik, Vice President, Processing, and Edgar Urbaez, Corporate Director, Technical Services, both of DPM, who are QPs and not independent of the Company, have also reviewed and approved the contents of this release.

The Mineral Resource and Mineral Reserve estimates contained herein may be subject to legal, political, environmental or other risks that could materially affect the potential development of such Mineral Resources. See the Technical Report for more information with respect to the key assumptions, parameters, methods and risks of determination associated with the foregoing Mineral Resource estimates.

Cautionary note to U.S. Investors concerning estimates of Mineral Resources. These estimates have been prepared in accordance with the requirements of Canadian securities laws, which differ from the requirements of U.S. securities laws. The terms "mineral resource", "measured mineral resource", "indicated mineral resource" and "inferred mineral resource" are defined in NI 43-101 and recognized by Canadian securities laws but are not defined terms under the U.S. Securities and Exchange Commission ("SEC") Guide 7 ("SEC Guide 7") or recognized under U.S. securities laws. U.S. investors are cautioned not to assume that any part or all of mineral deposits in these categories will ever be upgraded to mineral reserves. "Inferred mineral resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an "inferred mineral resource" will ever by upgraded to a higher category. Under Canadian securities laws, estimates of "inferred mineral resources" may not form the basis of feasibility or pre-feasibility studies. U.S. investors are cautioned not to assume that all or any part of an inferred mineral resource exists or is economically or legally mineable. Accordingly, these mineral resource estimates and related information may not be comparable to similar information made public by U.S. companies subject to the reporting and disclosure requirements under the U.S. federal securities laws and the rules and regulations thereunder, including SEC Guide 7.

FORWARD LOOKING STATEMENTS

This news release contains "forward-looking statements" that involve a number of risks and uncertainties. Forward-looking statements include, but are not limited to, statements with respect to the future price of gold and silver, the estimation of mineral reserves and resources, the realization of mineral estimates, the timing and amount of estimated future production and output, costs of production, capital expenditures, costs and timing of the development of new deposits, success of exploration activities, permitting time lines, currency fluctuations, requirements for additional capital, government regulation of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims, limitations on insurance coverage and timing and possible outcome of pending litigation. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made, and they involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any other future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others: the actual results of current exploration activities; actual results of current reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of gold, copper, zinc and

silver; possible variations in ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of development or construction activities, fluctuations in metal prices, as well as those risk factors discussed or referred to in Management's Discussion and Analysis under the heading "Risks and Uncertainties" and other documents filed from time to time with the securities regulatory authorities in all provinces and territories of Canada and available at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Unless required by securities laws, the Company undertakes no obligation to update forward-looking statements if circumstances or management's estimates or opinions should change. Accordingly, readers are cautioned not to place undue reliance on forward-looking statements.

DPM is a Canadian based, international gold mining company engaged in the acquisition, exploration, development, mining and processing of precious metals. The Company's principal operating assets include the Chelopech operation, which produces a copper concentrate containing gold and silver, located east of Sofia, Bulgaria; the Kapan operation, which produces a copper concentrate and a zinc concentrate both containing gold and silver, located in southern Armenia; and the Tsumeb smelter, a concentrate processing facility located in Namibia. DPM also holds interests in a number of developing gold properties located in Bulgaria, Serbia, and northern Canada, including interests held through its 53.1% owned subsidiary, Avala Resources Ltd., its 45.5% interest in Dunav Resources Ltd. and its 12.1% interest in Sabina Gold & Silver Corp.

Contacts:
Dundee Precious Metals Inc.
Rick Howes
President & Chief Executive Officer
(416) 365-2836
[email protected]

Dundee Precious Metals Inc.
Lori Beak
Senior Vice President, Investor & Regulatory
Affairs and Corporate Secretary
(416) 365-5165
[email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
You know you need the cloud, but you’re hesitant to simply dump everything at Amazon since you know that not all workloads are suitable for cloud. You know that you want the kind of ease of use and scalability that you get with public cloud, but your applications are architected in a way that makes the public cloud a non-starter. You’re looking at private cloud solutions based on hyperconverged infrastructure, but you’re concerned with the limits inherent in those technologies.
As Marc Andreessen says software is eating the world. Everything is rapidly moving toward being software-defined – from our phones and cars through our washing machines to the datacenter. However, there are larger challenges when implementing software defined on a larger scale - when building software defined infrastructure. In his session at 16th Cloud Expo, Boyan Ivanov, CEO of StorPool, provided some practical insights on what, how and why when implementing "software-defined" in the datacent...
ChatOps is an emerging topic that has led to the wide availability of integrations between group chat and various other tools/platforms. Currently, HipChat is an extremely powerful collaboration platform due to the various ChatOps integrations that are available. However, DevOps automation can involve orchestration and complex workflows. In his session at @DevOpsSummit at 20th Cloud Expo, Himanshu Chhetri, CTO at Addteq, will cover practical examples and use cases such as self-provisioning infra...
Blockchain. A day doesn’t seem to go by without seeing articles and discussions about the technology. According to PwC executive Seamus Cushley, approximately $1.4B has been invested in blockchain just last year. In Gartner’s recent hype cycle for emerging technologies, blockchain is approaching the peak. It is considered by Gartner as one of the ‘Key platform-enabling technologies to track.’ While there is a lot of ‘hype vs reality’ discussions going on, there is no arguing that blockchain is b...
Leading companies, from the Global Fortune 500 to the smallest companies, are adopting hybrid cloud as the path to business advantage. Hybrid cloud depends on cloud services and on-premises infrastructure working in unison. Successful implementations require new levels of data mobility, enabled by an automated and seamless flow across on-premises and cloud resources. In his general session at 21st Cloud Expo, Greg Tevis, an IBM Storage Software Technical Strategist and Customer Solution Architec...
Nordstrom is transforming the way that they do business and the cloud is the key to enabling speed and hyper personalized customer experiences. In his session at 21st Cloud Expo, Ken Schow, VP of Engineering at Nordstrom, discussed some of the key learnings and common pitfalls of large enterprises moving to the cloud. This includes strategies around choosing a cloud provider(s), architecture, and lessons learned. In addition, he covered some of the best practices for structured team migration an...
The need for greater agility and scalability necessitated the digital transformation in the form of following equation: monolithic to microservices to serverless architecture (FaaS). To keep up with the cut-throat competition, the organisations need to update their technology stack to make software development their differentiating factor. Thus microservices architecture emerged as a potential method to provide development teams with greater flexibility and other advantages, such as the abili...
Product connectivity goes hand and hand these days with increased use of personal data. New IoT devices are becoming more personalized than ever before. In his session at 22nd Cloud Expo | DXWorld Expo, Nicolas Fierro, CEO of MIMIR Blockchain Solutions, will discuss how in order to protect your data and privacy, IoT applications need to embrace Blockchain technology for a new level of product security never before seen - or needed.
The use of containers by developers -- and now increasingly IT operators -- has grown from infatuation to deep and abiding love. But as with any long-term affair, the honeymoon soon leads to needing to live well together ... and maybe even getting some relationship help along the way. And so it goes with container orchestration and automation solutions, which are rapidly emerging as the means to maintain the bliss between rapid container adoption and broad container use among multiple cloud host...
Blockchain is a shared, secure record of exchange that establishes trust, accountability and transparency across business networks. Supported by the Linux Foundation's open source, open-standards based Hyperledger Project, Blockchain has the potential to improve regulatory compliance, reduce cost as well as advance trade. Are you curious about how Blockchain is built for business? In her session at 21st Cloud Expo, René Bostic, Technical VP of the IBM Cloud Unit in North America, discussed the b...
In his general session at 21st Cloud Expo, Greg Dumas, Calligo’s Vice President and G.M. of US operations, discussed the new Global Data Protection Regulation and how Calligo can help business stay compliant in digitally globalized world. Greg Dumas is Calligo's Vice President and G.M. of US operations. Calligo is an established service provider that provides an innovative platform for trusted cloud solutions. Calligo’s customers are typically most concerned about GDPR compliance, application p...
Imagine if you will, a retail floor so densely packed with sensors that they can pick up the movements of insects scurrying across a store aisle. Or a component of a piece of factory equipment so well-instrumented that its digital twin provides resolution down to the micrometer.
In his keynote at 18th Cloud Expo, Andrew Keys, Co-Founder of ConsenSys Enterprise, provided an overview of the evolution of the Internet and the Database and the future of their combination – the Blockchain. Andrew Keys is Co-Founder of ConsenSys Enterprise. He comes to ConsenSys Enterprise with capital markets, technology and entrepreneurial experience. Previously, he worked for UBS investment bank in equities analysis. Later, he was responsible for the creation and distribution of life settle...
The cloud era has reached the stage where it is no longer a question of whether a company should migrate, but when. Enterprises have embraced the outsourcing of where their various applications are stored and who manages them, saving significant investment along the way. Plus, the cloud has become a defining competitive edge. Companies that fail to successfully adapt risk failure. The media, of course, continues to extol the virtues of the cloud, including how easy it is to get there. Migrating...
No hype cycles or predictions of a gazillion things here. IoT is here. You get it. You know your business and have great ideas for a business transformation strategy. What comes next? Time to make it happen. In his session at @ThingsExpo, Jay Mason, an Associate Partner of Analytics, IoT & Cybersecurity at M&S Consulting, presented a step-by-step plan to develop your technology implementation strategy. He also discussed the evaluation of communication standards and IoT messaging protocols, data...