Prophecy Receives Updated Chandgana Preliminary Economic Assessment

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 04/04/14 -- Prophecy Coal Corp. ("Prophecy" or the "Company") (TSX:PCY)(OTCQX:PRPCF)(FRANKFURT:1P2) announces that, further to its December 19, 2013 news release clarifying the Company's technical disclosure, the Company has today filed on SEDAR a revised National Instrument 43-101 compliant technical report on its Chandgana Tal coal mining licenses in central Mongolia dated effective November 30, 2012, titled "Technical Report, Coal Resources and Preliminary Economic Assessment, Coal Mine Component, Chandgana Tal Coal Project" (the "PEA"). The PEA examines the economics of coal production from the mining licenses and excludes the Chandgana Khavtgai exploration license. Prophecy's wholly-owned subsidiary Chandgana Coal LLC intends to mine the coal and supply it to the proposed 600MW (150MW x 4) Chandgana mine-mouth power plant (the "Power Plant"), which is planned to be operated by Prophecy's wholly-owned Prophecy Power Generation, LLC. The PEA was prepared by John T Boyd Co., one of the world's largest independent consulting firms exclusively serving the coal, mineral, financial, utility, and power-related industries. The PEA replaces the technical report on the Chandgana Tal Coal Project previously filed by the Company on SEDAR on November 30, 2012 (the "Previous Report") and the information contained in the PEA and this news release represents changes to the Company's pervious disclosure contained in its news releases dated May 10 and November 2, 2012 disclosing the results of the Previous Report which are summarized and reconciled below.

The following information is derived from the PEA, and should be read in the context of and is qualified in its entirety by the full text of the PEA. Highlights of the PEA are as follows:

Coal Resources and Mining

The two Chandgana Tal mining licenses contain an estimated 124 million tonnes of coal resources all in the measured category. The average in-place coal gross calorific value is 3,306 kcal/kg. After a short ramp-up period, mine production will be 3.5 million tonnes per year throughout the 30 year life of the mine, in order to meet the demands of the power plant. The mine will be a surface (open pit) mine and is located 2 km from the proposed power plant site. The aggregate coal seam thickness is as great as 50 m and the overburden is relatively thin, making for a low average strip ratio of 0.70:1 over the life of the mine.

The estimated total Run-of-Mine ("ROM") coal product tonnage recovered over the life-of-mine plan and other study results are shown in the table below:

STUDY RESULTS


----------------------------------------------------------------------------
              Description                             Amount                
----------------------------------------------------------------------------
         ROM Coal Product (kt)                        103,946               
----------------------------------------------------------------------------
             Waste (kBCM)                             73,122                
----------------------------------------------------------------------------
            Stripping Ratio                                                 
                (BCM:t)                                0.70                 
----------------------------------------------------------------------------
   Annual Estimated Production (kt)                    3,500                
----------------------------------------------------------------------------
           Mine Life (years)                            30                  
----------------------------------------------------------------------------

Operating Costs

The life of mine average total cash cost of sales is estimated at US $12.71 per tonne, including the fees for a contract miner with owner equipment. The breakdown of the cost is as follows:

UNIT CASH COST OF SALES


----------------------------------------------------------------------------
             Direct Costs                       Unit Cost (US $ /t)         
----------------------------------------------------------------------------
                 Labor                                 0.78                 
----------------------------------------------------------------------------
        Materials and Supplies                         6.30                 
----------------------------------------------------------------------------
         Subtotal Direct Costs                         7.08                 
----------------------------------------------------------------------------
              Contingency                                                   
----------------------------------------------------------------------------
      Cash Cost Contingency @ 10%                      0.71                 
----------------------------------------------------------------------------
            Indirect Costs                                                  
----------------------------------------------------------------------------
  General& Administration - Off Site                   0.75                 
----------------------------------------------------------------------------
  Royalties, Emissions Tax, Water Use                                       
           Fee, License Fees                           1.60                 
----------------------------------------------------------------------------
    Contractor Management, Margin,                                          
               Overhead                                2.57                 
----------------------------------------------------------------------------
        Subtotal Indirect Costs                        4.92                 
----------------------------------------------------------------------------
    Total Unit Cash Costs of Sales                     12.71                
----------------------------------------------------------------------------

Capital Costs

The initial pre-production capital costs are estimated at US $30.9 Million, including a 10% contingency, are summarized below:

ESTIMATED INITIAL PRE-PRODUCTION CAPITAL EXPENDITURES


----------------------------------------------------------------------------
                 Area                              Cost (US $mn)            
----------------------------------------------------------------------------
       Surface Equipment Capital                       14.2                 
----------------------------------------------------------------------------
      Site infrastructure Capital                       9.6                 
----------------------------------------------------------------------------
               Subtotal                                23.9                 
----------------------------------------------------------------------------
    Total Capital Contingency @ 10%                     2.4                 
----------------------------------------------------------------------------
       Pre-Production Cash Cost                         4.7                 
----------------------------------------------------------------------------
      Total Capital Expenditures                       30.9                 
----------------------------------------------------------------------------

The life of mine estimated capital costs total US $160.2 million.

The independent PEA study reports that the Chandgana Coal project will produce the following after-tax financial results:


--  28% Internal Rate of Return ("IRR"). 
--  5.3 Years payback on US $30.9 million capital. 
--  US $47.8 million net present value ("NPV") at a 10% discount rate. 

An after-tax financial model was prepared using an initial mine gate price of US $17.70 per tonne, 30 year mine life and 100% equity financing. The coal price is fully indexed and adjusted annually to account for variable costs such as fuel, parts, and wages. The mine gate price has been determined in reliance on the terms of the coal supply agreement executed June 5, 2013 between the Company's two wholly-owned subsidiaries, Chandgana Coal LLC and Prophecy Power Generation LLC pursuant to which all of the coal mined will be delivered to support the operation of the Power Plant (the "Coal Supply Agreement"). The Coal Supply Agreement is filed and available for review on SEDAR.

The Company cautions that the PEA is preliminary in nature and has a degree of accuracy of plus or minus 35%. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

The results of a sensitivity analysis, carried out to evaluate project economics with respect to coal price, NPV, and IRR, are described in the following table.

NET PRESENT VALUE (US $mn)


----------------------------------------------------------------------------
                  Base                                          Capital     
 Discount Rate %  Case    Coal Price      Operating Cost      Expenditure   
----------------------------------------------------------------------------
                         +10%     -10%     -10%     +10%     -10%    +10%   
                       (Better) (Worse)  (Better) (Worse)  (Better) (Worse) 
----------------------------------------------------------------------------
        8         66.0   99.9     32.1     95.5     36.5     71.1     61.0  
----------------------------------------------------------------------------
        10        47.8   74.6     20.9     71.2     24.3     52.1     43.4  
----------------------------------------------------------------------------
        12        34.7   56.4     13.0     53.7     15.7     38.5     30.9  
----------------------------------------------------------------------------
        15        21.4   37.6     5.0      35.7     7.0      24.6     18.1  
----------------------------------------------------------------------------
     IRR (%)       28     37       18       37       19       31       25   
----------------------------------------------------------------------------

Reconciliation

The foregoing represents changes to the information previously disclosed by the Company in the Previous Report and its November 2, 2012 announcement disclosing the results of the Previous Report.

The principal changes to the Company's previous disclosure are as follows:


1.  The economic analysis was changed to be performed on an after-tax basis;
2.  Depreciation has been included in the analysis for income tax
    calculation purposes; 
3.  Application of corporate income tax has been applied; 
4.  An indirect cost for water usage was added;  
5.  A direct cost figure in materials and supplies has been revised; and 
6.  Revised support for the price of coal at the mine gate coal has been
    provided. 

The Previous Report was prepared on a before tax basis. The change to an after-tax basis in the PEA decreased the base financial results including reducing the IRR from 36% to 28%, increased the payback period from 4 to 5.3 years, and decreased the NPV from US $70.5 million to US $47.8 million at a 10% discount rate. The Previous Report was prepared without depreciation. The inclusion of depreciation completed for income tax calculation purposes effected an approximately US $5 million per year positive adjustment to after tax cash flow. The Mongolian income tax is a two tier rate that makes for an approximate US $3 million decrease in net cash flow. Net annual cash flow decreased slightly in the PEA due to an increase in the total indirect costs from US $1.24 to US $1.60 per tonne to account for additional water usage fees determined and applied by the Mongolian government after the Previous Report was prepared. The final revised direct cost of materials and supplies was also decreased resulting in a net decrease in total direct costs from US $6.56 to US $6.30 per tonne. The PEA has also been amended to provide that the US $17.70 per tonne mine gate price has been determined in reliance on the terms of the Coal Supply Agreement. In addition, the PEA contains revised Certificates of Qualified Persons for its authors, has been revised to include cautionary language required by National Instrument 43-101, and reference to a Feasibility Study not supported by the report or filed on SEDAR has been removed.

Conclusion and Opportunity:

The financial evaluation indicates that the project is potentially economically viable given the coal price assumption of US $17.70 per tonne sold at the mine gate directly to the power plant. The coal price is fully indexed and will rise according to rising input costs such as fuel, labor, and parts. Therefore the coal project is expected to provide stable return throughout the life of mine. Furthermore, the mineral resource estimate covers only the Chandgana Tal mining licenses with potential to scale up the Chandgana power plant project and source additional coal supply from Chandgana Coal's nearby Khavtgai Uul coal deposit. An independent study sponsored by Asian Development Bank suggested a Mongolia power supply deficit of 600MW by 2016 and 900MW by 2019. This deficit could be satisfied by a scaled up Chandgana power plant.

The Company cautions that the PEA is preliminary in nature and has a degree of accuracy of plus or minus 35%.

The technical contents of this news release have been prepared under the supervision of by Christopher M. Kravits, P.Geo, General Mining Manager of Prophecy. Mr. Kravits is a Qualified Person as defined in NI 43-101 with 35 years of US and international relevant coal geology experience. He has been active in Mongolia since 2007.

The financial contents of this news release have been prepared under the supervision of John T Boyd Company and Robert J. Farmer, Lead Qualified Person on the revised PEA. Mr. Farmer is a Qualified Person as defined in NI 43-101.

About Prophecy Coal

Prophecy Coal Corp. is a Canadian company listed on the Toronto Stock Exchange engaged in developing energy projects in Mongolia. The Company's wholly-owned subsidiary Prophecy Power Generation LLC is advancing plans for a proposed 600 MW mine-mouth power plant, which has been permitted by the Mongolian government, adjacent to its Chandgana coal deposit. Substantially all of the Company's resources are not mineral reserves, hence they do not have demonstrated economic viability. The Company cautions the Chandgana project is in Mongolia and requires substantial capital to develop.

Further information on Prophecy Coal can be found at www.prophecycoal.com.

PROPHECY COAL CORP.

ON BEHALF OF THE BOARD

JOHN LEE, Executive Chairman

Neither the Toronto Stock Exchange nor its Regulation Services Provider (as that term is defined in the policies of the Toronto Stock Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note Regarding Forward-Looking Statements

Certain statements contained in this news release, including statements which may contain words such as "expects", "anticipates", "intends", "plans", "believes", "estimates", or similar expressions, and statements related to matters which are not historical facts, are forward-looking information within the meaning of applicable securities laws. Such forward-looking statements, which reflect management's expectations regarding Prophecy's future growth, results of operations, performance, business prospects and opportunities, are based on certain factors and assumptions and involve known and unknown risks and uncertainties which may cause the actual results, performance, or achievements to be materially different from future results, performance, or achievements expressed or implied by such forward-looking statements. These estimates and assumptions are inherently subject to significant business, economic, competitive and other uncertainties and contingencies, many of which, with respect to future events, are subject to change and could cause actual results to differ materially from those expressed or implied in any forward-looking statements made by Prophecy. In making forward-looking statements as may be included in this news release, Prophecy has made several assumptions that it believes are appropriate, including, but not limited to assumptions that: there being no significant disruptions affecting operations, such as due to labour disruptions; currency exchange rates being approximately consistent with current levels; certain price assumptions for coal, prices for and availability of fuel, parts and equipment and other key supplies remain consistent with current levels; production forecasts meeting expectations; the accuracy of Prophecy's current mineral resource estimates; labour and materials costs increasing on a basis consistent with Prophecy's current expectations; and that any additional required financing will be available on reasonable terms. Prophecy cannot assure you that any of these assumptions will prove to be correct.

Numerous factors could cause Prophecy's actual results to differ materially from those expressed or implied in the forward looking statements, including the following risks and uncertainties, which are discussed in greater detail under the heading "Risk Factors" in Prophecy's most recent Management Discussion and Analysis and Annual Information Form as filed on SEDAR and posted on Prophecy's website: Prophecy's history of net losses and lack of foreseeable cash flow; exploration, development and production risks, including risks related to the development of Prophecy Coal's Ulaan Ovoo coal property; Prophecy Coal not having a history of profitable mineral production; commencing mine development without a feasibility study; the uncertainty of mineral resource and mineral reserve estimates; the capital and operating costs required to bring Prophecy Coal's projects into production and the resulting economic returns from its projects; foreign operations and political conditions, including the legal and political risks of operating in Mongolia, which is a developing country and being subject to its local laws; the availability and timeliness of various government approvals and licences; the feasibility, funding and development of the Chandgana Power Plant; protecting title to Prophecy Coal's mineral properties; environmental risks; the competitive nature of the mining business; lack of infrastructure; Prophecy Coal's reliance on key personnel; uninsured risks; commodity price fluctuations; reliance on contractors; Prophecy Coal's need for substantial additional funding and the risk of not securing such funding on reasonable terms or at all; foreign exchange risk; anti-corruption legislation; recent global financial conditions; the payment of dividends; and conflicts of interest.

These factors should be considered carefully, and readers should not place undue reliance on the Prophecy's forward-looking statements. Prophecy believes that the expectations reflected in the forward-looking statements contained in this news release and the documents incorporated by reference herein are reasonable, but no assurance can be given that these expectations will prove to be correct. In addition, although Prophecy has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Prophecy undertakes no obligation to release publicly any future revisions to forward-looking statements to reflect events or circumstances after the date of this news or to reflect the occurrence of unanticipated events, except as expressly required by law.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
As enterprises work to take advantage of Big Data technologies, they frequently become distracted by product-level decisions. In most new Big Data builds this approach is completely counter-productive: it presupposes tools that may not be a fit for development teams, forces IT to take on the burden of evaluating and maintaining unfamiliar technology, and represents a major up-front expense. In his session at @BigDataExpo at @ThingsExpo, Andrew Warfield, CTO and Co-Founder of Coho Data, will dis...
SYS-CON Events announced today that Fusion, a leading provider of cloud services, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Fusion, a leading provider of integrated cloud solutions to small, medium and large businesses, is the industry's single source for the cloud. Fusion's advanced, proprietary cloud service platform enables the integration of leading edge solutions in the cloud, including clou...
As someone who has been dedicated to automation and Application Release Automation (ARA) technology for almost six years now, one of the most common questions I get asked regards Platform-as-a-Service (PaaS). Specifically, people want to know whether release automation is still needed when a PaaS is in place, and why. Isn't that what a PaaS provides? A solution to the deployment and runtime challenges of an application? Why would anyone using a PaaS then need an automation engine with workflow ...
With the Apple Watch making its way onto wrists all over the world, it’s only a matter of time before it becomes a staple in the workplace. In fact, Forrester reported that 68 percent of technology and business decision-makers characterize wearables as a top priority for 2015. Recognizing their business value early on, FinancialForce.com was the first to bring ERP to wearables, helping streamline communication across front and back office functions. In his session at @ThingsExpo, Kevin Roberts...
SYS-CON Events announced today that Commvault, a global leader in enterprise data protection and information management, has been named “Bronze Sponsor” of SYS-CON's 18th International Cloud Expo, which will take place on June 7–9, 2016, at the Javits Center in New York City, NY, and the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Commvault is a leading provider of data protection and information management...
Your business relies on your applications and your employees to stay in business. Whether you develop apps or manage business critical apps that help fuel your business, what happens when users experience sluggish performance? You and all technical teams across the organization – application, network, operations, among others, as well as, those outside the organization, like ISPs and third-party providers – are called in to solve the problem.
SYS-CON Events announced today that Alert Logic, Inc., the leading provider of Security-as-a-Service solutions for the cloud, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Alert Logic, Inc., provides Security-as-a-Service for on-premises, cloud, and hybrid infrastructures, delivering deep security insight and continuous protection for customers at a lower cost than traditional security solutions. Ful...
@DevOpsSummit taking place June 7-9, 2016 at Javits Center, New York City, and Nov 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with the 18th International @CloudExpo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. @DevOpsSummit at Cloud Expo New York Call for Papers is now open.
SYS-CON Events announced today that VAI, a leading ERP software provider, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. VAI (Vormittag Associates, Inc.) is a leading independent mid-market ERP software developer renowned for its flexible solutions and ability to automate critical business functions for the distribution, manufacturing, specialty retail and service sectors. An IBM Premier Business Part...
SYS-CON Events announced today that Catchpoint Systems, Inc., a provider of innovative web and infrastructure monitoring solutions, has been named “Silver Sponsor” of SYS-CON's DevOps Summit at 18th Cloud Expo New York, which will take place June 7-9, 2016, at the Javits Center in New York City, NY. Catchpoint is a leading Digital Performance Analytics company that provides unparalleled insight into customer-critical services to help consistently deliver an amazing customer experience. Designed...
Let’s face it, embracing new storage technologies, capabilities and upgrading to new hardware often adds complexity and increases costs. In his session at 18th Cloud Expo, Seth Oxenhorn, Vice President of Business Development & Alliances at FalconStor, will discuss how a truly heterogeneous software-defined storage approach can add value to legacy platforms and heterogeneous environments. The result reduces complexity, significantly lowers cost, and provides IT organizations with improved effi...
SYS-CON Events announced today that Pythian, a global IT services company specializing in helping companies adopt disruptive technologies to optimize revenue-generating systems, has been named “Bronze Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2015 at the Javits Center in New York, New York. Founded in 1997, Pythian is a global IT services company that helps companies compete by adopting disruptive technologies such as cloud, Big Data, advanced analytics, and DevO...
SYS-CON Events announced today that Men & Mice, the leading global provider of DNS, DHCP and IP address management overlay solutions, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. The Men & Mice Suite overlay solution is already known for its powerful application in heterogeneous operating environments, enabling enterprises to scale without fuss. Building on a solid range of diverse platform support,...
One of the bewildering things about DevOps is integrating the massive toolchain including the dozens of new tools that seem to crop up every year. Part of DevOps is Continuous Delivery and having a complex toolchain can add additional integration and setup to your developer environment. In his session at @DevOpsSummit at 18th Cloud Expo, Miko Matsumura, Chief Marketing Officer of Gradle Inc., will discuss which tools to use in a developer stack, how to provision the toolchain to minimize onboa...
The cloud promises new levels of agility and cost-savings for Big Data, data warehousing and analytics. But it’s challenging to understand all the options – from IaaS and PaaS to newer services like HaaS (Hadoop as a Service) and BDaaS (Big Data as a Service). In her session at @BigDataExpo at @ThingsExpo, Hannah Smalltree, a director at Cazena, will provide an educational overview of emerging “as-a-service” options for Big Data in the cloud. This is critical background for IT and data profes...