Platinum Group Reports Q2 2014 Financial and Operating Results

VANCOUVER, BRITISH COLUMBIA and JOHANNESBURG, SOUTH AFRICA -- (Marketwired) -- 04/11/14 -- Platinum Group Metals Ltd. (TSX:PTM)(NYSE MKT:PLG) ("Platinum Group" or the "Company") reports the Company's financial results for the six months ended February 28, 2014. For details of the consolidated financial statements (the "Financial Statements") and Management's Discussion and Analysis for the six months ended February 28, 2013 please see the Company's filings on SEDAR (www.sedar.com) or on EDGAR (www.sec.gov). Shareholders may request a copy of the complete Financial Statements from the Company free of charge and are encouraged to visit the Company's website at www.platinumgroupmetals.net.

The Company's cash position at February 28, 2014 was $203 million(1). The Company received net proceeds of $165 million on December 31, 2013 pursuant to the closing of a bought deal financing (see details below).

Platinum Group is focused on the construction of the WBJV Project 1 platinum mine ("Project 1") located near Rustenburg, South Africa. The Company is also focused on further exploration and initial engineering on the newly discovered Waterberg platinum deposit located near Mokopane, South Africa where the Company is the operator of the Waterberg Joint Venture Project (the "Waterberg JV Project") with the Japan Oil, Gas and Metals National Corporation ("JOGMEC") and Mnombo Wethu Consultants (Pty) Ltd. ("Mnombo"). The Company has also expanded its exploration on to prospecting rights covering 489 square kilometres immediately adjacent and north of the Waterberg JV Project property (the "Waterberg Extension Project").

At Project 1 the Company's owners' team oversees engineering, procurement, construction and management firm DRA Mineral Projects (Pty) Ltd. and underground mining contractor JIC Mining Services. Including subcontractors there are approximately 1,350 persons at present involved in underground development, mining and construction activities at Project 1.

Platinum Group is beginning a pre-feasibility study on the Waterberg JV Project with engineering firm WorleyParsons TWP while at the same time completing infill drilling on the project. In addition, 13 drill rigs are currently active on the Waterberg Extension Project and 1 rig is active on the Waterberg Joint Venture with the objective of expanding and upgrading the newly discovered Waterberg platinum deposit. An updated independent resource estimate for the Waterberg JV Project and an initial independent resource estimate for the Waterberg Extension Project are both expected for public release in the next few weeks.

(1) The Company holds cash in Canadian dollars, United States dollars and South African Rand, and changes in exchange rates may create variance in the cash holdings reported in Canadian dollars. All amounts herein are reported in Canadian dollars unless otherwise specified.

Recent Highlights


--  On March 4, 2014 the Company announced additional drilling results for
    the Waterberg Extension Project, confirming the extension of the
    Waterberg deposit northward on strike for approximately 4.5 km from the
    known 5.4 km long deposit on the Waterberg JV Project WE-022 intercepted
    56.02 metres assaying 3.18 g/t 3E ( 0.87 g/t Pt, 2.13 g/t Pd, 0.18 g/t
    including 22.00 metres assaying 4.11 g/t 3E (1.16 g/t Pt, 2.72 g/t Pd
    and 0.23 g/t Au). The drilling results confirmed the extension of the
    "Super F Zone" for an average intercept thickness of 31 meters and a
    true thickness of 24 meters in five drill intersections. 
    
--  On February 14, 2014 the Company announced a positive independent
    Preliminary Economic Assessment ("PEA") for the Waterberg JV Project.
    The PEA recommends the project advance to the pre-feasibility stage of
    development. Details of the PEA include: 
    
    --  Steady state production of 655,000 ounces of platinum, palladium and
        gold, "3E"; 
        
    --  A two year construction period planned in 2016 to 2018; 
        
    --  A Project post-tax NPV (7.5% discount rate) of 5.1 billion Rand or
        US$509 million (10R/US$); 
        
    --  Peak Funding of 8.85 billion Rand or US$ 885 million (10R/US$); 
        
    --  Major Risks to be assessed at pre-feasibility including smelting
        plans, water and power delivery and geotechnical work for mine
        design along with normal increased resource, metallurgical and cost
        confidence levels; and 
        
    --  Opportunities include significant resource expansion, optimization
        of mine plans, mine ramp up profiles, increased metallurgical
        recoveries and smelter terms and consideration of adjacent deposit
        exploration. 
        
        

See details and the risks and cautions to investors in the press release of February 14, 2013. The economic analysis is based on inferred resources and is preliminary in nature. Inferred resources are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the PEA will be realized. The estimates in this preliminary assessment are estimated at +/-30% accuracy on an engineering basis. The complete PEA technical report on the Waterberg Joint Venture property is filed on SEDAR (www.sedar.com).

The PEA was completed by international and South African engineering firm WorleyParsons. An NI 43-101 Technical report entitled "Waterberg Mineral Project Preliminary Economic Assessment" dated effective February 14, 2014 has been filed on SEDAR and was prepared by Dr. Michael Roberts, MSc, PhD, SAIMM of Worley Parsons TWP and Kenneth Lomberg, B.Sc. (Hons) Geology, B. Com., M. Eng. Pr.Sci.Nat., MGSSA, of Coffey Mining (SA) Pty Ltd.


--  On December 31, 2013 the Company closed a bought deal financing for
    148.5 million common shares of the Company at a price of $1.18 per share
    resulting in gross proceeds of $175.23 million. The offering closed
    December 31, 2013 with net proceeds to the Company after fees,
    commissions and costs of approximately $165 million. 
    
--  On December 9, 2013, the Company announced that Hole WE 08 at the
    Waterberg Extension Project returned preliminary assay values of 5.26
    grams/tonne "3E" platinum, palladium and gold (1.40g/t Pt, 3.59 g/t Pd
    and 0.27 g/t Au) over 53.22 metres (estimated true thickness of
    approximately 44 metres). Hole WE 08 is located approximately 340 metres
    northward along strike from previously announced hole WE 02 (15.63
    metres grading 3.16 g/t 3E, 1.11 Pt g/t, 1.92 g/t Pd, 0.13 g/t Au) and
    approximately 1,600 metres directly along strike from the Waterberg JV
    Project deposit. 
    
--  Drilling on the Waterberg Extension Project in November 2013 added 4.7
    kilometres of confirmed F zone mineralization to the north of the
    Waterberg platinum deposit area and has now identified 23 kilometres of
    new Bushveld Complex, including the initial 5.4 kilometre long Waterberg
    platinum deposit.  
    
--  On November 11, 2013, the Company announced a new mandate letter with
    Barclays Bank PLC, Absa Corporate and Investment Bank, a division of
    Absa Bank Limited, Caterpillar Financial SARL and Societe Generale
    Corporate & Investment Banking who have agreed to use commercially
    reasonable efforts to arrange a new project loan facility for up to US
    $195 million to continue development of the Project 1 platinum mine. The
    new mandate letter eliminates the involvement of Africa Wide Mineral
    Prospecting and Exploration (Pty) Limited ("Africa Wide"), a 100%
    subsidiary of Johannesburg Stock Exchange listed Wesizwe Platinum
    Limited and will build upon previous technical and legal due diligence,
    and is subject to the finalization of a facility agreement, among other
    conditions. 
    
--  On September 3, 2013, the Company announced an updated independent
    inferred resource estimate for the Waterberg JV Project of 167 million
    tonnes grading 3.26 grams per tonne of platinum, palladium and gold
    (0.98 g/t Pt, 1.97 g/t Pd, 0.32 g/t Au, Ken Lomberg QP) for a total of
    17.5 million ounces with significant copper and nickel credits. The
    estimate includes the "T1", "T2" and "F" layers in an extension of the
    Bushveld Complex discovered in late 2011. The shallowest edge of the
    known deposit is approximately 130 metres below surface with the
    resource estimate restricted to 1,000 metres vertical. (See report at
    www.sedar.com). 

Results For The Period

During the six months ended February 28, 2014, the Company had a net loss of $3.3 million (February 28, 2013 - net loss of $1.4 million). General and administrative expenses during the period were $4.5 million (February 28, 2013 - $4.2 million), gains on foreign exchange, due primarily to a stronger Rand at period end, were $0.75 million (February 28, 2013 -$1.52 million gain). Finance income consisting of interest earned and property rental fees in the period amounted to $2.7 million (February 28, 2013- $2.6 million). Net loss per share for the period amounted to $0.01 per share, as compared to a loss of $0.01 per share for the comparative period of fiscal 2013.

Accounts receivable at February 28, 2014 totalled $6.4 million while accounts payable and accrued liabilities amounted to $11.2 million. Accounts receivable were comprised primarily of value added taxes repayable to the Company in South Africa and amounts receivable from partners. Accounts payable included contract construction fees, drilling expenses, engineering fees, accrued professional fees and regular trade payables for ongoing exploration and development costs and administration.

Total expenditures by the Company for development and purchases of property and equipment for Project 1 during the period totaled approximately $65 million, before including the effects of foreign currency exchange rate fluctuations. Expenditures by the Company during the period for exploration on the Waterberg JV Project and the Waterberg Extension Project were approximately $4.7 million, with a further $0.5 million being funded for the Waterberg JV Project alone by joint venture partner, JOGMEC.

To date approximately 3.8 million man hours of construction work has been completed at the Project 1 platinum mine and approximately $281 million has been invested in construction, equipment and underground development. Underground development has reached the Merensky Reef, and initial mining blocks are in planning and early development. Stockpiling of early ore is underway. Crusher, mill and flotation circuit foundations are constructed to above ground level. Mill components have been ordered and are being fabricated with a number of items now complete. A 10MVA electrical supply was completed and energized in October. Two ventilation raises and fans are now functional. Underground mining of multiple declines and headings continues. Capital costs have generally been within budget, and first concentrate production is targeted for calendar fourth quarter of 2015. Underground development delays or delays in the delivery of key components or services could result in delays to the first concentrate production or ramp up.

On March 3, 2014 Africa Wide failed to pay approximately US $21.52 million for its share of a unanimously approved cash call. This follows their election on October 18, 2013 to not fund an approximate US $21.8 million cash call for their 26% share of a unanimously approved six month forward construction budget for Project 1. The Company estimates that Africa Wide will dilute to approximately a 17.1% holding in Maseve as a result of the second missed cash call. Africa Wide disagrees with the dilution calculation and the matter has been referred to binding arbitration which will confirm the dilution formula. The Company is currently working on a plan to sell Africa Wide's diluted interest in Maseve to qualified black economic empowerment partner Mnombo.

Outlook

The Company's key business objectives and Milestones for calendar 2014 are:


--  to build the WBJV Project 1 platinum mine safely and in accordance with
    the planned schedule and budget; 
    
--  to close the planned US $195 million new project loan facility, or
    complete an alternate financing for Project 1, in order to secure all of
    the funding required for the completion of Project 1, including mill
    completion, underground development and the establishment of sustained
    operations; 
    
--  the completion of a pre-feasibility study on the initial Waterberg JV
    Project deposit during calendar 2014 or early 2015; 
    
--  to continue exploration and definition drilling on the Waterberg JV
    Project and Waterberg Extension Project with eight or more drill rigs
    during 2014; 
    
--  to complete an updated independent resource estimate for the Waterberg
    JV project and complete an initial independent resource estimate for the
    Waterberg Extension Project; and 
    
--  to maintain and develop our strong relationship with JOGMEC and the new
    partner expected in June 2014 as a result of the current tender process
    for the transfer of JOGMEC's interest in the Waterberg Joint Venture. 

About Platinum Group Metals Ltd.

Platinum Group is based in Johannesburg, South Africa and Vancouver, Canada. The Company's business is currently focused on the construction of the Project 1 platinum mine and the exploration and initial engineering on the newly discovered Waterberg platinum deposit, where the Company is the operator of the Waterberg JV Project with JOGMEC and Mnombo. The Company has also expanded its exploration northward on to the Waterberg Extension Project. As a result of the resource scale and thickness of the Waterberg deposit, the Waterberg JV Project and the Waterberg Extension Project have increased in importance in the Company's business over the period.

Qualified Person

R. Michael Jones, P.Eng., the Company's President, Chief Executive Officer and a significant shareholder of the Company, is a non-independent qualified person as defined in National Instrument 43-101 Standards of Disclosure for Mineral Projects and is responsible for preparing the technical information contained in this news release.

On behalf of the Board of Platinum Group Metals Ltd.

Frank R. Hallam, CFO and Director

The Toronto Stock Exchange and the NYSE MKT LLC have not reviewed and do not accept responsibility for the accuracy or adequacy of this news release, which has been prepared by management.

This press release contains forward-looking information within the meaning of Canadian securities laws and forward-looking statements within the meaning of U.S. securities laws ("forward-looking statements"). Forward-looking statements are typically identified by words such as: believe, expect, anticipate, intend, estimate, plans, postulate and similar expressions, or are those, which, by their nature, refer to future events. All statements that are not statements of historical fact are forward-looking statements. Forward-looking statements in this press release include, without limitation, statements regarding the completion of the New Project Loan Facility, the Company's ability to secure alternative financing, the Company's plans with respect to future exploration, development and production on the Company's projects including mine construction at Project 1, the dilution of Africa Wide's interest in Maseve and the ability of the Company to sell such diluted interest to another bona fide black economic empowerment partner. Although the Company believes the forward-looking statements in this press release are reasonable, it can give no assurance that the expectations and assumptions in such statements will prove to be correct. The Company cautions investors that any forward-looking statements by the Company are not guarantees of future results or performance, and that actual results may differ materially from those in forward looking statements as a result of various factors, including, but not limited to, variations in market conditions; the nature, quality and quantity of any mineral deposits that may be located; metal prices; other prices and costs; currency exchange rates; the Company's ability to obtain any necessary permits, consents or authorizations required for its activities; the Company's ability to access further funding and produce minerals from its properties successfully or profitably, to continue its projected growth, or to be fully able to implement its business strategies and other risk factors described in the Company's Form 40-F annual report, annual information form and other filings with the SEC and Canadian securities regulators, which may be viewed at www.sec.gov and www.sedar.com, respectively.

Cautionary Note to U.S. Investors Regarding Estimates of Inferred Mineral Resources

This press release uses the terms "inferred mineral resources." We advise U.S. investors that while these terms are recognized and required by Canadian regulations, the SEC does not recognize them. "Inferred mineral resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an "inferred mineral resource" will ever be upgraded to a higher category. Under Canadian rules, estimates of "inferred mineral resources" may not form the basis of a feasibility study or prefeasibility studies, except in rare cases. The SEC normally only permits issuers to report mineralization that does not constitute "reserves" as in-place tonnage and grade without reference to unit measures. U.S. investors are cautioned not to assume that any part or all of an inferred resource exists or is economically or legally mineable.

Contacts:
Platinum Group Metals Ltd.
R. Michael Jones
President
(604) 899-5450 or Toll Free: (866) 899-5450

Platinum Group Metals Ltd.
Kris Begic
VP, Corporate Development
(604) 899-5450 or Toll Free: (866) 899-5450
www.platinumgroupmetals.net

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
"IoT is going to be a huge industry with a lot of value for end users, for industries, for consumers, for manufacturers. How can we use cloud to effectively manage IoT applications," stated Ian Khan, Innovation & Marketing Manager at Solgeniakhela, in this SYS-CON.tv interview at @ThingsExpo, held November 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA.
Successful digital transformation requires new organizational competencies and capabilities. Research tells us that the biggest impediment to successful transformation is human; consequently, the biggest enabler is a properly skilled and empowered workforce. In the digital age, new individual and collective competencies are required. In his session at 19th Cloud Expo, Bob Newhouse, CEO and founder of Agilitiv, drew together recent research and lessons learned from emerging and established compa...
Enterprise IT has been in the era of Hybrid Cloud for some time now. But it seems most conversations about Hybrid are focused on integrating AWS, Microsoft Azure, or Google ECM into existing on-premises systems. Where is all the Private Cloud? What do technology providers need to do to make their offerings more compelling? How should enterprise IT executives and buyers define their focus, needs, and roadmap, and communicate that clearly to the providers?
Financial Technology has become a topic of intense interest throughout the cloud developer and enterprise IT communities. Accordingly, attendees at the upcoming 20th Cloud Expo at the Javits Center in New York, June 6-8, 2017, will find fresh new content in a new track called FinTech.
Bert Loomis was a visionary. This general session will highlight how Bert Loomis and people like him inspire us to build great things with small inventions. In their general session at 19th Cloud Expo, Harold Hannon, Architect at IBM Bluemix, and Michael O'Neill, Strategic Business Development at Nvidia, discussed the accelerating pace of AI development and how IBM Cloud and NVIDIA are partnering to bring AI capabilities to "every day," on-demand. They also reviewed two "free infrastructure" pr...
Information technology is an industry that has always experienced change, and the dramatic change sweeping across the industry today could not be truthfully described as the first time we've seen such widespread change impacting customer investments. However, the rate of the change, and the potential outcomes from today's digital transformation has the distinct potential to separate the industry into two camps: Organizations that see the change coming, embrace it, and successful leverage it; and...
"Coalfire is a cyber-risk, security and compliance assessment and advisory services firm. We do a lot of work with the cloud service provider community," explained Ryan McGowan, Vice President, Sales (West) at Coalfire Systems, Inc., in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
"Dice has been around for the last 20 years. We have been helping tech professionals find new jobs and career opportunities," explained Manish Dixit, VP of Product and Engineering at Dice, in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
Get deep visibility into the performance of your databases and expert advice for performance optimization and tuning. You can't get application performance without database performance. Give everyone on the team a comprehensive view of how every aspect of the system affects performance across SQL database operations, host server and OS, virtualization resources and storage I/O. Quickly find bottlenecks and troubleshoot complex problems.
SYS-CON Events announced today that Dataloop.IO, an innovator in cloud IT-monitoring whose products help organizations save time and money, has been named “Bronze Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Dataloop.IO is an emerging software company on the cutting edge of major IT-infrastructure trends including cloud computing and microservices. The company, founded in the UK but now based in San Fran...
"We are a custom software development, engineering firm. We specialize in cloud applications from helping customers that have on-premise applications migrating to the cloud, to helping customers design brand new apps in the cloud. And we specialize in mobile apps," explained Peter Di Stefano, Vice President of Marketing at Impiger Technologies, in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
Rapid innovation, changing business landscapes, and new IT demands force businesses to make changes quickly. In the eyes of many, containers are at the brink of becoming a pervasive technology in enterprise IT to accelerate application delivery. In this presentation, attendees learned about the: The transformation of IT to a DevOps, microservices, and container-based architecture What are containers and how DevOps practices can operate in a container-based environment A demonstration of how ...
President Obama recently announced the launch of a new national awareness campaign to "encourage more Americans to move beyond passwords – adding an extra layer of security like a fingerprint or codes sent to your cellphone." The shift from single passwords to multi-factor authentication couldn’t be timelier or more strategic. This session will focus on why passwords alone are no longer effective, and why the time to act is now. In his session at 19th Cloud Expo, Chris Webber, security strateg...
"At ROHA we develop an app called Catcha. It was developed after we spent a year meeting with, talking to, interacting with senior citizens watching them use their smartphones and talking to them about how they use their smartphones so we could get to know their smartphone behavior," explained Dave Woods, Chief Innovation Officer at ROHA, in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events has announced today that Roger Strukhoff has been named conference chair of Cloud Expo and @ThingsExpo 2017 New York. The 20th Cloud Expo and 7th @ThingsExpo will take place on June 6-8, 2017, at the Javits Center in New York City, NY. "The Internet of Things brings trillions of dollars of opportunity to developers and enterprise IT, no matter how you measure it," stated Roger Strukhoff. "More importantly, it leverages the power of devices and the Internet to enable us all to im...