TORONTO, ONTARIO -- (Marketwired) -- 04/11/14 -- Petrolympic Ltd. ("Petrolympic" or the "Company") (TSX VENTURE:PCQ) is pleased to announce the results of an independent resource evaluation carried out by Sproule Associates Limited ("Sproule") on a structure drilled on its joint venture property in the Lower St. Lawrence area (the "Property") located in the Appalachian Basin of Quebec. Sproule conducted its evaluation according to the Canadian Oil and Gas Evaluation Handbook reserve and resource definitions. The Company holds an interest in 431,339 hectares (1,065,839 acres) of the Property through a joint-venture with Squatex Energy and Resources Inc. ("Squatex"), the operator on the Property.

The results of this independent evaluation (as shown in Table 1 below) are based on the data gathered when drilling the Masse No.1 core hole. The results of the evaluation builds on the data released by Petrolympic in it's press release dated November 15, 2013 (filed on www.sedar.com). Paul Laroche, a geologist with Petrolympic provides the following comments: "The well revealed a reservoir hosted in the Silurian Sayabec Formation and consisting of a 10 meter-thick interval of hydrothermally dolomitized limestone with high porosity and permeability values up to 20.8% and 1624 mD, respectively (as shown in Table 2 below). Contrary to shale gas, these types of reservoirs do not require hydraulic fracturation. The analysis of the gas charge of the reservoir indicated it is composed of 89% methane and devoid from hydrogen sulfide."

Jean-Claude Caron, President of Squatex draws a comparison between the Property and St. Flavien reservoir in the St. Lawrence Lowlands - one of the only two reservoirs that have produced natural gas in economic quantities in Quebec: "The parameters reported from Masse No.1 core hole are similar to St. Flavien reservoir, which is also hosted in hydrothermally dolomitized limestone with thickness varying between 1 and 8 meters, porosity values ranging from 2.5-10% (average between 3-5%). St. Flavien reservoir has produced 5.7BCFG prior to being converted into an underground gas storage facility that is still in operation since 1998."

The results obtained by Petrolympic and Squatex in the Lower St. Lawrence are encouraging and present additional opportunities since the evaluation is focused on only one of the three hydrocarbon-bearing zones identified in the well. Furthermore, several seismic anomalies with characteristics similar to Masse No.1 core hole have also been highlighted by the proprietary seismic data within the limits of the Property. This is not included in the Sproule resource evaluation and presents significant upside to the potential of the Property, further validating the pioneering efforts of Petrolympic and Squatex in exploring the potential of the area.

Petrolympic and their partner Squatex are now designing a drilling program to validate the potential of the Masse Structure, and are preparing an exploration program to further document and test other prospective structures identified within the Property."The timing is right for demonstrating the producibility of a natural gas conventional reservoir in the Lower St. Lawrence, since economic growth in the area will be likely stimulated by the recent election of a majority government in the province, and clean energy sources will be in high demand on close local markets", says Mendel Ekstein, President and CEO of Petrolympic.

Petrolympic also owns a 100% interest in two exploration permits in the same area, referred to as the Matapedia and the Mitis properties. Several conventional plays and exploration leads have been identified in these permits where oil and gas have been encountered in mining wells in the 90's. Based on proprietary seismic data, the prospective Sayabec Formation is also believed to be present at depth in these two permits.

Table 1: Results of the resource evaluation as presented in Sproule's report.

----------------------------------------------------------------------------
                                  Table S-2                                 
 Summary of Project Gross Unrisked Undiscovered Unrecoverable Gas Initially-
                               in-Place (GIIP)                              
 Sayabec Formation of the Masse Structure, Lower St. Lawrence Area, Quebec, 
   Canada(1,2) Estimated by Sproule Associates Limited, As of February 28,  
                                     2014                                   
----------------------------------------------------------------------------
Structure     Formation                       Gas (BCF)(2,3)                
                             -----------------------------------------------
                                Low(4)  Best(5)  High(6)             Mean(7)
                             ---------------------------                    
                                 (P90)    (P50)    (P10)                    
----------------------------------------------------------------------------
Masse         Sayabec                3        8       26                  12
----------------------------------------------------------------------------
1.   Undiscovered Petroleum Initially-in-place (equivalent to undiscovered  
     resources) is the quantity of petroleum that is estimated, on a given  
     date, to be contained in accumulations yet to be discovered. The       
     recoverable portion of undiscovered petroleum initially in place is    
     referred to as "prospective resources", the remainder as               
     "unrecoverable". Only the in-place volumes are presented here as a     
     development project to recover any hydrocarbons discovered has not been
     defined. There is no certainty that any portion of these unrisked      
     undiscovered GIIP will be discovered and, if discovered, there is no   
     certainty that it will be developed or, if it is developed, there is no
     certainty as to either the timing of such development or whether it    
     will be commercially viable to produce any portion of these resources. 
                                                                            
2.   These are the project gross unrisked undiscovered petroleum initially  
     in place volumes (i.e. 100% project gross) estimated for the Sayabec   
     Formation of the Masse Structure without any adjustments for working   
     interest and before deduction of any royalties.                        
                                                                            
3.   "BCF" is billions of cubic feet, "MMboe" is millions of barrels of oil 
     equivalent.                                                            
                                                                            
4.   Low Estimate is considered to be a conservative estimate of the        
     quantity that will actually be in-place. It is likely that the actual  
     remaining quantities in-place will exceed the low estimate. If         
     probabilistic methods are used, there should be at least a 90 percent  
     probability (P90) that the quantities actually in-place will equal or  
     exceed the low estimate.                                               
                                                                            
5.   Best Estimate is considered to be the best estimate of the quantity    
     that will actually be in-place. It is equally likely that the actual   
     remaining quantities in-place will be greater or less than the best    
     estimate. If probabilistic methods are used, there should be at least a
     50 percent probability (P50) that the quantities actually in-place will
     equal or exceed the best estimate.                                     
                                                                            
6.   High Estimate is considered to be an optimistic estimate of the        
     quantity that will actually be in-place. It is unlikely that the actual
     remaining quantities in-place will exceed the high estimate. If        
     probabilistic methods are used, there should be at least a 10 percent  
     probability (P10) that the quantities actually in-place will equal or  
     exceed the high estimate.                                              
                                                                            
7.   Statistical aggregation is the process of probabilistically aggregating
     distributions that represent estimates of resource quantities at the   
     reservoir, prospect, or portfolio level. Arithmetic summation and      
     statistical aggregation of the means yield similar results. Arithmetic 
     summation of the Low Estimate, Best Estimate and High Estimate are not 
     statistically appropriate. Both the statistical and arithmetic         
     summation of the unrisked prospects may be misleading because it       
     assumes success for each of the prospect entities. The chance of this  
     occurring is extremely unlikely. Actual recovery is likely to be less  
     and may be zero.                                                       

Table 2: Core laboratory analyses from the Masse No.1 core hole, as reviewed by Sproule and used as input parameters in the resource evaluation.

----------------------------------------------------------------------------
SQUATEX RESSOURCE ET ENERGIE SQUATEX MASSE #1                               
                                                                            
Field :                                                   Formation :       
                                                                            
Province : QUEBEC                                         Coring equip :    
                                                                            
                                                          Coring fluid :    
License :                                                 WATER BASE MUD    
                                                                            
                            CORE ANALYSIS RESULTS                           
----------------------------------------------------------------------------
                                              PERMEABILITY      PERMEABILITY
                                                 (MAXIMUM)          (90 DEG)
                         DEPTH  SAMPLE LENGTH         Kair              Kair
SAMPLE NUMBER                m              m           mD                mD
----------------------------------------------------------------------------
FD 1                   1845.20           0.11         0.02              0.01
FD 2                   1847.10           0.07         1624              1584
FD 3                   1848.00           0.09         0.01              0.01
FD 4                   1856.00           0.05         0.06              0.02
                                                less than                 
FD 5                   1873.50           0.04         0.01   less than 0.01
                                                                            
Results of five core sample analyses for the Masse # 1 well. The Company    
 determined an average porosity estimate of 4,1% for the dolomitized zone of
 interest using results from Samples FD-1 (1,845.2 m; 3,7%), FD-2 (1,847.1  
 m; 20,8%), and FD-3 (1,848.0 m;1,3%). A porosity of 4,1% over a net pay    
 thickness of 5 m (4,7m = approx. 3%; 0,3 m = 20,8%) is a mathematical      
 average that assumes the Masse # 1 well is representative of the average   
 petrophysical characteristics for the entire Masse Structure - which in    
 reality is likely not the case (Estimation du Gaz en Place - Structure     
 Masse, September 2013).                                                    
----------------------------------------------------------------------------

----------------------------------------------------------------------------
SQUATEX RESSOURCE ET ENERGIE                                                
 SQUATEX MASSE #1           File No. : 52131-13-0145                        
                                                                            
Field :         Formation :            Date : 2013-07-26                    
                                                                            
Province :                                                                  
 QUEBEC         Coring equip :         Analysts : DJB                       
                                                                            
                Coring fluid : WATER                                        
License :       BASE MUD               Core Dia : 48 mm                     
                                                                            
                            CORE ANALYSIS RESULTS                           
----------------------------------------------------------------------------
                PERMEABILITY                                                
                  (VERTICAL)   POROSITY       BULK     GRAIN                
                        Kair   (HELIUM)    DENSITY   DENSITY                
SAMPLE NUMBER             mD   fraction    (kg/m3)   (kg/m3)     DESCRIPTION
----------------------------------------------------------------------------
                  less than                                               
FD 1                    0.01      0.037       2710      2810 dol i ppv sv mv
                  less than                                               
FD 2                    0.01      0.208       2220      2800    dol i ppv sv
                  less than                                               
FD 3                    0.01      0.013       2780      2810        dol i sv
FD 4                    0.02      0.007       2640      2660   ss vf f vfrac
                  less than                                               
FD 5                    0.01      0.002       2640      2640         ss vf f
                                                                            
Results of five core sample analyses for the Masse # 1 well. The Company    
 determined an average porosity estimate of 4,1% for the dolomitized zone of
 interest using results from Samples FD-1 (1,845.2 m; 3,7%), FD-2 (1,847.1  
 m; 20,8%), and FD-3 (1,848.0 m;1,3%). A porosity of 4,1% over a net pay    
 thickness of 5 m (4,7m = approx. 3%; 0,3 m = 20,8%) is a mathematical      
 average that assumes the Masse # 1 well is representative of the average   
 petrophysical characteristics for the entire Masse Structure - which in    
 reality is likely not the case (Estimation du Gaz en Place - Structure     
 Masse, September 2013).                                                    
----------------------------------------------------------------------------

About Petrolympic Ltd.

Petrolympic Ltd. is a Canadian junior oil and gas company actively exploring for premium light crude oil and natural gas in North America. The Company is presently focused on its near-term oil production asset in the prolific Maverick Basin of Texas, USA. The Company also holds an interest in a total of 754,216 hectares (1,863,668 acres) of oil and gas exploration permits in the Appalachian Basin of Quebec that include holdings in the St. Lawrence Lowlands and Gaspe Peninsula. The Company's holdings in the St. Lawrence Lowlands consist of a 30% interest in 217,370 hectares (536,941 acres) through a joint venture with Squatex Energy and Resources Inc. ("Squatex"), a 12% interest in 8,000 hectares (19,768 acres) through the Farmout Agreement with Canbriam Energy Inc., and a 100% interest in 56,622 hectares (139,913 acres) located over the Lowlands shallow carbonates platform on the south shore of the St. Lawrence River, less than 30 kilometers southwest of Montreal. These properties represent a major position in the Utica Lorraine and Trenton-Black River Plays. Petrolympic also maintains holdings in the Gaspe and Lower St. Lawrence regions, including a 30% interest in 431,339 hectares (1,065,839 acres) through a joint venture with Squatex and a 100% interest in a block of exploration permits totalling 40,885 hectares (101,029 acres) located between Rimouski and Matane prospective for hydrothermal dolomite hosted light oil.

About Squatex Energy and Resources Inc.

Squatex Energy and Resources Inc. ("Squatex") is an oil and gas exploration company created in on April 12, 2002 under the Canada Business Corporation Act having its main office located at 7055, Boul. Taschereau, suite 500, Brossard (Quebec) J4Z 1A7. Squatex is a reporting issuer only in the province of Quebec. Its shares are not traded in any formally organized stock exchange market. The main objective of Squatex is, as the operator, to carry out exploration work in order to evaluate the oil and gas potential of a territory under leases covering 656,093 hectares. Squatex owns in the St. Lawrence Lowlands a 70% interest over 217,370 hectares under a joint venture agreement with Petrolympic Ltd. (TSX VENTURE:PCQ) and a 28% interest over 8,000 hectares that were farmed out to Canbriam Energy Inc. Squatex also owns a 70% interest over 431,339 hectares in the Lower St. Lawrence under its joint operation agreement with Petrolympic Ltd.

Forward-Looking Statements

This press release includes certain "forward-looking information" within the meaning of the Securities Act (Ontario), including, but not limited to, statements as to timing and extent of exploration programs and the availability of exploration results. As such, forward-looking information addresses future events and conditions and so involves inherent risks and uncertainties, as disclosed under the heading "Risk Factors" and elsewhere in Petrolympic documents filed from time to time with the Ontario Securities Commission and other regulatory authorities. Actual results could differ significantly from those currently projected as a result of, among those factors, adverse weather, regulatory changes, delays in receiving permits, accidents and delays in completing exploration activities not all of which are in the control of Petrolympic. The forward-looking information contained herein is Petrolympic's reasonable estimate today of future events and conditions, but no assurance can be given that such events or conditions will occur. The reader is cautioned not to rely on these forward-looking statements. Petrolympic disclaims any obligation to update these forward-looking statements.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
Petrolympic Ltd.
Mendel Ekstein
President and CEO
(845) 656-0184
[email protected]

Squatex Energy and Resources Inc.
Jean-Claude Caron
President and CEO
(819) 929-3758
[email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
DX World EXPO, LLC, a Lighthouse Point, Florida-based startup trade show producer and the creator of "DXWorldEXPO® - Digital Transformation Conference & Expo" has announced its executive management team. The team is headed by Levent Selamoglu, who has been named CEO. "Now is the time for a truly global DX event, to bring together the leading minds from the technology world in a conversation about Digital Transformation," he said in making the announcement.
"Space Monkey by Vivent Smart Home is a product that is a distributed cloud-based edge storage network. Vivent Smart Home, our parent company, is a smart home provider that places a lot of hard drives across homes in North America," explained JT Olds, Director of Engineering, and Brandon Crowfeather, Product Manager, at Vivint Smart Home, in this SYS-CON.tv interview at @ThingsExpo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today that Conference Guru has been named “Media Sponsor” of the 22nd International Cloud Expo, which will take place on June 5-7, 2018, at the Javits Center in New York, NY. A valuable conference experience generates new contacts, sales leads, potential strategic partners and potential investors; helps gather competitive intelligence and even provides inspiration for new products and services. Conference Guru works with conference organizers to pass great deals to gre...
DevOps is under attack because developers don’t want to mess with infrastructure. They will happily own their code into production, but want to use platforms instead of raw automation. That’s changing the landscape that we understand as DevOps with both architecture concepts (CloudNative) and process redefinition (SRE). Rob Hirschfeld’s recent work in Kubernetes operations has led to the conclusion that containers and related platforms have changed the way we should be thinking about DevOps and...
The Internet of Things will challenge the status quo of how IT and development organizations operate. Or will it? Certainly the fog layer of IoT requires special insights about data ontology, security and transactional integrity. But the developmental challenges are the same: People, Process and Platform. In his session at @ThingsExpo, Craig Sproule, CEO of Metavine, demonstrated how to move beyond today's coding paradigm and shared the must-have mindsets for removing complexity from the develop...
In his Opening Keynote at 21st Cloud Expo, John Considine, General Manager of IBM Cloud Infrastructure, led attendees through the exciting evolution of the cloud. He looked at this major disruption from the perspective of technology, business models, and what this means for enterprises of all sizes. John Considine is General Manager of Cloud Infrastructure Services at IBM. In that role he is responsible for leading IBM’s public cloud infrastructure including strategy, development, and offering m...
The next XaaS is CICDaaS. Why? Because CICD saves developers a huge amount of time. CD is an especially great option for projects that require multiple and frequent contributions to be integrated. But… securing CICD best practices is an emerging, essential, yet little understood practice for DevOps teams and their Cloud Service Providers. The only way to get CICD to work in a highly secure environment takes collaboration, patience and persistence. Building CICD in the cloud requires rigorous ar...
Companies are harnessing data in ways we once associated with science fiction. Analysts have access to a plethora of visualization and reporting tools, but considering the vast amount of data businesses collect and limitations of CPUs, end users are forced to design their structures and systems with limitations. Until now. As the cloud toolkit to analyze data has evolved, GPUs have stepped in to massively parallel SQL, visualization and machine learning.
"Evatronix provides design services to companies that need to integrate the IoT technology in their products but they don't necessarily have the expertise, knowledge and design team to do so," explained Adam Morawiec, VP of Business Development at Evatronix, in this SYS-CON.tv interview at @ThingsExpo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
To get the most out of their data, successful companies are not focusing on queries and data lakes, they are actively integrating analytics into their operations with a data-first application development approach. Real-time adjustments to improve revenues, reduce costs, or mitigate risk rely on applications that minimize latency on a variety of data sources. In his session at @BigDataExpo, Jack Norris, Senior Vice President, Data and Applications at MapR Technologies, reviewed best practices to ...
Widespread fragmentation is stalling the growth of the IIoT and making it difficult for partners to work together. The number of software platforms, apps, hardware and connectivity standards is creating paralysis among businesses that are afraid of being locked into a solution. EdgeX Foundry is unifying the community around a common IoT edge framework and an ecosystem of interoperable components.
"ZeroStack is a startup in Silicon Valley. We're solving a very interesting problem around bringing public cloud convenience with private cloud control for enterprises and mid-size companies," explained Kamesh Pemmaraju, VP of Product Management at ZeroStack, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
Large industrial manufacturing organizations are adopting the agile principles of cloud software companies. The industrial manufacturing development process has not scaled over time. Now that design CAD teams are geographically distributed, centralizing their work is key. With large multi-gigabyte projects, outdated tools have stifled industrial team agility, time-to-market milestones, and impacted P&L stakeholders.
"Akvelon is a software development company and we also provide consultancy services to folks who are looking to scale or accelerate their engineering roadmaps," explained Jeremiah Mothersell, Marketing Manager at Akvelon, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
Enterprises are adopting Kubernetes to accelerate the development and the delivery of cloud-native applications. However, sharing a Kubernetes cluster between members of the same team can be challenging. And, sharing clusters across multiple teams is even harder. Kubernetes offers several constructs to help implement segmentation and isolation. However, these primitives can be complex to understand and apply. As a result, it’s becoming common for enterprises to end up with several clusters. Thi...