Pretium Resources Inc.: Brucejack Project Update

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 04/16/14 -- Pretium Resources Inc. (TSX: PVG)(NYSE: PVG) ("Pretivm") is pleased to announce the following update on its activities underway and planned for 2014 at its high-grade gold Brucejack Project.

Permitting

Pretivm expects to file its Environmental Assessment Certificate application ("EAC application") this quarter once it receives the final Application Information Requirements from the British Columbia Environmental Assessment Office ("BCEAO"), which is expected shortly. Once filed, the application will be evaluated for completeness over a 30-day period by BCEAO with the involvement of a working group including representatives of First Nations and local governments and other government agencies. Once the application has been accepted, the BCEAO has a maximum of 180 days to complete its review and prepare an assessment report for a decision by the Minister of Environment and the Minister of Energy and Mines.

In coordination with the provincial permitting process, the Canadian Environmental Assessment Agency will review the Environmental Impact Statement ("EIS") which Pretivm will submit concurrently with the provincial EAC application. Provincial and federal approval of the EAC application and EIS, respectively, allow for the issuance of the statutory permits and authorizations to begin construction of a mine at Brucejack.

Feasibility Study

Work to update the Brucejack Project feasibility study has been ongoing, with the mine plan and mining stopes now updated to incorporate the revised economic parameters of $1,100/oz gold, $17/oz silver and $0.92 CAD:US exchange rate. Based on this work, the production rate of 2,700 tonnes per day has been confirmed. Other updates include equipment and materials pricing to the second quarter, and the update of labour rates, schedule and productivity. The amended Brucejack Project feasibility study is on track for completion in June.

On completion of the amended feasibility study, basic engineering will commence in the third quarter, including the order of long-lead items to facilitate the start of construction once permits for the Project have been received.

Exploration

Subsequent to the bulk sample program, underground exploration in the Valley of the Kings was undertaken to assess the geological nature of the stockwork mineralization between the dominant east-west system and the north-south Cleopatra structure in the area of the 426615E cross-cut and 615 lateral. Non-selective material, which featured visible gold to varying degrees, was bagged from the blast rounds from benching (rounds of 3 meters by 2 meters and ranging in length from 10 to 15 meters), and from raising (rounds of 1.5 meters by 1 meter by 2 meters). The gold mineralization was hosted in variably-oriented parts of the system, and not limited to a single structural feature.

In February 2014, 1,000 tonnes of the bagged material from the 2013 Valley of the Kings exploration was processed at the Contact Mill in Montana. From the production of gravity and flotation concentrates we have recovered approximately 3,120 ounces of gold. The bulk of the assays have been received to date from Inspectorate America Corporation, and final gold production remains subject to remaining assays and final establishment of weights and assays and settlement.

The Valley of Kings hosts Measured and Indicated gold resources of 8.7 million ounces (15.3 million tonnes grading 17.6 grams per tonne gold).

A portion of the proceeds from this one-time production will be used to fund initiatives in northern British Columbia promoting community development. Under British Columbia's Mineral Tenure Act regulations, we are permitted to process up to 1,000 tonnes per year per claim unit. We will evaluate the potential for the production of 1,000 tonnes of selective high-grade material later in the year.

Crews are mobilizing to site to commence the 2014 exploration program at Brucejack which has been planned with a focus on continued resource definition in the Valley of the Kings, and which includes 15,000 meters of underground infill and step-out drilling to the east and west. The design of an access ramp from the 1345-meter level access ramp to the 1260-meter level is now being finalized.

Ian I Chang, M.A.Sc., P.Eng., Vice President, Project Development, Pretium Resources Inc. is the Qualified Person (QP) responsible for Brucejack Project development. Kenneth C. McNaughton, M.A.Sc., P.Eng., Chief Exploration Officer, Pretium Resources Inc. is the Qualified Person (QP) responsible for the Brucejack Project exploration program.

About Pretivm

Pretivm is creating value through gold at its high-grade gold Brucejack Project, located in northern British Columbia. Permitting of a high-grade underground gold mine at Brucejack is underway, with commercial production targeted to commence in 2016.

Forward-Looking Statements

This News Release contains "forward-looking information" and "forward-looking statements" within the meaning of applicable Canadian and United States securities legislation. Forward-looking information may include, but is not limited to, risks related to information with respect to our planned exploration and development activities, the adequacy of Pretivm's financial resources, the estimation of mineral reserves and resources including the 2013 Valley of the Kings Mineral Resource estimate, realization of mineral reserve and resource estimates and timing of development of Pretivm's Brucejack Project, costs and timing of future exploration, results of future exploration and drilling, production and processing estimates, capital and operating cost estimates, timelines and similar statements relating to the economic viability of the Brucejack Project, timing and receipt of approvals, consents and permits under applicable legislation, Pretivm's executive compensation approach and practice, and adequacy of financial resources. Wherever possible, words such as "plans", "expects", "projects", "assumes", "budget", "strategy", "scheduled", "estimates", "forecasts", "anticipates", "believes", "intends", "targets" and similar expressions or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative forms of any of these terms and similar expressions, have been used to identify forward-looking statements and information. Statements concerning mineral reserve and resource estimates may also be deemed to constitute forward-looking information to the extent that they involve estimates of the mineralization that will be encountered if the property is developed. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be forward-looking information.

Forward-looking information is subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ from those expressed or implied by the forward-looking information, including, without limitation, those risks identified in Pretivm's Annual Information Form dated March 31, 2014 filed on SEDAR at www.sedar.com and in the United States on Form 40-F through EDGAR at the SEC's website at www.sec.gov. Forward-looking information is based on the expectations and opinions of Pretivm's management on the date the statements are made. The assumptions used in the preparation of such statements, although considered reasonable at the time of preparation, may prove to be imprecise. We do not assume any obligation to update forward-looking information, whether as a result of new information, future events or otherwise, other than as required by applicable law. For the reasons set forth above, prospective investors should not place undue reliance on forward-looking information. Neither the TSX nor the NYSE has approved or disapproved of the information contained herein.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Advances in technology and ubiquitous connectivity have made the utilization of a dispersed workforce more common. Whether that remote team is located across the street or country, management styles/ approaches will have to be adjusted to accommodate this new dynamic. In his session at 17th Cloud Expo, Sagi Brody, Chief Technology Officer at Webair Internet Development Inc., focused on the challenges of managing remote teams, providing real-world examples that demonstrate what works and what do...
It's easy to assume that your app will run on a fast and reliable network. The reality for your app's users, though, is often a slow, unreliable network with spotty coverage. What happens when the network doesn't work, or when the device is in airplane mode? You get unhappy, frustrated users. An offline-first app is an app that works, without error, when there is no network connection.
Father business cycles and digital consumers are forcing enterprises to respond faster to customer needs and competitive demands. Successful integration of DevOps and Agile development will be key for business success in today’s digital economy. In his session at DevOps Summit, Pradeep Prabhu, Co-Founder & CEO of Cloudmunch, covered the critical practices that enterprises should consider to seamlessly integrate Agile and DevOps processes, barriers to implementing this in the enterprise, and pr...
In most cases, it is convenient to have some human interaction with a web (micro-)service, no matter how small it is. A traditional approach would be to create an HTTP interface, where user requests will be dispatched and HTML/CSS pages must be served. This approach is indeed very traditional for a web site, but not really convenient for a web service, which is not intended to be good looking, 24x7 up and running and UX-optimized. Instead, talking to a web service in a chat-bot mode would be muc...
More and more companies are looking to microservices as an architectural pattern for breaking apart applications into more manageable pieces so that agile teams can deliver new features quicker and more effectively. What this pattern has done more than anything to date is spark organizational transformations, setting the foundation for future application development. In practice, however, there are a number of considerations to make that go beyond simply “build, ship, and run,” which changes ho...
SYS-CON Events announced today that Interoute, owner-operator of one of Europe's largest networks and a global cloud services platform, has been named “Bronze Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2015 at the Javits Center in New York, New York. Interoute is the owner-operator of one of Europe's largest networks and a global cloud services platform which encompasses 12 data centers, 14 virtual data centers and 31 colocation centers, with connections to 195 ad...
Most people haven’t heard the word, “gamification,” even though they probably, and perhaps unwittingly, participate in it every day. Gamification is “the process of adding games or game-like elements to something (as a task) so as to encourage participation.” Further, gamification is about bringing game mechanics – rules, constructs, processes, and methods – into the real world in an effort to engage people. In his session at @ThingsExpo, Robert Endo, owner and engagement manager of Intrepid D...
SYS-CON Events announced today that Pythian, a global IT services company specializing in helping companies adopt disruptive technologies to optimize revenue-generating systems, has been named “Bronze Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2015 at the Javits Center in New York, New York. Founded in 1997, Pythian is a global IT services company that helps companies compete by adopting disruptive technologies such as cloud, Big Data, advanced analytics, and DevO...
One of the bewildering things about DevOps is integrating the massive toolchain including the dozens of new tools that seem to crop up every year. Part of DevOps is Continuous Delivery and having a complex toolchain can add additional integration and setup to your developer environment. In his session at @DevOpsSummit at 18th Cloud Expo, Miko Matsumura, Chief Marketing Officer of Gradle Inc., will discuss which tools to use in a developer stack, how to provision the toolchain to minimize onboa...
With microservices, SOA and distributed architectures becoming more popular, it is becoming increasingly harder to keep track of where time is spent in a distributed application when trying to diagnose performance problems. Distributed tracing systems attempt to address this problem by following application requests across service boundaries, persisting metadata along the way that provide context for fine-grained performance monitoring.
With an estimated 50 billion devices connected to the Internet by 2020, several industries will begin to expand their capabilities for retaining end point data at the edge to better utilize the range of data types and sheer volume of M2M data generated by the Internet of Things. In his session at @ThingsExpo, Don DeLoach, CEO and President of Infobright, will discuss the infrastructures businesses will need to implement to handle this explosion of data by providing specific use cases for filte...
SYS-CON Events announced today that Men & Mice, the leading global provider of DNS, DHCP and IP address management overlay solutions, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. The Men & Mice Suite overlay solution is already known for its powerful application in heterogeneous operating environments, enabling enterprises to scale without fuss. Building on a solid range of diverse platform support,...
SYS-CON Events announced today that Fusion, a leading provider of cloud services, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Fusion, a leading provider of integrated cloud solutions to small, medium and large businesses, is the industry's single source for the cloud. Fusion's advanced, proprietary cloud service platform enables the integration of leading edge solutions in the cloud, including clou...
SYS-CON Events announced today that Commvault, a global leader in enterprise data protection and information management, has been named “Bronze Sponsor” of SYS-CON's 18th International Cloud Expo, which will take place on June 7–9, 2016, at the Javits Center in New York City, NY, and the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Commvault is a leading provider of data protection and information management...
SYS-CON Events announced today that AppNeta, the leader in performance insight for business-critical web applications, will exhibit and present at SYS-CON's @DevOpsSummit at Cloud Expo New York, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. AppNeta is the only application performance monitoring (APM) company to provide solutions for all applications – applications you develop internally, business-critical SaaS applications you use and the networks that deli...