Welcome!

News Feed Item

Bilbao Silver-Lead-Zinc Project - Preliminary Economic Assessment

TORONTO, ONTARIO -- (Marketwired) -- 04/28/14 -- Xtierra Inc. (TSX VENTURE:XAG) ("Xtierra" or the "Company"), reports that it has received an updated NI 43-101 compliant resource estimate and a Preliminary Economic Assessment (PEA) on the Bilbao Project, both prepared by RungePincockMinarco (Canada) Limited (RPM).

The Bilbao Project is a polymetallic sulphide and oxide replacement silver-lead-zinc-copper deposit located approximately 500km northwest of Mexico City in the southeastern part of the State of Zacatecas.

RPM updated the previous resource model taking into account additional drilling completed in both 2012 and 2013 and coordinated and supervised various third party independent consultants to carry out various studies including: Nordmin Engineering Ltd. developed a mine design and production schedule; DRA Americas Inc. analyzed metallurgical testing and recovery methods and designed a process plant; Golder Associates carried out various environmental studies including the design of a tailings disposal facility; and Micon International Limited carried out a high level review of metal markets.

The following disclosure is based on and/or derived from the PEA. The PEA is preliminary in nature in that it includes in part inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability. There is no certainty that the results projected by the PEA will be realized with further work and actual results may vary substantially. Because inferred resources are speculative, the modifying factors that are applied to assess the potential economic viability of the project are also speculative.

Exploration and Drilling

RPM, after reviewing the extensive work previously completed and the large amount of information generated, recommended extending the scope of the previously completed infill drilling program by a minimum of four holes and assaying historical core in strategic locations.

Six infill holes were drilled in June 2013, completing an additional drilling campaign in the southern part of the silver-zinc-lead project. This drilling followed a 10 hole, 2032 metre infill drilling campaign during the third quarter of 2012.

Since 2006, Xtierra has drilled 113 diamond drill-holes in the Bilbao deposit. All of the drill-holes are diamond NQ-HQ core holes with most (104) being vertical. The drill campaigns defined a general grid of 50 m by 50 m and a tighter drilling grid of 26 holes defining a 35 m by 35 m in the high grade core. The drilled zone extends over an area of 530m along north-south axis and 580m along east-west axis.

Mineral Resource Estimates

The new Zn/Pb/Ag/Cu resource estimation of the Bilbao deposit was prepared by RPM to incorporate new drilling information acquired during 2011-2013. The geological model was generated using 113 holes (all the logged drill holes). The block resource model was estimated using 105 holes which had assays. A lithology model was built and Indicator and Ordinary Kriging (OK) were used to estimate Zn, Pb, Ag and Cu resources. Density measurements were updated using 224 new density determinations completed since the last 2010 model was constructed. The previous 2011 model was based on the average of 14 measurements and assigned a density of 3.6g/cc to sulphide blocks while the new 2013 model established a mean density of 3.3 g/cc for the sulphide zone.

RPM used three year trailing average prices of US$0.94 lb/Zn, US$1.01 lb/Pb and US$30.24 oz/Ag for purposes of determining cutoff grades and Zn equivalent values. Metallurgical recoveries were applied in the equivalent equation as 76.7%, 90.6% and 73.4% for Zn, Pb, and Ag, respectively. The Zn equivalent equation used is as follows: Zneq = Zn + 0.969(i)Pb + 0.09947(i)Ag.

The total resources by mineral type at 3% Zn equivalent cut-off, excluding approximately 1 million tonnes of previously mined out ore, estimated by RPM and reported in April 2014 are shown in the following table:


----------------------------------------------------------------------------
                Zn                                                          
            equiv.  Indicated   Inferred               Zn            Ag   Cu
Ore Type       (%)     Tonnes     TonnesTotal Tonnes  (%)  Pb (%) (ppm)  (%)
----------------------------------------------------------------------------
Oxide         6.50    791,082  3,069,582   3,860,664 1.70    2.33    42 0.17
----------------------------------------------------------------------------
Mixed         7.10    778,336    238,923   1,017,259 2.06    2.17    52 0.18
----------------------------------------------------------------------------
Sulphide      6.88  4,555,809  1,201,032   5,756,841 2.03    1.40    69 0.17
----------------------------------------------------------------------------
Total         6.76  6,125,227  4,509,537  10,634,764 1.91    1.81    58 0.17
----------------------------------------------------------------------------

The previous resource estimation was originally carried out by Richard Parker Consulting Geologist in 2011 and included 84 drill holes. The resources reported in 2011 (including both oxide and sulphide) were 10,617,891 tonnes @ 6.48% Zneq in the Indicated category and 430,000 tonnes @ 5.19% Zneq in the Inferred category. (Technical Report dated April, 2011 entitled "Geology and revised Minerals resources of the Bilbao Silver-Lead-Zinc Deposit - State of Zacatecas, Mexico" by RTG Parker, Consulting Geologist).

Net Smelter Return Cut-off Value

The Net Smelter Return (NSR) cutoff value of US$45.21 per tonne of ore used for the Bilbao Project stope tonnes and grade determination is based on direct mining, processing and G&A costs.

Potentially Mineable Resource

The potentially mineable underground resource is estimated by RPM to be 5.2M tonnes at grades of 2.10 % Zn, 1.40 % Pb and 63.96 grams Ag per tonne. The tonnes and grade include an average dilution of 10 percent, at zero grade, as well as mining losses of 5%. The RPM PEA relies on Indicated Mineral Resources (approximately 75 percent of the total resource tonnes) as well as Inferred Mineral Resources (approximately 25 percent of the total resource tonnes).

Mine Design and Production Planning

The current mine plan incorporated in the PEA targets the extraction of the sulphide zone only given the results of the metallurgical test work on the oxide and transition zones completed to date.

The mine production schedule is based on a production rate of 2,000 tpd of potentially economic mineralization, or 720,000 tonnes per year. This provides for a mine life of approximately 8 years, mining out the resources available.

Underground mining methods will be used to access the sulphide zone located approximately 50 meters below surface, and accessed via a portal and ramp system. The main access to the underground mine will be via a main ramp from surface to the 1860 Level.

The main proposed mining method is Longhole Open Stoping using downholes, while near the top of the deposit Longhole Open Stoping using upholes will be employed. Longhole stopes will be backfilled with a cemented rock fill.

Based on the selected mining method a dilution factor of 10% is applied which allows for dilution from hanging and footwall wall exposures and cemented backfill dilution which results from blasting against backfilled stopes. Mining recovery of 95% is assumed for this deposit.

Recovery Methods

The mineral processing plant described is for the treatment of a silver-lead-zinc sulfide ore at a design throughput rate of 2,000 t/d. The mineral processing plant will produce lead-silver and zinc concentrates which will be transported off-site.

The process flow sheet selected for the Bilbao process plant comprises two stages of crushing, two stages of grinding, lead rougher flotation, lead regrind, lead cleaner and lead concentrate and dewatering stages, zinc rougher flotation, zinc regrind, zinc cleaner flotation and zinc concentrate and dewatering stages.

The plant will be capable of processing 720,000 tonnes per year with an average grade of 2.1%, 1.4% and 63.96 g/t of zinc, lead and silver respectively. The plant has an operating regime of 360 days per year, 7 days per week, 24 hours per day and a plant utilization of 92%, resulting in an average nominal throughput of 91 tonnes per hour.

The plant will produce, on average, 16,913 dry tonnes per year of silver-rich lead concentrate, and 26,966 dry tonnes per year of zinc concentrate. Plant recovery is estimated to be 76.7% for zinc, 90.6% for lead and 73.4% for silver over the life of the mine.

Capital and Operating Costs

Project capital costs, as of April 2014, are estimated by RPM to be US$99.5 million including an allowance for contingencies of US$8.7 million, equivalent to 8.8% of total capital expenditure. The capital cost outlines total pre-production capital of US$91.2 million and remaining other capital and sustaining capital costs of US$8.3 million for the eight year production life, including acquisition to replace mine equipment fleet, plant and infrastructure.

The operating expenditure is based on all development work in waste being performed by contractors, and stope development by Xtierra personnel and equipment fleets. The strategy was determined as the most cost effective for the operation and ensures sustainability of a skilled labor force. The average total unit operating cost over the life of the project is US$66.90/t of ore, including mining, processing, general and administration, freight and insurance, smelting, refining and penalty costs.

Economic Analysis

The economic analysis was completed by RPM for a 720,000 tonne per year processing plant capacity and is based on the potentially mineable underground resource of 5.2 million tonnes at grades of 2.10 % Zn, 1.40 % Pb and 63.96 grams Ag per tonne.

At the request of Xtierra, RPM has based its economic analysis of the Bilbao project on three-year average metal prices. For the three-year period ending 31 October, 2013, the rolling average prices based on LME cash buyer quotes for zinc and lead, and as reported by Kitco on www.kitco.com for silver are as follows: Zinc US$0.92/lb; Lead US$1.00/lb; and Silver US$30.38/oz.

Total revenue for the project is based on 720,000 tonnes per year production to be reached in production year 2 and continuing for the life of the project average US$73.6 million per year (gross revenue). The current plan estimates 11,000 tonnes of zinc concentrate and 7,000 tonnes of lead concentrate in the first production year.

Cash Flow

Pre-tax earnings total US$59.9 million over the eight year mining plan to extract the Indicated and Inferred potentially minable resource. Economic results of the Bilbao Project pre-tax cash flow model indicate an Internal Rate of Return (IRR) of 13.2% and a Net Present Value (NPV) of US$11.0 million at a 10% discount rate and a NPV of US$18.7 million at an 8% discount rate. RPM considered the ten percent discount rate appropriate for this evaluation as the overall project risks are considered to be relatively low in terms of total capital committed, geological risk and market risk.

This preliminary economic assessment is preliminary in nature. It includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary economic assessment will be realized.

After-tax net cash flow totals US$32.6 million over the eight year mine plan. Economic results of the Project after-tax cash flow model indicate an IRR of 8.1% and an after-tax NPV of negative US$5.8 million at a 10% discount rate and a NPV of US$359,000 at an 8% discount rate.

RPM also developed a sensitivity analysis to the Project's IRR and NPV to +/- 15 percent changes to key assumptions in the cash flow model based on variations in key project elements of metal price, operating and capital costs. The Bilbao Project was found to be most sensitive to changes in operating costs where a 15% reduction in operating costs would result in pre-tax NPV of US$45.0 million and a pre-tax IRR of 22.0%. RPM noted that there may be opportunity to reduce operating costs significantly (approx. US$5/t to US$6/t) by reducing the number of stopes filled with backfill. With regard to changes in metal prices, the Bilbao Project was found to be most sensitive to movements in the price of silver.

Recommendations by RPM

Recommendations have been made by RPM in the PEA identifying various opportunities to increase the mineable resource and reduce operating costs through additional exploration and engineering, improving the overall economics of the project. RPM recommendations include:


--  Additional definition drilling targeted at the Bilbao transition and
    sulphide zones could lead to re-classification of inferred resources to
    indicated resources, potentially contributing to the total mineable
    resource studied at the pre-feasibility level; 
    
--  The potential to increase level spacing and correspondingly reduce level
    development, through use of cable bolts, may lead to lower mine
    development costs and should be further assessed; 
    
--  Further analysis of hydraulic and sand backfilling options, in terms of
    preparation and distribution, may further reduce overall operating
    costs; 
    
--  There may also be opportunity to reduce operating costs significantly
    (approx. US$5/t to US$6/t) by reducing the number of stopes filled with
    backfill all together. Further geotechnical study would need to be
    carried out for this scenario to better understand possible ore losses
    with pillars left in place, and possible recovery of these pillars
    through caving activity. Potential also exists for deferral of ramp and
    associated development; 
    
--  Inclusion of transition zone material in the mine plan should be
    investigated (requiring additional metallurgical testwork) to extend the
    life of mine and/or potentially increase the mining rate per year; 
    
--  Further optimization of stope sequencing could lead to improved cash
    flow and should be studied; 
    
--  Exploration drilling at the Bilbao 2 area, approximately 1.5 km south of
    Bilbao, has potential to offer additional mineral resources to the
    project due to the fact that current trenching, sampling and resulting
    soil geochemistry information identifies similarities between the two
    areas. An additional source of feed to the designed plant could lengthen
    the overall life of the mine, increase the daily production rate, or
    result in a combination of the two, improving the NPV and IRR of the
    project. 

RPM noted that the Bilbao deposit contains a reasonable quantity of mineral resources between the oxide, transition, and sulphide mineral zones; however, the lack of metallurgical test data available for the transition zone and identified recovery challenges for the oxide zone currently limit the scope of this PEA to the total mineable sulphide resources to offset the capital costs associated with the project.

A Technical Report in compliance with NI 43-101 has been filed on SEDAR.

Future Plans

Having now received the completed Preliminary Economic Analysis for the Bilbao Project from RPM, the Company's focus going forward is to seek alternatives to maximize the value of Bilbao including seeking to develop Bilbao either alone or in joint venture with a partner or through corporate transactions.

RPM have made numerous recommendations throughout the PEA identifying various opportunities to increase the mineable resource and reduce operating costs through additional exploration and engineering, improving the overall economics of the Bilbao project.

Further metallurgical test work on the oxide ore to optimize economic metal recoveries, including the recovery of lead by means of gravity separation, has shown some promise and further metallurgical test-work on the oxide ore should be undertaken.

The continuing operations of the Company are dependent upon its ability to raise adequate financing and additional funding will be required for working capital, optimisation and feasibility studies, further exploration and for financing in the longer term to develop the Bilbao project.

Cautionary Notes:

This press release may contain "forward-looking information" within the meaning of applicable Canadian securities legislation. The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of the content of this release.

For further information visit www.xtierra.ca.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Whether you like it or not, DevOps is on track for a remarkable alliance with security. The SEC didn’t approve the merger. And your boss hasn’t heard anything about it. Yet, this unruly triumvirate will soon dominate and deliver DevSecOps faster, cheaper, better, and on an unprecedented scale. In his session at DevOps Summit, Frank Bunger, VP of Customer Success at ScriptRock, discussed how this cathartic moment will propel the DevOps movement from such stuff as dreams are made on to a practic...
In their Live Hack” presentation at 17th Cloud Expo, Stephen Coty and Paul Fletcher, Chief Security Evangelists at Alert Logic, provided the audience with a chance to see a live demonstration of the common tools cyber attackers use to attack cloud and traditional IT systems. This “Live Hack” used open source attack tools that are free and available for download by anybody. Attendees learned where to find and how to operate these tools for the purpose of testing their own IT infrastructure. The...
SYS-CON Events announced today that CA Technologies has been named “Platinum Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY, and the 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CA Technologies helps customers succeed in a future where every business – from apparel to energy – is being rewritten by software. From ...
SYS-CON Events announced today that MobiDev, a client-oriented software development company, will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place June 6-8, 2017, at the Javits Center in New York City, NY, and the 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. MobiDev is a software company that develops and delivers turn-key mobile apps, websites, web services, and complex softw...
SYS-CON Events announced today that Loom Systems will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Founded in 2015, Loom Systems delivers an advanced AI solution to predict and prevent problems in the digital business. Loom stands alone in the industry as an AI analysis platform requiring no prior math knowledge from operators, leveraging the existing staff to succeed in the digital era. With offices in S...
SYS-CON Events announced today that Cloud Academy will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Cloud Academy is the industry’s most innovative, vendor-neutral cloud technology training platform. Cloud Academy provides continuous learning solutions for individuals and enterprise teams for Amazon Web Services, Microsoft Azure, Google Cloud Platform, and the most popular cloud computing technologies. Ge...
Historically, some banking activities such as trading have been relying heavily on analytics and cutting edge algorithmic tools. The coming of age of powerful data analytics solutions combined with the development of intelligent algorithms have created new opportunities for financial institutions. In his session at 20th Cloud Expo, Sebastien Meunier, Head of Digital for North America at Chappuis Halder & Co., will discuss how these tools can be leveraged to develop a lasting competitive advanta...
"My role is working with customers, helping them go through this digital transformation. I spend a lot of time talking to banks, big industries, manufacturers working through how they are integrating and transforming their IT platforms and moving them forward," explained William Morrish, General Manager Product Sales at Interoute, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.
For organizations that have amassed large sums of software complexity, taking a microservices approach is the first step toward DevOps and continuous improvement / development. Integrating system-level analysis with microservices makes it easier to change and add functionality to applications at any time without the increase of risk. Before you start big transformation projects or a cloud migration, make sure these changes won’t take down your entire organization.
With billions of sensors deployed worldwide, the amount of machine-generated data will soon exceed what our networks can handle. But consumers and businesses will expect seamless experiences and real-time responsiveness. What does this mean for IoT devices and the infrastructure that supports them? More of the data will need to be handled at - or closer to - the devices themselves.
DevOps is often described as a combination of technology and culture. Without both, DevOps isn't complete. However, applying the culture to outdated technology is a recipe for disaster; as response times grow and connections between teams are delayed by technology, the culture will die. A Nutanix Enterprise Cloud has many benefits that provide the needed base for a true DevOps paradigm.
My team embarked on building a data lake for our sales and marketing data to better understand customer journeys. This required building a hybrid data pipeline to connect our cloud CRM with the new Hadoop Data Lake. One challenge is that IT was not in a position to provide support until we proved value and marketing did not have the experience, so we embarked on the journey ourselves within the product marketing team for our line of business within Progress. In his session at @BigDataExpo, Sum...
The taxi industry never saw Uber coming. Startups are a threat to incumbents like never before, and a major enabler for startups is that they are instantly “cloud ready.” If innovation moves at the pace of IT, then your company is in trouble. Why? Because your data center will not keep up with frenetic pace AWS, Microsoft and Google are rolling out new capabilities In his session at 20th Cloud Expo, Don Browning, VP of Cloud Architecture at Turner, will posit that disruption is inevitable for c...
SYS-CON Events announced today that Ocean9will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Ocean9 provides cloud services for Backup, Disaster Recovery (DRaaS) and instant Innovation, and redefines enterprise infrastructure with its cloud native subscription offerings for mission critical SAP workloads.
SYS-CON Events announced today that Telecom Reseller has been named “Media Sponsor” of SYS-CON's 20th International Cloud Expo, which will take place on June 6–8, 2017, at the Javits Center in New York City, NY. Telecom Reseller reports on Unified Communications, UCaaS, BPaaS for enterprise and SMBs. They report extensively on both customer premises based solutions such as IP-PBX as well as cloud based and hosted platforms.