Integra Gold SEDAR Files Technical Report for Initial Preliminary Economic Assessment for the Lamaque Gold Project

VANCOUVER, BC--(Marketwired - April 29, 2014) - Integra Gold Corp. (TSX VENTURE: ICG) ("Integra" or the "Company") is pleased to announce that it has filed on SEDAR today the NI 43-101 technical report for the Preliminary Economic Assessment ("PEA"), disclosed in the Company's news release dated March 11, 2014, for its Lamaque Gold Project ("Lamaque") located in Val-d'Or, Québec. The PEA, prepared by InnovExplo Inc. ("InnovExplo") with technical contributions from AMEC, Golder Associates, Geologica Groupe-Conseil Inc., Geopointcom Inc. and WSP Engineering, demonstrates the strong economic potential of the Lamaque Project.

The report will be available under the Company's profile on SEDAR and on the Company's website via the following link: http://www.integragold.com/i/pdf/reports/43-101_PEA_Lamaque_2014.pdf.

PEA Highlights:

  • Base Case Pre-tax IRR of 51% and NPV (5% discount rate) of CAD$146.0 M
  • Average annual production of 112,400 gold ("Au") ounces per year with peak annual production at 143,300 Au ounces per year and total production of 505,600 Au ounces
  • Life of Mine ("LOM") cash cost of CAD$665 per Au ounce and cash costs plus sustaining costs of CAD$805 per Au ounce
  • In excess of 56,600 meters ("m") in 157 drill holes has now been completed subsequent to the database cut-off date of April 24, 2013 for the resource estimates used in the PEA which highlights the strong potential for resource growth
  • Proposed underground operation with a vertical depth of 620 m and material processed at nearby mills via toll, or custom, milling
  • The plan as outlined in the PEA will have minimal impact on the community as there are no homes, businesses, or other infrastructure where the proposed mining will take place
  • Potential to significantly reduce capital expenditures by delaying development of second ramp until cash flow from the first ramp has been achieved

"We were impressed with the results of the first PEA and look forward to seeing the impact an updated resource will have on what are already very promising numbers," noted President and CEO Stephen de Jong. "With this additional 57,000 meters of drilling we are confident we will continue to see the Lamaque resource and projected mine life grow increasing the overall viability and appeal of the project."

PEA Base Case Assumptions and Summary

============================================================================
Gold Price (USD$)                                                   $1,275  
----------------------------------------------------------------------------
Exchange Rate (CAD$ to USD$)                                        1.05    
----------------------------------------------------------------------------
Gold Price (CAD$)                                                   $1,339  
----------------------------------------------------------------------------
Average Annual Gold Production (ounces)                             112,400 
----------------------------------------------------------------------------
Peak Annual Gold Production (ounces)                                143,300 
----------------------------------------------------------------------------
Pre-Production Capital Costs (CAD$)                                 $69.2 M 
----------------------------------------------------------------------------
LOM Sustaining Capital (CAD$)                                       $66.8 M 
----------------------------------------------------------------------------
Pre-Production Period (years)                                       2       
----------------------------------------------------------------------------
Mine Life (years)                                                   4.25    
----------------------------------------------------------------------------
Cash Cost per Au Ounce (CAD$)                                       $665    
----------------------------------------------------------------------------
Cash Costs and Sustaining Cost per Au Ounce (CAD$)                  $805    
============================================================================
                                                                            
============================================================================
PRE-TAX                                                                     
----------------------------------------------------------------------------
Life of Mine NPV at 5% Discount Rate (CAD$)                         $146.0 M
----------------------------------------------------------------------------
Internal Rate of Return                                             51%     
----------------------------------------------------------------------------
Payback Period (years)                                              1.5     
============================================================================
                                                                            
============================================================================
AFTER-TAX                                                                   
----------------------------------------------------------------------------
Life of Mine NPV at 5% Discount Rate (CAD$)                         $88.5 M 
----------------------------------------------------------------------------
Internal Rate of Return                                             38%     
----------------------------------------------------------------------------
Payback Period (years)                                              1.8     
============================================================================

PEA Production Profile (Diluted Head Grade after Mining)

============================================================================
                                            Grade            Au Ounces      
         Year              Tonnes         (g/t Au)           Recovered      
============================================================================
    Pre-production            -               -                  -          
----------------------------------------------------------------------------
    Pre-production         124,500          7.46              28,000        
----------------------------------------------------------------------------
           1               398,500          7.97              95,500        
----------------------------------------------------------------------------
           2               512,400          9.35              143,300       
----------------------------------------------------------------------------
           3               463,700          9.25              127,000       
----------------------------------------------------------------------------
           4               501,500          6.76              98,700        
----------------------------------------------------------------------------
           5               80,800           5.88              13,100        
============================================================================
         TOTAL            2,081,400         8.19              505,600       
============================================================================

2014 Lamaque Drill Program

Planned drilling for 2014 at the Lamaque project has been increased to a minimum of 45,000 m. This includes the recently completed 24,000 m definition program at the Triangle Zone, definition drilling at the Fortune Zone (8,000 m), exploration drilling at Plug No. 5 (5,000 m) and Mine No. 3 targets (6,000 m), and geotechnical drilling at Parallel, Triangle, and Fortune zones (2,000 m). The Plug No. 5 and Mine No. 3 targets are not currently included in the Lamaque Project's total resource and following the proposed drill programs the Company will conduct resource estimation on these targets in the latter part of 2014.

The PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the PEA will be realized.

Project and Company Profile

Integra's Lamaque gold project is located in the heart of the Val-d'Or gold camp in the Province of Québec, Canada, approximately 550 km northwest of Montréal. Québec is rated one of the best mining jurisdictions in the world. Infrastructure, human resources and mining expertise are readily available.

The Company's primary objective is to continue to prove up additional resources while advancing the existing resource towards production. The project is divided into three main clusters of mineralization, the North, South and West Cluster. The North Cluster consists of the Parallel, Fortune, No. 5 Plug, and No. 3 Mine zones and is located approximately 1 km northwest from the South Cluster, which includes the No. 4 Plug, Triangle and Triangle South zones. The Sixteen Zone and No. 6 Vein form the West Cluster. The zones from the West Cluster, as well as the Mine No. 3 and Plug No. 5 zones from the North Cluster are not included in the PEA.

Qualified Person

The Lamaque Project is under the direct supervision of Hervé Thiboutot, Eng. Senior Vice-President of the Company, and Francois Chabot, Eng. and Operations and Engineering Manager of the Company. Both Mr. Thiboutot and Mr. Chabot are Qualified Persons ("QP") as defined by National Instrument 43-101.

In addition, each of the individuals listed below are independent QP for the purposes of NI 43-101. All scientific and technical information in this press release in respect of the Lamaque Project or the PEA is based upon information prepared by or under the supervision of those individuals.

For InnovExplo Inc., Sylvie Poirier, Eng. (Mining) and Laurent Roy, Eng. (Mining); for Geologica, Alain-Jean Beauregard, Geol. (Geology) and Daniel Gaudreault, Eng. (Geology); for GeoPointcom, Christian D'Amours, Geol. (Resources); for Amec, Stephan Bergeron, Eng. (Environment); for Golder Associates, James Tod, Eng. (Geo-Mechanics); and for WSP Engineering, Michel Garon, Eng. (Metallurgy).

The Company's QPs have reviewed the technical content of this press release.

ON BEHALF OF THE BOARD OF DIRECTORS

Stephen de Jong
CEO & President

Follow Integra Gold On:

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

Cautionary Note Regarding Forward Looking Statements: Certain disclosures in this release constitute forward-looking statements. In making the forward-looking statements in this release, the Company has applied certain factors and assumptions that are based on the Company's current beliefs as well as assumptions made by and information currently available to the Company, including that the Company is able to obtain any government or other regulatory approvals required to complete the private placement and Company's planned exploration activities, that the Company is able to complete the private placement, that the Company is able to procure personnel, equipment and supplies required for its exploration activities in sufficient quantities and on a timely basis and that actual results of exploration activities are consistent with management's expectations. Although the Company considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect, and the forward-looking statements in this release are subject to numerous risks, uncertainties and other factors that may cause future results to differ materially from those expressed or implied in such forward-looking statements. Such risk factors include, among others, that the private placement will not be completed, that actual results of the Company's exploration activities will be different than those expected by management and that the Company will be unable to obtain or will experience delays in obtaining any required government approvals or be unable to procure required equipment and supplies in sufficient quantities and on a timely basis. Readers are cautioned not to place undue reliance on forward-looking statements. The Company does not intend, and expressly disclaims any intention or obligation to, update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by law.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
The Transparent Cloud-computing Consortium (abbreviation: T-Cloud Consortium) will conduct research activities into changes in the computing model as a result of collaboration between "device" and "cloud" and the creation of new value and markets through organic data processing High speed and high quality networks, and dramatic improvements in computer processing capabilities, have greatly changed the nature of applications and made the storing and processing of data on the network commonplace.
An IoT product’s log files speak volumes about what’s happening with your products in the field, pinpointing current and potential issues, and enabling you to predict failures and save millions of dollars in inventory. But until recently, no one knew how to listen. In his session at @ThingsExpo, Dan Gettens, Chief Research Officer at OnProcess, will discuss recent research by Massachusetts Institute of Technology and OnProcess Technology, where MIT created a new, breakthrough analytics model f...
Without a clear strategy for cost control and an architecture designed with cloud services in mind, costs and operational performance can quickly get out of control. To avoid multiple architectural redesigns requires extensive thought and planning. Boundary (now part of BMC) launched a new public-facing multi-tenant high resolution monitoring service on Amazon AWS two years ago, facing challenges and learning best practices in the early days of the new service. In his session at 19th Cloud Exp...
Digitization is driving a fundamental change in society that is transforming the way businesses work with their customers, their supply chains and their people. Digital transformation leverages DevOps best practices, such as Agile Parallel Development, Continuous Delivery and Agile Operations to capitalize on opportunities and create competitive differentiation in the application economy. However, information security has been notably absent from the DevOps movement. Speed doesn’t have to negat...
The Internet of Things can drive efficiency for airlines and airports. In their session at @ThingsExpo, Shyam Varan Nath, Principal Architect with GE, and Sudip Majumder, senior director of development at Oracle, will discuss the technical details of the connected airline baggage and related social media solutions. These IoT applications will enhance travelers' journey experience and drive efficiency for the airlines and the airports. The session will include a working demo and a technical d...
While DevOps promises a better and tighter integration among an organization’s development and operation teams and transforms an application life cycle into a continual deployment, Chef and Azure together provides a speedy, cost-effective and highly scalable vehicle for realizing the business values of this transformation. In his session at @DevOpsSummit at 19th Cloud Expo, Yung Chou, a Technology Evangelist at Microsoft, will present a unique opportunity to witness how Chef and Azure work tog...
In this strange new world where more and more power is drawn from business technology, companies are effectively straddling two paths on the road to innovation and transformation into digital enterprises. The first path is the heritage trail – with “legacy” technology forming the background. Here, extant technologies are transformed by core IT teams to provide more API-driven approaches. Legacy systems can restrict companies that are transitioning into digital enterprises. To truly become a lea...
Almost two-thirds of companies either have or soon will have IoT as the backbone of their business in 2016. However, IoT is far more complex than most firms expected. How can you not get trapped in the pitfalls? In his session at @ThingsExpo, Tony Shan, a renowned visionary and thought leader, will introduce a holistic method of IoTification, which is the process of IoTifying the existing technology and business models to adopt and leverage IoT. He will drill down to the components in this fra...
Your business relies on your applications and your employees to stay in business. Whether you develop apps or manage business critical apps that help fuel your business, what happens when users experience sluggish performance? You and all technical teams across the organization – application, network, operations, among others, as well as, those outside the organization, like ISPs and third-party providers – are called in to solve the problem.
Digital transformation is too big and important for our future success to not understand the rules that apply to it. The first three rules for winning in this age of hyper-digital transformation are: Advantages in speed, analytics and operational tempos must be captured by implementing an optimized information logistics system (OILS) Real-time operational tempos (IT, people and business processes) must be achieved Businesses that can "analyze data and act and with speed" will dominate those t...
If you had a chance to enter on the ground level of the largest e-commerce market in the world – would you? China is the world’s most populated country with the second largest economy and the world’s fastest growing market. It is estimated that by 2018 the Chinese market will be reaching over $30 billion in gaming revenue alone. Admittedly for a foreign company, doing business in China can be challenging. Often changing laws, administrative regulations and the often inscrutable Chinese Interne...
I'm a lonely sensor. I spend all day telling the world how I'm feeling, but none of the other sensors seem to care. I want to be connected. I want to build relationships with other sensors to be more useful for my human. I want my human to understand that when my friends next door are too hot for a while, I'll soon be flaming. And when all my friends go outside without me, I may be left behind. Don't just log my data; use the relationship graph. In his session at @ThingsExpo, Ryan Boyd, Engi...
Internet of @ThingsExpo, taking place November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with the 19th International Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world and ThingsExpo Silicon Valley Call for Papers is now open.
Adobe is changing the world though digital experiences. Adobe helps customers develop and deliver high-impact experiences that differentiate brands, build loyalty, and drive revenue across every screen, including smartphones, computers, tablets and TVs. Adobe content solutions are used daily by millions of companies worldwide-from publishers and broadcasters, to enterprises, marketing agencies and household-name brands. Building on its established design leadership, Adobe enables customers not o...
If you’re responsible for an application that depends on the data or functionality of various IoT endpoints – either sensors or devices – your brand reputation depends on the security, reliability, and compliance of its many integrated parts. If your application fails to deliver the expected business results, your customers and partners won't care if that failure stems from the code you developed or from a component that you integrated. What can you do to ensure that the endpoints work as expect...