Klondex Announces Fire Creek PEA Results, Including All-In Sustaining Cash Costs of $636/oz Gold

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 04/29/14 -- Klondex Mines Ltd. (TSX: KDX)(OTCQX: KLNDF) ("Klondex" or the "Company") is pleased to announce the results of an independent Preliminary Economic Assessment ("PEA") for its wholly-owned Fire Creek Exploration Project ("Fire Creek" or the "Project") near Elko, Nevada. The PEA was prepared by Practical Mining, LLC ("PM"). All figures are quoted in US dollars. The technical report associated with the PEA will be filed on SEDAR within 45 days.


---------------------------------------------------------------------------
Fire Creek Project Estimates Highlights at $1250/oz Gold:
---------------------------------------------------------------------------
All-in sustaining (including Ag by-product)        $636/oz
---------------------------------------------------------------------------
Cash costs (including Ag by-product)               $459/oz
---------------------------------------------------------------------------
LOM estimate                                       5 yrs
---------------------------------------------------------------------------
Average LOM gold grade                             0.68 opt Au; 23.3 g/t Au
---------------------------------------------------------------------------
Average LOM silver grade                           0.34 opt Ag; 11.7 g/t Ag
---------------------------------------------------------------------------
Total production                                   280k ozs Au; 139k oz Ag
---------------------------------------------------------------------------
Capital costs                                      $49.6 mm
---------------------------------------------------------------------------
Pay-back period                                    0.5 yrs
---------------------------------------------------------------------------
After-tax cash flow                                $157.3 mm
---------------------------------------------------------------------------
After-tax 5% NPV                                   $141.5 mm
---------------------------------------------------------------------------
Profitability Index (see definition:
 http://www.klondexmines.com/s/definitions.asp)    4.1
---------------------------------------------------------------------------
Note: The IRR could not be calculated because the cash flow is positive in
 the first year and every succeeding year of the project.

Paul Huet, Klondex President and CEO, stated, "The Fire Creek PEA represents a significant and encouraging milestone for Klondex. The PEA details an initial mine plan with immediate positive cash flows that have the potential to remain economic in low gold price environments. We believe Fire Creek is a unique project, and what sets it apart are the gold grades, short path to production, and the substantial exploration upside. The PEA establishes that our mining operation has the potential to be the cornerstone for our growth for many years."

He continued, "Drilling in the past few years has been constrained to surface and infill drilling for definition, within 7% of our land package. This year, we have allocated $9mm for waste development and new drilling platforms to test new extensions of our current veins and the potential for new discoveries, particularly to the West and North Zones."

Assuming an average gold and silver price of $1,250 and $18 per ounce, respectively, Fire Creek has an estimated $157.3 mm after-tax cash flow, a $141.5mm after-tax net present value ("NPV") at a 5% discount rate and a $128.3 mm after-tax NPV at a 10% discount rate. The PEA cash flow is presented at the project level and does not include obligations for servicing corporate debt.

The PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the preliminary economic assessment will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Mineral Resources

The PEA is based on a mineral resource estimate with an effective date of December 31, 2013. The Fire Creek database used for the mineral resource estimate includes 408 drill holes totaling over 133,000 m (437,000 ft) and 1,120 channel and face samples and is reflective of underground development work at Fire Creek during 2013 resulting in the processing of 8,007 tons of mineralized material.

The PEA provides a basis to estimate project operating and capital costs and establish a projection of the potential mineable mineral resources including measured, indicated and inferred categories in accordance with National Instrument 43-101. The mineral resource estimate which forms the basis of the PEA is as follows, at a 0.225 opt Au cut-off grade:


---------------------------------------------------------------------------
                    Measured                          Indicated
       --------------------------------------------------------------------
                             Cont.  Cont.                      Cont.  Cont.
Cut-off                       Gold Silver                       Gold Silver
 Grade    Tons  Gold Silver (000's (000's   Tons  Gold Silver (000's (000's
 (opt) (000's) (opt)  (opt)    oz)    oz)(000's) (opt)  (opt)    oz)    oz)
---------------------------------------------------------------------------
0.15        22  1.67   1.08     37     24    308  0.85   0.64    263    197
0.20        22  1.68   1.09     37     24    248  1.02   0.73    253    180
0.225       22  1.68   1.09     37     24    213  1.16   0.80    246    171
0.25        22  1.68   1.09     37     24    200  1.22   0.83    244    166
0.30        22  1.69   1.10     37     24    175  1.36   0.88    237    154
---------------------------------------------------------------------------

---------------------------------------------------------------------------
             Measured and Indicated                   Inferred
       --------------------------------------------------------------------
                             Cont.  Cont.                      Cont.  Cont.
Cut-off                       Gold Silver                       Gold Silver
 Grade    Tons  Gold Silver (000's (000's   Tons  Gold Silver (000's (000's
 (opt) (000's) (opt)  (opt)    oz)    oz)(000's) (opt)  (opt)    oz)    oz)
---------------------------------------------------------------------------
0.15       331  0.91   0.67    300    221    904  0.52   0.37    470    334
0.20       270  1.08   0.76    290    204    705  0.62   0.42    439    299
0.225      235  1.21   0.83    284    195    627  0.68   0.45    424    281
0.25       222  1.26   0.85    281    190    576  0.72   0.47    413    269
0.30       197  1.40   0.91    275    178    473  0.82   0.50    387    236
---------------------------------------------------------------------------

1.  Notes: Mineral resources, which are not mineral reserves, do not have
    demonstrated economic viability. The estimate of mineral resources may
    be materially affected by environmental, permitting, legal, title,
    socio-political, marketing, or other relevant issues.
2.  The quantity and grade of reported inferred mineral resources in this
    estimation are uncertain in nature and there is insufficient exploration
    to define these inferred mineral resources as an indicated or measured
    mineral resource. It is uncertain if further exploration will result in
    upgrading such inferred mineral resources to an indicated or measured
    mineral resource category.
3.  Mineral resources have been estimated at a cut-off grade of 0.225 opt
    (7.7 g/t) calculated with a $1,250 per ounce gold price, $18 per ounce
    silver price 94% gold recovery and 92% silver recovery mineral resources
    include allowances of 5% mining losses and 10% dilution.

Mine Planning

The Fire Creek mine plan assumes that a total of 439,000 tons of material containing 297,300 ounces of gold and 150,800 ounces of silver will be mined over the five year period. Key projected production statistics are summarized below.


---------------------------------------------------------------------------
                  Fire Creek Mine Plan (contained ounces)
Mineral
 Resource
 Category                 2014     2015     2016     2017     2018    Total
---------------------------------------------------------------------------
Measured       kt          9.2      7.0      1.6      4.5      9.6     32.0
               Au koz     11.8      5.1      1.9      8.5     13.0     40.4
               Ag koz      8.2      3.1      1.0      5.6      9.0     26.9
---------------------------------------------------------------------------
Indicated      Kt         34.3     65.5     62.3     32.8     16.2    211.1
               Au koz     24.1     45.5     45.5     20.8      9.0    144.9
               Ag koz     15.0     27.6     25.2      9.7      5.5     83.0
---------------------------------------------------------------------------
Total M & I    Kt         43.5     72.5     63.9     37.3     25.8    243.1
               Au koz     35.9     50.6     47.4     29.4     22.0    185.3
               Ag koz     23.2     30.7     26.1     15.4     14.6    109.9
---------------------------------------------------------------------------
Inferred       Kt         16.8     20.6     64.7     89.5      4.3    195.9
               Au koz      9.4     14.1     32.3     50.6      5.6    112.0
               Ag koz      6.0      9.3      9.1     13.6      2.9     40.9
---------------------------------------------------------------------------

The Fire Creek PEA mine plan only includes mineral resources within the veins which can be readily accessed from the existing development platform. The majority of mineral resources in the North Zone and all of the mineral resources in the Far North Zone were not considered in the current mine plan due to the mine development requirements for these zones. As additional exploration information is gained, the mine plan may be extended to the north to include these mineral resources.

Additionally, some of the mineral resources near the current development platform are contained in veins of insufficient width to meet cut-off grades when minimum mining widths are applied. Alternative mining methods which reduce dilution and/or development requirements should be investigated for the extraction of these mineral resources.

Underground Mining

The proposed mining methods for Fire Creek will be any one or more of the following: end slice stoping with delayed backfill, also referred to as long hole stoping; cut and fill stoping; and shrinkage stoping. The final choice of mining method will depend upon the geometry of the stope block, proximity to main access ramps, ventilation and escape routes, the relative strength or weakness of the mineral resources and adjacent wall rock, and finally the value or grade of the mineral resources. The choice of mining method for individual stoping areas will not be made until stope delineation and definition drilling is completed.

Metallurgy & Processing

Mined material from Fire Creek will be shipped to Klondex's Midas Mill for processing. The Fire Creek material will be blended with the Midas material prior to milling.

The Midas Mill was constructed in 1997 and has a nameplate capacity of 1,200 short tons per day. The mill uses conventional leach technology with counter current decantation followed by Merrill Crowe precipitation. Dore is further refined at Johnson Matthey refineries in Utah. Process toll milling has been performed periodically since 2008. Historically, the gold recovery has ranged from 92% to 97%, and silver recovery from 87% to 93%, depending upon processing rates and ore types. Mill availability for the life of the project is estimated at 95%.

Klondex began operating the Midas Mill on February 19, 2014 and immediately began processing a blend of the Fire Creek and Midas mineralized material at a rate averaging 25 tons per hour. At the end of the first quarter of 2014, over 7,800 tons of Fire Creek mineralized material was processed with gold and silver recoveries calculated at 96% and 95%, respectively. Currently, the mill is being operated at 50% of its capacity.

Capital Costs

Projected Life of Mine (LOM) constant dollar capital expenditures are detailed in the table below. Mine development comprises over 57% of total capital requirements, resource conversion drilling 23% and mining equipment 11%.


---------------------------------------------------------------------------
                      Fire Creek Capital Costs (mm's)
Category                       2014    2015    2016    2017    2018   Total
---------------------------------------------------------------------------
Waste Development               6.7     6.8     9.4     5.5     0.0    28.4
---------------------------------------------------------------------------
RIB Construction                0.7     0.0     0.0     0.0     0.0     0.7
---------------------------------------------------------------------------
Site Facilities                 1.6     1.1     0.0     0.0     0.0     2.7
---------------------------------------------------------------------------
Environmental Assessment        0.9     0.0     0.0     0.0     0.0     0.9
---------------------------------------------------------------------------
Mining Equipment                0.4     2.2     2.0     0.9     0.0     5.5
---------------------------------------------------------------------------
Drilling                        2.3     3.0     3.0     3.0     0.0    11.3
---------------------------------------------------------------------------
Total                          12.7    13.1    14.4     9.4     0.0    49.6
---------------------------------------------------------------------------

Operating Costs

Projected operating costs are based on actual costs incurred to date, internal estimates and costs from similar operations in the area. Operating cost estimates are summarized in the following table.


---------------------------------------------------------------------------
                         Fire Creek Operating Costs
---------------------------------------------------------------------------
Category                                            $/dry ton          $/oz
---------------------------------------------------------------------------
Mining Cost                                          $ 169.74      $ 266.57
---------------------------------------------------------------------------
Surface Transportation                                $ 36.75       $ 57.72
---------------------------------------------------------------------------
Processing                                            $ 40.00       $ 62.82
---------------------------------------------------------------------------
Site Administration and Overhead                      $ 13.67       $ 21.47
---------------------------------------------------------------------------
Refining and Sales                                     $ 3.18        $ 5.00
---------------------------------------------------------------------------
Royalties Payable                                      $ 8.84       $ 13.89
---------------------------------------------------------------------------
Nevada Net Proceeds                                   $ 25.46       $ 40.03
---------------------------------------------------------------------------
Silver By-product Sales Credit                       $ (5.68)      $ (8.93)
---------------------------------------------------------------------------
Total Cash Cost                                      $ 291.96      $ 458.57
---------------------------------------------------------------------------

---------------------------------------------------------------------------
Capital                                              $ 113.01      $ 177.48
---------------------------------------------------------------------------
Total Cost                                           $ 404.97      $ 636.05
---------------------------------------------------------------------------

Project Sensitivities

The project shows resilience to variances in gold price from $750/oz Au up to $1750/oz Au.


---------------------------------------------------------------------------
                    After-tax NPV @ 5% Discount ($ mm's)
---------------------------------------------------------------------------
Gold Price         $750       $1,000       $1,250       $1,500       $1,750
---------------------------------------------------------------------------
NPV                 $32          $92         $141         $200         $256
---------------------------------------------------------------------------

Environmental

Klondex conducts mineral exploration activities in compliance with all applicable local, state and federal environmental protection legislation. Klondex is unaware of any existing environmental issues or compliance problems which have the potential to impact proposed production at Fire Creek. Klondex is working closely with all regulators to ensure that the permitting and compliance strategies are acceptable and minimize delays in production or mine development. At this time, there are no community or social impact matters associated with work being completed at Fire Creek.

Future Permitting

Klondex is currently waiting for approval to an amendment to the Plan of Operations and Reclamation permits (NVN-07976 and reclamation permit 0028); this amendment will allow Klondex to construct and operate two Rapid Infiltration Basins (RIBs) at Fire Creek. Klondex received approval for the Water Pollution Permit for construction and operations of the RIBs (WPCP2013102) in February 2014. Also, Klondex does not anticipate any delays or permitting issues associated with acquiring the required permits for Fire Creek full production. Klondex has initiated a baseline data collection program to as part of anticipated future permitting necessities.

Qualified Person

The technical information contained in this press release has been reviewed and approved by Mark Odell (Nevada PE 13708 and SME 2402150) and Karl Swanson (SME 443076 and AusIMM 304871), who are considered independent Qualified Persons as defined by Canadian National Instrument 43-101.

About Klondex Mines Ltd. (www.klondexmines.com)

Klondex Mines is focused on becoming a leading integrated gold producer. It is focused on the production, development and exploration of its high quality gold and silver projects, including its central 1200 tpd mill in North Central Nevada. The company is operating an ongoing bulk sampling program at Fire Creek, and is producing gold and silver on an ongoing basis from the Midas Project, located approx. 100 miles north of Fire Creek.

Cautionary Note Regarding Technical Information and Forward-looking Information

A production decision at the Midas mine was made by prior owners of the mine, prior to the completion of the acquisition of the Midas mine by Klondex. To the knowledge of Klondex, this production decision was not based on a feasibility study of mineral reserves demonstrating economic and technical viability prepared in accordance with National Instrument 43-101 but was based on internal studies conducted by the prior owner of the mine. Klondex has no reason to believe that the data on which such studies were based or that the results of such studies are unreliable. However, readers are cautioned that there is increased uncertainty and higher risk of economic and technical failure associated with such production decisions.

This news release contains certain information that may constitute forward-looking information under applicable Canadian securities legislation, including but not limited to information about current expectations on the timing and success of exploration, development and metallurgical sampling activities, the timing, extent and success of mining operations, the Company's intention and ability to monetize mineralized material, the successful execution of the bulk sampling program at the Fire Creek Project, project development and related permitting, the results of economic analyses in respect of the Fire Creek Project (including those contained in the PEA), the extension of the proposed mine plan beyond the existing development platform at the Fire Creek Project, the ability to expand mineral resources beyond the current mineral resource estimate at the Fire Creek Project, estimates of gold and silver prices, estimates of costs, and estimates of mine development and construction. This forward-looking information entails various risks and uncertainties that are based on current expectations and actual results may differ materially from those contained in such information. These uncertainties and risks include, but are not limited to, the strength of the global economy; the price of gold and silver; operational, funding and liquidity risks; the degree to which mineral resource estimates are reflective of actual mineral resources; the degree to which factors which would make a mineral deposit commercially viable are present; the risks and hazards associated with underground operations; and the ability of Klondex to fund its substantial capital requirements and operations. Risks and uncertainties about the Company's business are more fully discussed in the Company's disclosure materials filed with the securities regulatory authorities in Canada and available at www.sedar.com. Readers are urged to read these materials. Klondex assumes no obligation to update any forward-looking information or to update the reasons why actual results could differ from such information unless required by law.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that Alert Logic, Inc., the leading provider of Security-as-a-Service solutions for the cloud, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Alert Logic, Inc., provides Security-as-a-Service for on-premises, cloud, and hybrid infrastructures, delivering deep security insight and continuous protection for customers at a lower cost than traditional security solutions. Ful...
Recognizing the need to identify and validate information security professionals’ competency in securing cloud services, the two leading membership organizations focused on cloud and information security, the Cloud Security Alliance (CSA) and (ISC)^2, joined together to develop an international cloud security credential that reflects the most current and comprehensive best practices for securing and optimizing cloud computing environments.
SYS-CON Events announced today that FalconStor Software® Inc., a 15-year innovator of software-defined storage solutions, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. FalconStor Software®, Inc. (NASDAQ: FALC) is a leading software-defined storage company offering a converged, hardware-agnostic, software-defined storage and data services platform. Its flagship solution FreeStor®, utilizes a horizonta...
In most cases, it is convenient to have some human interaction with a web (micro-)service, no matter how small it is. A traditional approach would be to create an HTTP interface, where user requests will be dispatched and HTML/CSS pages must be served. This approach is indeed very traditional for a web site, but not really convenient for a web service, which is not intended to be good looking, 24x7 up and running and UX-optimized. Instead, talking to a web service in a chat-bot mode would be muc...
SYS-CON Events announced today that Column Technologies will exhibit at SYS-CON's @DevOpsSummit at Cloud Expo, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Established in 1998, Column Technologies is a global technology solutions provider with over 400 employees, headquartered in the United States with offices in Canada, India, and the United Kingdom. Column Technologies provides “Best of Breed” technology solutions that automate the key DevOps principal...
SYS-CON Events announced today that AppNeta, the leader in performance insight for business-critical web applications, will exhibit and present at SYS-CON's @DevOpsSummit at Cloud Expo New York, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. AppNeta is the only application performance monitoring (APM) company to provide solutions for all applications – applications you develop internally, business-critical SaaS applications you use and the networks that deli...
Fortunately, meaningful and tangible business cases for IoT are plentiful in a broad array of industries and vertical markets. These range from simple warranty cost reduction for capital intensive assets, to minimizing downtime for vital business tools, to creating feedback loops improving product design, to improving and enhancing enterprise customer experiences. All of these business cases, which will be briefly explored in this session, hinge on cost effectively extracting relevant data from ...
More and more companies are looking to microservices as an architectural pattern for breaking apart applications into more manageable pieces so that agile teams can deliver new features quicker and more effectively. What this pattern has done more than anything to date is spark organizational transformations, setting the foundation for future application development. In practice, however, there are a number of considerations to make that go beyond simply “build, ship, and run,” which changes ho...
When building large, cloud-based applications that operate at a high scale, it’s important to maintain a high availability and resilience to failures. In order to do that, you must be tolerant of failures, even in light of failures in other areas of your application. “Fly two mistakes high” is an old adage in the radio control airplane hobby. It means, fly high enough so that if you make a mistake, you can continue flying with room to still make mistakes. In his session at 18th Cloud Expo, Lee...
SYS-CON Events announced today that (ISC)²® (“ISC-squared”) will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Two leading non-profits focused on cloud and information security, (ISC)² and Cloud Security Alliance (CSA), developed the Certified Cloud Security Professional (CCSP) certification to address the increased demand for cloud security expertise due to rapid growth in cloud. Recently named “The Next...
The Art of DevOps provides a fun overview to help teams understand DevOps. Written in the style of the famous 6th century Chinese manuscript “The Art of War,” this eBook describes DevOps in the form of a mission to continuously deliver assets to the operational battlegrounds safely, securely, and quickly. It’s a fun read with valuable insights.
SYS-CON Events announced today that iDevices®, the preeminent brand in the connected home industry, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. iDevices, the preeminent brand in the connected home industry, has a growing line of HomeKit-enabled products available at the largest retailers worldwide. Through the “Designed with iDevices” co-development program and its custom-built IoT Cloud Infrastruc...
There will be new vendors providing applications, middleware, and connected devices to support the thriving IoT ecosystem. This essentially means that electronic device manufacturers will also be in the software business. Many will be new to building embedded software or robust software. This creates an increased importance on software quality, particularly within the Industrial Internet of Things where business-critical applications are becoming dependent on products controlled by software. Qua...
As enterprises work to take advantage of Big Data technologies, they frequently become distracted by product-level decisions. In most new Big Data builds this approach is completely counter-productive: it presupposes tools that may not be a fit for development teams, forces IT to take on the burden of evaluating and maintaining unfamiliar technology, and represents a major up-front expense. In his session at @BigDataExpo at @ThingsExpo, Andrew Warfield, CTO and Co-Founder of Coho Data, will dis...
The Quantified Economy represents the total global addressable market (TAM) for IoT that, according to a recent IDC report, will grow to an unprecedented $1.3 trillion by 2019. With this the third wave of the Internet-global proliferation of connected devices, appliances and sensors is poised to take off in 2016. In his session at @ThingsExpo, David McLauchlan, CEO and co-founder of Buddy Platform, will discuss how the ability to access and analyze the massive volume of streaming data from mil...