TORONTO, ONTARIO -- (Marketwired) -- 05/05/14 -- Orvana Minerals Corp. (TSX: ORV) (the "Company" or "Orvana") is providing a general update in anticipation of the attendance by Daniella Dimitrov, Orvana's Chief Financial Officer, at the European Gold Forum in Zurich, Switzerland May 6 to May 8, 2014. Ms. Dimitrov is scheduled to present on Thursday, May 8, 2014 at 09:10 a.m. CET.

Operational Update and Outlook

Following a hoisting accident at its Boinas Mine in Spain in June 2013, the Company has been completing the recovery and upgrades to the capabilities of the hoist with enhanced performance design and safety improvements. The hoist and shaft repairs, upgrades and the majority of commissioning were completed during the second quarter of fiscal 2014 allowing hoisting to recommence. The final certification process is expected to be completed early in the third quarter of fiscal 2014. During the certification process the hoist is operational.

Production at the EVBC Mines was lower in the first half of fiscal 2014 primarily as a result of lower than planned grades in the areas mined. Due to the hoisting accident, an alternative production schedule continued to be used during the second quarter of fiscal 2014 which incorporated ramp haulage for all ore, waste and backfill haulage. Backfilling is now generally caught up to normal levels and will be further facilitated with the reduced trucking usage for ore due to hoisting capability. With the completion of the hoist repairs and upgrades and the recovery of the San Martin area, the Company will continue to focus on improving head grades, increasing metal production and reducing total all-in costs per ounce of gold in the second half of fiscal 2014. Management expects the return to higher grade mineralization to take some additional time and, accordingly, is revising its production guidance lower given the volumes of metals produced to date.

At its Don Mario Mine in Bolivia, the Company commissioned two new gravity concentrators towards the end of March 2014. This is expected to increase gold recoveries to between 60% and 65% from between 40% and 45%, resulting in expected increased gold production in the second half of fiscal 2014 and thereafter. Additional work to improve the concentrator support structure and permanent bagging area is currently in progress to ensure optimization of recoveries. Sales of the new gold concentrate are expected to commence by mid-third quarter of fiscal 2014. Given the production from the Don Mario Mine to date and expectations for the balance of the fiscal year, management is revising its production guidance upward for all three metals.

The net result of the changes in guidance for the EVBC and Don Mario Mines is that Orvana's overall guidance for gold remains largely unchanged with the high end of the guidance being reduced. The guidance for copper and silver is being increased. The following table sets out consolidated operating performance data for the EVBC and Don Mario Mines for the periods set out below together with updated fiscal 2014 guidance:


----------------------------------------------------------------------------
                                                    Original         Revised
                                                      FY2014          FY2014
                    Q1 2014 Q2 2014 YTD 2014        Guidance        Guidance
----------------------------------------------------------------------------
EVBC Mines
Milled (tonnes)
 (dmt)              180,713 186,111  366,824
Gold
 Grade (g/t)           2.62    2.80     2.71
 Recovery (%)          92.0    92.2     92.1
 Production (oz)     13,988  15,441   29,429   65,000-75,000   60,000-65,000
Copper
 Grade (%)             0.40    0.41     0.41
 Recovery (%)          79.3    78.2     78.7
 Production ('000
  lbs)                1,258   1,322    2,580         6.0-6.5         5.5-6.0
Silver
 Grade (g/t)           7.23    8.15     7.70
 Recovery (%)          80.5    79.6     80.1
 Production (oz)     33,838  38,846   72,684 175,000-200,000 160,000-180,000
----------------------------------------------------------------------------
Don Mario Mine
Milled (tonnes)     206,416 199,526  405,942
Gold
 Grade (g/t)           1.48    1.45     1.46
 Recovery (%)          49.7    44.1     47.7
 Production (oz)      4,867   4,094    8,961   15,000-18,000   20,000-21,000
Copper
 Grade (%)             1.38    1.51     1.44
 Recovery (%)          55.3    56.3     55.8
 Production ('000
  lbs)                3,461   3,726    7,186       12.0-14.0       13.5-15.0
Silver
 Grade (g/t)          53.57   64.30    58.84
 Recovery (%)          61.6    57.9     59.6
 Production (oz)    218,992 238,810  457,802 700,000-750,000 800,000-900,000
----------------------------------------------------------------------------
Total EVBC and Don
 Mario Mines
Gold (oz)                             38,389   80,000-93,000   80,000-86,000
Copper (million
 lbs)                                    9.8       18.0-20.5       19.0-21.0
                                                                    960,000-
Silver (oz)                          530,486 875,000-950,000       1,080,000
----------------------------------------------------------------------------

Retirement of Chief Operating Officer

Orvana also announces that Mr. James Jacques, Orvana's Chief Operating Officer, is retiring effective May 18, 2014. Since joining the Company in 2011, Mr. Jacques has made significant contributions to the advancement of the EVBC and Don Mario Mines and the Copperwood Project. Orvana's Board of Directors expresses its gratitude to Mr. Jacques for his dedication and services to the Company. "Jim's contributions are numerous in consistently advancing organizational and operational objectives. He will be missed," said Michael Winship, President and Chief Executive Officer. "We thank Jim for his contributions and hard work and wish him the very best." A search is underway for Mr. Jacques replacement.

Divestiture of Copperwood

On February 11, 2014, the Company announced that it had entered into a definitive agreement to sell its Copperwood project for total cash consideration of up to $25 million in aggregate, of which $20 million will be paid in cash on closing and $5 million may be paid in cash or shares of the acquirer, Highland Copper Company Inc. ("Highland"), at Orvana's option, upon occurrence of certain events following closing and/or commercial production including the price of copper exceeding $4.25 and $4.50 within certain specified periods of time. The closing, expected to occur on or before May 31, 2014, is conditional upon, among other things, the completion of a financing by Highland to fund the purchase of Copperwood.

Quarterly Conference Call

The Company will release its second quarter financial results on May 14, 2014 and hold a conference call on May 15, 2014 at 11:00 a.m. (EST) to discuss its financial and operational results. Following the presentation there will be a question and answer period for analysts and investors. The conference call details are as follows and are also available on the front page of Orvana's website (www.orvana.com):

Toll-Free call 877-588-9586;

Participants in the US may call 1-702-800-7084.

About Orvana

Orvana Minerals is a multi-mine gold and copper producer. Orvana's primary asset is the El Valle-Boinas/Carles gold-copper mines in northern Spain. Orvana also owns and operates the Don Mario Mine in Bolivia, processing its copper-gold-silver Upper Mineralized Zone deposit. In February 2014, the Company announced the divestiture of its Copperwood copper project in Michigan, United States. Additional information is available at Orvana's website (www.orvana.com).

Forward Looking Disclaimer

Certain statements in this press release constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws ("forward-looking statements"). Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, potentials, future events or performance (often, but not always, using words or phrases such as "believes", "expects" "plans", "estimates" or "intends" or stating that certain actions, events or results "may", "could", "would", "might", "will" or "are projected to" be taken or achieved) are not statements of historical fact, but are forward-looking statements.

Forward-looking statements relate to, among other things, all aspects of the development of El Valle-Boinas/Carles Mines in Spain (the "EVBC Mines") and the Don Mario Mine in Bolivia and their operations and production; the timing and outcome of such development and production; estimates of future production, operating costs and capital expenditures; mineral resource and reserve estimates; estimates of permitting time lines; statements and information regarding future feasibility studies and their results; future transactions; future metal prices; the ability to achieve additional growth and geographic diversification; future financial performance, including the ability to increase cash flow and profits; future financing requirements; and mine development plans.

Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by Orvana as of the date of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. The estimates and assumptions of Orvana contained or incorporated by reference in this news release, which may prove to be incorrect, include, but are not limited to, the various assumptions set forth herein and in the Company's most recently filed Management's Discussion & Analysis and Annual Information Form in respect of the Company's most recently completed fiscal year (the "Annual Disclosures"), or as otherwise expressly incorporated herein by reference as well as: there being no significant disruptions affecting operations, whether due to labour disruptions, supply disruptions, power disruptions, damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at the EVBC and Don Mario Mines being consistent with the Company's current expectations; political developments in any jurisdiction in which the Company operates being consistent with its current expectations; certain price assumptions for gold, copper and silver; prices for key supplies being approximately consistent with current levels; production and cost of sales forecasts meeting expectations; the accuracy of the Company's current mineral reserve and mineral resource estimates; and labour and materials costs increasing on a basis consistent with Orvana's current expectations.

A variety of inherent risks, uncertainties and factors, many of which are beyond the Company's control, affect the operations, performance and results of the Company and its business, and could cause actual events or results to differ materially from estimated or anticipated events or results expressed or implied by forward looking statements. Some of these risks, uncertainties and factors include fluctuations in the price of gold, silver and copper; the need to recalculate estimates of resources based on actual production experience; the failure to achieve production estimates; variations in the grade of ore mined; variations in the cost of operations; the availability of qualified personnel; the Company's ability to obtain and maintain all necessary regulatory approvals and licenses; the Company's ability to use cyanide in its mining operations; risks generally associated with mineral exploration and development, including the Company's ability to continue to operate the EVBC Mines and/or the Don Mario Mine; the sale of the Company's Copperwood Project in Michigan; the Company's ability to acquire and develop mineral properties and to successfully integrate such acquisitions; the Company's ability to obtain financing when required on terms that are acceptable to the Company; challenges to the Company's interests in its property and mineral rights; current, pending and proposed legislative or regulatory developments or changes in political, social or economic conditions in the countries in which the Company operates; general economic conditions worldwide; and the risks identified in the Annual Disclosures under the heading "Risks and Uncertainties". This list is not exhaustive of the factors that may affect any of the Company's forward-looking statements and reference should also be made to the Company's Annual Disclosures for a description of additional risk factors.

Forward-looking statements are based on management's current plans, estimates, projections, beliefs and opinions and, except as required by law, the Company does not undertake any obligation to update forward-looking statements should assumptions related to these plans, estimates, projections, beliefs and opinions change. Readers are cautioned not to put undue reliance on forward-looking statements.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Basho Technologies has announced the latest release of Basho Riak TS, version 1.3. Riak TS is an enterprise-grade NoSQL database optimized for Internet of Things (IoT). The open source version enables developers to download the software for free and use it in production as well as make contributions to the code and develop applications around Riak TS. Enhancements to Riak TS make it quick, easy and cost-effective to spin up an instance to test new ideas and build IoT applications. In addition to...
You think you know what’s in your data. But do you? Most organizations are now aware of the business intelligence represented by their data. Data science stands to take this to a level you never thought of – literally. The techniques of data science, when used with the capabilities of Big Data technologies, can make connections you had not yet imagined, helping you discover new insights and ask new questions of your data. In his session at @ThingsExpo, Sarbjit Sarkaria, data science team lead ...
Extracting business value from Internet of Things (IoT) data doesn’t happen overnight. There are several requirements that must be satisfied, including IoT device enablement, data analysis, real-time detection of complex events and automated orchestration of actions. Unfortunately, too many companies fall short in achieving their business goals by implementing incomplete solutions or not focusing on tangible use cases. In his general session at @ThingsExpo, Dave McCarthy, Director of Products...
Many private cloud projects were built to deliver self-service access to development and test resources. While those clouds delivered faster access to resources, they lacked visibility, control and security needed for production deployments. In their session at 18th Cloud Expo, Steve Anderson, Product Manager at BMC Software, and Rick Lefort, Principal Technical Marketing Consultant at BMC Software, discussed how a cloud designed for production operations not only helps accelerate developer in...
Ask someone to architect an Internet of Things (IoT) solution and you are guaranteed to see a reference to the cloud. This would lead you to believe that IoT requires the cloud to exist. However, there are many IoT use cases where the cloud is not feasible or desirable. In his session at @ThingsExpo, Dave McCarthy, Director of Products at Bsquare Corporation, will discuss the strategies that exist to extend intelligence directly to IoT devices and sensors, freeing them from the constraints of ...
WebRTC is bringing significant change to the communications landscape that will bridge the worlds of web and telephony, making the Internet the new standard for communications. Cloud9 took the road less traveled and used WebRTC to create a downloadable enterprise-grade communications platform that is changing the communication dynamic in the financial sector. In his session at @ThingsExpo, Leo Papadopoulos, CTO of Cloud9, discussed the importance of WebRTC and how it enables companies to focus...
Venafi has extended the power of its platform in an easy-to-use utility for DevOps teams available for immediate download. Now DevOps teams can eliminate the hassle of acquiring and installing TLS keys and certificates. Instead, customers can focus on speeding up continuous development and deployment, while security teams have complete visibility and can keep the DevOps environment secure and compliant to protect customer data. Extending the Venafi Trust Protection Platform requires only a singl...
Aspose.Total for .NET is the most complete package of all file format APIs for .NET as offered by Aspose. It empowers developers to create, edit, render, print and convert between a wide range of popular document formats within any .NET, C#, ASP.NET and VB.NET applications. Aspose compiles all .NET APIs on a daily basis to ensure that it contains the most up to date versions of each of Aspose .NET APIs. If a new .NET API or a new version of existing APIs is released during the subscription peri...
The competitive landscape of the global cloud computing market in the healthcare industry is crowded due to the presence of a large number of players. The large number of participants has led to the fragmented nature of the market. Some of the major players operating in the global cloud computing market in the healthcare industry are Cisco Systems Inc., Carestream Health Inc., Carecloud Corp., AGFA Healthcare, IBM Corp., Cleardata Networks, Merge Healthcare Inc., Microsoft Corp., Intel Corp., an...
The best-practices for building IoT applications with Go Code that attendees can use to build their own IoT applications. In his session at @ThingsExpo, Indraneel Mitra, Senior Solutions Architect & Technology Evangelist at Cognizant, provided valuable information and resources for both novice and experienced developers on how to get started with IoT and Golang in a day. He also provided information on how to use Intel Arduino Kit, Go Robotics API and AWS IoT stack to build an application tha...
With an estimated 50 billion devices connected to the Internet by 2020, several industries will begin to expand their capabilities for retaining end point data at the edge to better utilize the range of data types and sheer volume of M2M data generated by the Internet of Things. In his session at @ThingsExpo, Don DeLoach, CEO and President of Infobright, discussed the infrastructures businesses will need to implement to handle this explosion of data by providing specific use cases for filterin...
Is your aging software platform suffering from technical debt while the market changes and demands new solutions at a faster clip? It’s a bold move, but you might consider walking away from your core platform and starting fresh. ReadyTalk did exactly that. In his General Session at 19th Cloud Expo, Michael Chambliss, Head of Engineering at ReadyTalk, will discuss why and how ReadyTalk diverted from healthy revenue and over a decade of audio conferencing product development to start an innovati...
Early adopters of IoT viewed it mainly as a different term for machine-to-machine connectivity or M2M. This is understandable since a prerequisite for any IoT solution is the ability to collect and aggregate device data, which is most often presented in a dashboard. The problem is that viewing data in a dashboard requires a human to interpret the results and take manual action, which doesn’t scale to the needs of IoT.
SYS-CON Events announced today the Kubernetes and Google Container Engine Workshop, being held November 3, 2016, in conjunction with @DevOpsSummit at 19th Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA. This workshop led by Sebastian Scheele introduces participants to Kubernetes and Google Container Engine (GKE). Through a combination of instructor-led presentations, demonstrations, and hands-on labs, students learn the key concepts and practices for deploying and maintainin...
Cloud analytics is dramatically altering business intelligence. Some businesses will capitalize on these promising new technologies and gain key insights that’ll help them gain competitive advantage. And others won’t. Whether you’re a business leader, an IT manager, or an analyst, we want to help you and the people you need to influence with a free copy of “Cloud Analytics for Dummies,” the essential guide to this explosive new space for business intelligence.