Energizer Resources Provides Update and Review of Significant Progress on Molo Project Development Milestones

TORONTO, ONTARIO -- (Marketwired) -- 05/06/14 -- Energizer Resources Inc. (TSX: EGZ) (OTCQX: ENZR) (FRANKFURT: YE5) ("Energizer" or the "Company") is pleased to provide a summary of the milestones achieved over the past 18 months and the current status on its flagship Molo Graphite Project in Madagascar.

Feasibility Study in Progress

After completing a private placement on January 15th of this year, Energizer launched a Feasibility Study (FS) through its EPCM contractor, DRA, which is Africa's leading mine engineering and construction company. As part of this study the following work has been completed:


--  Discussions with Madagascar-based contractors regarding fuel, logistics,
    equipment, civil engineering and earthworks.
--  29 infill diamond drill holes and 16 trenches to elevate a portion of
    Molo Graphite Project's Canadian National Instrument ("NI") 43-101
    compliant indicated resource to measured status.
--  3-D variability test work drilling with 4 diamond drill holes.
--  9 geotechnical holes for quantification of rock mechanics.
--  Detailed topographic surveying for pit shell modeling, civil works and
    hydrogeological analysis.
--  Topsoil thickness survey over deposit (deposit found to be covered by a
    thin veneer of soil averaging a thickness of 0.8 metres).
--  Hydrogeological test work over the deposit, including a resistivity
    survey and water sample analysis.

Richard Schler, Energizer's Chief Executive Officer stated, "We look forward to building on the substantial progress we have achieved over the past months in advancing our Molo Graphite Project, which included the completion of an operational pilot plant run as part of our Molo Feasibility Study. I believe this will be an exciting year for Energizer as we work towards achieving the important milestones of securing both mine financing and off-take agreements. Although we have been very active over the past few months pursuing these initiatives, they are tasks that do not easily lend themselves to providing regular news flow. With the recent positive developments in the global flake graphite market centering around lithium-ion batteries for electrical vehicles and large scale energy storage, I believe that conditions are ideal to support the rapid advancement of the Molo Graphite Project".

Feasibility Study Progress Builds Upon Milestone Accomplishments


--  In November 2012, Energizer announced its NI 43-101 resources estimate
    with 9,246m of drilling, establishing the Molo as one of the largest
    known, all-flake graphite deposits in the world;
    --  84.0Mt Indicated @ 6.36% carbon ©.
    --  40.3Mt Inferred @ 6.29%C.

--  On February 26, 2013, Energizer announced the positive results of a PEA
    study, indicating robust economics: $421 Million USD Pre-tax NPV
    discounted @ 10%; 48% Internal rate of return (IRR); 3-year payback;
    $162 Million USD Capital cost.

--  On October 21, 2013, Energizer announced the signing of a Letter of
    Intent with Caterpillar Mining Finance regarding project financing loan
    arrangements for the Molo mine.

--  On November 6, 2013, Energizer announced the results of GDMS analysis
    testing by SGS Canada Inc, the highest level of analytical testing
    possible, and confirmed that the Molo graphite concentrate can achieve
    an ultra-high purity of greater than 99.9%. The hydrometallurgical
    purification test used conventional leach technology.

--  On November 20, 2013, Energizer announced the appointment of Robin
    Borley, B.Tech, Mining Engineering as a Board Director and Senior Vice
    President of Mine Development. Mr. Borley served previously as Mining
    Director for DRA.

--  On January 15, 2014, Energizer announced that it had closed a private
    placement of 61,204,067 common share units at a price of $0.12 for gross
    proceeds of C$7,344,488

--  On January 31, 2014, Energizer announced the robust results from the
    completion of a large scale pilot plant operation. Over 13 tonnes of
    Molo graphite concentrate was produced and results confirmed that a
    significant portion (43.5%) of the flake size distribution is classified
    as "large" and "jumbo-flake", 78.3% of Molo flake meets the minimum
    required size to produce battery-grade graphite and up to 97.7% purity
    can be achieved. through simple flotation alone. These pilot plant
    results were superior to those released in the Company's positive PEA
    study.

--  On April 16, 2014, Energizer announced it finalized the purchase of the
    remaining 25% interest in the Molo Graphite Project from joint venture
    partner Malagasy Minerals Limited. This now gives the Company 100%
    ownership of the Molo Graphite Project area and a 100% interest to all
    of the industrial mineral rights within the acquired property, which
    totals 940 square kilometres (363 square miles).

Targeted Milestones

Energizer is targeting the following key milestones:


--  Upgrading the Molo resource from Indicated to Measured status by Q3
    2014;
--  Completion of full feasibility study by Q4 2014;
--  Completion of partnership and financing agreements, which are currently
    ongoing.
--  Application for mining permit in Q4 2014 upon completion of the FS;
--  Estimated construction schedule of 12-16 months following the securing
    of mine permitting and financing. Project commissioning is targeted to
    begin in Q2/Q3 of 2016.

Qualified Person

Craig Scherba, P.Geo., President and COO is the qualified person for the technical information provided in this release.

About Energizer Resources

Energizer Resources is a mineral exploration and mine development company based in Toronto, Canada, that is developing its 100%-owned, flagship Molo Graphite Project in southern Madagascar.

The Molo Graphite Project is one of the largest known crystalline flake graphite deposits in the world. The Molo Project hosts a NI 43-101 compliant indicated mineral resource of 84.04 million tonnes grading 6.36% carbon (Cg) and an inferred resource grading 6.29% Cg of crystalline flake graphite.

Energizer's total land package in southern Madagascar encompasses approximately 320 kilometers (198 miles) of continuous graphitic trends, where all graphite mineralization is immediately at surface. In addition to the Molo Graphite Project, Energizer has also identified through drilling, trenching and geological mapping at least six other zones that could be potential stand-alone graphite deposits.

Energizer has initiated a Full Feasibility Study, with results to be released to the market by Q4 2014. Results of the Company's recently completed pilot plant operation confirmed that 43.5% of the Molo deposit is classified as the premium-priced large and extra-large flake, with an average purity level in excess of 97% Cg achieved through standard flotation alone. The Company is targeting production in Q2/Q3 of 2016.

For more information on the Molo Graphite Project, please visit our website at www.energizerresources.com.

Safe Harbour: This press release may contain forward-looking statements that may involve a number of risks and uncertainties. Actual events or results could differ materially from expectations and projections set out herein. The above resource estimates were calculated in accordance with National Instrument 43-101 as required by Canadian securities regulatory authorities. For United States reporting purposes, Industry Guide 7 (under the Securities Exchange Act of 1934), as interpreted by the Staff of the SEC, applies different standards in order to classify mineralization as a reserve. Among other things, the terms "measured", "indicated" and "inferred" mineral resources are required pursuant to National Instrument 43-101, the U.S. Securities and Exchange Commission does not recognize such terms. Canadian standards differ significantly from the requirements of the U.S. Securities and Exchange Commission, and mineral resource information contained herein is not comparable to similar information regarding mineral reserves disclosed in accordance with the requirements of the U.S. Securities and Exchange Commission.

Mineral resources are not mineral reserves and do not have demonstrated economic viability. This mineral resource estimate includes inferred resources that are normally considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is also no certainty that the inferred mineral resource will be converted to the measured and indicated mineral resource categories through further drilling, or into a mineral reserve once economic considerations are applied.

U.S. investors should understand that "inferred" mineral resources have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. In addition, investors are cautioned not to assume that any part or all of the Company's mineral resources constitute or will be converted into reserves. Cautionary Statement: Neither TSX Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Exchange) accepts responsibility for the adequacy or accuracy of this release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Aspose.Total for .NET is the most complete package of all file format APIs for .NET as offered by Aspose. It empowers developers to create, edit, render, print and convert between a wide range of popular document formats within any .NET, C#, ASP.NET and VB.NET applications. Aspose compiles all .NET APIs on a daily basis to ensure that it contains the most up to date versions of each of Aspose .NET APIs. If a new .NET API or a new version of existing APIs is released during the subscription peri...
Security, data privacy, reliability, and regulatory compliance are critical factors when evaluating whether to move business applications from in-house, client-hosted environments to a cloud platform. Quality assurance plays a vital role in ensuring that the appropriate level of risk assessment, verification, and validation takes place to ensure business continuity during the migration to a new cloud platform.
SYS-CON Events announced today that 910Telecom will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Housed in the classic Denver Gas & Electric Building, 910 15th St., 910Telecom is a carrier-neutral telecom hotel located in the heart of Denver. Adjacent to CenturyLink, AT&T, and Denver Main, 910Telecom offers connectivity to all major carriers, Internet service providers, Internet backbones and ...
Ovum, a leading technology analyst firm, has published an in-depth report, Ovum Decision Matrix: Selecting a DevOps Release Management Solution, 2016–17. The report focuses on the automation aspects of DevOps, Release Management and compares solutions from the leading vendors.
Continuous testing helps bridge the gap between developing quickly and maintaining high quality products. But to implement continuous testing, CTOs must take a strategic approach to building a testing infrastructure and toolset that empowers their team to move fast. Download our guide to laying the groundwork for a scalable continuous testing strategy.
Adding public cloud resources to an existing application can be a daunting process. The tools that you currently use to manage the software and hardware outside the cloud aren’t always the best tools to efficiently grow into the cloud. All of the major configuration management tools have cloud orchestration plugins that can be leveraged, but there are also cloud-native tools that can dramatically improve the efficiency of managing your application lifecycle. In his session at 18th Cloud Expo, ...
SYS-CON Events announced today that LeaseWeb USA, a cloud Infrastructure-as-a-Service (IaaS) provider, will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. LeaseWeb is one of the world's largest hosting brands. The company helps customers define, develop and deploy IT infrastructure tailored to their exact business needs, by combining various kinds cloud solutions.
Qosmos has announced new milestones in the detection of encrypted traffic and in protocol signature coverage. Qosmos latest software can accurately classify traffic encrypted with SSL/TLS (e.g., Google, Facebook, WhatsApp), P2P traffic (e.g., BitTorrent, MuTorrent, Vuze), and Skype, while preserving the privacy of communication content. These new classification techniques mean that traffic optimization, policy enforcement, and user experience are largely unaffected by encryption. In respect wit...
StackIQ has announced the release of Stacki 3.2. Stacki is an easy-to-use Linux server provisioning tool. Stacki 3.2 delivers new capabilities that simplify the automation and integration of site-specific requirements. StackIQ is the commercial entity behind this open source bare metal provisioning tool. Since the release of Stacki in June of 2015, the Stacki core team has been focused on making the Community Edition meet the needs of members of the community, adding features and value, while ...
For basic one-to-one voice or video calling solutions, WebRTC has proven to be a very powerful technology. Although WebRTC’s core functionality is to provide secure, real-time p2p media streaming, leveraging native platform features and server-side components brings up new communication capabilities for web and native mobile applications, allowing for advanced multi-user use cases such as video broadcasting, conferencing, and media recording.
SYS-CON Events announced today the Kubernetes and Google Container Engine Workshop, being held November 3, 2016, in conjunction with @DevOpsSummit at 19th Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA. This workshop led by Sebastian Scheele introduces participants to Kubernetes and Google Container Engine (GKE). Through a combination of instructor-led presentations, demonstrations, and hands-on labs, students learn the key concepts and practices for deploying and maintainin...
SYS-CON Events announced today that Venafi, the Immune System for the Internet™ and the leading provider of Next Generation Trust Protection, will exhibit at @DevOpsSummit at 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Venafi is the Immune System for the Internet™ that protects the foundation of all cybersecurity – cryptographic keys and digital certificates – so they can’t be misused by bad guys in attacks...
ReadyTalk has expanded the capabilities of the FoxDen collaboration platform announced late last year to include FoxDen Connect, an in-room video collaboration experience that launches with a single touch. With FoxDen Connect, users can now not only engage in HD video conferencing between iOS and Android mobile devices or Chrome browsers, but also set up in-person meeting rooms for video interactions. A host’s mobile device automatically recognizes the presence of a meeting room via beacon tech...
The cloud market growth today is largely in public clouds. While there is a lot of spend in IT departments in virtualization, these aren’t yet translating into a true “cloud” experience within the enterprise. What is stopping the growth of the “private cloud” market? In his general session at 18th Cloud Expo, Nara Rajagopalan, CEO of Accelerite, explored the challenges in deploying, managing, and getting adoption for a private cloud within an enterprise. What are the key differences between wh...
Deploying applications in hybrid cloud environments is hard work. Your team spends most of the time maintaining your infrastructure, configuring dev/test and production environments, and deploying applications across environments – which can be both time consuming and error prone. But what if you could automate provisioning and deployment to deliver error free environments faster? What could you do with your free time?