Rio Alto Drills 314 m @ 0.7 g/t Au at La Arena

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 05/15/14 -- Rio Alto Mining Limited ("Rio Alto" or the "Company") (TSX: RIO)(NYSE: RIOM)(LMA: RIO)(DBFrankfurt: MS2) is pleased to report assay results from 19 reverse circulation ("RC") drill holes within and around the Calaorco Pit at the Company's La Arena Gold Oxide Mine located in La Libertad, northern Peru.

Reference is made to the 2014 oxide gold Reserve Pit which is detailed in the La Arena Project Technical Report with an effective date of December 31, 2013, prepared on behalf of the Company by Mining Plus Peru S.A.C. (the "December 2013 Report"), a copy of which is available under the Company's SEDAR profile at www.sedar.com.

The more significant intercepts were:

CA-R14-007 - 74 m @ 0.42 g/t Au, including 22 m @ 1.06 g/t Au, all of which being outside the 2014 Reserve Pit.

CA-R14-015 - 314 m @ 0.7 g/t Au, of which 166 m @ 0.80 g/t Au being outside the 2014 Reserve Pit.

CA-R14-016 - 230 m @ 0.97 g/t Au, of which 74 m @ 0.67 g/t Au being outside the 2014 Reserve Pit.

Rio Alto acquired the La Arena Gold Project in mid-2009 from IAMGOLD with the objective of bringing the mine into production as rapidly as possible. Twenty months later, the first gold bar at La Arena was poured and since then the Company has produced approximately 550,000 ounces of gold. The principal focus during the first two years of project ownership was to achieve gold production to allow the Company to generate cash flow and fund further expansion and development of the project from this cash flow. Exploration drilling was deferred during this period and only commenced after positive cash flow started to be generated by the project in early 2012.

Since 2012, oxide drilling has resulted in the gold oxide reserve increasing from 821,000 ounces at the beginning of 2011 to 1,056,000 ounces at the beginning of 2014 with approximately 500,000 ounces having been produced during the first two and half years of production. This represents an increase of approximately 780,000 ounces since mining commenced at La Arena.

The following results are from the first 19 RC holes drilled at Calaorco during 2014 with 13 out of the 19 holes intersecting gold mineralization above the mining cutoff grade. These drill holes were within ("Inside") and extended outside or below ("Outside") the 2014 gold oxide Reserve Pit.

The results of the recent drilling program demonstrate that a large amount of oxide brecciated sandstone mineralization (the main mineral type at La Arena) lies outside the 2014 Reserve Pit. The results are very encouraging and indicate the potential to increase oxide gold resources and reserves and the possibility of extending mine life beyond 2019.

A total of 14,200 metres of RC drilling is currently planned to be completed during 2014, in and around the Calaorco Pit. The Company's geologists will interpret the data generated by this drilling program, once it is completed, with the objective of calculating an updated resource and reserve estimate for the gold oxide mineralization at La Arena. Management expects that this drilling program has the potential to allow positive changes to be made to the resource block classification, define new resource blocks and given that the deposit is open to the northwest and at depth, identify new areas to test in order to further increase resources and reserves in the future. The updated resource and reserve estimate for the gold oxide mineralization at La Arena is expected to be released in Q1, 2015.

Drill Results

References to the comments in the following table refer to intercepts within ("Inside") the 2014 Reserve Pit or drill hole intercepts that extended outside or below ("Outside") the 2014 Reserve Pit. A map illustrating drill hole locations and selected drill hole cross sections related to this press release may be accessed by following this link.

Hole ID      From     To  Interval  Au g/t  Ag g/t  Cu ppm          Comments
============================================================================
CA-R14-001           Not significant Intercepts
CA-R14-002           Not significant Intercepts
CA-R14-003    116    176        60    0.31    1.97      77    Inside Reserve
                                                                         Pit
 Including    116    134        18    0.72    3.56     151   Outside Reserve
                                                                         Pit
CA-R14-003    190    218        28    0.44    1.04     176   Outside Reserve
                                                                         Pit
CA-R14-004      6     26        20    0.14    0.13      28    Inside Reserve
                                                                         Pit
CA-R14-004     92    110        18    0.15    0.21      28    Inside Reserve
                                                                         Pit
CA-R14-004    120    168        48    0.38    0.92      36   Outside Reserve
                                                                         Pit
CA-R14-005           Not significant Intercepts
CA-R14-006           Not significant Intercepts
CA-R14-007     12     94        82    0.62    0.62     101    Inside Reserve
                                                                         Pit
CA-R14-007    110    138        28    0.19    0.32      16   Outside Reserve
                                                                         Pit
CA-R14-007    150    164        14    0.16    0.33      44   Outside Reserve
                                                                         Pit
CA-R14-007    202    276        74    0.42    0.51      83   Outside Reserve
                                                                         Pit
 Including    254    276        22    1.06    1.30     146   Outside Reserve
                                                                         Pit
CA-R14-008           Not significant Intercepts
CA-R14-009     30     90        60    0.18    0.36      52    Inside Reserve
                                                                         Pit
CA-R14-009    112    272       160    0.40    0.71      68   Outside Reserve
                                                                         Pit
 Including    254    268        14    1.56    0.73     113   Outside Reserve
                                                                         Pit
CA-R14-010           Not significant Intercepts
CA-R14-011           Not significant Intercepts
CA-R14-012           Not significant Intercepts
CA-R14-013     28     44        16    0.29    0.73      16    Inside Reserve
                                                                         Pit
CA-R14-013     66     76        10    0.23    0.74      17    Inside Reserve
                                                                         Pit
CA-R14-013    108    118        10    0.16    0.32      23   Outside Reserve
                                                                         Pit
CA-R14-013    132    150        18    0.18    0.32      21   Outside Reserve
                                                                         Pit
CA-R14-013    166    248        82    0.25    0.26      66   Outside Reserve
                                                                         Pit
 Including    166    188        22    0.46    0.39     163   Outside Reserve
                                                                         Pit
CA-R14-014     18     56        38    0.20    0.13      60    Inside Reserve
                                                                         Pit
CA-R14-014     64    118        54    0.70    0.55      55    Inside Reserve
                                                                         Pit
 Including     82     86         4    1.26    1.15      24    Inside Reserve
                                                                         Pit
 Including    102    108         6    4.10    1.57     238    Inside Reserve
                                                                         Pit
CA-R14-014    156    162         6    1.93    0.87     226   Outside Reserve
                                                                         Pit
CA-R14-014    152    222        70    0.35    0.34      50   Outside Reserve
                                                                         Pit
 Including    206    210         4    1.12    0.30     133   Outside Reserve
                                                                         Pit
CA-R14-014    232    282        50    0.74    0.19      88   Outside Reserve
                                                                         Pit
 Including    266    280        14    1.90    0.24     233   Outside Reserve
                                                                         Pit
CA-R14-014    294    304        10    0.15    0.22      11   Outside Reserve
                                                                         Pit
CA-R14-015      0      8         8    0.29    0.10     113    Inside Reserve
                                                                         Pit
CA-R14-015     22    336       314    0.70    0.21     113    Inside Reserve
                                                                         Pit
 Including     22     26         4    2.15    0.10     432    Inside Reserve
                                                                         Pit
 Including     72     86        14    0.96    0.21      43    Inside Reserve
                                                                         Pit
 Including     96    110        14    2.18    0.53      72   Outside Reserve
                                                                         Pit
 Including    170    336       166    0.80    0.24     137   Outside Reserve
                                                                         Pit
CA-R14-016      0    230       230    0.97    0.72      78    Inside/Outside
                                                                 Reserve Pit
 Including      0     36        36    2.75    1.11      28    Inside Reserve
                                                                         Pit
 Including    156    230        74    0.67    0.70     123   Outside Reserve
                                                                         Pit
 Including    214    230        16    1.38    1.99     242   Outside Reserve
                                                                         Pit
CA-R14-017      0    164       164    0.45    0.17      80    Inside/Outside
                                                                 Reserve Pit
 Including     40     48         8    1.72    0.23     372    Inside Reserve
                                                                         Pit
 Including     82     94        12    1.69    0.15     269    Inside Reserve
                                                                         Pit
CA-R14-017    206    226        20    0.23    0.10      17   Outside Reserve
                                                                         Pit
CA-R14-018    102    210       108    0.20    0.80      32    Inside Reserve
                                                                         Pit
 Including    114    128        14    0.82    1.63      73   Outside Reserve
                                                                         Pit
CA-R14-019     30     78        48    0.72    0.68      69    Inside Reserve
                                                                         Pit
 Including     38     68        30    1.04    0.67      94    Inside Reserve
                                                                         Pit
CA-R14-019     88    138        50    0.21    0.65      22    Inside Reserve
                                                                         Pit
CA-R14-019    172    210        38    0.49    1.22     211   Outside Reserve
                                                                         Pit
 Including    182    192        10    0.85    1.78      80   Outside Reserve
                                                                         Pit
CA-R14-019    224    241        17    0.32    0.35      32   Outside Reserve
                                                                         Pit

Sampling of the reverse circulation drilling and sample preparation were performed by Rio Alto personnel and were carried out under strict protocols recommended in the NI 43-101 Technical Report dated July 31, 2010 prepared by Coffey Mining Pty Ltd for the Company (the "Report"). Samples were taken every 2m and split in half to yield seven to ten kilogram samples. Drill sample recovery was generally in excess of 90%. Rio Alto has a rigorous QA/QC program over the chain-of-custody of samples and the insertion of blanks, duplicates, and certified reference standards in each batch of samples. Samples were shipped to CERTIMIN in Lima where they were dried, crushed, pulverized, and assayed. All gold assays were obtained by standard 50g fire assaying with AA finish. All silver assays reported in the press release were obtained by Aqua-Regia dissolution followed by ICP measurement. CERTIMIN is an ISO 9001:2000 certified laboratory.

Phase II Update

Good progress is being made in respect to the completion of the feasibility study for the Phase II copper/gold project at La Arena. On January 6, 2014, the Company announced that it had received formal notification from the Ministry of Energy and Mines of Peru that approval had been given for modifications to its Environmental Impact Study (EIA) for the La Arena Project Gold Oxide Mine. This EIA modification allows Rio Alto to apply for permits for a future Phase II open pit sulphide mine, construct an 18,000 tonne per day copper/gold concentrator, expand the current waste dump facilities to accommodate sulphide waste and to use the Calaorco Pit for tailings deposition once open pit oxide reserves are exhausted. However, the recent increase in the size of the adjacent gold oxide deposit and possible expansion of the oxide resources and reserves as a consequence of the ongoing drill program, has meant that the general layout of the Phase II infrastructure needs to be revised. It is important that none of the Phase II infrastructure, such as process plant, conveying systems, stockpiles and waste dumps are impeding the possible future expansion of the oxide mine and its associated infrastructure. This revision of the general layout has meant that the completion of the feasibility study will be delayed until later in the year. Current estimates for timing are sometime in Q4, 2014.

"We are all excited at the results coming out of our current oxide drilling program at La Arena. It is hoped that the program underway can increase the size and life of the gold oxide mine and provide our technical team with a better understanding of what the optimal general layout for Phase II should be. La Arena has been a great project from the outset and continues to evolve positively for all stakeholders involved," commented Alex Black, President & CEO.

Mr. Enrique Garay, MSc. P.Geo (AIG Member), Vice President Geology of Rio Alto, is the Qualified Person (as defined by NI 43-101) responsible for managing the Company's exploration programs and disclosure of drilling results. Mr. Garay has read and approved the scientific and technical information in this news release.

For additional information regarding La Arena Project please refer to the December 2013 Report prepared on behalf of the Company by Mining Plus Peru S.A.C., a copy of which is available on the Company's SEDAR profile at www.sedar.com.

Forward-Looking Statements

Certain statements contained herein constitute forward-looking statements, most particularly the potential to increase the resource and reserve estimate of the gold oxide mineralization at La Arena Project, the timing for the completion of an updated resource and reserve estimate for the gold oxide mineralization at La Arena Project, to extend the life of La Arena Gold Oxide Mine and the timing for the completion of a feasibility study for the La Arena copper/gold sulphide project. All statements included herein, other than statements of historical fact, are forward-looking information and such information involves various risks and uncertainties. Rio Alto believes the expectations reflected in these forward looking statements are reasonable but no assurance can be given that these expectations will prove to be correct and such forward-looking statements in this press release should not be unduly relied upon. A description of assumptions used to develop such forward-looking information and a description of risk factors that may cause actual results to differ materially from forward-looking information can be found in Rio Alto's disclosure documents on the SEDAR website at www.sedar.com. Forward-looking statements included in this press release are made as of the date of this press release and Rio Alto disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, except as expressly required by applicable securities legislation.

To learn more about Rio Alto Mining Limited, please visit: www.rioaltomining.com or Rio Alto's SEDAR profile at www.sedar.com.

ON BEHALF OF THE BOARD OF RIO ALTO MINING LIMITED

Alex Black, President, CEO & Director

Contacts:
Rio Alto Mining Limited
Alex Black
President & CEO
+511 625 9900
866.393.4493 (FAX)
[email protected]

Rio Alto Mining Limited
Alejandra Gomez
Investor Relations
604.628.1401
866.393.4493 (FAX)
[email protected]
www.rioaltomining.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that DXWorldExpo has been named “Global Sponsor” of SYS-CON's 21st International Cloud Expo, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Digital Transformation is the key issue driving the global enterprise IT business. Digital Transformation is most prominent among Global 2000 enterprises and government institutions.
One of the biggest challenges with adopting a DevOps mentality is: new applications are easily adapted to cloud-native, microservice-based, or containerized architectures - they can be built for them - but old applications need complex refactoring. On the other hand, these new technologies can require relearning or adapting new, oftentimes more complex, methodologies and tools to be ready for production. In his general session at @DevOpsSummit at 20th Cloud Expo, Chris Brown, Solutions Marketi...
SYS-CON Events announced today that Nihon Micron will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Nihon Micron Co., Ltd. strives for technological innovation to establish high-density, high-precision processing technology for providing printed circuit board and metal mount RFID tags used for communication devices. For more inf...
SYS-CON Events announced today that Ryobi Systems will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Ryobi Systems Co., Ltd., as an information service company, specialized in business support for local governments and medical industry. We are challenging to achive the precision farming with AI. For more information, visit http:...
SYS-CON Events announced today that mruby Forum will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. mruby is the lightweight implementation of the Ruby language. We introduce mruby and the mruby IoT framework that enhances development productivity. For more information, visit http://forum.mruby.org/.
SYS-CON Events announced today that Mobile Create USA will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Mobile Create USA Inc. is an MVNO-based business model that uses portable communication devices and cellular-based infrastructure in the development, sales, operation and mobile communications systems incorporating GPS capabi...
SYS-CON Events announced today that Daiya Industry will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Daiya Industry specializes in orthotic support systems and assistive devices with pneumatic artificial muscles in order to contribute to an extended healthy life expectancy. For more information, please visit https://www.daiyak...
SYS-CON Events announced today that Fusic will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Fusic Co. provides mocks as virtual IoT devices. You can customize mocks, and get any amount of data at any time in your test. For more information, visit https://fusic.co.jp/english/.
SYS-CON Events announced today that Keisoku Research Consultant Co. will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Keisoku Research Consultant, Co. offers research and consulting in a wide range of civil engineering-related fields from information construction to preservation of cultural properties. For more information, vi...
SYS-CON Events announced today that MIRAI Inc. will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. MIRAI Inc. are IT consultants from the public sector whose mission is to solve social issues by technology and innovation and to create a meaningful future for people.
SYS-CON Events announced today that Interface Corporation will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Interface Corporation is a company developing, manufacturing and marketing high quality and wide variety of industrial computers and interface modules such as PCIs and PCI express. For more information, visit http://www.i...
Today companies are looking to achieve cloud-first digital agility to reduce time-to-market, optimize utilization of resources, and rapidly deliver disruptive business solutions. However, leveraging the benefits of cloud deployments can be complicated for companies with extensive legacy computing environments. In his session at 21st Cloud Expo, Craig Sproule, founder and CEO of Metavine, will outline the challenges enterprises face in migrating legacy solutions to the cloud. He will also prese...
SYS-CON Events announced today that Enroute Lab will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Enroute Lab is an industrial design, research and development company of unmanned robotic vehicle system. For more information, please visit http://elab.co.jp/.
Elon Musk is among the notable industry figures who worries about the power of AI to destroy rather than help society. Mark Zuckerberg, on the other hand, embraces all that is going on. AI is most powerful when deployed across the vast networks being built for Internets of Things in the manufacturing, transportation and logistics, retail, healthcare, government and other sectors. Is AI transforming IoT for the good or the bad? Do we need to worry about its potential destructive power? Or will we...
In his session at @ThingsExpo, Greg Gorman is the Director, IoT Developer Ecosystem, Watson IoT, will provide a short tutorial on Node-RED, a Node.js-based programming tool for wiring together hardware devices, APIs and online services in new and interesting ways. It provides a browser-based editor that makes it easy to wire together flows using a wide range of nodes in the palette that can be deployed to its runtime in a single-click. There is a large library of contributed nodes that help so...