Atacama Pacific Provides Cerro Maricunga and Corporate Update

TORONTO, ONTARIO -- (Marketwired) -- 05/15/14 -- Atacama Pacific Gold Corporation (TSX VENTURE: ATM) ("Atacama Pacific") is pleased to provide an update on the Cerro Maricunga oxide-associated gold project prefeasibility study and the disposal of its surplus water interests in the area of Cerro Maricunga.

The Cerro Maricunga prefeasibility study remains on schedule for completion during the second quarter of 2014. The key mining and processing segments of the report are progressing well and quotes for equipment and key infrastructural items, such as the water pipeline, are pending.

A further set of six column tests have recently been completed with final results anticipated in June 2014. Excluding the pending results, Atacama Pacific has completed 29 column tests and over 200 bottle rolls tests, from various depths throughout the pit-confined resource, confirming that the Cerro Maricunga deposit is amenable to heap leach processing.

Cerro Maricunga hosts a pit-confined, oxide-associated gold resource of 3.470 million ounces of gold in 248.8 million tonnes grading 0.43 grams per tonne gold ("g/t Au") in the measured and indicated category with a further 43,000 ounces of gold in 3.1 million tonnes grading 0.43 g/t Au in the inferred category. The estimate was confined within a Whittle pit shell modelled at a gold price of US$1,200 per ounce with a cut-off grade of 0.18 g/t Au.

As announced on July 10, 2013, Atacama Pacific purchased 80 litres per second ('l/s") of water from a Chilean water utility in Copiapo, Chile, Aguas Chanar S.A. ("Aguas Chanar"), for the development of Cerro Maricunga, along with the right of first refusal for additional water if and when available.

With a secure and sustainable source of water acquired for Cerro Maricunga, Atacama Pacific has been disposing of its water exploration interests in the region.

As reported on November 19, 2013, Atacama Pacific entered into an agreement to sell its water-related rights to a Chilean subsidiary of Gold Fields Ltd. ("Gold Fields"). Atacama Pacific recently received a second payment from Gold Fields of US$300,000 and with that payment, Gold Fields is committed to making a further payment of US$500,000 on December 31, 2014. Upon receipt of approval from the Direccion General de Aguas, the Chilean water authority, for all or a portion of the 42 l/s of water discovered previously by Atacama Pacific within the concessions, Atacama Pacific will receive a payment of US$62,000 per l/s approved. If Gold Fields receives approval for the 42 l/s of water discovered, the final payment to Atacama Pacific would be US$2,604,000.

On May 15, 2014, Atacama Pacific entered into an agreement with Hydro Exploraciones SpA under which it will issue 350,000 common shares at a price of $1.15 per share to settle all obligations under two water exploration agreements. These agreements were related to water concessions located 70 kilometres to the east of Cerro Maricunga. The share payment agreement is subject to approval by the TSX Venture Exchange.

Dr. Albrecht Schneider, the Executive Chairman, a director and 9.9% shareholder of Atacama Pacific, owns a controlling interest in Hydro Exploraciones SpA.

National Instrument 43-101

As defined by Section 1.5 of National Instrument 43-101 ("NI 43-101") of the Canadian Securities Administrators, the Qualified Person for the Cerro Maricunga Property is Sergio Diaz, a resident of Santiago, Chile and a registered member of the "Comision Calificadora de Competencias en Recursos y Reservas Mineras" (Chilean Mining Commission, registry n degrees 051), an accepted foreign association as defined by NI 43-101 (Appendix A). Mr. Diaz has reviewed and verified the contents of this press release.

The Cerro Maricunga resource estimate was prepared under CIM Definition Standards (2005). Dr. Eduardo Magri, a mining engineer (University of Witwatersrand) and a Fellow of the Southern African Institute of Mining and Metallurgy with over 30 years of industry experience, is the Independent Qualified Person for the resource estimate.

About Atacama Pacific Gold Corporation

Atacama's business is the acquisition, exploration and development of precious metals resource properties in Chile. Atacama's goal is to become a producer of gold through the exploration and development of its Cerro Maricunga project, located in Region III, 117 kilometres northeast of the city of Copiapo. Atacama also has interests in four other mineral properties within close proximity of Cerro Maricunga and a fifth property in Chile's Region I.

FORWARD-LOOKING STATEMENTS

This news release contains forward-looking statements, including predictions, projections and forecasts. Forward-looking statements include, but are not limited to, statements with respect to the timing of the prefeasibility study, statements regarding the expectation to increase mineral resources, statements regarding expectations for receipt of permits and environmental approvals, exploration results (including with respect to water resources), the success of exploration activities generally, mine development prospects, and potential future gold production. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "planning", "expects" or "does not expect", "continues", "scheduled", "estimates", "forecasts", "intends", "potential", "anticipates", "does not anticipate", or "belief", or describes a "goal", or variation of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

Forward-looking statements involve known and unknown risks, future events, conditions, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, prediction, projection, forecast, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, the results of due diligence activities, changes in economic parameters and assumptions, the interpretation and actual results of current exploration activities; changes in project parameters as plans continue to be refined; the results of regulatory and permitting processes; future prices of gold; possible variations in grade or recovery rates; failure of equipment or processes to operate as anticipated; labour disputes and other risks of the mining industry; the results of further economic and technical studies, delays in obtaining governmental approvals or financing or in the completion of exploration, as well as those factors disclosed in Atacama Pacific's publicly filed documents.

Although Atacama Pacific has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
Atacama Pacific Gold Corporation
Carl B. Hansen
President and CEO
416 861 8267
[email protected]
www.atacamapacific.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
With more than 30 Kubernetes solutions in the marketplace, it's tempting to think Kubernetes and the vendor ecosystem has solved the problem of operationalizing containers at scale or of automatically managing the elasticity of the underlying infrastructure that these solutions need to be truly scalable. Far from it. There are at least six major pain points that companies experience when they try to deploy and run Kubernetes in their complex environments. In this presentation, the speaker will d...
While DevOps most critically and famously fosters collaboration, communication, and integration through cultural change, culture is more of an output than an input. In order to actively drive cultural evolution, organizations must make substantial organizational and process changes, and adopt new technologies, to encourage a DevOps culture. Moderated by Andi Mann, panelists discussed how to balance these three pillars of DevOps, where to focus attention (and resources), where organizations might...
The deluge of IoT sensor data collected from connected devices and the powerful AI required to make that data actionable are giving rise to a hybrid ecosystem in which cloud, on-prem and edge processes become interweaved. Attendees will learn how emerging composable infrastructure solutions deliver the adaptive architecture needed to manage this new data reality. Machine learning algorithms can better anticipate data storms and automate resources to support surges, including fully scalable GPU-c...
When building large, cloud-based applications that operate at a high scale, it's important to maintain a high availability and resilience to failures. In order to do that, you must be tolerant of failures, even in light of failures in other areas of your application. "Fly two mistakes high" is an old adage in the radio control airplane hobby. It means, fly high enough so that if you make a mistake, you can continue flying with room to still make mistakes. In his session at 18th Cloud Expo, Le...
Machine learning has taken residence at our cities' cores and now we can finally have "smart cities." Cities are a collection of buildings made to provide the structure and safety necessary for people to function, create and survive. Buildings are a pool of ever-changing performance data from large automated systems such as heating and cooling to the people that live and work within them. Through machine learning, buildings can optimize performance, reduce costs, and improve occupant comfort by ...
As Cybric's Chief Technology Officer, Mike D. Kail is responsible for the strategic vision and technical direction of the platform. Prior to founding Cybric, Mike was Yahoo's CIO and SVP of Infrastructure, where he led the IT and Data Center functions for the company. He has more than 24 years of IT Operations experience with a focus on highly-scalable architectures.
The explosion of new web/cloud/IoT-based applications and the data they generate are transforming our world right before our eyes. In this rush to adopt these new technologies, organizations are often ignoring fundamental questions concerning who owns the data and failing to ask for permission to conduct invasive surveillance of their customers. Organizations that are not transparent about how their systems gather data telemetry without offering shared data ownership risk product rejection, regu...
CI/CD is conceptually straightforward, yet often technically intricate to implement since it requires time and opportunities to develop intimate understanding on not only DevOps processes and operations, but likely product integrations with multiple platforms. This session intends to bridge the gap by offering an intense learning experience while witnessing the processes and operations to build from zero to a simple, yet functional CI/CD pipeline integrated with Jenkins, Github, Docker and Azure...
René Bostic is the Technical VP of the IBM Cloud Unit in North America. Enjoying her career with IBM during the modern millennial technological era, she is an expert in cloud computing, DevOps and emerging cloud technologies such as Blockchain. Her strengths and core competencies include a proven record of accomplishments in consensus building at all levels to assess, plan, and implement enterprise and cloud computing solutions. René is a member of the Society of Women Engineers (SWE) and a m...
Dhiraj Sehgal works in Delphix's product and solution organization. His focus has been DevOps, DataOps, private cloud and datacenters customers, technologies and products. He has wealth of experience in cloud focused and virtualized technologies ranging from compute, networking to storage. He has spoken at Cloud Expo for last 3 years now in New York and Santa Clara.
Enterprises are striving to become digital businesses for differentiated innovation and customer-centricity. Traditionally, they focused on digitizing processes and paper workflow. To be a disruptor and compete against new players, they need to gain insight into business data and innovate at scale. Cloud and cognitive technologies can help them leverage hidden data in SAP/ERP systems to fuel their businesses to accelerate digital transformation success.
Containers and Kubernetes allow for code portability across on-premise VMs, bare metal, or multiple cloud provider environments. Yet, despite this portability promise, developers may include configuration and application definitions that constrain or even eliminate application portability. In this session we'll describe best practices for "configuration as code" in a Kubernetes environment. We will demonstrate how a properly constructed containerized app can be deployed to both Amazon and Azure ...
Poor data quality and analytics drive down business value. In fact, Gartner estimated that the average financial impact of poor data quality on organizations is $9.7 million per year. But bad data is much more than a cost center. By eroding trust in information, analytics and the business decisions based on these, it is a serious impediment to digital transformation.
Digital Transformation: Preparing Cloud & IoT Security for the Age of Artificial Intelligence. As automation and artificial intelligence (AI) power solution development and delivery, many businesses need to build backend cloud capabilities. Well-poised organizations, marketing smart devices with AI and BlockChain capabilities prepare to refine compliance and regulatory capabilities in 2018. Volumes of health, financial, technical and privacy data, along with tightening compliance requirements by...
Predicting the future has never been more challenging - not because of the lack of data but because of the flood of ungoverned and risk laden information. Microsoft states that 2.5 exabytes of data are created every day. Expectations and reliance on data are being pushed to the limits, as demands around hybrid options continue to grow.