Maya Gold & Silver Announces First Mineral Reserves at Zgounder Silver Mine and Files a Pre-Feasibility Study (PFS)

BLAINVILLE, QUEBEC -- (Marketwired) -- 05/22/14 -- Maya Gold & Silver Inc. ("Maya" or the "Corporation") (TSX VENTURE: MYA) announces that it has filed on SEDAR today the Pre-Feasibility Study ("PFS") for its Zgounder Silver Mine in Morocco. The results from the PFS demonstrate the economic viability of the Zgounder Mine based on the mineral reserves derived from resources that were outlined by GoldMinds Geoservices Inc. The PFS highlighted that a significant amount of inferred resources are present which have the potential to be converted to reserves with additional drilling, and there remains an excellent exploration potential to further expand the size of the existing mineral inventory. The PFS also provided a more conservative estimate of profitability than the Preliminary Economic Assessment (PEA) due to the exclusion of the inferred resources; conversely, thereby the PFS provides estimates that have a lower geological risk, which is key element for financing purposes.

Highlights of the Zgounder Silver Mine PFS Study include:

--  An anticipated mine life of 6 years with the current reserves with
    Internal rate of return of 128 per cent;

--  First year silver production of 582,600 ounces, followed by two years at
    885,400 ounces, and the final three years at 914,000 ounces per year;

--  Mill feed grade estimated at 317 g/t Ag;

--  Total operating cost of USD109.50 per tonne (averaged over the expected
    mine's life);

--  Additional capex requirements total USD3.8 million, which include the
    proposed concentrator expansion;

--  Net present value of USD27.9 million (discounted at 6.5 per cent) at
    silver price of USD20.50 per ounce;

--  The Zgounder PFS was prepared as a strictly underground mine based
    solely on the measured and indicated mineral resources reported on
    February 19, 2014.


               Mineral Reserve Estimate as at March 21st, 2014
----------------------------------------------------------------------------
         Proven                 Probable              Proven + Probable
----------------------------------------------------------------------------
         Ag                       Ag                         Ag
 Tonnes  g/t   Ounces    Tonnes   g/t   Ounces     Tonnes   g/t     Ounces
----------------------------------------------------------------------------
152,000  281  1,371,000  421,000  330  4,474,000  573,000  317.3  5,845,000
----------------------------------------------------------------------------

Notes:

The reserves have been estimated in accordance with the definitions and guidelines adopted from the Canadian Institute of Mining, Metallurgy and Petroleum (CIM Standards on Mineral Resources and Reserves). The reserves are based entirely on measured and indicated resources and were converted as probable and proven respectively. Since the material is from underground mining operations, the cut-off grade includes the costs of production, processing and the general & administration (G&A).

Parameters of cut-off grade estimation (the exchange rate has been set at 7.63 MAD = $1.00, as of December 29, 2013.)

                     ----------------------------------
                     Parameters          Unit      Data
                     ----------------------------------
                     Mining             USD/t     32.79
                     Mining dilution        %     10.00
                     Development        USD/t     10.79
                     Processing         USD/t     45.89
                     G&A                USD/t      8.54
                     Metal price       USD/oz     20.50
                     Metal price          U/g      0.66
                     Process recovery       %      0.90
                     Cut-off grade        g/t       166
                     ----------------------------------

Details of the mineral resource estimate and the previously completed Preliminary Economic Assessment (PEA) can be found in the Company's new release dated March 5 th, 2014 which has been filed and is available for viewing and download on www.sedar.com or on Maya's website (http://mayagoldsilver.com/wp-content/uploads/2014/03/2014-19-03_MayaPEA_Final-Report.pdf). It is clear that the results of the PEA are significantly better than those presented herein due to the exclusion of the inferred resources. Maya anticipates that further drilling of the deposit could convert a significant portion of the inferred tonnage and potential structures into mineral resources of better categories and translate into additional years of production and revenue.

Additional to the mineral resource and reserves described herein and within previous press releases, a Mineral Potential between 1.5 to 2.0 million tonnes grading 300 to 400 g/t Ag has been estimated. The "Mineral Potential" is the tonnage which could be contained between elevations 1975 and 1750 (225m vertical panel) along the existing mine openings. This represents the historical amount processed by the previous operator plus the current NI 43-101 mineral resource disclosure between the surface and level 1925. It does not consider the eastern extension (276400E) where surface medieval workings extent for another 200 meters eastward with no drilling beneath. The potential quantity and grade reported as "Mineral Potential", is conceptual in nature, that there has been insufficient exploration to define a mineral resource and that it is uncertain if further exploration will result in the target being delineated as a mineral resource.

The report, titled "NI 43-101 Technical Report, Pre-Feasibility Study of the Zgounder Silver Deposit, Kingdom of Morocco" is dated May 16, 2014 with an effective date of March 21, 2014. It was prepared in conformity with NI 43-101 by Claude Duplessis, Eng. of Goldminds Geoservices Inc. and Gaston Gagnon, Eng. and Gilbert Rousseau, Eng. of SGS Canada Inc.; each is an "Independent Qualified Person" under NI 43-101.

Qualified Persons

The technical content of this news release has been reviewed by Gaston Gagnon, Eng. and Gilbert Rousseau, Eng. from SGS Canada Inc. and by Claude Duplessis Eng. Sr. Geological Engineer from GoldMinds Geoservices Inc.: all independent Qualified Persons under NI 43-101 standards.

ABOUT MAYA

Maya Gold & Silver Inc. is a Canadian listed mining focused on the exploration and development of gold and silver deposits in Morocco. Maya recently initiated mining at its Zgounder Mine. The Corporation's shares trade on the TSX Venture Exchange under the symbol "MYA".

For further information on Maya visit www.mayagoldsilver.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward-looking statements

This release may contain forward-looking statements including management's assessments of future plans and operations, and expectations of future production. These statements are based on current expectations that involve a number of risks and uncertainties, which could cause actual results to differ materially from those anticipated. These risks include, but are not limited to, the risks associated with the mining and exploration industry (e.g. operational risks in development, exploration and production; delays or changes in plans with respect to exploration or development projects or capital expenditures; the uncertainty of reserve estimates; the uncertainty of estimates and projections relating to production and the uncertainty of the availability of capital). The assumptions used in the preparation of such statements, although considered reasonable at the time of preparation, may prove to be imprecise and, as such, undue reliance should not be placed on forward-looking statements.

Contacts:
Maya Gold & Silver Inc.
Guy Goulet
Chief Executive Officer
450-435-0700 ext. 204

Nathalie Dion
Investor Relations
450-435-0700 ext. 202

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that CAST Software will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CAST was founded more than 25 years ago to make the invisible visible. Built around the idea that even the best analytics on the market still leave blind spots for technical teams looking to deliver better software and prevent outages, CAST provides the software intelligence that matter ...
The next XaaS is CICDaaS. Why? Because CICD saves developers a huge amount of time. CD is an especially great option for projects that require multiple and frequent contributions to be integrated. But… securing CICD best practices is an emerging, essential, yet little understood practice for DevOps teams and their Cloud Service Providers. The only way to get CICD to work in a highly secure environment takes collaboration, patience and persistence. Building CICD in the cloud requires rigorous ar...
SYS-CON Events announced today that Daiya Industry will exhibit at the Japanese Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Ruby Development Inc. builds new services in short period of time and provides a continuous support of those services based on Ruby on Rails. For more information, please visit https://github.com/RubyDevInc.
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busine...
As businesses evolve, they need technology that is simple to help them succeed today and flexible enough to help them build for tomorrow. Chrome is fit for the workplace of the future — providing a secure, consistent user experience across a range of devices that can be used anywhere. In her session at 21st Cloud Expo, Vidya Nagarajan, a Senior Product Manager at Google, will take a look at various options as to how ChromeOS can be leveraged to interact with people on the devices, and formats th...
First generation hyperconverged solutions have taken the data center by storm, rapidly proliferating in pockets everywhere to provide further consolidation of floor space and workloads. These first generation solutions are not without challenges, however. In his session at 21st Cloud Expo, Wes Talbert, a Principal Architect and results-driven enterprise sales leader at NetApp, will discuss how the HCI solution of tomorrow will integrate with the public cloud to deliver a quality hybrid cloud e...
SYS-CON Events announced today that Yuasa System will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Yuasa System is introducing a multi-purpose endurance testing system for flexible displays, OLED devices, flexible substrates, flat cables, and films in smartphones, wearables, automobiles, and healthcare.
Is advanced scheduling in Kubernetes achievable? Yes, however, how do you properly accommodate every real-life scenario that a Kubernetes user might encounter? How do you leverage advanced scheduling techniques to shape and describe each scenario in easy-to-use rules and configurations? In his session at @DevOpsSummit at 21st Cloud Expo, Oleg Chunikhin, CTO at Kublr, will answer these questions and demonstrate techniques for implementing advanced scheduling. For example, using spot instances ...
Companies are harnessing data in ways we once associated with science fiction. Analysts have access to a plethora of visualization and reporting tools, but considering the vast amount of data businesses collect and limitations of CPUs, end users are forced to design their structures and systems with limitations. Until now. As the cloud toolkit to analyze data has evolved, GPUs have stepped in to massively parallel SQL, visualization and machine learning.
The session is centered around the tracing of systems on cloud using technologies like ebpf. The goal is to talk about what this technology is all about and what purpose it serves. In his session at 21st Cloud Expo, Shashank Jain, Development Architect at SAP, will touch upon concepts of observability in the cloud and also some of the challenges we have. Generally most cloud-based monitoring tools capture details at a very granular level. To troubleshoot problems this might not be good enough.
DevOps is under attack because developers don’t want to mess with infrastructure. They will happily own their code into production, but want to use platforms instead of raw automation. That’s changing the landscape that we understand as DevOps with both architecture concepts (CloudNative) and process redefinition (SRE). Rob Hirschfeld’s recent work in Kubernetes operations has led to the conclusion that containers and related platforms have changed the way we should be thinking about DevOps and...
SYS-CON Events announced today that Taica will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Taica manufacturers Alpha-GEL brand silicone components and materials, which maintain outstanding performance over a wide temperature range -40C to +200C. For more information, visit http://www.taica.co.jp/english/.
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busine...
We all know that end users experience the Internet primarily with mobile devices. From an app development perspective, we know that successfully responding to the needs of mobile customers depends on rapid DevOps – failing fast, in short, until the right solution evolves in your customers' relationship to your business. Whether you’re decomposing an SOA monolith, or developing a new application cloud natively, it’s not a question of using microservices – not doing so will be a path to eventual b...
Enterprises have taken advantage of IoT to achieve important revenue and cost advantages. What is less apparent is how incumbent enterprises operating at scale have, following success with IoT, built analytic, operations management and software development capabilities – ranging from autonomous vehicles to manageable robotics installations. They have embraced these capabilities as if they were Silicon Valley startups. As a result, many firms employ new business models that place enormous impor...