True Gold Announces Completion of Detailed Engineering

Potential for Cost Savings Identified in Key Areas

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 05/29/14 -- True Gold Mining Inc. (TSX VENTURE: TGM) "True Gold" or the "Company") is pleased to announce that detailed engineering and construction-level design work for the proposed Karma Gold Mine ("Karma Mine") were completed on schedule and under budget, and indicate a potential for cost savings in a number of important areas.

In total, detailed engineering results indicate a potential savings of up to $9.7 million. This represents a possible 7% decrease in initial CAPEX from the $131.5 million estimated in the Karma Feasibility Study(1). Given that the Feasibility Study estimate is considered accurate to within a +/- 15% range, the results of detailed engineering suggest a very low risk of a cost overrun as the project advances through construction.

"We are very pleased with the results from detailed engineering, which reinforce the technical simplicity and low capital cost nature of this open pit, heap leach project," stated Peter Carter, Chief Operating Officer and Vice President, Engineering of True Gold. "These results further support the Karma Mine as a leading development project globally."

Potential cost savings were identified in a number of areas, including:


--  Earthworks, civil construction, and fuel storage costs can be reduced by
    employing a construction methodology proven during the building of the
    recently completed barrage.

--  Freight costs can be reduced through in-country fabrication and local
    and regional sourcing of materials.

--  Relocation costs for the settlement of Tang-Zugu can be eliminated by
    rescheduling the construction of the leach pad without impacting the
    production plan.

The detailed engineering work was undertaken by SENET Pty ("SENET") of Johannesburg, South Africa, a mineral process and engineering firm with extensive heap leach and Africa mine construction experience. SENET was the consulting engineering firm that successfully completed the Karma Feasibility Study in December 2013, and more recently assisted True Gold in overseeing construction of the recently completed barrage (water dam).

In addition to completing detailed engineering, the Company has undertaken preliminary construction activities including construction of the plant site access road and administration offices, and the upgrade of 10 kilometres of public road leading to the project site. Recently, True Gold announced the signing of a letter of intent to purchase its major mining equipment, and held a ground breaking ceremony to officially mark the start of construction of the Karma Mine.

(1) See Technical Report, entitled "Updated Resource Estimate and Feasibility Study on the Karma Gold Project," prepared by P&E Mining Consultants Inc. dated effective December 17, 2013, a copy of which is available under the Company's profile on SEDAR at www.sedar.com.

Qualified Persons

Peter C. Carter, P. Eng., Chief Operating Officer and Vice President Engineering of the Company, is the designated Qualified Person for this news release within the meaning of National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") and has reviewed and verified that the technical information contained in this release is accurate and approves of the written disclosure of same.

About True Gold

True Gold Mining Inc. is where gold comes to life. We are committed to growing a successful gold exploration, development and production company, by focusing on projects with low costs, low technical risks and solid economics. The Company's board, management and technical teams have proven track records in gold exploration, development, operations and production worldwide.

Additional information about the Company and its activities may be found on the Company's website at www.truegoldmining.com and under the Company's profile at www.sedar.com.

ON BEHALF OF THE BOARD

Dwayne Melrose, President & CEO

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Certain statements made and information contained in this news release and elsewhere constitutes "forward-looking information" within the meaning of Canadian securities legislation. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may constitute forward-looking statements. Such forward-looking statements are based on certain assumptions and are subject to risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation, with respect to statements regarding, the potential to growing a successful gold exploration, development and production company, expectations that corporate social responsibility ("CSR") programs and local community engagement will reduce project risk, continued excellent community relations that will bear clear benefits for local residents and the Company, including improved project design, reduced costs, water for community use and reduced social impacts, continued local community support for the development of the Karma Project, the possibility that the key personnel in the Karma Project CSR leadership team may not perform as anticipated or remain with the Company, accidents, and risks and uncertainties relating to equipment breakdowns, risk of undiscovered, title defects and surface access, labour disputes, the potential for unexpected costs and expenses, commodity price fluctuations, currency fluctuations, risk that the Company will not be able to access the required financing for the development of the Karma Project, political risk, the potential accretive nature that newly discovered mineralization at previously disclosed drill targets may have on the Karma Project, the potential for growth and scalability of the Karma Project including, but not limited to, potential for additional mining centres, risks and uncertainties relating to the interpretation of drill results and the estimation of mineral resources and reserves, the geology, grade and continuity of mineral deposits, the possibility that future exploration and development results in the Karma Project will not be consistent with the Company's expectations, the resource estimate (as disclosed in the Technical

Report dated effective March 13, 2014 titled "Technical Report and Updated Resource Estimate on the Karma Gold Project Burkina Faso, West Africa" which is available under the Company's profile at www.sedar.com), and other risks and uncertainties including those described under Risk Factors in each management discussion and analysis and in the Company's annual information form which are available under the Company's profile at www.sedar.com. Forward-looking information is based on various assumptions including, without limitation, the expectations and beliefs of management, the assumed long term price of gold, that the Company will receive required permits and access to surface rights, that the Company can access required financing to be in a position to consider a production decision, appropriate and sufficient equipment and labour will be available and accessible to the Company to meet its development goals, retention of key personnel and that the political environment within Burkina Faso will continue to support the development of environmentally safe mining projects. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Accordingly, readers are advised not to place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statement that may be made from time to time by the Company or on its behalf, except in accordance with applicable securities laws.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
If there is anything we have learned by now, is that every business paves their own unique path for releasing software- every pipeline, implementation and practices are a bit different, and DevOps comes in all shapes and sizes. Software delivery practices are often comprised of set of several complementing (or even competing) methodologies – such as leveraging Agile, DevOps and even a mix of ITIL, to create the combination that’s most suitable for your organization and that maximize your busines...
Struggling to keep up with increasing application demand? Learn how Platform as a Service (PaaS) can streamline application development processes and make resource management easy.
In his session at @ThingsExpo, Chris Klein, CEO and Co-founder of Rachio, will discuss next generation communities that are using IoT to create more sustainable, intelligent communities. One example is Sterling Ranch, a 10,000 home development that – with the help of Siemens – will integrate IoT technology into the community to provide residents with energy and water savings as well as intelligent security. Everything from stop lights to sprinkler systems to building infrastructures will run ef...
SYS-CON Events announced today that Peak 10, Inc., a national IT infrastructure and cloud services provider, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Peak 10 provides reliable, tailored data center and network services, cloud and managed services. Its solutions are designed to scale and adapt to customers’ changing business needs, enabling them to lower costs, improve performance and focus inter...
You think you know what’s in your data. But do you? Most organizations are now aware of the business intelligence represented by their data. Data science stands to take this to a level you never thought of – literally. The techniques of data science, when used with the capabilities of Big Data technologies, can make connections you had not yet imagined, helping you discover new insights and ask new questions of your data. In his session at @ThingsExpo, Sarbjit Sarkaria, data science team lead ...
Whether your IoT service is connecting cars, homes, appliances, wearable, cameras or other devices, one question hangs in the balance – how do you actually make money from this service? The ability to turn your IoT service into profit requires the ability to create a monetization strategy that is flexible, scalable and working for you in real-time. It must be a transparent, smoothly implemented strategy that all stakeholders – from customers to the board – will be able to understand and comprehe...
Machine Learning helps make complex systems more efficient. By applying advanced Machine Learning techniques such as Cognitive Fingerprinting, wind project operators can utilize these tools to learn from collected data, detect regular patterns, and optimize their own operations. In his session at 18th Cloud Expo, Stuart Gillen, Director of Business Development at SparkCognition, will discuss how research has demonstrated the value of Machine Learning in delivering next generation analytics to im...
In the world of DevOps there are ‘known good practices’ – aka ‘patterns’ – and ‘known bad practices’ – aka ‘anti-patterns.' Many of these patterns and anti-patterns have been developed from real world experience, especially by the early adopters of DevOps theory; but many are more feasible in theory than in practice, especially for more recent entrants to the DevOps scene. In this power panel at @DevOpsSummit at 18th Cloud Expo, moderated by DevOps Conference Chair Andi Mann, panelists will dis...
See storage differently! Storage performance problems have only gotten worse and harder to solve as applications have become largely virtualized and moved to a cloud-based infrastructure. Storage performance in a virtualized environment is not just about IOPS, it is about how well that potential performance is guaranteed to individual VMs for these apps as the number of VMs keep going up real time. In his session at 18th Cloud Expo, Dhiraj Sehgal, in product and marketing at Tintri, will discu...
So, you bought into the current machine learning craze and went on to collect millions/billions of records from this promising new data source. Now, what do you do with them? Too often, the abundance of data quickly turns into an abundance of problems. How do you extract that "magic essence" from your data without falling into the common pitfalls? In her session at @ThingsExpo, Natalia Ponomareva, Software Engineer at Google, will provide tips on how to be successful in large scale machine lear...
Unless you don’t use the internet, don’t live in California, or haven’t been paying attention to the recent news… you should be aware that self-driving cars are on their way to becoming a reality. I have seen them – they are real. If you believe in the future reality of self-driving cars, then continue reading on. If you don’t believe in the future possibilities, then I am not sure what to do to convince you other than discuss the very real changes that will roll out with the consumer producti...
Up until last year, enterprises that were looking into cloud services usually undertook a long-term pilot with one of the large cloud providers, running test and dev workloads in the cloud. With cloud’s transition to mainstream adoption in 2015, and with enterprises migrating more and more workloads into the cloud and in between public and private environments, the single-provider approach must be revisited. In his session at 18th Cloud Expo, Yoav Mor, multi-cloud solution evangelist at Cloudy...
There is an ever-growing explosion of new devices that are connected to the Internet using “cloud” solutions. This rapid growth is creating a massive new demand for efficient access to data. And it’s not just about connecting to that data anymore. This new demand is bringing new issues and challenges and it is important for companies to scale for the coming growth. And with that scaling comes the need for greater security, gathering and data analysis, storage, connectivity and, of course, the...
This is not a small hotel event. It is also not a big vendor party where politicians and entertainers are more important than real content. This is Cloud Expo, the world's longest-running conference and exhibition focused on Cloud Computing and all that it entails. If you want serious presentations and valuable insight about Cloud Computing for three straight days, then register now for Cloud Expo.
IoT device adoption is growing at staggering rates, and with it comes opportunity for developers to meet consumer demand for an ever more connected world. Wireless communication is the key part of the encompassing components of any IoT device. Wireless connectivity enhances the device utility at the expense of ease of use and deployment challenges. Since connectivity is fundamental for IoT device development, engineers must understand how to overcome the hurdles inherent in incorporating multipl...