True Gold Announces Completion of Detailed Engineering

Potential for Cost Savings Identified in Key Areas

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 05/29/14 -- True Gold Mining Inc. (TSX VENTURE: TGM) "True Gold" or the "Company") is pleased to announce that detailed engineering and construction-level design work for the proposed Karma Gold Mine ("Karma Mine") were completed on schedule and under budget, and indicate a potential for cost savings in a number of important areas.

In total, detailed engineering results indicate a potential savings of up to $9.7 million. This represents a possible 7% decrease in initial CAPEX from the $131.5 million estimated in the Karma Feasibility Study(1). Given that the Feasibility Study estimate is considered accurate to within a +/- 15% range, the results of detailed engineering suggest a very low risk of a cost overrun as the project advances through construction.

"We are very pleased with the results from detailed engineering, which reinforce the technical simplicity and low capital cost nature of this open pit, heap leach project," stated Peter Carter, Chief Operating Officer and Vice President, Engineering of True Gold. "These results further support the Karma Mine as a leading development project globally."

Potential cost savings were identified in a number of areas, including:


--  Earthworks, civil construction, and fuel storage costs can be reduced by
    employing a construction methodology proven during the building of the
    recently completed barrage.

--  Freight costs can be reduced through in-country fabrication and local
    and regional sourcing of materials.

--  Relocation costs for the settlement of Tang-Zugu can be eliminated by
    rescheduling the construction of the leach pad without impacting the
    production plan.

The detailed engineering work was undertaken by SENET Pty ("SENET") of Johannesburg, South Africa, a mineral process and engineering firm with extensive heap leach and Africa mine construction experience. SENET was the consulting engineering firm that successfully completed the Karma Feasibility Study in December 2013, and more recently assisted True Gold in overseeing construction of the recently completed barrage (water dam).

In addition to completing detailed engineering, the Company has undertaken preliminary construction activities including construction of the plant site access road and administration offices, and the upgrade of 10 kilometres of public road leading to the project site. Recently, True Gold announced the signing of a letter of intent to purchase its major mining equipment, and held a ground breaking ceremony to officially mark the start of construction of the Karma Mine.

(1) See Technical Report, entitled "Updated Resource Estimate and Feasibility Study on the Karma Gold Project," prepared by P&E Mining Consultants Inc. dated effective December 17, 2013, a copy of which is available under the Company's profile on SEDAR at www.sedar.com.

Qualified Persons

Peter C. Carter, P. Eng., Chief Operating Officer and Vice President Engineering of the Company, is the designated Qualified Person for this news release within the meaning of National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") and has reviewed and verified that the technical information contained in this release is accurate and approves of the written disclosure of same.

About True Gold

True Gold Mining Inc. is where gold comes to life. We are committed to growing a successful gold exploration, development and production company, by focusing on projects with low costs, low technical risks and solid economics. The Company's board, management and technical teams have proven track records in gold exploration, development, operations and production worldwide.

Additional information about the Company and its activities may be found on the Company's website at www.truegoldmining.com and under the Company's profile at www.sedar.com.

ON BEHALF OF THE BOARD

Dwayne Melrose, President & CEO

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Certain statements made and information contained in this news release and elsewhere constitutes "forward-looking information" within the meaning of Canadian securities legislation. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may constitute forward-looking statements. Such forward-looking statements are based on certain assumptions and are subject to risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation, with respect to statements regarding, the potential to growing a successful gold exploration, development and production company, expectations that corporate social responsibility ("CSR") programs and local community engagement will reduce project risk, continued excellent community relations that will bear clear benefits for local residents and the Company, including improved project design, reduced costs, water for community use and reduced social impacts, continued local community support for the development of the Karma Project, the possibility that the key personnel in the Karma Project CSR leadership team may not perform as anticipated or remain with the Company, accidents, and risks and uncertainties relating to equipment breakdowns, risk of undiscovered, title defects and surface access, labour disputes, the potential for unexpected costs and expenses, commodity price fluctuations, currency fluctuations, risk that the Company will not be able to access the required financing for the development of the Karma Project, political risk, the potential accretive nature that newly discovered mineralization at previously disclosed drill targets may have on the Karma Project, the potential for growth and scalability of the Karma Project including, but not limited to, potential for additional mining centres, risks and uncertainties relating to the interpretation of drill results and the estimation of mineral resources and reserves, the geology, grade and continuity of mineral deposits, the possibility that future exploration and development results in the Karma Project will not be consistent with the Company's expectations, the resource estimate (as disclosed in the Technical

Report dated effective March 13, 2014 titled "Technical Report and Updated Resource Estimate on the Karma Gold Project Burkina Faso, West Africa" which is available under the Company's profile at www.sedar.com), and other risks and uncertainties including those described under Risk Factors in each management discussion and analysis and in the Company's annual information form which are available under the Company's profile at www.sedar.com. Forward-looking information is based on various assumptions including, without limitation, the expectations and beliefs of management, the assumed long term price of gold, that the Company will receive required permits and access to surface rights, that the Company can access required financing to be in a position to consider a production decision, appropriate and sufficient equipment and labour will be available and accessible to the Company to meet its development goals, retention of key personnel and that the political environment within Burkina Faso will continue to support the development of environmentally safe mining projects. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Accordingly, readers are advised not to place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statement that may be made from time to time by the Company or on its behalf, except in accordance with applicable securities laws.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that eCube Systems, a leading provider of middleware modernization, integration, and management solutions, will exhibit at @DevOpsSummit at 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. eCube Systems offers a family of middleware evolution products and services that maximize return on technology investment by leveraging existing technical equity to meet evolving business needs. ...
SYS-CON Events announced today Telecom Reseller has been named “Media Sponsor” of SYS-CON's 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Telecom Reseller reports on Unified Communications, UCaaS, BPaaS for enterprise and SMBs. They report extensively on both customer premises based solutions such as IP-PBX as well as cloud based and hosted platforms.
The 19th International Cloud Expo has announced that its Call for Papers is open. Cloud Expo, to be held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, brings together Cloud Computing, Big Data, Internet of Things, DevOps, Digital Transformation, Microservices and WebRTC to one location. With cloud computing driving a higher percentage of enterprise IT budgets every year, it becomes increasingly important to plant your flag in this fast-expanding business opportuni...
For basic one-to-one voice or video calling solutions, WebRTC has proven to be a very powerful technology. Although WebRTC’s core functionality is to provide secure, real-time p2p media streaming, leveraging native platform features and server-side components brings up new communication capabilities for web and native mobile applications, allowing for advanced multi-user use cases such as video broadcasting, conferencing, and media recording.
Pulzze Systems was happy to participate in such a premier event and thankful to be receiving the winning investment and global network support from G-Startup Worldwide. It is an exciting time for Pulzze to showcase the effectiveness of innovative technologies and enable them to make the world smarter and better. The reputable contest is held to identify promising startups around the globe that are assured to change the world through their innovative products and disruptive technologies. There w...
Is the ongoing quest for agility in the data center forcing you to evaluate how to be a part of infrastructure automation efforts? As organizations evolve toward bimodal IT operations, they are embracing new service delivery models and leveraging virtualization to increase infrastructure agility. Therefore, the network must evolve in parallel to become equally agile. Read this essential piece of Gartner research for recommendations on achieving greater agility.
Data is the fuel that drives the machine learning algorithmic engines and ultimately provides the business value. In his session at Cloud Expo, Ed Featherston, a director and senior enterprise architect at Collaborative Consulting, will discuss the key considerations around quality, volume, timeliness, and pedigree that must be dealt with in order to properly fuel that engine.
To leverage Continuous Delivery, enterprises must consider impacts that span functional silos, as well as applications that touch older, slower moving components. Managing the many dependencies can cause slowdowns. See how to achieve continuous delivery in the enterprise.
Enterprises have forever faced challenges surrounding the sharing of their intellectual property. Emerging cloud adoption has made it more compelling for enterprises to digitize their content, making them available over a wide variety of devices across the Internet. In his session at 19th Cloud Expo, Santosh Ahuja, Director of Architecture at Impiger Technologies, will introduce various mechanisms provided by cloud service providers today to manage and share digital content in a secure manner....
Using new techniques of information modeling, indexing, and processing, new cloud-based systems can support cloud-based workloads previously not possible for high-throughput insurance, banking, and case-based applications. In his session at 18th Cloud Expo, John Newton, CTO, Founder and Chairman of Alfresco, described how to scale cloud-based content management repositories to store, manage, and retrieve billions of documents and related information with fast and linear scalability. He addres...
Aspose.Total for .NET is the most complete package of all file format APIs for .NET as offered by Aspose. It empowers developers to create, edit, render, print and convert between a wide range of popular document formats within any .NET, C#, ASP.NET and VB.NET applications. Aspose compiles all .NET APIs on a daily basis to ensure that it contains the most up to date versions of each of Aspose .NET APIs. If a new .NET API or a new version of existing APIs is released during the subscription peri...
Akana has announced the availability of version 8 of its API Management solution. The Akana Platform provides an end-to-end API Management solution for designing, implementing, securing, managing, monitoring, and publishing APIs. It is available as a SaaS platform, on-premises, and as a hybrid deployment. Version 8 introduces a lot of new functionality, all aimed at offering customers the richest API Management capabilities in a way that is easier than ever for API and app developers to use.
SYS-CON Events announced today that Isomorphic Software will exhibit at DevOps Summit at 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Isomorphic Software provides the SmartClient HTML5/AJAX platform, the most advanced technology for building rich, cutting-edge enterprise web applications for desktop and mobile. SmartClient combines the productivity and performance of traditional desktop software with the simp...
DevOps at Cloud Expo, taking place Nov 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 19th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long dev...
Personalization has long been the holy grail of marketing. Simply stated, communicate the most relevant offer to the right person and you will increase sales. To achieve this, you must understand the individual. Consequently, digital marketers developed many ways to gather and leverage customer information to deliver targeted experiences. In his session at @ThingsExpo, Lou Casal, Founder and Principal Consultant at Practicala, discussed how the Internet of Things (IoT) has accelerated our abil...