True Gold Announces Completion of Detailed Engineering

Potential for Cost Savings Identified in Key Areas

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 05/29/14 -- True Gold Mining Inc. (TSX VENTURE: TGM) "True Gold" or the "Company") is pleased to announce that detailed engineering and construction-level design work for the proposed Karma Gold Mine ("Karma Mine") were completed on schedule and under budget, and indicate a potential for cost savings in a number of important areas.

In total, detailed engineering results indicate a potential savings of up to $9.7 million. This represents a possible 7% decrease in initial CAPEX from the $131.5 million estimated in the Karma Feasibility Study(1). Given that the Feasibility Study estimate is considered accurate to within a +/- 15% range, the results of detailed engineering suggest a very low risk of a cost overrun as the project advances through construction.

"We are very pleased with the results from detailed engineering, which reinforce the technical simplicity and low capital cost nature of this open pit, heap leach project," stated Peter Carter, Chief Operating Officer and Vice President, Engineering of True Gold. "These results further support the Karma Mine as a leading development project globally."

Potential cost savings were identified in a number of areas, including:


--  Earthworks, civil construction, and fuel storage costs can be reduced by
    employing a construction methodology proven during the building of the
    recently completed barrage.

--  Freight costs can be reduced through in-country fabrication and local
    and regional sourcing of materials.

--  Relocation costs for the settlement of Tang-Zugu can be eliminated by
    rescheduling the construction of the leach pad without impacting the
    production plan.

The detailed engineering work was undertaken by SENET Pty ("SENET") of Johannesburg, South Africa, a mineral process and engineering firm with extensive heap leach and Africa mine construction experience. SENET was the consulting engineering firm that successfully completed the Karma Feasibility Study in December 2013, and more recently assisted True Gold in overseeing construction of the recently completed barrage (water dam).

In addition to completing detailed engineering, the Company has undertaken preliminary construction activities including construction of the plant site access road and administration offices, and the upgrade of 10 kilometres of public road leading to the project site. Recently, True Gold announced the signing of a letter of intent to purchase its major mining equipment, and held a ground breaking ceremony to officially mark the start of construction of the Karma Mine.

(1) See Technical Report, entitled "Updated Resource Estimate and Feasibility Study on the Karma Gold Project," prepared by P&E Mining Consultants Inc. dated effective December 17, 2013, a copy of which is available under the Company's profile on SEDAR at www.sedar.com.

Qualified Persons

Peter C. Carter, P. Eng., Chief Operating Officer and Vice President Engineering of the Company, is the designated Qualified Person for this news release within the meaning of National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") and has reviewed and verified that the technical information contained in this release is accurate and approves of the written disclosure of same.

About True Gold

True Gold Mining Inc. is where gold comes to life. We are committed to growing a successful gold exploration, development and production company, by focusing on projects with low costs, low technical risks and solid economics. The Company's board, management and technical teams have proven track records in gold exploration, development, operations and production worldwide.

Additional information about the Company and its activities may be found on the Company's website at www.truegoldmining.com and under the Company's profile at www.sedar.com.

ON BEHALF OF THE BOARD

Dwayne Melrose, President & CEO

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Certain statements made and information contained in this news release and elsewhere constitutes "forward-looking information" within the meaning of Canadian securities legislation. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may constitute forward-looking statements. Such forward-looking statements are based on certain assumptions and are subject to risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation, with respect to statements regarding, the potential to growing a successful gold exploration, development and production company, expectations that corporate social responsibility ("CSR") programs and local community engagement will reduce project risk, continued excellent community relations that will bear clear benefits for local residents and the Company, including improved project design, reduced costs, water for community use and reduced social impacts, continued local community support for the development of the Karma Project, the possibility that the key personnel in the Karma Project CSR leadership team may not perform as anticipated or remain with the Company, accidents, and risks and uncertainties relating to equipment breakdowns, risk of undiscovered, title defects and surface access, labour disputes, the potential for unexpected costs and expenses, commodity price fluctuations, currency fluctuations, risk that the Company will not be able to access the required financing for the development of the Karma Project, political risk, the potential accretive nature that newly discovered mineralization at previously disclosed drill targets may have on the Karma Project, the potential for growth and scalability of the Karma Project including, but not limited to, potential for additional mining centres, risks and uncertainties relating to the interpretation of drill results and the estimation of mineral resources and reserves, the geology, grade and continuity of mineral deposits, the possibility that future exploration and development results in the Karma Project will not be consistent with the Company's expectations, the resource estimate (as disclosed in the Technical

Report dated effective March 13, 2014 titled "Technical Report and Updated Resource Estimate on the Karma Gold Project Burkina Faso, West Africa" which is available under the Company's profile at www.sedar.com), and other risks and uncertainties including those described under Risk Factors in each management discussion and analysis and in the Company's annual information form which are available under the Company's profile at www.sedar.com. Forward-looking information is based on various assumptions including, without limitation, the expectations and beliefs of management, the assumed long term price of gold, that the Company will receive required permits and access to surface rights, that the Company can access required financing to be in a position to consider a production decision, appropriate and sufficient equipment and labour will be available and accessible to the Company to meet its development goals, retention of key personnel and that the political environment within Burkina Faso will continue to support the development of environmentally safe mining projects. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Accordingly, readers are advised not to place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statement that may be made from time to time by the Company or on its behalf, except in accordance with applicable securities laws.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that AppNeta, the leader in performance insight for business-critical web applications, will exhibit and present at SYS-CON's @DevOpsSummit at Cloud Expo New York, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. AppNeta is the only application performance monitoring (APM) company to provide solutions for all applications – applications you develop internally, business-critical SaaS applications you use and the networks that deli...
Join us at Cloud Expo | @ThingsExpo 2016 – June 7-9 at the Javits Center in New York City and November 1-3 at the Santa Clara Convention Center in Santa Clara, CA – and deliver your unique message in a way that is striking and unforgettable by taking advantage of SYS-CON's unmatched high-impact, result-driven event / media packages.
With major technology companies and startups seriously embracing IoT strategies, now is the perfect time to attend @ThingsExpo 2016 in New York and Silicon Valley. Learn what is going on, contribute to the discussions, and ensure that your enterprise is as "IoT-Ready" as it can be! Internet of @ThingsExpo, taking place Nov 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 17th Cloud Expo and will feature technical sessions from a rock star conference faculty ...
In the rush to compete in the digital age, a successful digital transformation is essential, but many organizations are setting themselves up for failure. There’s a common misconception that the process is just about technology, but it’s not. It’s about your business. It shouldn’t be treated as an isolated IT project; it should be driven by business needs with the committed involvement of a range of stakeholders.
SYS-CON Events announced today that BMC Software has been named "Siver Sponsor" of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2015 at the Javits Center in New York, New York. BMC is a global leader in innovative software solutions that help businesses transform into digital enterprises for the ultimate competitive advantage. BMC Digital Enterprise Management is a set of innovative IT solutions designed to make digital business fast, seamless, and optimized from mainframe to mo...
SoftLayer operates a global cloud infrastructure platform built for Internet scale. With a global footprint of data centers and network points of presence, SoftLayer provides infrastructure as a service to leading-edge customers ranging from Web startups to global enterprises. SoftLayer's modular architecture, full-featured API, and sophisticated automation provide unparalleled performance and control. Its flexible unified platform seamlessly spans physical and virtual devices linked via a world...
The IoTs will challenge the status quo of how IT and development organizations operate. Or will it? Certainly the fog layer of IoT requires special insights about data ontology, security and transactional integrity. But the developmental challenges are the same: People, Process and Platform. In his session at @ThingsExpo, Craig Sproule, CEO of Metavine, will demonstrate how to move beyond today's coding paradigm and share the must-have mindsets for removing complexity from the development proc...
18th Cloud Expo, taking place June 7-9, 2016, at the Javits Center in New York City, NY, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy. Meanwhile, 94% of enterprises are using some...
SYS-CON Events announced today that Isomorphic Software will exhibit at SYS-CON's [email protected] at Cloud Expo New York, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Isomorphic Software provides the SmartClient HTML5/AJAX platform, the most advanced technology for building rich, high-productivity enterprise web applications for any device. SmartClient couples the industry’s broadest, deepest UI component set with a java server framework to deliver an end-...
In his keynote at 18th Cloud Expo, Andrew Keys, Co-Founder of ConsenSys Enterprise, will provide an overview of the evolution of the Internet and the Database and the future of their combination – the Blockchain. Andrew Keys is Co-Founder of ConsenSys Enterprise. He comes to ConsenSys Enterprise with capital markets, technology and entrepreneurial experience. Previously, he worked for UBS investment bank in equities analysis. Later, he was responsible for the creation and distribution of life ...
SYS-CON Events announced today that Tintri Inc., a leading producer of VM-aware storage (VAS) for virtualization and cloud environments, will exhibit at the 18th International CloudExpo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, New York, and the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
Designing IoT applications is complex, but deploying them in a scalable fashion is even more complex. A scalable, API first IaaS cloud is a good start, but in order to understand the various components specific to deploying IoT applications, one needs to understand the architecture of these applications and figure out how to scale these components independently. In his session at @ThingsExpo, Nara Rajagopalan is CEO of Accelerite, will discuss the fundamental architecture of IoT applications, ...
The IoT is changing the way enterprises conduct business. In his session at @ThingsExpo, Eric Hoffman, Vice President at EastBanc Technologies, discuss how businesses can gain an edge over competitors by empowering consumers to take control through IoT. We'll cite examples such as a Washington, D.C.-based sports club that leveraged IoT and the cloud to develop a comprehensive booking system. He'll also highlight how IoT can revitalize and restore outdated business models, making them profitable...
SYS-CON Events announced today that Commvault, a global leader in enterprise data protection and information management, has been named “Bronze Sponsor” of SYS-CON's 18th International Cloud Expo, which will take place on June 7–9, 2016, at the Javits Center in New York City, NY, and the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Commvault is a leading provider of data protection and information management...
SYS-CON Events announced today Object Management Group® has been named “Media Sponsor” of SYS-CON's 18th International Cloud Expo, which will take place on June 7–9, 2016, at the Javits Center in New York City, NY, and the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.