Copper North Announces Results of Preliminary Economic Assessment of Gold and Silver Recovery at Carmacks Copper

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 05/30/14 -- Copper North Mining Corp. ("Copper North" or the "Company") (TSX VENTURE: COL) is pleased to announce the results of a preliminary economic assessment (the "PEA") that evaluates the recovery of gold and silver alongside the recovery of copper at the proposed Carmacks Copper leach project. The Project is located near the village of Carmacks in Central Yukon. The PEA will be filed on SEDAR within the next 45 days.

By adding gold and silver extraction, the PEA supersedes the Oct 2012 Feasibility Study of copper leaching prepared by M3 Engineering and Technology Corporation ("M3"). The NI 43-101 compliant report was filed on SEDAR Nov 27, 2012. The Feasibility Study for Carmacks Copper was limited to the evaluation of heap leaching of oxide copper to produce cathode copper, and did not include gold and silver recovery.

The Company indicated in its April 25, 2014 news release that it was undertaking a strategic review of the Carmacks Copper project to explore opportunities for improving project economics. The first phase of the review was to evaluate the recovery of gold and silver alongside the copper leach facility and is the basis of the PEA. The PEA combines the previous study of copper heap leaching with the results of the Phase I conceptual study of gold and silver recovery. The first phase of work was undertaken by Alistair Kent, P.Eng. of Merit Consultants International Inc. and Dr. Morris Beattie, P.Eng.; both are Independent Qualified Persons. Their work to assess the potential viability of additional gold and silver recovery, as presented in this PEA, has been combined with the results of the previous studies on geology, mineral resources, potential mining plan, and potential copper heap leaching design.

The PEA will be followed by a second phase of re-engineering and optimization of the mine and processing plan. Upon completion of Phase II study, considering improvement opportunities, a new prefeasibility or feasibility study will be prepared for project financing purposes.

The results of the preliminary leach test work and modelling of gold and silver recovery are positive and a broader study is warranted. The previous potential open pit mine plan remains unchanged from that proposed in the M3 Feasibility Study and is the basis of the PEA. Estimated capital and operating costs for the recovery of gold and silver are added to the estimate for copper recovery (M3 Feasibility Study) to provide new capital and operating costs for the PEA. The addition of capital and operating costs for gold and silver recovery, to those from the M3 Feasibility Study, are conceptual and substantial additional work is required to provide the certainty of a feasibility study.

Dr. Harlan Meade, President and CEO of Copper North states: "The results of the Preliminary Economic Assessment" are quite favourable and confirm that the recovery of gold and silver alongside copper recovery is feasible and provides a very positive potential improvement in project economics. The increase in annual net operating revenues significantly reduces the cash operating cost for copper, after deduction of gold and silver credits, to US$1.07/lb copper from the previous US$1.59/lb. The inclusion of gold and silver recovery into the previous mine and processing plan, provides an opportunity to reconsider leach alternatives for operational efficiency. The proposed Phase II plan includes a review of various copper, gold and silver leach alternatives.

Project Economics

The Base Case metal price in the M3 Feasibility Study was US$3.20/lb copper which is near the median of current medium to long term analyst forecasts for copper. For continuity purposes the PEA Base Case pricing for copper remains US$3.20/lb, with gold at US$1330/oz and silver at US$21.50/oz. An Exchange Rate of CAD$1.00 equals US$0.90 has been assumed in the PEA.

The impact of the addition of gold and silver recovery, are summarized as follows:

--  Net Revenues increased approximately 28% from US$677 million to US$870
--  Net Cash from Operations increases by 42% from US$333 million to US$471
--  Life of Mine Operating Cost increases from US$344 million to US$398
    million; a 15% increase
--  Life of Mine Cash Operating Cost, after gold and silver credits,
    decreased from US$1.59/lb to US$1.07/lb for copper
--  Pre-tax NPV(discounted at 8%) is US$66 million and After-tax NPV(8%) is
    US$32 million
--  Pre-tax Internal Rate of Return is 15% and After-tax IRR is 12%
--  Copper recovery remains unchanged at 85% and gold recovery is 78% and
    silver recovery 75%
--  Capex increased from US$178 million including contingency for the M3
    Feasibility Study to US$225 million (including a contingency of US$21M)
    for the PEA
--  Potential Life of Mine Annual production is 30,000,000 pounds copper,
    17,300 ounces gold and 165,000 ounces silver
--  Mine Life approximately 8 years

Development Plan

The PEA development plan includes the Measured and Indicated mineral resources, conceptual mine plan and crushing of the mineralization as stated in the M3 Feasibility Study. The previous copper-only leach plan has the crushed material being placed permanently on one large lined pad with staged inter-liners, and standard dispensing of weak sulphuric acid over the leach materials and recovery of pregnant fluid for processing in the Solvent Extraction Electowinning (SXEW) facility to produce cathode copper. The PEA assumes that several smaller on-off pads will be constructed for leaching of the copper, after which the leach materials are washed to remove residual acid and dissolved copper. The washed materials will then be moved to the gold and silver permanent leach pad and prepared for cyanidation with the addition of lime and agglomeration to improve cyanide leaching. A weak cyanide solution is applied using drip emitters on the leach materials and the pregnant solution would be collected and piped to a sulphidation-acidification-recycle-thickening/adsortion-desorption-recovery (SART/ADR) plant for the further removal of any copper in the solution before recovering gold and silver.

The PEA entails the addition of on-off pads for copper leaching and additional handling equipment and fluid piping, and the addition of a SART/ADR plant. Conceptual design of the additions provides the basis for estimating the increase in the operating and capital requirements.

Mineral Resource and Mining

The following table summarizes the mineral resource for zones 1, 4 and 7 for the Measured and Indicated mineral resources that total 11,980,000 tonnes grading 1.07% total copper of which 0.86% is soluble copper. The mineral resource also contains substantial gold and silver. The resources in the oxide classification form the basis for the potentially mineable mineralization by open pit methods.

Mineral Resources at a 0.25% Total Copper Cut-Off

                                Tonnage t    TCu    CuX    CuS     Au     Ag
Zone                   Class        (000)    (%)    (%)    (%)  (g/t)  (g/t)
               Measured (ME)        4,031   1.10   0.90   0.20  0.588  5.666
              Indicated (IN)        7,949   1.04   0.83   0.20  0.391  4.039
Oxide                 ME+IN        11,980   1.07   0.86   0.21  0.456  4.578
                    Inferred           90   0.73   0.53   0.20  0.128  1.809

               Measured (ME)          695   0.80   0.02   0.77  0.261  2.542
              Indicated (IN)        3,645   0.74   0.03   0.71  0.205  2.296
Sulphide              ME+IN         4,340   0.75   0.03   0.73  0.221  2.369
                    Inferred        4,031   0.71   0.01   0.70  0.179  1.900

Measured and Indicated mineral resources within the proposed open pit total 11,551,000 tonnes grading 0.805% soluble copper, 0.456g/t gold and 4.578 g/t silver. The PEA is preliminary in nature, and includes only Measured and Indicated mineral resources. The Inferred mineral resources are considered too speculative geologically to have economic considerations applied to them to be categorized as mineral reserves; furthermore, there is no certainty that the mineral resources will be economic and become a mining reserve, and the Company is not relying upon the mineral reserves in the prior feasibility study.

In-Pit Mineral Resource

The conceptual mining plan entails mining 1,750,000 tonnes per annum using open pit method. The mineralization will be transported to the crushing circuit and after 3-stage crushing the mineralization will be loaded by conveyors to the leach pads for copper extraction. Life of Mine waste to potentially mineable material ratio is 5.1:1 with a maximum mining rate of 37,500 tonnes per day.

In-Pit Mineral Resource              Tot Cu Sol Cu Nonsol Cu  Gold   Silver
 Category                   K tonnes    (%)    (%)       (%)  (g/t)    (g/t)
Measured Mineral Resource      4,127  1.039  0.851     0.188  0.559     5.39
Indicated Mineral Resource     7,424  0.943  0.780     0.163  0.365     3.76
Measured & Indicated
 Resource                     11,551  0.977  0.805     0.172  0.435     4.34
1.) Total material in potential Open Pit of 69,957,000 tonnes and Waste to
 Mineral Resource ratio of 5.1:1.

2.) Resources are fully diluted and based on a cut-off grade of 0.18%
 soluble copper

Metallurgy and Process Plan

Extensive test work on the oxide copper mineralization, consisting largely of malachite, azurite and tenorite, has demonstrated rapid leaching of the copper with the addition of weak sulphuric acid. Processing of the copper mineralization is planned for leaching on three lined pads utilizing the same parameters as previously established for the copper leach.

The copper leach metallurgical work undertaken in 2009 by PRA Metallurgical Division, of Inspectorate, also included an evaluation of gold and silver recovery by cyaniding of the copper leach residues by means of column testing. On the basis of these column tests results, overall copper recovery is predicted at 85%, gold recovery at 78% and silver recovery at 75%.

The review by Dr. Morris Beattie also indicated the recovery of additional copper remaining after the acid leach, and removal of this dissolved copper in a SART circuit in the gold and silver recovery ADR plant.

Qualified Persons

The scientific and technical information in this news release has been reviewed and approved by Dr. Harlan Meade, P. Geo., President and CEO of the Company, and Independent Qualified Persons under NI 43-101: Alistair Kent, P.Eng. Merit Consultants International Inc.; Dr. Giles Arsenau, P.Geo., mineral resource estimation; Dr. Morris Beattie, P.Eng., metallurgical consultant; Michael Hester, FAusIMM, mining consultant and John Hull, P.Eng., geotechnical consultant.

Project Opportunities

The PEA has indicated that the recovery of gold and silver should be positive to project economics. The PEA evaluation has also indicated an opportunity to reduce capital and operating cost utilizing vat leach technology. The evaluation of vat leaching of copper, compared to the heap leach method, is in progress.

Benchmarking with other projects indicates that there may also be an opportunity to reduce capital by taking a different approach to engineering and procurement; this opportunity is also under review.

The commencement of Phase II work to undertake the detailed engineering required for a feasibility level report, is contingent on raising additional capital. The Phase II work is expected to take approximately 9 months to complete.

The review also indicates the potential to expand both oxide and sulphide mineral resources with additional exploration in the various other zones. It is proposed to undertake leach tests on sulphide mineralization; should this be feasible, there is potential to extend production beyond the current 8-year mine life.

About Copper North

The Company is focused on the exploration and development of copper deposits. Its core asset is the Carmacks Project in the Yukon which is progressing to feasibility study for the early production of copper, gold and silver from proposed leach operations. The Company's Redstone Project in the North West Territories is a large high grade copper deposit that is at the early exploration stage. The copper mineralization at Redstone is extensive, spanning 180 kilometers of copper-bearing strata.

On behalf of the Board of Directors,

Dr. Harlan D. Meade, President, CEO, and Director

Cautionary and Forward-Looking Information Comments

This news release includes certain forward-looking information or forward-looking statements (collectively "Forward-Looking Information") for the purposes of applicable securities laws. Forward-Looking Information includes, but is not limited to, statements with respect to the results of the PEA and potential recovery of gold and silver at the Carmacks project; potential improvement in project economics and reduction in operating costs; the proposed Phase II study and its timing; the potential pre-feasibility or feasibility study on the Carmacks project; the proposed exploration and development activities and their timing and potential mineralization; possible events, conditions or performance that are based on assumptions about future courses of action; the timing and costs of future exploration and development activities on Carmacks; permitting and infrastructure time lines and requirements; and requirements for additional capital. In certain cases, Forward-Looking Information can be identified by the use of words and phrases such as "plans", "expects" or "does not expect", "scheduled", "estimates", anticipates", "potential", "recommends" or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would" or "will be taken", "occur" or "be achieved". These statements address future events and conditions and, as such, involve known and unknown risks, uncertainties and other factors, which may cause the actual results, performance or achievements to differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include, among others, that the development plans under the PEA will not proceed as planned, the gold and silver recovery will not impact revenue and operating costs as projected, the timing and success of future exploration and development activities, exploration and development risks, market prices, exploitation and exploration results, availability of capital and financing, general economic, market or business conditions, uninsured risks, regulatory changes, defects in title, availability of personnel, materials and equipment, timeliness of government approvals, unanticipated environmental impacts on operations and other exploration risks detailed herein and from time to time in the filings made by the Company with securities regulators.

In making the forward-looking statements, the Company has applied several material assumptions including, but not limited to, the assumptions that the results of the PEA and the proposed plans thereunder will proceed as planned, that the recovery of gold and silver will have a positive impact on project economics and reduce operating costs, that the proposed exploration and development of Carmacks will proceed as planned, the Company will be able to timely obtain permits and licences required for development of the property and conduct its operations, that market fundamentals will result in sustained metals and mineral prices, current exploration and other objectives concerning Carmacks can be achieved, that the Company's other corporate activities will proceed as expected, and any additional financing needed will be available on reasonable terms. Although the Company has attempted to identify important factors that could affect the Company and may cause actual actions, events or results to differ materially from those described herein, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that Forward-Looking Information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on Forward-Looking Information. The Company expressly disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise except as otherwise required by applicable securities legislation.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Copper North Mining Corp.
Dr. Harlan Meade, President and CEO
Julien Francois, Chief Financial Officer
Tel: 604.638.2502
Email: [email protected]
Web: www.coppernorthmining.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
DXWorldEXPO LLC announced today that ICOHOLDER named "Media Sponsor" of Miami Blockchain Event by FinTechEXPO. ICOHOLDER give you detailed information and help the community to invest in the trusty projects. Miami Blockchain Event by FinTechEXPO has opened its Call for Papers. The two-day event will present 20 top Blockchain experts. All speaking inquiries which covers the following information can be submitted by email to [email protected] Miami Blockchain Event by FinTechEXPO also offers s...
As DevOps methodologies expand their reach across the enterprise, organizations face the daunting challenge of adapting related cloud strategies to ensure optimal alignment, from managing complexity to ensuring proper governance. How can culture, automation, legacy apps and even budget be reexamined to enable this ongoing shift within the modern software factory? In her Day 2 Keynote at @DevOpsSummit at 21st Cloud Expo, Aruna Ravichandran, VP, DevOps Solutions Marketing, CA Technologies, was jo...
Predicting the future has never been more challenging - not because of the lack of data but because of the flood of ungoverned and risk laden information. Microsoft states that 2.5 exabytes of data are created every day. Expectations and reliance on data are being pushed to the limits, as demands around hybrid options continue to grow.
Poor data quality and analytics drive down business value. In fact, Gartner estimated that the average financial impact of poor data quality on organizations is $9.7 million per year. But bad data is much more than a cost center. By eroding trust in information, analytics and the business decisions based on these, it is a serious impediment to digital transformation.
Daniel Jones is CTO of EngineerBetter, helping enterprises deliver value faster. Previously he was an IT consultant, indie video games developer, head of web development in the finance sector, and an award-winning martial artist. Continuous Delivery makes it possible to exploit findings of cognitive psychology and neuroscience to increase the productivity and happiness of our teams.
The IoT Will Grow: In what might be the most obvious prediction of the decade, the IoT will continue to expand next year, with more and more devices coming online every single day. What isn’t so obvious about this prediction: where that growth will occur. The retail, healthcare, and industrial/supply chain industries will likely see the greatest growth. Forrester Research has predicted the IoT will become “the backbone” of customer value as it continues to grow. It is no surprise that retail is ...
Digital Transformation: Preparing Cloud & IoT Security for the Age of Artificial Intelligence. As automation and artificial intelligence (AI) power solution development and delivery, many businesses need to build backend cloud capabilities. Well-poised organizations, marketing smart devices with AI and BlockChain capabilities prepare to refine compliance and regulatory capabilities in 2018. Volumes of health, financial, technical and privacy data, along with tightening compliance requirements by...
Business professionals no longer wonder if they'll migrate to the cloud; it's now a matter of when. The cloud environment has proved to be a major force in transitioning to an agile business model that enables quick decisions and fast implementation that solidify customer relationships. And when the cloud is combined with the power of cognitive computing, it drives innovation and transformation that achieves astounding competitive advantage.
Evan Kirstel is an internationally recognized thought leader and social media influencer in IoT (#1 in 2017), Cloud, Data Security (2016), Health Tech (#9 in 2017), Digital Health (#6 in 2016), B2B Marketing (#5 in 2015), AI, Smart Home, Digital (2017), IIoT (#1 in 2017) and Telecom/Wireless/5G. His connections are a "Who's Who" in these technologies, He is in the top 10 most mentioned/re-tweeted by CMOs and CIOs (2016) and have been recently named 5th most influential B2B marketeer in the US. H...
How is DevOps going within your organization? If you need some help measuring just how well it is going, we have prepared a list of some key DevOps metrics to track. These metrics can help you understand how your team is doing over time. The word DevOps means different things to different people. Some say it a culture and every vendor in the industry claims that their tools help with DevOps. Depending on how you define DevOps, some of these metrics may matter more or less to you and your team.
DevOpsSummit New York 2018, colocated with CloudEXPO | DXWorldEXPO New York 2018 will be held November 11-13, 2018, in New York City. Digital Transformation (DX) is a major focus with the introduction of DXWorldEXPO within the program. Successful transformation requires a laser focus on being data-driven and on using all the tools available that enable transformation if they plan to survive over the long term. A total of 88% of Fortune 500 companies from a generation ago are now out of bus...
DXWordEXPO New York 2018, colocated with CloudEXPO New York 2018 will be held November 11-13, 2018, in New York City and will bring together Cloud Computing, FinTech and Blockchain, Digital Transformation, Big Data, Internet of Things, DevOps, AI, Machine Learning and WebRTC to one location.
Dion Hinchcliffe is an internationally recognized digital expert, bestselling book author, frequent keynote speaker, analyst, futurist, and transformation expert based in Washington, DC. He is currently Chief Strategy Officer at the industry-leading digital strategy and online community solutions firm, 7Summits.
@DevOpsSummit New York 2018, colocated with CloudEXPO | DXWorldEXPO New York 2018 will be held November 11-13, 2018, in New York City. From showcase success stories from early adopters and web-scale businesses, DevOps is expanding to organizations of all sizes, including the world's largest enterprises - and delivering real results.
DXWorldEXPO LLC announced today that Dez Blanchfield joined the faculty of CloudEXPO's "10-Year Anniversary Event" which will take place on November 11-13, 2018 in New York City. Dez is a strategic leader in business and digital transformation with 25 years of experience in the IT and telecommunications industries developing strategies and implementing business initiatives. He has a breadth of expertise spanning technologies such as cloud computing, big data and analytics, cognitive computing, m...