Northern Vertex Files Third Quarter Fiscal 2014 Financial Results and Gold Recoveries Reach 82%

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 05/30/14 -- Northern Vertex Mining Corp. (the "Company") (TSX VENTURE: NEE)(OTCQX: NHVCF) announces that the Company's unaudited interim consolidated financial results for the third quarter fiscal 2014 ended March 31, 2014 (the "Q3 Financials") have been filed on SEDAR. The full version of the Financial Statements and Management's Discussion & Analysis can be viewed on the Company's website at www.northernvertex.com or on SEDAR at www.sedar.com.

Highlights of the Company's Q3 Financials include:


--  Gold and silver sales (net of royalties and selling costs) from the
    Phase I - Pilot Plant of $5,085,427 year-to-date;
--  Excluding non-cash, unrealized foreign exchange gains or losses, net
    loss for the quarter was $908,129, compared to a net loss of $4,153,471
    for the comparative period last year. Net income for the quarter was
    $119,519, primarily due to a $1,027,648 non-cash, unrealized foreign
    exchange gain, and income per share of $0.002 compared to a net loss of
    $4,165,466 and loss per share of $0.079 for the same period last year;
--  Net loss, on a year-to-date basis, of $2,689,968, including a $1,371,519
    non-cash, unrealized foreign exchange gain, and a loss per share of
    $0.049 compared to a net loss of $6,541,307 and loss per share of $0.137
    for the comparative period last year. Excluding non-cash, unrealized
    foreign exchange gains or losses, net loss was $4,061,487, compared to a
    net loss of $6,533,203 for the comparative period last year; and
--  Working capital of $1,783,284 as of March 31, 2014 compared to
    $5,719,985 as of June 30, 2013.

Dick Whittington, President & CEO, states, "The Moss Mine project is now significantly de-risked following the many technical successes of our Phase I Pilot Plant project and I am delighted to see the gold recoveries of 82%, ten percent above our Preliminary Economic Assessment ("PEA") expectations. Coupled with the excellent economics outlined in the PEA, we are confident that the intrinsic value of the project will be appreciated by the market in due course. In the meantime, I would like, once again, to thank the Northern Vertex team, our community stakeholders, contractors, suppliers and shareholders for their continued support."

Gold and Silver Sales Proceeds

Proceeds received from the Pilot Plant, as of May 28, 2014, totalled US$4.2 million from the sale of 3,206 ounces of gold at an average selling price of US$1,252.71 per ounce and 11,047 ounces of silver at an average selling price of US$20.28 per ounce. Approximately US$1.5 million, using estimated gold and silver market prices of US$1,250 and US$20 per ounce, respectively, is expected over the next five months for total estimated sales proceeds from the Phase I - Pilot Plant of US$5.7 million. Gold and silver sales from the Pilot Plant as per the PEA budget were estimated at US$5.3 million, using prices for gold and silver of US$1,500 and US$30 per ounce, respectively. Given the decrease in metals prices since the date of the PEA, the increase in sales proceeds the Company anticipates over the PEA budget can be attributed to additional tonnage placed on the leach pad and the significantly higher recoveries of gold (82% versus 75%, as noted in the PEA).

Operating Results


--  As of May 28, 2014, the Company has operated for 583 days without a Lost
    Time Accident or an MSHA Reportable Accident (Mine Safety & Health
    Administration, US Department of Labor);
--  Heap leaching continues and gold and silver are being adsorbed in the
    carbon columns, carbon is being chemically stripped at off-site
    facilities and gold and silver sales continue;
--  Gold recovery rates, on the first five out of six leach cells is 82%
    after an average of 240 days and exceeds expectations indicated in the
    PEA. Silver recovery is 38.8% on the five cells. Gold and silver
    continue to be recovered from the heap leach operation of the Moss mine;
    and
--  The application for an amendment to the Aquifer Protection Permit was
    approved by the Arizona Department of Environmental Quality in late
    December. The amendment permits an increase in the quantity of
    mineralized material that can be heap leached to a nominal 125,000 tons
    (approximately 112,500 tonnes) from the previously approved 100,000 tons
    (approximately 90,000 tonnes). The increase in allowable tonnage has
    enabled the Company to leach material from a larger area of the Phase I
    pit and to test recoveries from varying crush sizes further enhancing
    the contribution and the value of the pilot plant phase. Additional
    material has been stacked on the heap and the maximum allowable tonnage
    has been placed in accordance with the permit.

Cost Management

At the beginning of the third quarter of the 2014 fiscal year, the Company underwent a significant company-wide staff and cost reduction program in an effort to continue to exercise fiscal responsibility and to better position itself in a rapidly changing economic and financial climate, while advancing its crucial strategic priorities. The main short-term objective was to develop sustainable cash flow while reducing overhead and operating costs. The Company implemented a hardline cost reduction program which included headcount reductions of over 40%, including certain senior positions, significant reductions in office space, exploration, corporate communications, general and administrative overhead and a halting of consulting arrangements with further reductions planned once the leaching process is completed later in the calendar year. Remaining staff, both corporate and at the mine site, have taken salary and wage reductions, and salary and consulting fee suspensions have been implemented for senior management and directors. These cost reduction measures have had a significant impact on overall costs and ultimately led to increased cash preservation.

Financing

On May 26, 2014, the Company announced a non-brokered private placement offering of up to 10 million units at a purchase price of $0.25 per unit, for aggregate gross proceeds to the Company of up to $2,500,000. Each unit will consist of one common share and one-half transferable share purchase warrant. Each whole warrant will entitle the holder to acquire one common share at an exercise price of $0.60 for a period of 24 months from the closing date of the private placement. The Company intends to use the net proceeds of the Private Placement for the advancement of the Company's Moss Mine Gold-Silver earn-in property located in Mohave County, Arizona, primarily the completion of a feasibility study and general corporate purposes. All securities issued will be subject to a four-month hold period.

About Northern Vertex:

Northern Vertex Mining Corp. is a Canadian based exploration and mining company focused on the reactivation of the Moss Mine Gold-Silver Project located in NW Arizona, USA where the Company has the right to earn-in to a 70% property interest through a Joint Venture with Patriot Gold Corp. The Moss Mine Gold-Silver Project is an epithermal, brecciated, low sulphidation quartz-calcite vein and stockwork system which extends over a strike length of 1,400 meters and has been drill tested to depths of 220 meters vertically. It is a potential heap leach, open pit project being advanced under a three-phase business plan, specifically designed to ensure that technical, economic, permitting and funding requirements are met prior to each phase proceeding. The Company's management comprises an experienced management team with a strong background in all aspects of acquisition, exploration, development, operations and financing of mining projects worldwide. The Company is focused on working effectively and respectfully with our stakeholders in the vicinity of the historical Moss Mine and enhancing the capacity of the local communities in the area.

Qualified Persons:

The foregoing technical information contained in this news release has been approved by Mr. L.J. Bardswich, P. Eng., General Manager Moss Project, and a Qualified Person ("QP") for the purpose of National Instrument 43-101 (Standards of Disclosure for Mineral Projects).

ON BEHALF OF THE BOARD OF DIRECTORS

J.R.H. (Dick) Whittington, President & CEO

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note About Forward Looking Information

This news release contains statements about our future business and planned activities. These are "forward-looking" because we have used what we know and expect today to make a statement about the future. Forward-looking statements including but are not limited to comments regarding the timing and content of upcoming work and analyses. Forward-looking statements usually include words such as may, intend, plan, expect, anticipate, believe or other similar words. We believe the expectations reflected in these forward-looking statements are reasonable. However, actual events and results could be substantially different because of the risks and uncertainties associated with our business or events that happen after the date of this news release. You should not place undue reliance on forward-looking statements. As a general policy, we do not update forward-looking statements except as required by securities laws and regulations.

Cautionary Note to U.S. Investors:

This news release uses the terms "Measured", "Indicated", and "Inferred" resources. U.S. investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize them. "Inferred Mineral Resources" have a great amount of uncertainty as to their existence, and as to their economic and legal feasibility. It cannot be assumed that all or any part of an Inferred Mineral Resource will ever be upgraded to a higher category. Under Canadian rules, estimates of Inferred Mineral Resources may not form the basis of feasibility or other economic studies. U.S. investors are cautioned not to assume that all or any part of Measured or Indicated Mineral Resources will ever be converted into Mineral Reserves. U.S. Investors are also cautioned not to assume that all or any part of a Mineral Resource is economically or legally mineable.

2014 number 08

Contacts:
Northern Vertex Mining Corp.
Investor Relations
604-601-3656 or 1-855-633-8798
www.northernvertex.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
In order to meet the rapidly changing demands of today’s customers, companies are continually forced to redefine their business strategies in order to meet these needs, stay relevant and continue to see profitable growth. IoT deployment and development is integral in this transformation, and today businesses are increasingly seeing the value of investing their resources into IoT deployments. These technologies are able increase ROI through projects such as connecting supply chains or enabling sm...
SYS-CON Events announced today that delaPlex will exhibit at SYS-CON's @CloudExpo, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. delaPlex pioneered Software Development as a Service (SDaaS), which provides scalable resources to build, test, and deploy software. It’s a fast and more reliable way to develop a new product or expand your in-house team.
Most DevOps journeys involve several phases of maturity. Research shows that the inflection point where organizations begin to see maximum value is when they implement tight integration deploying their code to their infrastructure. Success at this level is the last barrier to at-will deployment. Storage, for instance, is more capable than where we read and write data. In his session at @DevOpsSummit at 20th Cloud Expo, Josh Atwell, a Developer Advocate for NetApp, will discuss the role and value...
SYS-CON Events announced today that Cloudistics, an on-premises cloud computing company, has been named “Bronze Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Cloudistics delivers a complete public cloud experience with composable on-premises infrastructures to medium and large enterprises. Its software-defined technology natively converges network, storage, compute, virtualization, and management into a ...
As DevOps methodologies expand their reach across the enterprise, organizations face the daunting challenge of adapting related cloud strategies to ensure optimal alignment, from managing complexity to ensuring proper governance. How can culture, automation, legacy apps and even budget be reexamined to enable this ongoing shift within the modern software factory?
New competitors, disruptive technologies, and growing expectations are pushing every business to both adopt and deliver new digital services. This ‘Digital Transformation’ demands rapid delivery and continuous iteration of new competitive services via multiple channels, which in turn demands new service delivery techniques – including DevOps. In this power panel at @DevOpsSummit 20th Cloud Expo, moderated by DevOps Conference Co-Chair Andi Mann, panelists will examine how DevOps helps to meet th...
A strange thing is happening along the way to the Internet of Things, namely far too many devices to work with and manage. It has become clear that we'll need much higher efficiency user experiences that can allow us to more easily and scalably work with the thousands of devices that will soon be in each of our lives. Enter the conversational interface revolution, combining bots we can literally talk with, gesture to, and even direct with our thoughts, with embedded artificial intelligence, whic...
Every successful software product evolves from an idea to an enterprise system. Notably, the same way is passed by the product owner's company. In his session at 20th Cloud Expo, Oleg Lola, CEO of MobiDev, will provide a generalized overview of the evolution of a software product, the product owner, the needs that arise at various stages of this process, and the value brought by a software development partner to the product owner as a response to these needs.
SYS-CON Events announced today that A&I Solutions has been named “Bronze Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Founded in 1999, A&I Solutions is a leading information technology (IT) software and services provider focusing on best-in-class enterprise solutions. By partnering with industry leaders in technology, A&I assures customers high performance levels across all IT environments including: mai...
SYS-CON Events announced today that EARP will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. "We are a software house, so we perfectly understand challenges that other software houses face in their projects. We can augment a team, that will work with the same standards and processes as our partners' internal teams. Our teams will deliver the same quality within the required time and budget just as our partn...
SYS-CON Events announced today that delaPlex will exhibit at SYS-CON's @ThingsExpo, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. delaPlex pioneered Software Development as a Service (SDaaS), which provides scalable resources to build, test, and deploy software. It’s a fast and more reliable way to develop a new product or expand your in-house team.
SYS-CON Events announced today that Tappest will exhibit MooseFS at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. MooseFS is a breakthrough concept in the storage industry. It allows you to secure stored data with either duplication or erasure coding using any server. The newest – 4.0 version of the software enables users to maintain the redundancy level with even 50% less hard drive space required. The software func...
Most technology leaders, contemporary and from the hardware era, are reshaping their businesses to do software in the hope of capturing value in IoT. Although IoT is relatively new in the market, it has already gone through many promotional terms such as IoE, IoX, SDX, Edge/Fog, Mist Compute, etc. Ultimately, irrespective of the name, it is about deriving value from independent software assets participating in an ecosystem as one comprehensive solution.
Regardless of what business you’re in, it’s increasingly a software-driven business. Consumers’ rising expectations for connected digital and physical experiences are driving what some are calling the "Customer Experience Challenge.” In his session at @DevOpsSummit at 20th Cloud Expo, Marco Morales, Director of Global Solutions at CollabNet, will discuss how organizations are increasingly adopting a discipline of Value Stream Mapping to ensure that the software they are producing is poised to o...
In his keynote at @ThingsExpo, Chris Matthieu, Director of IoT Engineering at Citrix and co-founder and CTO of Octoblu, focused on building an IoT platform and company. He provided a behind-the-scenes look at Octoblu’s platform, business, and pivots along the way (including the Citrix acquisition of Octoblu).