Centerra Gives Notice of Potential Kumtor Mine Shutdown Due to Absence of Mine Plan Approval

TORONTO, ONTARIO -- (Marketwired) -- 06/02/14 -- Centerra Gold Inc. (TSX: CG) announces that despite its efforts to obtain approval from Kyrgyz Republic authorities for the 2014 Kumtor mine plan and related permits, such approval and permits have not been issued. Therefore, absent the issuance of such approval and permits by June 13, 2014, Centerra intends to begin an orderly shutdown of operations at the Kumtor project. Prior to such date, Centerra will continue to work and cooperate with relevant authorities in an attempt to facilitate the issuance of such approval and permits.

As previously disclosed, the Company's subsidiary in the Kyrgyz Republic, Kumtor Gold Company ("KGC"), has been working since late 2013 with the relevant government agencies to obtain approval of its 2014 annual mine plan and related operating permits. Unfortunately, this year, despite repeated submissions and discussions with senior officials, such approvals and permits have not been provided. The continuing absence of such approval and permits creates significant uncertainty and risks for Centerra and its employees.

KGC has consistently operated the Kumtor project to high environmental, safety and technical standards. Throughout Kumtor's history, we have engaged constructively and in good faith with relevant authorities to obtain approval of mine plans and designs. We also note that the 2009 Restated Investment Agreement between the Kyrgyz Republic, Centerra and KGC requires that government agencies be reasonable in their review of mining plans and also provides certain assurances and guarantees to Centerra regarding the issuance of required permits.

The shutdown plan provides for the shutdown of all mine and mill operations on the close of business June 13, 2014. KGC would retain sufficient staff to provide essential environmental and safety monitoring, security and essential maintenance of the mill and mine equipment.

The impact of the potential shutdown on future operations will depend in part on the duration of the shutdown. The Company has begun an analysis of possible impacts and would expect to make a statement in this regard if the shutdown proceeds and after it has completed the necessary analysis. The Kumtor mine operation is complex and the Kumtor open pit is subject to significant geo-technical and other challenges, including in-flow of water, ice movement from the Davydov glacier toward the open pit and pit-wall instability. An extended shutdown without active monitoring and management of such challenges would likely have a material adverse impact on the Kumtor mine and the Company's operations, future cash flows, earnings, results of operations and financial condition.

Centerra notes that all disputes in relation to the Kumtor project are subject to international arbitration in accordance with the agreements governing the project.

Cautionary Note Regarding Forward-looking Information

Information contained in this news release which is not a statement of historical facts, may be "forward-looking information" for the purposes of Canadian securities laws. Such forward-looking information involves risks, uncertainties and other factors that could cause actual results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward looking information. The words "expects", "continue", "may", "will", and similar expressions identify forward-looking information. This forward-looking information includes statements as to management's expectations with respect to, among other things the possible shutdown of mining operations at the Kumtor project, the continuing absence of approvals for the 2014 Kumtor annual mine plan and the issuance of related permits, the timing and impact of an orderly shutdown on mining operations, retention of sufficient staff for essential environmental and safety monitoring, security and essential maintenance of the mill and mine equipment, the possible impact of a potential shutdown on future operations and Centerra's analysis thereof, and the complexity of the Kumtor mine's operations, including geotechnical and other challenges. Forward-looking information is necessarily based upon a number of estimates and assumptions that, while considered reasonable by us, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Factors that could cause actual results or events to differ materially from current expectations include, among other things, the political and regulatory risks associated with the Company's operations in the Kyrgyz Republic, the impact of the failure of relevant Kyrgyz Government agencies to provide approvals of annual mine plans and other required permits and authorizations, risks related to environmental, safety and technical matters, the impact of the significant environmental claims made in December 2012 and February 2013 relating to the Kumtor Project, and the Company's ability to enforce its legal rights. There may be other factors that cause results, assumptions, performance, achievements, prospects or opportunities in future periods not to be as anticipated, estimated or intended. See "Risk Factors" in the Company's Annual Information Form for the year ended December 31, 2013 available on SEDAR at www.sedar.com.

There can be no assurances that forward-looking information and statements will prove to be accurate, as many factors and future events, both known and unknown could cause actual results, performance or achievements to vary or differ materially, from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements contained herein or incorporated by reference. Accordingly, all such factors should be considered carefully when making decisions with respect to Centerra, and prospective investors should not place undue reliance on forward-looking information. Forward-looking information is as of June 2, 2014. Centerra assumes no obligation to update or revise forward-looking information to reflect changes in assumptions, changes in circumstances or any other events affecting such forward-looking information, except as required by applicable law.

About Centerra

Centerra is a gold mining company focused on operating, developing, exploring and acquiring gold properties primarily in Asia, the former Soviet Union and other markets worldwide. Centerra is a leading North American-based gold producer and is the largest Western-based gold producer in Central Asia. Centerra's shares trade on the Toronto Stock Exchange (TSX) under the symbol CG. The Company is headquartered in Toronto, Ontario, Canada.

Additional information on Centerra is available on the Company's web site at www.centerragold.com and at SEDAR at www.sedar.com.

Contacts:
Centerra Gold Inc.
John W. Pearson
Vice President, Investor Relations
(416) 204-1241
john.pearson@centerragold.com
www.centerragold.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
DevOps at Cloud Expo, taking place October 31 - November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 21st Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to w...
SYS-CON Events announced today that CAST Software will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CAST was founded more than 25 years ago to make the invisible visible. Built around the idea that even the best analytics on the market still leave blind spots for technical teams looking to deliver better software and prevent outages, CAST provides the software intelligence that matter ...
SYS-CON Events announced today that Daiya Industry will exhibit at the Japanese Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Ruby Development Inc. builds new services in short period of time and provides a continuous support of those services based on Ruby on Rails. For more information, please visit https://github.com/RubyDevInc.
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busine...
Is advanced scheduling in Kubernetes achievable? Yes, however, how do you properly accommodate every real-life scenario that a Kubernetes user might encounter? How do you leverage advanced scheduling techniques to shape and describe each scenario in easy-to-use rules and configurations? In his session at @DevOpsSummit at 21st Cloud Expo, Oleg Chunikhin, CTO at Kublr, will answer these questions and demonstrate techniques for implementing advanced scheduling. For example, using spot instances ...
As businesses evolve, they need technology that is simple to help them succeed today and flexible enough to help them build for tomorrow. Chrome is fit for the workplace of the future — providing a secure, consistent user experience across a range of devices that can be used anywhere. In her session at 21st Cloud Expo, Vidya Nagarajan, a Senior Product Manager at Google, will take a look at various options as to how ChromeOS can be leveraged to interact with people on the devices, and formats th...
First generation hyperconverged solutions have taken the data center by storm, rapidly proliferating in pockets everywhere to provide further consolidation of floor space and workloads. These first generation solutions are not without challenges, however. In his session at 21st Cloud Expo, Wes Talbert, a Principal Architect and results-driven enterprise sales leader at NetApp, will discuss how the HCI solution of tomorrow will integrate with the public cloud to deliver a quality hybrid cloud e...
SYS-CON Events announced today that Yuasa System will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Yuasa System is introducing a multi-purpose endurance testing system for flexible displays, OLED devices, flexible substrates, flat cables, and films in smartphones, wearables, automobiles, and healthcare.
DevOps is under attack because developers don’t want to mess with infrastructure. They will happily own their code into production, but want to use platforms instead of raw automation. That’s changing the landscape that we understand as DevOps with both architecture concepts (CloudNative) and process redefinition (SRE). Rob Hirschfeld’s recent work in Kubernetes operations has led to the conclusion that containers and related platforms have changed the way we should be thinking about DevOps and...
SYS-CON Events announced today that Taica will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Taica manufacturers Alpha-GEL brand silicone components and materials, which maintain outstanding performance over a wide temperature range -40C to +200C. For more information, visit http://www.taica.co.jp/english/.
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busine...
SYS-CON Events announced today that SourceForge has been named “Media Sponsor” of SYS-CON's 21st International Cloud Expo, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. SourceForge is the largest, most trusted destination for Open Source Software development, collaboration, discovery and download on the web serving over 32 million viewers, 150 million downloads and over 460,000 active development projects each and every month.
SYS-CON Events announced today that Nihon Micron will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Nihon Micron Co., Ltd. strives for technological innovation to establish high-density, high-precision processing technology for providing printed circuit board and metal mount RFID tags used for communication devices. For more inf...
Enterprises have taken advantage of IoT to achieve important revenue and cost advantages. What is less apparent is how incumbent enterprises operating at scale have, following success with IoT, built analytic, operations management and software development capabilities – ranging from autonomous vehicles to manageable robotics installations. They have embraced these capabilities as if they were Silicon Valley startups. As a result, many firms employ new business models that place enormous impor...
SYS-CON Events announced today that MIRAI Inc. will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. MIRAI Inc. are IT consultants from the public sector whose mission is to solve social issues by technology and innovation and to create a meaningful future for people.