Welcome!

News Feed Item

I-Minerals Updated Pre-Feasibility Study of Its Bovill Kaolin Project Yields $212 Million After Tax NPV and 30.5% IRR

VANCOUVER, BC--(Marketwired - June 03, 2014) - I-Minerals Inc. (TSX VENTURE: IMA) (OTCQX: IMAHF) ("the Company") is pleased to announce that further to its press release of May 14, 2014 wherein the Company announced Measured and Indicated Mineral Resources of 11.2 million short tons of Kaolin-Halloysite-Quartz-potassium feldspar ("K-Spar") bearing primary clay on its Bovill Kaolin Project (the "Bovill Kaolin Project"), SRK has now provided the accompanying results of the Technical Economic Model (TEM) of the Updated Prefeasibility Study ("PFS"). The Bovill Kaolin Project is a strategically located long term resource of high purity quartz, K-spar, halloysite and kaolin formed through the weathering of a border phase of the Idaho Batholith causing all minerals to be contained within a fine white clay-sand mixture referred to as "primary clay." The Bovill Kaolin Project is located within 5 kilometers of state highways with electricity and natural gas already at the property boundary. Highlights of the TEM include:

  • US$330 million Pre-Tax NPV; US$212 million After Tax NPV
  • 38.2% Pre-Tax IRR; 30.5% After Tax IRR
  • Initial Capital Cost of $72.7 million and Total Life of Mine Capital costs $90.8 million
  • 11.2 million short tons of resources
  • 6.9 million short tons of reserves
  • 25+ year mine life with 0.69:1 strip ratio
  • 3 year estimated after tax payback

Statement of Mineral Resources
The Measured and Indicated Mineral Resources are reported in Table 1. No mining cut-off grade is applied since all material within the pit design that does not report to tailings can be mined for a profit. Three mineral products are included in the resource: feldspathic sand, a combination of potassium feldspar ("K-spar") and quartz, kaolinite clay and halloysite clay:

 Table 1: Statement of Measured and Indicated Mineral Resources from the WBL Pit and Middle Ridge areas, (as of 20 April 2014)*

                                                                            
----------------------------------------------------------------------------
                         Percent (%)                                        
            ----------------------------------------------------------------
                Tons       Quartz &     Kaolinite   Halloysite              
             (000,000s)   K-Spar Sand     Clay         Clay         Waste   
----------------------------------------------------------------------------
  Measured           3.3         76.0         13.0          4.5          7.0
----------------------------------------------------------------------------
  Indicated          7.9         74.4         15.6          2.7          7.3
----------------------------------------------------------------------------
  Total             11.2         75.0         14.8          3.2          7.1
----------------------------------------------------------------------------
                                                                            
                                                                            
----------------------------------------------------------------------------
           Tons (000s)                                                      
           -----------------------------------------------------------------
               Quartz &                                                     
              K-Spar Sand    Kaolinite Clay  Halloysite Clay      Waste     
----------------------------------------------------------------------------
  Measured       2,505             417             148             222      
----------------------------------------------------------------------------
  Indicated      5,902            1,239            215             579      
----------------------------------------------------------------------------
  Total          8,407            1,656            363             801      
----------------------------------------------------------------------------
                                                                            

* Note that values presented here have been rounded to reflect the level of accuracy.

Results of the Pre-Feasibility Study
The PFS assumed a weighted average price of primary clay products -- halloysite, kaolin, metakaolin, quartz and K-spar -- of $255/ton as supported by market studies completed by I-Minerals, preliminary studies being undertaken by a European company specializing in halloysite research, and a market study conducted by a major international marketing and research firm. If all of the known Mineral Resource eventually convert to Mineral Reserves, the project mine life could potentially expand to 40 years; however initial indicative economics were performed assuming a 25 year market for primary clay products. Mineral Reserves are presented below in Table 2 and production highlights are tabulated in Table 3. 

Table 2: Statement of Mineral Reserves, (as of May 30, 2014) All figures thousands of tons*

                                                                            
  --------------------------------------------------------------------------
                            Million    Halloysite     Kaolin                
  Reserve                   Tonnes       Grade        Grade      Sand Grade 
  --------------------------------------------------------------------------
  Kelly Hump                                                                
  Proven                          1.9         4.5%        12.6%        76.4%
  Probable                        1.1         5.6%        14.3%        72.9%
  --------------------------------------------------------------------------
  Kelly South                                                               
  Proven                            0         0.0%         0.0%         0.0%
  Probable                        1.4         1.4%        21.6%        69.9%
  --------------------------------------------------------------------------
  Middle Ridge                                                              
  Proven                          0.8         6.4%        11.9%        74.6%
  Probable                        1.6         4.2%        12.1%        76.0%
  --------------------------------------------------------------------------
  WBL                                                                       
  Proven                            0         0.0%         0.0%         0.0%
  Probable                        0.9         2.2%        15.3%        75.2%
  --------------------------------------------------------------------------
                                                                            

* Note that values presented here have been rounded to reflect the level of accuracy.

Table 3: Production Highlights

----------------------------------------------------------------------------
Parameter                                                              Value
----------------------------------------------------------------------------
Average Annual Plant Production Rate                                 275 kst
----------------------------------------------------------------------------
Process Throughput Rate (nominal)                       800 tons ore per day
----------------------------------------------------------------------------
Stripping Ratio (waste: ore)                                            0.69
----------------------------------------------------------------------------
Mine Life (market limited)                                         25+ years
----------------------------------------------------------------------------
                                                                            

The reserves of primary clay are under a shallow layer of overburden generally less than 20 feet. Initial pits are limited to depths of approximately 75 feet. Given the physical properties of the primary clay, no drilling or blasting is required. The process flow sheet includes wet screw classification and screen separation of the halloysite -- kaolinite clay fraction -- from the quartz -- K-spar sand fraction. The clay fraction is separated into kaolinite and halloysite using -hydrocylone-, centrifuge, and differential flotation techniques to yield +90% halloysite products. After tertiary grinding, the quartz and K-spar in the sand fraction are separated using standard wet flotation and dry rare earth magnetic separation techniques. Employing up to three stage flotation, quartz purities with less than 200 PPM of total impurities have been produced without the use of any acid leaching techniques.

On an after-tax basis, technical-economics indicate an NPV6% of US$212 million with an IRR of 30.5%. Payback will occur 3 years from the start of production. Economic results are summarized below. 

Table 4: Economic Results1

                                                                            
----------------------------------------------------------------------------
Description                        LoM Value      LoM Value       Unit Cost 
                                      (US$Ms)        (US$Ms)       (US$/ton 
                                      Pre-Tax      Atfer-Tax        product 
----------------------------------------------------------------------------
Gross Revenue                   $     1,270.4  $     1,270.4  $      254.79 
  Marketing                              (5.0)          (5.0)        ($1.00)
  Royalties (5% sales)                  (63.5)         (63.5)       ($12.74)
----------------------------------------------------------------------------
          Gross Income          $     1,201.9  $     1,201.9  $      241.05 
  Mining Costs                          (50.4)         (50.4)       ($10.10)
  Processing Costs                     (295.1)        (295.1)       ($59.18)
  G&A Costs                              (7.2)          (7.2)        ($1.43)
----------------------------------------------------------------------------
        Operating Costs               ($352.6)       ($352.6)       ($70.72)
  Mine Capital                           (1.4)          (1.4)             - 
  Process Capital                       (69.3)         (69.3)             - 
  Tailings Capital                      (14.1)         (14.1)             - 
  Owner Capital                          (6.1)          (6.1)             - 
----------------------------------------------------------------------------
          LoM Capital                  ($90.8)        ($90.8)             - 
  Taxes                                               (262.5)             - 
----------------------------------------------------------------------------
         Subtotal Capital & Tax        ($90.8)       ($353.4)             - 
============================================================================
                      CASH FLOW $       758.4  $       495.9              - 
                          NPV6% $       330.7  $       212.7              - 
                            IRR          38.2%          30.5%             - 
----------------------------------------------------------------------------
                                                                            

1 Differences in totals and subtotals are due to rounding, and are not material to the results presented. 

The technical economics results for the PFS and its supporting Mineral Resource estimate presented in this press release was completed by SRK Consulting (US) Inc. ("SRK") in Lakewood, Colorado. Tetra Tech ("TT") in Denver, Colorado was commissioned by the Company to complete design of the Proposed Tailings Facility (PTF). HDR, Inc. (HDR) in Boise, Idaho was commissioned by the Company to aid in permitting and environmental issues. Roberts & Schaefer ("R&S"), a KBR Company, was commissioned to complete the design for the planned processing and product packaging facilities. 

Dr. Bart Stryhas constructed the geologic model and resource estimation results reported herein. He is responsible for the resource estimation methodology and the resource statement. Dr. Stryhas is a Qualified Person (QP) and is independent of the issuer applying all of the tests in Section 1.4 of NI 43-101. Valerie 0bie (QP) completed the reserve estimation reported herein and is responsible for the economic assessment.

I-Minerals' Bovill Kaolin Project is a pre-feasibility level mining venture located in north-central Idaho. The mineral reserves delineated from the primary clay represent the largest confirmed deposits of high quality K-feldspar, quartz, and halloysite in the Western United States. This pre-feasibility study is preliminary in nature. 

"Fundamental changes in the K-spar market have compelled us to expand the production as compared with our maiden Prefeasibility Study, results from which were announced in January 2013," stated Thomas Conway, President & CEO of I-Minerals Inc. "To meet the increased demands in the K-spar market in the Updated PFS we are modelling production on a 24 hours per day seven days a week basis ("24/7") as compared with the Maiden PFS production rate of 24/5. Capital costs are up only modestly (about 7.6 million) as compared with the Maiden PFS to reflect increases in Owners Cost which now includes items such as the cost of a full feasibility that were not included in the maiden PFS. First year's sales were also reduced from Life of Mine averages to reflect the realities of ramping up production. The impacts of lower year 1 revenue and increased initial costs probably shaved a few points off the IRR and several million of the NPV as compared with the assumptions utilized in the Maiden PFS. Nonetheless the Updated PFS has yielded very robust results as highlighted by a NPV almost three times higher than the CAPEX and a payback of just over 3 years."

Mr. Conway continued "Given the limited options currently available to K-spar customers we are very confident in our K-spar pricing assumptions and have materially discounted the pricing on the incremental tonnages of halloysite and quartz sold at volumes in excess of 24/5 levels. With the PFS milestone achieved we are about a year from a full feasibility on the Bovill Kaolin Deposit, with great strides already having been made in the associated permitting process. All told, we are very pleased with the results of the Updated PFS and recognize there may be opportunities to further improve upon the results as we push forward with the full feasibility study."

The NI 43-101 compliant Technical Report is being completed by SRK, TT, HDR and R&S and will be filed on SEDAR (at www.sedar.com) in its entirety as required. All values presented in this press release are in US imperial units and Q2 2014 US dollars. 

I-Minerals Inc.

per: "Thomas M. Conway

Thomas M. Conway,
President & CEO

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS NEWS RELEASE.

This News Release includes certain "forward looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995. Without limitation, statements regarding potential mineralization and resources, exploration results, and future plans and objectives of the Company are forward looking statements that involve various risks. Actual results could differ materially from those projected as a result of the following factors, among others: changes in the world wide price of mineral market conditions, risks inherent in mineral exploration, risk associated with development, construction and mining operations, the uncertainty of future profitability and uncertainty of access to additional capital.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that EastBanc Technologies will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. EastBanc Technologies has been working at the frontier of technology since 1999. Today, the firm provides full-lifecycle software development delivering flexible technology solutions that seamlessly integrate with existing systems – whether on premise or cloud. EastBanc Technologies partners with p...
SYS-CON Events announced today that IBM Cloud Data Services has been named “Bronze Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. IBM Cloud Data Services offers a portfolio of integrated, best-of-breed cloud data services for developers focused on mobile computing and analytics use cases.
SYS-CON Events announced today that Super Micro Computer, Inc., a global leader in Embedded and IoT solutions, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Supermicro (NASDAQ: SMCI), the leading innovator in high-performance, high-efficiency server technology, is a premier provider of advanced server Building Block Solutions® for Data Center, Cloud Computing, Enterprise IT, Hadoop/Big Data, HPC and ...
The Internet of Things (IoT) is growing rapidly by extending current technologies, products and networks. By 2020, Cisco estimates there will be 50 billion connected devices. Gartner has forecast revenues of over $300 billion, just to IoT suppliers. Now is the time to figure out how you’ll make money – not just create innovative products. With hundreds of new products and companies jumping into the IoT fray every month, there’s no shortage of innovation. Despite this, McKinsey/VisionMobile data...
18th Cloud Expo, taking place June 7-9, 2016, at the Javits Center in New York City, NY, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy. Meanwhile, 94% of enterprises are using some...
We’ve been doing it for years, decades for some. How many websites have you created accounts on? Your bank, your credit card companies, social media sites, hotels and travel sites, online shopping sites, and that’s just the start. We do it often without even thinking about it, quickly entering our personal information, our data, in a plethora of systems. Sometimes we’re not even aware of the information we are providing. It could be very personal information (think of the security questions you ...
@DevOpsSummit taking place June 7-9, 2016 at Javits Center, New York City, and Nov 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with the 18th International @CloudExpo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world.
The cloud era has reached the stage where it is no longer a question of whether a company should migrate, but when. Enterprises have embraced the outsourcing of where their various applications are stored and who manages them, saving significant investment along the way. Plus, the cloud has become a defining competitive edge. Companies that fail to successfully adapt risk failure. The media, of course, continues to extol the virtues of the cloud, including how easy it is to get there. Migrating...
In today's enterprise, digital transformation represents organizational change even more so than technology change, as customer preferences and behavior drive end-to-end transformation across lines of business as well as IT. To capitalize on the ubiquitous disruption driving this transformation, companies must be able to innovate at an increasingly rapid pace. Traditional approaches for driving innovation are now woefully inadequate for keeping up with the breadth of disruption and change facin...
As machines are increasingly connected to the internet, it’s becoming easier to discover the numerous ways Industrial IoT (IIoT) is helping to shape the business world. This is exactly why we have decided to take a closer look at this pervasive movement and to examine the desire to connect more things! Now if you need a refresher on IIoT and how it is changing the world, take a moment and listen to Greg Gorbach with ARC Advisory Group. Gorbach believes, "IIoT will significantly change the worl...
WebRTC is bringing significant change to the communications landscape that will bridge the worlds of web and telephony, making the Internet the new standard for communications. Cloud9 took the road less traveled and used WebRTC to create a downloadable enterprise-grade communications platform that is changing the communication dynamic in the financial sector. In his session at @ThingsExpo, Leo Papadopoulos, CTO of Cloud9, will discuss the importance of WebRTC and how it enables companies to fo...
"What we see what happens when you have a completely networked society and the potential to now drive the value creation and the collaboration and the ecosystems that are possible when you start to be able to connect people and industries together in ways that have never been possible before," explained Esmeralda Swartz, VP of Marketing Enterprise & Cloud at Ericsson, in this SYS-CON.tv interview at @ThingsExpo, held November 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA.
How will your company move to the cloud while ensuring a solid security posture? Organizations from small to large are increasingly adopting cloud solutions to deliver essential business services at a much lower cost. According to cyber security experts, the frequency and severity of cyber-attacks are on the rise, causing alarm to businesses and customers across a variety of industries. To defend against exploits like these, a company must adopt a comprehensive security defense strategy that is ...
SYS-CON Events announced today that AppNeta, the leader in performance insight for business-critical web applications, will exhibit and present at SYS-CON's @DevOpsSummit at Cloud Expo New York, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. AppNeta is the only application performance monitoring (APM) company to provide solutions for all applications – applications you develop internally, business-critical SaaS applications you use and the networks that deli...
SYS-CON Events announced today that Zerto will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Zerto is committed to keeping enterprise and cloud IT running 24/7 by providing innovative, simple, reliable and scalable business continuity software solutions. Through the Zerto Cloud Continuity Platform™, organizations can seamlessly move and protect virtualized workloads between public, private and hybrid clou...