Lundin Petroleum AB: Update on the Brynhild project, offshore Norway

STOCKHOLM, SWEDEN -- (Marketwired) -- 06/09/14 -- Lundin Petroleum AB (TSX: LUP)(OMX: LUPE)

The Brynhild project is progressing at a slower pace than anticipated due to commissioning issues related to the FPSO operated by Shell on the Pierce Field in the UK sector. The upstream portion of the Brynhild project operated by Lundin Petroleum is progressing satisfactorily but the production start-up is now expected late in the third quarter of 2014.

The Brynhild field offshore Norway is a subsea tie-back to the Pierce field, operated by Shell (Enterprise Oil Ltd), in the UK sector. The production facility for the Pierce and Brynhild production is the Haewene Brim FPSO owned and operated by Bluewater owned Pierce Production Company Limited.

A comprehensive modification programme has been carried out on the Haewene Brim FPSO by owner Bluewater on behalf of the Pierce operator Shell in order to prepare for introduction of hydrocarbons from the Brynhild field commingled with the existing Pierce field.

The completed scope for the modifications include upgrading of the topside heaters, significant upgrades of metering systems, installation of upgraded subsea control system and replacement of the risers. Whilst the upgrades of the topside and subsea equipment as well as the risers' installations have been completed, ongoing commissioning activities for start-up have taken longer than anticipated to be completed prior to the re-introduction of hydrocarbons into the FPSO.

As a result of the revised Brynhild first oil date, Lundin Petroleum's net production for 2014 is now expected to be in the range 25,000 - 30,000 barrels of oil equivalent per day (boepd).

Ashley Heppenstall, President and CEO of Lundin Petroleum, commented: "We are disappointed and frustrated that the Haewene Brim FPSO is still not ready to accept Brynhild production. Nevertheless we remain confident regarding the productivity of the Brynhild reservoir and the project delays have had no impact on Brynhild reserves. The delay in first production has clearly impacted our 2014 production guidance but we still retain our production guidance for 2015 of approximately 50,000 boepd"

Lundin Norway AS, a wholly owned subsidiary of Lundin Petroleum AB, is the operator of PL148 with a 90 percent interest. The partner is Talisman Energy Norge with a 10 percent interest.

Lundin Petroleum is a Swedish independent oil and gas exploration and production company with a well balanced portfolio of world-class assets primarily located in Europe and South East Asia. The Company is listed at the NASDAQ OMX, Stockholm (ticker "LUPE") and at the Toronto Stock Exchange (TSX) (Ticker "LUP"). Lundin Petroleum has proven and probable reserves of 194 million barrels of oil equivalent (MMboe).

This information has been made public in accordance with the Securities Market Act (SFS 2007:528) and/or the Financial Instruments Trading Act (SFS 1991:980).

Forward-Looking Statements

Certain statements made and information contained herein constitute "forward-looking information" (within the meaning of applicable securities legislation). Such statements and information (together, "forward-looking statements") relate to future events, including the Company's future performance, business prospects or opportunities. Forward-looking statements include, but are not limited to, statements with respect to estimates of reserves and/or resources, future production levels, future capital expenditures and their allocation to exploration and development activities, future drilling and other exploration and development activities. Ultimate recovery of reserves or resources are based on forecasts of future results, estimates of amounts not yet determinable and assumptions of management.

All statements other than statements of historical fact may be forward-looking statements. Statements concerning proven and probable reserves and resource estimates may also be deemed to constitute forward-looking statements and reflect conclusions that are based on certain assumptions that the reserves and resources can be economically exploited. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "seek", "anticipate", "plan", "continue", "estimate", "expect", "may", "will", "project", "predict", "potential", "targeting", "intend", "could", "might", "should", "believe" and similar expressions) are not statements of historical fact and may be "forward-looking statements". Forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements. No assurance can be given that these expectations and assumptions will prove to be correct and such forward-looking statements should not be relied upon. These statements speak only as on the date of the information and the Company does not intend, and does not assume any obligation, to update these forward-looking statements, except as required by applicable laws. These forward-looking statements involve risks and uncertainties relating to, among other things, operational risks (including exploration and development risks), productions costs, availability of drilling equipment, reliance on key personnel, reserve estimates, health, safety and environmental issues, legal risks and regulatory changes, competition, geopolitical risk, and financial risks. These risks and uncertainties are described in more detail under the heading "Risks and Risk Management" and elsewhere in the Company's annual report. Readers are cautioned that the foregoing list of risk factors should not be construed as exhaustive. Actual results may differ materially from those expressed or implied by such forward-looking statements. Forward-looking statements are expressly qualified by this cautionary statement.

Reserves and Resources

Unless otherwise stated, Lundin Petroleum's reserve and resource estimates are as at 31 December 2013, and have been prepared and audited in accordance with National Instrument 51-101 Standards of Disclosure for Oil and Gas Activities ("NI 51-101") and the Canadian Oil and Gas Evaluation Handbook ("COGE Handbook")."). Unless otherwise stated, all reserves estimates contained herein are the aggregate of "Proved Reserves" and "Probable Reserves", together also known as "2P Reserves". For further information on reserve and resource classifications, see "Reserves, Resources and Production" in the Company's annual report.

Contingent Resources

Contingent Resources are those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations using established technology or technology under development, but are not currently considered to be commercially recoverable due to one or more contingencies. Contingencies may include factors such as economic, legal, environmental, political and regulatory matters or a lack of markets. There is no certainty that it will be commercially viable for the Company to produce any portion of the Contingent Resources. . Unless otherwise stated, all contingent resource estimates contained herein are the best estimate ("2C") contingent resources.

Prospective Resources

Prospective Resources are those quantities of petroleum estimated, as of a given date, to be potentially recoverable from undiscovered accumulations by application of future development projects. Prospective Resources have both a chance of discovery and a chance of development. There is no certainty that any portion of the Prospective Resources will be discovered. If discovered, there is no certainty that it will be commercially viable to produce any portion of the Prospective Resources. Unless otherwise stated, all Prospective Resource estimates contained herein are reflecting a P50 Prospective Resource estimate. Risked Prospective Resources reported herein are partially risked. They have been risked for chance of discovery, but have not been risked for chance of development.

BOEs

BOEs may be misleading, particularly if used in isolation. A BOE conversion ratio of 6 Mcf : 1 Bbl is based on an energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the wellhead.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
The many IoT deployments around the world are busy integrating smart devices and sensors into their enterprise IT infrastructures. Yet all of this technology – and there are an amazing number of choices – is of no use without the software to gather, communicate, and analyze the new data flows. Without software, there is no IT. In this power panel at @ThingsExpo, moderated by Conference Chair Roger Strukhoff, Dave McCarthy, Director of Products at Bsquare Corporation; Alan Williamson, Principal...
Businesses and business units of all sizes can benefit from cloud computing, but many don't want the cost, performance and security concerns of public cloud nor the complexity of building their own private clouds. Today, some cloud vendors are using artificial intelligence (AI) to simplify cloud deployment and management. In his session at 20th Cloud Expo, Ajay Gulati, Co-founder and CEO of ZeroStack, will discuss how AI can simplify cloud operations. He will cover the following topics: why clou...
Video experiences should be unique and exciting! But that doesn’t mean you need to patch all the pieces yourself. Users demand rich and engaging experiences and new ways to connect with you. But creating robust video applications at scale can be complicated, time-consuming and expensive. In his session at @ThingsExpo, Zohar Babin, Vice President of Platform, Ecosystem and Community at Kaltura, discussed how VPaaS enables you to move fast, creating scalable video experiences that reach your aud...
Cloud Expo, Inc. has announced today that Andi Mann returns to 'DevOps at Cloud Expo 2017' as Conference Chair The @DevOpsSummit at Cloud Expo will take place on June 6-8, 2017, at the Javits Center in New York City, NY. "DevOps is set to be one of the most profound disruptions to hit IT in decades," said Andi Mann. "It is a natural extension of cloud computing, and I have seen both firsthand and in independent research the fantastic results DevOps delivers. So I am excited to help the great t...
Rapid innovation, changing business landscapes, and new IT demands force businesses to make changes quickly. In the eyes of many, containers are at the brink of becoming a pervasive technology in enterprise IT to accelerate application delivery. In this presentation, attendees learned about the: The transformation of IT to a DevOps, microservices, and container-based architecture What are containers and how DevOps practices can operate in a container-based environment A demonstration of how ...
In this strange new world where more and more power is drawn from business technology, companies are effectively straddling two paths on the road to innovation and transformation into digital enterprises. The first path is the heritage trail – with “legacy” technology forming the background. Here, extant technologies are transformed by core IT teams to provide more API-driven approaches. Legacy systems can restrict companies that are transitioning into digital enterprises. To truly become a lead...
Without lifecycle traceability and visibility across the tool chain, stakeholders from Planning-to-Ops have limited insight and answers to who, what, when, why and how across the DevOps lifecycle. This impacts the ability to deliver high quality software at the needed velocity to drive positive business outcomes. In his general session at @DevOpsSummit at 19th Cloud Expo, Phil Hombledal, Solution Architect at CollabNet, discussed how customers are able to achieve a level of transparency that e...
WebRTC is the future of browser-to-browser communications, and continues to make inroads into the traditional, difficult, plug-in web communications world. The 6th WebRTC Summit continues our tradition of delivering the latest and greatest presentations within the world of WebRTC. Topics include voice calling, video chat, P2P file sharing, and use cases that have already leveraged the power and convenience of WebRTC.
"At ROHA we develop an app called Catcha. It was developed after we spent a year meeting with, talking to, interacting with senior citizens watching them use their smartphones and talking to them about how they use their smartphones so we could get to know their smartphone behavior," explained Dave Woods, Chief Innovation Officer at ROHA, in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
"Venafi has a platform that allows you to manage, centralize and automate the complete life cycle of keys and certificates within the organization," explained Gina Osmond, Sr. Field Marketing Manager at Venafi, in this SYS-CON.tv interview at DevOps at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
20th Cloud Expo, taking place June 6-8, 2017, at the Javits Center in New York City, NY, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy.
Application transformation and DevOps practices are two sides of the same coin. Enterprises that want to capture value faster, need to deliver value faster – time value of money principle. To do that enterprises need to build cloud-native apps as microservices by empowering teams to build, ship, and run in production. In his session at @DevOpsSummit at 19th Cloud Expo, Neil Gehani, senior product manager at HPE, discussed what every business should plan for how to structure their teams to delive...
"We analyze the video streaming experience. We are gathering the user behavior in real time from the user devices and we analyze how users experience the video streaming," explained Eric Kim, Founder and CEO at Streamlyzer, in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
In his keynote at 18th Cloud Expo, Andrew Keys, Co-Founder of ConsenSys Enterprise, provided an overview of the evolution of the Internet and the Database and the future of their combination – the Blockchain. Andrew Keys is Co-Founder of ConsenSys Enterprise. He comes to ConsenSys Enterprise with capital markets, technology and entrepreneurial experience. Previously, he worked for UBS investment bank in equities analysis. Later, he was responsible for the creation and distribution of life sett...
Get deep visibility into the performance of your databases and expert advice for performance optimization and tuning. You can't get application performance without database performance. Give everyone on the team a comprehensive view of how every aspect of the system affects performance across SQL database operations, host server and OS, virtualization resources and storage I/O. Quickly find bottlenecks and troubleshoot complex problems.