Click here to close now.


News Feed Item

Atacama Pacific Announces Continued Positive Metallurgical Results From Cerro Maricunga Oxide Gold Project

TORONTO, ONTARIO -- (Marketwired) -- 06/09/14 -- Atacama Pacific Gold Corporation (TSX VENTURE: ATM) ("Atacama Pacific") is pleased to report the results from six column percolation leach tests completed on gold mineralization from its Cerro Maricunga oxide gold deposit located in northern Chile. The tests were undertaken to compare the gold recoveries from mineralization crushed to different sizes and to examine the impact of crushing using high pressure grind rolls ("HPGR") on recoveries. The test work also examined the impact of reducing the amount of lime used to control leach solution pH.

Table 1 summarizes the results of the column tests. Highlights from the current test work include:

--  Only a minor decrease in gold recoveries was observed when increasing
    crush size to 105 mm.
--  HPGR crushed mineralization did not achieved significantly higher gold
    recoveries compared to conventionally crushed material.
--  Majority of leachable gold was extracted in the first twenty days at
    crush sizes less than 21 mm.

Table 1 - Summary of Column Test Results, Cerro Maricunga Deposit
Test    Head     Gold Crush             Lime +
#      Grade Recovery  Size  NaCN(1) Cement(2)  Note
        (g/t         (P80 =
         Au)      (%)   mm)   (kg/t)    (kg/t)
68801A  0.33       72 105.0     0.96       1.0  Conventionally crushed
68801B  0.33       74  21.0     1.96       1.8  Conventionally crushed
68811   0.44       83   7.6     2.42       2.0  Conventionally crushed
68815   0.44       84   7.2     2.10       1.9  HPGR
68813   0.58       86   6.4     2.47       1.8  HPGR
68814   0.58       84   6.9     2.24       1.8  HPGR, fines processed
1. Reduced levels of lime resulted in a tripling of NaCN consumption due to
 the loss of solution pH control
2. Totals include 1 kg of cement

The current testing examined the impact of reducing the initial amount of lime added to the columns, which has a direct impact on leach solution pH and NaCN consumption. The solution pH of the current tests averaged between 9.0 and 9.5 resulting in significantly higher than previously determined NaCN consumption. The solution pH of all previous columns had been maintained between 10 and 11 establishing heap leach NaCN consumption in the order of 0.24 kg/t.

Test Results

As confirmed by column tests 68801A and 68801B, coarser crushed mineralization achieved slightly lower gold recoveries (72% at a 105 mm crush versus 74% at a 21 mm crush) similar to earlier column test results. Previous testing undertaken on mineralization crushed to 19 mm achieved gold recoveries of 78 to 89% compared to recoveries of 76 to 80% from mineralization crushed between 50 and 150 mm.

Three tests were completed on material crushed with HPGR following up on a HPGR-related column test announced on May 9, 2013 which attained a gold recovery of 85%. The current tests achieved gold recoveries varying from 84% to 86%. Two columns, completed on the same sample material, examined the impact of HPGR and conventional crushing with the HPGR test (68815) achieving 84% recoveries and the conventional test achieving 83% recoveries. There appears to be no significant benefit to using HPGR crushing.

Metallurgical Test Details

The column tests, conducted by Kappes, Cassidy and Associates, Reno, Nevada, were run 84 days. Table 2 summarizes the test details. Column slump, the difference between the initial sample height in a column compared to the height after test completion, was low. The initial leach solution for each column test contained 1.0 g NaCN/l and an on-flow solution NaCN concentration of 0.6 g/l was maintained during the test period.

Table 2 - Column Test Details
Test        Head       Gold    Test   Crush     Dry  Initial   Final  Column
#          Grade   Recovery  Period    Size  Weight   Height  Height   Slump

        (g/t Au)        (%)    days     mm)      kg        m       m       %
68801A      0.33         72      84   105.0     699     3.09    3.07     0.6
68801B      0.33         74      84    21.0      49     2.02    2.00     0.9
68811       0.44         83      84     7.6      49     1.77    1.73     1.8
68815       0.44         84      84     7.2      55     1.93    1.90     2.0
68813       0.58         86      84     6.4      55     1.91    1.88     2.0
68814       0.58         84      84     6.9      55     1.91    1.87     1.3

Prefeasibility Update

The Cerro Maricunga prefeasibility study is progressing well. The mineral processing and the majority of the mining plans have been completed and Atacama Pacific is waiting for supplier quotes for fleet equipment and some infrastructural items. All quotes are expected prior to the end of June and the PFS should be available for release in early July 2014.

Share Issuance

As announced on May 15, 2014, Atacama Pacific entered into an agreement with Hydro Exploraciones SpA under which it agreed to issue 350,000 common shares at a price of $1.15 per share to settle all obligations under two water exploration agreements. These agreements are related to water concessions located 70 km to the east of the Cerro Maricunga and subject to a water exploration joint venture agreement with Exeter Resources Corporation. These shares were issued on June 6, 2014 following approval of the transaction by the TSX Venture Exchange. The hold period on these shares will expire on October 7, 2014.

About Atacama Pacific Gold Corporation

Atacama Pacific's primary mineral property is the Cerro Maricunga oxide-associated, breccia-hosted gold project, located in Region III, 140 kilometres by road northeast of the city of Copiapo. In Atacama Pacific's January 2013 PEA envisions a large open pit operation mining 80,000 tonne per day with a conventional heap leach processing facility producing 2.7 million ounces of gold over a 10 year mine life with cash costs of US$652 per ounce. On January 28, 2014, Atacama Pacific announced an updated pit confined resource estimate of 3.47 million ounces of gold (248.8 million tonnes grading 0.43 g/t gold) in the measured and indicated category with a further 0.043 million ounces (3.1 million tonnes grading 0.43 g/t gold) in the inferred category. The resource estimate was based upon a cut-off grade of 0.18 g/t gold.

National Instrument 43-101

As defined by Section 1.5 of National Instrument 43-101 ("NI 43-101") of the Canadian Securities Administrators, the Qualified Person for the Cerro Maricunga Property is Sergio Diaz, a resident of Santiago, Chile and a registered member of the "Comision Calificadora de Competencias en Recursos y Reservas Mineras" (Chilean Mining Commission, registry n degrees 051), an accepted foreign association as defined by NI 43-101 (Appendix A). Mr. Diaz has reviewed the contents of this press release.

The Cerro Maricunga resource estimate was prepared under CIM Definition Standards (2005). Dr. Eduardo Magri, a mining engineer (University of Witwatersrand) and a Fellow of the Southern African Institute of Mining and Metallurgy with over 30 years of industry experience, is the Independent Qualified Person for the resource estimate.


This news release contains forward-looking statements, including predictions, projections and forecasts. Forward-looking statements include, but are not limited to, statements with respect to the PEA, including the potential total gold production of 2.7 million ounces over a 10.1 year mine life, initial life of mine estimated operating cash costs of US$652/oz Au, preliminary initial capital cost estimate of US$514.6 million with sustaining capital of US$249.0 million, pre-tax pay-back period of 2.5 years at US$1,450/oz Au and 1.7 years at US$1,700/oz Au, pre-tax NPV of $741 million at US$1,450/oz Au and a 5% discount rate After-tax NPV5% of US$531 million, pre-tax NPV5% of US$1,247 million and an after-tax NPV5% of US$923 million at US$1,700/oz Au, pre-tax IRR) of 33.9% at US$1,450/oz Au (after-tax IRR of 26.6%), statements regarding the expectation to increase mineral resources, statements regarding expectations for receipt of permits and environmental approvals, exploration results (including with respect to water resources), the success of exploration activities generally, mine development prospects, and potential future gold production. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "planning", "expects" or "does not expect", "continues", "scheduled", "estimates", "forecasts", "intends", "potential", "anticipates", "does not anticipate", or "belief", or describes a "goal", or variation of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

Forward-looking statements involve known and unknown risks, future events, conditions, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, prediction, projection, forecast, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, the results of due diligence activities, changes in economic parameters and assumptions, the interpretation and actual results of current exploration activities; changes in project parameters as plans continue to be refined; the results of regulatory and permitting processes; future prices of gold; possible variations in grade or recovery rates; failure of equipment or processes to operate as anticipated; labour disputes and other risks of the mining industry; the results of further economic and technical studies, delays in obtaining governmental approvals or financing or in the completion of exploration, as well as those factors disclosed in Atacama Pacific's publicly filed documents.

Although Atacama Pacific has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
WebRTC converts the entire network into a ubiquitous communications cloud thereby connecting anytime, anywhere through any point. In his session at WebRTC Summit,, Mark Castleman, EIR at Bell Labs and Head of Future X Labs, will discuss how the transformational nature of communications is achieved through the democratizing force of WebRTC. WebRTC is doing for voice what HTML did for web content.
The APN DevOps Competency highlights APN Partners who demonstrate deep capabilities delivering continuous integration, continuous delivery, and configuration management. They help customers transform their business to be more efficient and agile by leveraging the AWS platform and DevOps principles.
Developing software for the Internet of Things (IoT) comes with its own set of challenges. Security, privacy, and unified standards are a few key issues. In addition, each IoT product is comprised of at least three separate application components: the software embedded in the device, the backend big-data service, and the mobile application for the end user's controls. Each component is developed by a different team, using different technologies and practices, and deployed to a different stack/...
WebRTC is about the data channel as much as about video and audio conferencing. However, basically all commercial WebRTC applications have been built with a focus on audio and video. The handling of “data” has been limited to text chat and file download – all other data sharing seems to end with screensharing. What is holding back a more intensive use of peer-to-peer data? In her session at @ThingsExpo, Dr Silvia Pfeiffer, WebRTC Applications Team Lead at National ICT Australia, will look at di...
NHK, Japan Broadcasting will feature upcoming @ThingsExpo Silicon Valley in a special IoT documentary which will be filmed on the expo floor November 3 to 5, 2015 in Santa Clara. NHK is the sole public TV network in Japan equivalent to BBC in UK and the largest in Asia with many award winning science and technology programs. Japanese TV is producing a documentary about IoT and Smart technology covering @ThingsExpo Silicon Valley. The program will be aired during the highest viewership season of ...
SYS-CON Events announced today that Luxoft Holding, Inc., a leading provider of software development services and innovative IT solutions, has been named “Bronze Sponsor” of SYS-CON's @ThingsExpo, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. Luxoft’s software development services consist of core and mission-critical custom software development and support, product engineering and testing, and technology consulting.
In today's digital world, change is the one constant. Disruptive innovations like cloud, mobility, social media, and the Internet of Things have reshaped the market and set new standards in customer expectations. To remain competitive, businesses must tap the potential of emerging technologies and markets through the rapid release of new products and services. However, the rigid and siloed structures of traditional IT platforms and processes are slowing them down – resulting in lengthy delivery ...
According to Forrester, public cloud platforms are evolving, blurring the lines between Software as a Service (SaaS), Infrastructure as a Service (IaaS), and Platform as a Service (PaaS) in order to satisfy the needs of enterprises and widen their appeal to developers. In The Forrester Wave™: Enterprise Public Cloud Platforms, Q4 2014, Forrester evaluates the 16 most significant Enterprise Public Cloud Platforms and details how each vendor fulfills the 19 evaluation criteria points.
The broad selection of hardware, the rapid evolution of operating systems and the time-to-market for mobile apps has been so rapid that new challenges for developers and engineers arise every day. Security, testing, hosting, and other metrics have to be considered through the process. In his session at Big Data Expo, Walter Maguire, Chief Field Technologist, HP Big Data Group, at Hewlett-Packard, will discuss the challenges faced by developers and a composite Big Data applications builder, foc...
Nowadays, a large number of sensors and devices are connected to the network. Leading-edge IoT technologies integrate various types of sensor data to create a new value for several business decision scenarios. The transparent cloud is a model of a new IoT emergence service platform. Many service providers store and access various types of sensor data in order to create and find out new business values by integrating such data.
SYS-CON Events announced today that G2G3 will exhibit at SYS-CON's @DevOpsSummit Silicon Valley, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. Based on a collective appreciation for user experience, design, and technology, G2G3 is uniquely qualified and motivated to redefine how organizations and people engage in an increasingly digital world.
The cloud has reached mainstream IT. Those 18.7 million data centers out there (server closets to corporate data centers to colocation deployments) are moving to the cloud. In his session at 17th Cloud Expo, Achim Weiss, CEO & co-founder of ProfitBricks, will share how two companies – one in the U.S. and one in Germany – are achieving their goals with cloud infrastructure. More than a case study, he will share the details of how they prioritized their cloud computing infrastructure deployments ...
The modern software development landscape consists of best practices and tools that allow teams to deliver software in a near-continuous manner. By adopting a culture of automation, measurement and sharing, the time to ship code has been greatly reduced, allowing for shorter release cycles and quicker feedback from customers and users. Still, with all of these tools and methods, how can teams stay on top of what is taking place across their infrastructure and codebase? Hopping between services a...
Interested in leveraging automation technologies and a cloud architecture to make developers more productive? Learn how PaaS can benefit your organization to help you streamline your application development, allow you to use existing infrastructure and improve operational efficiencies. Begin charting your path to PaaS with OpenShift Enterprise.
Recently announced Azure Data Lake addresses the big data 3V challenges; volume, velocity and variety. It is one more storage feature in addition to blobs and SQL Azure database. Azure Data Lake (should have been Azure Data Ocean IMHO) is really omnipotent. Just look at the key capabilities of Azure Data Lake: