Asanko Gold Mine Phase 1 Project Update

Highlights:

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 06/18/14 -- Asanko Gold Inc. ("Asanko" or the "Company") (TSX:AKG)(NYSE MKT:AKG) is pleased to provide an update on activities at the fully funded and permitted Asanko Gold Mine (the "AGM" or the "Project") in Ghana. In early April, the Company engaged DRA as the Engineering, Procurement, Construction and Management ("EPCM") contractor for the design and construction of Phase 1 of the Project as well as Knight Piesold to design the Tailings Storage Facility and carry out detailed geotechnical engineering works for the site. Shortly thereafter, the Company initiated an early works program designed to advance the critical activities that will allow the Company to maintain its project schedule, targeting first gold in Q1 2016.

Detailed engineering and early works programs are proceeding on schedule, ground breaking at the plant site is expected to commence in August 2014, pending a positive investment decision on the Project by the Board in July.

Asanko Gold Mine Site Early Works

The site early works program, which began in April 2014 with a budget of approximately US$16 million, has been progressing on schedule and on budget. For photos of the early works progress at AGM, please click on the following link: http://www.asanko.com/s/photogallery.asp


--  Upgrading of the site access road is nearing completion with 8km out of
    11 km completed. 
    
--  Refurbishment of the mining village is 80% complete. 
    
--  The plant medical clinic construction is nearing completion and will be
    operational in early July. 
    
--  Mobile equipment orders have been placed and delivery of key equipment
    is scheduled for July. 
    
--  Refurbishment and upgrades to the site's airstrip have been completed
    and inspected by the regulatory authorities. 
    
--  Construction of the communication tower and office potable water systems
    have commenced. 

Detailed Engineering

Since commencing work in early April, DRA have advanced several key front-end engineering and design activities, including:


--  Plant layout is now complete, revised to incorporate a potential Phase 2
    expansion to the plant. 
    
--  An initial order is expected to be placed shortly for the detailed
    design of the 161kV electrical infrastructure. 
    
--  Various structural and civil designs are underway to allow bulk earth
    works to commence at the plant site in August 2014. 
    
--  Mechanical equipment list, process and instrumentation diagrams and
    process design criteria have been completed. 
    
--  Operating costs are in the process of being updated. 
    
--  Civil, mechanical, electrical and infrastructure designs have been
    completed to sufficient detail to allow the detailed capital cost to be
    estimated. 
    
--  The Control Base Estimate ("CBE") or detailed capital cost estimate for
    the Project is in the final stages of completion with all tenders
    closed. 

Knight Piesold have advanced geotechnical engineering with some additional geotechnical drilling completed over the past two months to support the detailed mine plan for the Nkran pit.

Resource Update & Mine Planning

Asanko's independent Qualified Person with respect to NI 43-101 has completed revisions to the Mineral Resource Estimate ("MRE") for the Nkran and Adubiaso pits, which are currently being used for detailed mine planning.

While the overall MRE has not changed materially since the previous estimate (announced in September 2012 and the basis for the Company's current disclosure), the revised estimate incorporates a more detailed geological model and utilises a combination of Indicator Kriging and Ordinary Kriging to bring a higher level of confidence and detail to the MRE which makes it more suitable for detailed mine planning.

DRA are currently working on the detailed mine plan, with a preliminary plan to be ready for the Board's investment decision in July and the final plan to be finalised during Q3 2014.

The revised MRE, detailed mine plan and CBE will all be combined into a Definitive Project Plan which is expected to be completed by Q4 2014 and filed as a NI 43-101 compliant technical report.

The contract tendering process has begun for the pre-strip component of the Nkran pit, which the Company expects to begin in Q4 2014. The pre-stripping of Nkran involves cutting back the existing pit from historical mining operations. Total pre-strip requirements are approximately 26 million tonnes of material to be moved to access the Nkran ore for the commencement of mining operations in Q3 2015. The cost of the pre-strip has been included in the Project's capital cost, as per the Company's current disclosure.

Permitting

Phase 1 of the Project is fully permitted for the commencement of construction. In early June, the Minerals Commission declared a moratorium over the expected mining and infrastructure areas. The declaration of a moratorium is an important precursor to construction activity and will establish the basis for crop compensation and land use deprivation processes to commence with the local communities. In addition, work is underway on a Resettlement Action Plan ("RAP") which will be reviewed and approved by the Ghanaian Environmental Protection Agency in Q4 2014.

The Company continues to advance the permitting required to mine both Dynamite Hill and the Phase 2 mining operations at Esaase. In early June, a Temporary Mining Permit was received for the Esaase deposit which would allow mining operations to commence at Esaase. Full environmental permitting at Esaase is ongoing.

Organisational Capability

On June 1st, the Company officially appointed Jonathan Ebo Collins as General Manager - Asanko Gold Mine. Charles Amoah, the current acting General Manager and a metallurgist, will continue with the Company as Manager - Processing. Recruitment is underway for other key operating positions as the Company continues to build its organisational capability in Ghana.

Jonathan is a Ghanaian national and a mining engineer with over 25 years of operational experience in the African mining sector. He has worked in Ghana, South Africa and Liberia, predominantly for major natural resources companies such as Xstrata Coal, Anglo American, Arcelor Mittal, Total, and Sasol. He began his career with Ashanti Goldfields, now AngloGold Ashanti, at the Obuasi mine before moving to South Africa to work in the coal industry. During his career, he has been Mine Manager and General Manager of several large coal operations with both open pit and underground mines and he has overseen projects from construction and commissioning through to operations. He has won multiple national safety awards in recognition of the outstanding safety performance of the mines under his management. Jonathan holds a Bachelor of Science and a Postgraduate Diploma in Mining Engineering and is a member of the South African Institute of Mining and Metallurgy (SAIMM).

For further information please visit www.asanko.com

About Asanko Gold Inc.

Asanko's vision is to become a mid-tier gold mining company that maximizes value for all its stakeholders. Asanko's flagship project is the fully financed, multi-million ounce Asanko Gold Mine Project located in Ghana, West Africa.

Asanko is managed by highly skilled and successful technical, operational and financial professionals. The Company is strongly committed to the highest standards for environmental management, social responsibility, and health and safety for its employees and neighbouring communities.

Forward-Looking and other Cautionary Information

This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, that address estimated resource quantities, grades and contained metals, possible future mining, exploration and development activities, are forward-looking statements. Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices for metals, the conclusions of detailed feasibility and technical analyses, lower than expected grades and quantities of resources, mining rates and recovery rates and the lack of availability of necessary capital, which may not be available to the Company on terms acceptable to it or at all. The Company is subject to the specific risks inherent in the mining business as well as general economic and business conditions. For more information on the Company, Investors should review the Company's annual Form 20-F filing with the United States Securities Commission and its home jurisdiction filings that are available at www.sedar.com.

Neither Toronto Stock Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note to US Investors Regarding Mineral Reporting Standards:

Asanko has prepared its disclosure in accordance with the requirements of securities laws in effect in Canada, which differ from the requirements of US securities laws. Terms relating to mineral resources in this press release are defined in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects under the guidelines set out in the Canadian Institute of Mining, Metallurgy, and Petroleum Standards on Mineral Resources and Mineral Reserves. The Securities and Exchange Commission (the "SEC") permits mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. Asanko uses certain terms, such as, "measured mineral resources", "indicated mineral resources", "inferred mineral resources" and "probable mineral reserves", that the SEC does not recognize (these terms may be used in this press release and are included in the public filings of Asanko which have been filed with securities commissions or similar authorities in Canada).

Contacts:
Alex Buck, Manager - Investor Relations
Telephone: +44-7932-740-452
Email: [email protected]

Greg McCunn, Chief Financial Officer
Telephone: +1-778-729-0604
Email: [email protected]

Asanko Gold Inc.
General [email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Rapid innovation, changing business landscapes, and new IT demands force businesses to make changes quickly. In the eyes of many, containers are at the brink of becoming a pervasive technology in enterprise IT to accelerate application delivery. In this presentation, attendees learned about the: The transformation of IT to a DevOps, microservices, and container-based architecture What are containers and how DevOps practices can operate in a container-based environment A demonstration of how ...
More and more brands have jumped on the IoT bandwagon. We have an excess of wearables – activity trackers, smartwatches, smart glasses and sneakers, and more that track seemingly endless datapoints. However, most consumers have no idea what “IoT” means. Creating more wearables that track data shouldn't be the aim of brands; delivering meaningful, tangible relevance to their users should be. We're in a period in which the IoT pendulum is still swinging. Initially, it swung toward "smart for smar...
Extracting business value from Internet of Things (IoT) data doesn’t happen overnight. There are several requirements that must be satisfied, including IoT device enablement, data analysis, real-time detection of complex events and automated orchestration of actions. Unfortunately, too many companies fall short in achieving their business goals by implementing incomplete solutions or not focusing on tangible use cases. In his general session at @ThingsExpo, Dave McCarthy, Director of Products...
Successful digital transformation requires new organizational competencies and capabilities. Research tells us that the biggest impediment to successful transformation is human; consequently, the biggest enabler is a properly skilled and empowered workforce. In the digital age, new individual and collective competencies are required. In his session at 19th Cloud Expo, Bob Newhouse, CEO and founder of Agilitiv, drew together recent research and lessons learned from emerging and established compa...
Without a clear strategy for cost control and an architecture designed with cloud services in mind, costs and operational performance can quickly get out of control. To avoid multiple architectural redesigns requires extensive thought and planning. Boundary (now part of BMC) launched a new public-facing multi-tenant high resolution monitoring service on Amazon AWS two years ago, facing challenges and learning best practices in the early days of the new service. In his session at 19th Cloud Exp...
"Venafi has a platform that allows you to manage, centralize and automate the complete life cycle of keys and certificates within the organization," explained Gina Osmond, Sr. Field Marketing Manager at Venafi, in this SYS-CON.tv interview at DevOps at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
Effectively SMBs and government programs must address compounded regulatory compliance requirements. The most recent are Controlled Unclassified Information and the EU's GDPR have Board Level implications. Managing sensitive data protection will likely result in acquisition criteria, demonstration requests and new requirements. Developers, as part of the pre-planning process and the associated supply chain, could benefit from updating their code libraries and design by incorporating changes. In...
"Coalfire is a cyber-risk, security and compliance assessment and advisory services firm. We do a lot of work with the cloud service provider community," explained Ryan McGowan, Vice President, Sales (West) at Coalfire Systems, Inc., in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
CloudJumper, a Workspace as a Service (WaaS) platform innovator for agile business IT, has been recognized with the Customer Value Leadership Award for its nWorkSpace platform by Frost & Sullivan. The company was also featured in a new report(1) by the industry research firm titled, “Desktop-as-a-Service Buyer’s Guide, 2016,” which provides a comprehensive comparison of DaaS providers, including CloudJumper, Amazon, VMware, and Microsoft.
Regulatory requirements exist to promote the controlled sharing of information, while protecting the privacy and/or security of the information. Regulations for each type of information have their own set of rules, policies, and guidelines. Cloud Service Providers (CSP) are faced with increasing demand for services at decreasing prices. Demonstrating and maintaining compliance with regulations is a nontrivial task and doing so against numerous sets of regulatory requirements can be daunting task...
Businesses and business units of all sizes can benefit from cloud computing, but many don't want the cost, performance and security concerns of public cloud nor the complexity of building their own private clouds. Today, some cloud vendors are using artificial intelligence (AI) to simplify cloud deployment and management. In his session at 20th Cloud Expo, Ajay Gulati, Co-founder and CEO of ZeroStack, will discuss how AI can simplify cloud operations. He will cover the following topics: why clou...
Fact: storage performance problems have only gotten more complicated, as applications not only have become largely virtualized, but also have moved to cloud-based infrastructures. Storage performance in virtualized environments isn’t just about IOPS anymore. Instead, you need to guarantee performance for individual VMs, helping applications maintain performance as the number of VMs continues to go up in real time. In his session at Cloud Expo, Dhiraj Sehgal, Product and Marketing at Tintri, sha...
The WebRTC Summit New York, to be held June 6-8, 2017, at the Javits Center in New York City, NY, announces that its Call for Papers is now open. Topics include all aspects of improving IT delivery by eliminating waste through automated business models leveraging cloud technologies. WebRTC Summit is co-located with 20th International Cloud Expo and @ThingsExpo. WebRTC is the future of browser-to-browser communications, and continues to make inroads into the traditional, difficult, plug-in web ...
In his keynote at 18th Cloud Expo, Andrew Keys, Co-Founder of ConsenSys Enterprise, provided an overview of the evolution of the Internet and the Database and the future of their combination – the Blockchain. Andrew Keys is Co-Founder of ConsenSys Enterprise. He comes to ConsenSys Enterprise with capital markets, technology and entrepreneurial experience. Previously, he worked for UBS investment bank in equities analysis. Later, he was responsible for the creation and distribution of life sett...
20th Cloud Expo, taking place June 6-8, 2017, at the Javits Center in New York City, NY, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy.