Asanko Gold Mine Phase 1 Project Update

Highlights:

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 06/18/14 -- Asanko Gold Inc. ("Asanko" or the "Company") (TSX:AKG)(NYSE MKT:AKG) is pleased to provide an update on activities at the fully funded and permitted Asanko Gold Mine (the "AGM" or the "Project") in Ghana. In early April, the Company engaged DRA as the Engineering, Procurement, Construction and Management ("EPCM") contractor for the design and construction of Phase 1 of the Project as well as Knight Piesold to design the Tailings Storage Facility and carry out detailed geotechnical engineering works for the site. Shortly thereafter, the Company initiated an early works program designed to advance the critical activities that will allow the Company to maintain its project schedule, targeting first gold in Q1 2016.

Detailed engineering and early works programs are proceeding on schedule, ground breaking at the plant site is expected to commence in August 2014, pending a positive investment decision on the Project by the Board in July.

Asanko Gold Mine Site Early Works

The site early works program, which began in April 2014 with a budget of approximately US$16 million, has been progressing on schedule and on budget. For photos of the early works progress at AGM, please click on the following link: http://www.asanko.com/s/photogallery.asp


--  Upgrading of the site access road is nearing completion with 8km out of
    11 km completed. 
    
--  Refurbishment of the mining village is 80% complete. 
    
--  The plant medical clinic construction is nearing completion and will be
    operational in early July. 
    
--  Mobile equipment orders have been placed and delivery of key equipment
    is scheduled for July. 
    
--  Refurbishment and upgrades to the site's airstrip have been completed
    and inspected by the regulatory authorities. 
    
--  Construction of the communication tower and office potable water systems
    have commenced. 

Detailed Engineering

Since commencing work in early April, DRA have advanced several key front-end engineering and design activities, including:


--  Plant layout is now complete, revised to incorporate a potential Phase 2
    expansion to the plant. 
    
--  An initial order is expected to be placed shortly for the detailed
    design of the 161kV electrical infrastructure. 
    
--  Various structural and civil designs are underway to allow bulk earth
    works to commence at the plant site in August 2014. 
    
--  Mechanical equipment list, process and instrumentation diagrams and
    process design criteria have been completed. 
    
--  Operating costs are in the process of being updated. 
    
--  Civil, mechanical, electrical and infrastructure designs have been
    completed to sufficient detail to allow the detailed capital cost to be
    estimated. 
    
--  The Control Base Estimate ("CBE") or detailed capital cost estimate for
    the Project is in the final stages of completion with all tenders
    closed. 

Knight Piesold have advanced geotechnical engineering with some additional geotechnical drilling completed over the past two months to support the detailed mine plan for the Nkran pit.

Resource Update & Mine Planning

Asanko's independent Qualified Person with respect to NI 43-101 has completed revisions to the Mineral Resource Estimate ("MRE") for the Nkran and Adubiaso pits, which are currently being used for detailed mine planning.

While the overall MRE has not changed materially since the previous estimate (announced in September 2012 and the basis for the Company's current disclosure), the revised estimate incorporates a more detailed geological model and utilises a combination of Indicator Kriging and Ordinary Kriging to bring a higher level of confidence and detail to the MRE which makes it more suitable for detailed mine planning.

DRA are currently working on the detailed mine plan, with a preliminary plan to be ready for the Board's investment decision in July and the final plan to be finalised during Q3 2014.

The revised MRE, detailed mine plan and CBE will all be combined into a Definitive Project Plan which is expected to be completed by Q4 2014 and filed as a NI 43-101 compliant technical report.

The contract tendering process has begun for the pre-strip component of the Nkran pit, which the Company expects to begin in Q4 2014. The pre-stripping of Nkran involves cutting back the existing pit from historical mining operations. Total pre-strip requirements are approximately 26 million tonnes of material to be moved to access the Nkran ore for the commencement of mining operations in Q3 2015. The cost of the pre-strip has been included in the Project's capital cost, as per the Company's current disclosure.

Permitting

Phase 1 of the Project is fully permitted for the commencement of construction. In early June, the Minerals Commission declared a moratorium over the expected mining and infrastructure areas. The declaration of a moratorium is an important precursor to construction activity and will establish the basis for crop compensation and land use deprivation processes to commence with the local communities. In addition, work is underway on a Resettlement Action Plan ("RAP") which will be reviewed and approved by the Ghanaian Environmental Protection Agency in Q4 2014.

The Company continues to advance the permitting required to mine both Dynamite Hill and the Phase 2 mining operations at Esaase. In early June, a Temporary Mining Permit was received for the Esaase deposit which would allow mining operations to commence at Esaase. Full environmental permitting at Esaase is ongoing.

Organisational Capability

On June 1st, the Company officially appointed Jonathan Ebo Collins as General Manager - Asanko Gold Mine. Charles Amoah, the current acting General Manager and a metallurgist, will continue with the Company as Manager - Processing. Recruitment is underway for other key operating positions as the Company continues to build its organisational capability in Ghana.

Jonathan is a Ghanaian national and a mining engineer with over 25 years of operational experience in the African mining sector. He has worked in Ghana, South Africa and Liberia, predominantly for major natural resources companies such as Xstrata Coal, Anglo American, Arcelor Mittal, Total, and Sasol. He began his career with Ashanti Goldfields, now AngloGold Ashanti, at the Obuasi mine before moving to South Africa to work in the coal industry. During his career, he has been Mine Manager and General Manager of several large coal operations with both open pit and underground mines and he has overseen projects from construction and commissioning through to operations. He has won multiple national safety awards in recognition of the outstanding safety performance of the mines under his management. Jonathan holds a Bachelor of Science and a Postgraduate Diploma in Mining Engineering and is a member of the South African Institute of Mining and Metallurgy (SAIMM).

For further information please visit www.asanko.com

About Asanko Gold Inc.

Asanko's vision is to become a mid-tier gold mining company that maximizes value for all its stakeholders. Asanko's flagship project is the fully financed, multi-million ounce Asanko Gold Mine Project located in Ghana, West Africa.

Asanko is managed by highly skilled and successful technical, operational and financial professionals. The Company is strongly committed to the highest standards for environmental management, social responsibility, and health and safety for its employees and neighbouring communities.

Forward-Looking and other Cautionary Information

This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, that address estimated resource quantities, grades and contained metals, possible future mining, exploration and development activities, are forward-looking statements. Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices for metals, the conclusions of detailed feasibility and technical analyses, lower than expected grades and quantities of resources, mining rates and recovery rates and the lack of availability of necessary capital, which may not be available to the Company on terms acceptable to it or at all. The Company is subject to the specific risks inherent in the mining business as well as general economic and business conditions. For more information on the Company, Investors should review the Company's annual Form 20-F filing with the United States Securities Commission and its home jurisdiction filings that are available at www.sedar.com.

Neither Toronto Stock Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note to US Investors Regarding Mineral Reporting Standards:

Asanko has prepared its disclosure in accordance with the requirements of securities laws in effect in Canada, which differ from the requirements of US securities laws. Terms relating to mineral resources in this press release are defined in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects under the guidelines set out in the Canadian Institute of Mining, Metallurgy, and Petroleum Standards on Mineral Resources and Mineral Reserves. The Securities and Exchange Commission (the "SEC") permits mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. Asanko uses certain terms, such as, "measured mineral resources", "indicated mineral resources", "inferred mineral resources" and "probable mineral reserves", that the SEC does not recognize (these terms may be used in this press release and are included in the public filings of Asanko which have been filed with securities commissions or similar authorities in Canada).

Contacts:
Alex Buck, Manager - Investor Relations
Telephone: +44-7932-740-452
Email: [email protected]

Greg McCunn, Chief Financial Officer
Telephone: +1-778-729-0604
Email: [email protected]

Asanko Gold Inc.
General [email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Adding public cloud resources to an existing application can be a daunting process. The tools that you currently use to manage the software and hardware outside the cloud aren’t always the best tools to efficiently grow into the cloud. All of the major configuration management tools have cloud orchestration plugins that can be leveraged, but there are also cloud-native tools that can dramatically improve the efficiency of managing your application lifecycle.
SYS-CON Events announced today that Juniper Networks (NYSE: JNPR), an industry leader in automated, scalable and secure networks, will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Juniper Networks challenges the status quo with products, solutions and services that transform the economics of networking. The company co-innovates with customers and partners to deliver automated, scalable and secure network...
DevOps is often described as a combination of technology and culture. Without both, DevOps isn't complete. However, applying the culture to outdated technology is a recipe for disaster; as response times grow and connections between teams are delayed by technology, the culture will die. A Nutanix Enterprise Cloud has many benefits that provide the needed base for a true DevOps paradigm. In his Day 3 Keynote at 20th Cloud Expo, Chris Brown, a Solutions Marketing Manager at Nutanix, will explore t...
SYS-CON Events announced today that SoftLayer, an IBM Company, has been named “Gold Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2016, at the Javits Center in New York, New York. SoftLayer, an IBM Company, provides cloud infrastructure as a service from a growing number of data centers and network points of presence around the world. SoftLayer’s customers range from Web startups to global enterprises.
SYS-CON Events announced today that Linux Academy, the foremost online Linux and cloud training platform and community, will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Linux Academy was founded on the belief that providing high-quality, in-depth training should be available at an affordable price. Industry leaders in quality training, provided services, and student certification passes, its goal is to c...
Some people worry that OpenStack is more flash then substance; however, for many customers this could not be farther from the truth. No other technology equalizes the playing field between vendors while giving your internal teams better access than ever to infrastructure when they need it. In his session at 20th Cloud Expo, Chris Brown, a Solutions Marketing Manager at Nutanix, will talk through some real-world OpenStack deployments and look into the ways this can benefit customers of all sizes....
Deep learning has been very successful in social sciences and specially areas where there is a lot of data. Trading is another field that can be viewed as social science with a lot of data. With the advent of Deep Learning and Big Data technologies for efficient computation, we are finally able to use the same methods in investment management as we would in face recognition or in making chat-bots. In his session at 20th Cloud Expo, Gaurav Chakravorty, co-founder and Head of Strategy Development ...
SYS-CON Events announced today that CA Technologies has been named “Platinum Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY, and the 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CA Technologies helps customers succeed in a future where every business – from apparel to energy – is being rewritten by software. From ...
Interoute has announced the integration of its Global Cloud Infrastructure platform with Rancher Labs’ container management platform, Rancher. This approach enables enterprises to accelerate their digital transformation and infrastructure investments. Matthew Finnie, Interoute CTO commented “Enterprises developing and building apps in the cloud and those on a path to Digital Transformation need Digital ICT Infrastructure that allows them to build, test and deploy faster than ever before. The int...
In his session at @ThingsExpo, Eric Lachapelle, CEO of the Professional Evaluation and Certification Board (PECB), will provide an overview of various initiatives to certifiy the security of connected devices and future trends in ensuring public trust of IoT. Eric Lachapelle is the Chief Executive Officer of the Professional Evaluation and Certification Board (PECB), an international certification body. His role is to help companies and individuals to achieve professional, accredited and worldw...
What if you could build a web application that could support true web-scale traffic without having to ever provision or manage a single server? Sounds magical, and it is! In his session at 20th Cloud Expo, Chris Munns, Senior Developer Advocate for Serverless Applications at Amazon Web Services, will show how to build a serverless website that scales automatically using services like AWS Lambda, Amazon API Gateway, and Amazon S3. We will review several frameworks that can help you build serverle...
SYS-CON Events announced today that Loom Systems will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Founded in 2015, Loom Systems delivers an advanced AI solution to predict and prevent problems in the digital business. Loom stands alone in the industry as an AI analysis platform requiring no prior math knowledge from operators, leveraging the existing staff to succeed in the digital era. With offices in S...
SYS-CON Events announced today that Interoute, owner-operator of one of Europe's largest networks and a global cloud services platform, has been named “Bronze Sponsor” of SYS-CON's 20th Cloud Expo, which will take place on June 6-8, 2017 at the Javits Center in New York, New York. Interoute is the owner-operator of one of Europe's largest networks and a global cloud services platform which encompasses 12 data centers, 14 virtual data centers and 31 colocation centers, with connections to 195 add...
The Software Defined Data Center (SDDC), which enables organizations to seamlessly run in a hybrid cloud model (public + private cloud), is here to stay. IDC estimates that the software-defined networking market will be valued at $3.7 billion by 2016. Security is a key component and benefit of the SDDC, and offers an opportunity to build security 'from the ground up' and weave it into the environment from day one. In his session at 16th Cloud Expo, Reuven Harrison, CTO and Co-Founder of Tufin, ...
SYS-CON Events announced today that T-Mobile will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. As America's Un-carrier, T-Mobile US, Inc., is redefining the way consumers and businesses buy wireless services through leading product and service innovation. The Company's advanced nationwide 4G LTE network delivers outstanding wireless experiences to 67.4 million customers who are unwilling to compromise on ...