Welcome!

News Feed Item

Construction of the Phoenix Gold Project Continues on Schedule and on Budget

TORONTO, ONTARIO -- (Marketwired) -- 06/19/14 -- Rubicon Minerals Corporation (TSX:RMX)(NYSE MKT:RBY) ("Rubicon" or the "Company") has substantially advanced the Phoenix Gold Project ("Project"), with project construction and development remaining on budget and on schedule for projected production in mid-2015.

"We are pleased with the progress of the construction and de-risking of the Phoenix Gold Project," said Michael A. Lalonde, President and Chief Executive Officer of Rubicon. "The Project is tracking to schedule and budget compared to the targets we had set earlier this year. We will continue to closely monitor our activities and associated capital costs as the Project progresses toward the projected operating phase in mid-2015."

The Phoenix Gold Project Development and Construction Update

Underground Project Development and Construction

Advance rates on both the lateral and vertical development have been tracking on schedule. Rubicon has completed 875 metres of a planned 8,023 metres (or 10.9%) of total underground development (lateral and vertical) at and above the 685-metre level. The completion of this planned underground development is required to commence projected production. The Company continues lateral development at the 122-, 183-, 244-, 305-, 610-, and 685-metre levels. The 244- and 305-metre levels were previously advanced to the deposit, prior to the completion of shaft sinking. An exploration drift on the 244-metre level is progressing well, with 13 drill stations completed of a planned 18 stations. There are two drills currently operating on the level. The development of the main ventilation pilot raise from the 305-metre level to surface will be completed by the end of June. At the present time, all underground development is being carried out by a contractor. Rubicon is in the process procuring equipment and hiring staff to replace the majority of the contractors engaged in lateral development, which could potentially lower costs and increase productivity. A summary of the total underground development is displayed in Figure 1.

The Company has secured favourable lease terms for all of its underground equipment needs. The lease terms are 4.5% over a 5-year term, with a 10% down payment. The lease will cover $15.0 million of mobile equipment purchases over the next two years, or 25 units. The initial fleet of mobile equipment has started to arrive on site, and is being commissioned.

The Company has approximately $42.0 million (as at May 31, 2014) of total underground development capital remaining to the start of potential production.

Mill Construction

Full mill construction recommenced on April 1, 2014, with civil works in the mill building continuing. Civil, process, and electrical engineering for the mill is approximately 81.0% complete. The Elution plant, which extracts gold from the carbon in the leaching process, is near completion. The equipment for the Elution plant has been installed, with the piping and electrical work remaining to be completed. The formation of the tank bases, pump bases, containment areas and pillars have been completed. Concrete will soon be poured in the mill thickener area, just outside the mill building.

Rubicon has approximately $71.5 million (as at May 31, 2014) of mill capital expenditures remaining to completion. Mill construction is on track to be completed and commissioned by mid-2015.

Surface Infrastructure and On-Site Construction

The Actiflo system, which will be the final stage of effluent water treatment, has been fully commissioned. The raw ore bin has been installed in the head frame. The construction of the tailings management facility, which was halted during the winter months, has resumed and is near completion. Rubicon has approximately $31.7 million (as at May 31, 2014) of on-site construction remaining to completion.

See figures 2, 3, 4 for the pictures of the construction and development progress of the Phoenix Gold Project. For more pictures of the Project construction and development progress, please visit our website at http://www.rubiconminerals.com/Investors/Photo-Galleries/default.aspx.

Pre-Production Capital and Timeline to Potential Production

As of May 31, 2014, Rubicon estimates that pre-production capital to complete the Project is $167.5 million, including contingency. A breakdown of the capital expenditures remaining can be seen in Table 1. Rubicon has approximately $180 million in cash and cash equivalents on its balance sheet to date and anticipates it will receive the US$45 million remaining on the Royal Gold streaming transaction over the next several quarters, as spending on construction and development increases. The construction of the Phoenix Gold Project remains on schedule and on budget. The timeline to projected production remains mid-2015.


                                                                            
Table 1: Capital Expenditures Remaining as of May 31, 2014                  
                                                                            
----------------------------------------------------------------------------
Project capex spent, October 1, 2011 to May 31, 2014         C$205.2 million
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Remaining capex to projected production                                     
----------------------------------------------------------------------------
  Mill                                                        C$71.5 million
----------------------------------------------------------------------------
  Underground development                                     C$42.0 million
----------------------------------------------------------------------------
  On-site construction                                        C$31.7 million
----------------------------------------------------------------------------
  Indirects & definition drilling                             C$22.3 million
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Total remaining capex to projected production (with                         
 contingency)                                                C$167.5 million
----------------------------------------------------------------------------

Aboriginal Communities

The Waubaskang First Nation's ("WFN") application for judicial review of the Production Closure Plan for the Phoenix Gold Project was heard by the Ontario Divisional Court between April 15th and 17th. The timeline for a decision was not provided. This application has not impacted construction and development activities at the Phoenix Gold Project. Rubicon continues to believe that the WFN application is without merit and will vigorously defend its position.

To view Figures 1-4, click on the following link: http://media3.marketwire.com/docs/952915f.pdf

About Rubicon Minerals Corporation

Rubicon Minerals Corporation is an advanced stage gold development company. The Company is focused on responsible and environmentally sustainable development of its Phoenix Gold Project in Red Lake, Ontario. The start of potential gold production is projected in mid-2015, based on current forecasts. The Phoenix Gold Project is fully permitted for initial production at 1,250 tonnes per day. In addition, Rubicon controls over 100 square miles of prime exploration ground in the prolific Red Lake gold district which hosts Goldcorp's high-grade, world class Red Lake Mine. Rubicon's shares are listed on the NYSE MKT (RBY) and the Toronto Stock Exchange (RMX).

RUBICON MINERALS CORPORATION

Mike Lalonde, President and Chief Executive Officer

The content of this news release has been read and approved by Daniel Labine, P.Eng., Vice President of Operations and Mark Ross, B.Sc., P.Geo., Chief Mine Geologist, for Rubicon. Both are Qualified Persons as defined by NI 43-101.

Forward-Looking Statements

This news release contains statements that constitute "forward-looking statements" within the meaning of Section 21E of the United States Securities Exchange Act of 1934 and "forward looking information" within the meaning of applicable Canadian provincial securities legislation (collectively, "forward-looking statements"). Forward-looking statements often, but not always, are identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect", "targeting", "look forward" and "intend" and statements that an event or result "may", "will", "would", "should", "could", or "might" occur or be achieved and other similar expressions.

Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and represent management's best judgment based on facts and assumptions that management considers reasonable. The material assumptions upon which such forward-looking statements are based include, among others; that the demand for gold and base metal deposits will develop as anticipated; that the price of gold will remain at levels that will render the Phoenix Gold Project economic; that operating and capital plans will not be disrupted by issues such as mechanical failure, unavailability of parts and supplies, labour disturbances, interruption in transportation or utilities, or adverse weather conditions; that Rubicon will meet its estimated timeline for the development of the Phoenix Gold Project; that Rubicon will continue to have the ability to attract and retain skilled staff; that the mineral resource estimate as disclosed in the New Preliminary Economic Assessment with an effective date of June 25, 2013 and with an issue date of February 28, 2014 ("New PEA") will be realized; and that there are no material unanticipated variations in the cost of energy or supplies, or in the pre-production capital and operating cost estimate as disclosed in the New PEA. Rubicon makes no representation that reasonable business people in possession of the same information would reach the same conclusions.

Capital expenditures and time required to develop new mines are considerable and changes in cost or construction schedules can significantly increase both the time and capital required to build and complete a development project. Additional capital costs may be to be incurred in respect of the Phoenix Gold Project.

The New PEA is preliminary in nature as it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the New PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources referred to in the New PEA are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource category.

Forward-looking statements in this news release include, but are not limited to statements regarding potential production and the projected timing of the completion of certain construction activities associated with the Phoenix Gold Project.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Rubicon to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others: future prices of gold and other metals; possible variations in mineralization, grade or recovery rates; actual results of current exploration activities; actual results of reclamation activities; conclusions of future economic evaluations; changes in project parameters as plans continue to be refined; failure of equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays and other risks related to joint venture operations; timing and receipt of regulatory approvals of operations; the ability of Rubicon and other relevant parties to satisfy regulatory requirements; the availability of financing for proposed transactions and programs on reasonable terms; the ability of third-party service providers to deliver services on reasonable terms and in a timely manner; and delays in the completion of development or construction activities. Other factors that could cause the actual results to differ include market prices, results of exploration, availability of capital and financing on acceptable terms, inability to obtain required regulatory approvals, unanticipated difficulties or costs in any rehabilitation which may be necessary, market conditions and general business, economic, competitive, political and social conditions.

It is important to note that the information provided in this news release is preliminary in nature. There is no certainty that a potential mine will be realized. A mine production decision that is made without a bankable feasibility study carries additional potential risks which include, but are not limited to, the inclusion of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mine design and mining schedules, metallurgical flow sheets and process plant designs may require additional detailed work to ensure satisfactory operational conditions.

Forward-looking statements contained herein are made as of the date of this news release and Rubicon disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

Cautionary Note to U.S. Readers Regarding Estimates of Indicated and Inferred Resources

This news release uses the terms "indicated mineral resources" and "inferred resources". The Company advises U.S. investors that while these terms are recognized and required by Canadian securities administrators, they are not recognized by the SEC. "Inferred resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an "inferred" or "indicated mineral resource" will ever be upgraded to a higher category.

Under Canadian rules, estimates of "inferred mineral resources" may not form the basis of feasibility studies, pre-feasibility studies or other economic studies, except in prescribed cases, such as in a preliminary economic assessment under certain circumstances. The SEC normally only permits issuers to report mineralization that does not constitute "reserves" as in-place tonnage and grade without reference to unit measures. Under U.S. standards, mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. U.S. investors are cautioned not to assume that any part or all of an indicated or inferred resource exists or is economically or legally mineable. Information concerning descriptions of mineralization and resources contained herein may not be comparable to information made public by U.S. companies subject to the reporting and disclosure requirements of the SEC.

Mineral Resources

Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources in this estimation are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource and it is uncertain if further exploration will result in upgrading them to an indicated or measured mineral resource category. The mineral resources in this press release were reported using CIM Standards.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that Pulzze Systems will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Pulzze Systems, Inc. provides infrastructure products for the Internet of Things to enable any connected device and system to carry out matched operations without programming. For more information, visit http://www.pulzzesystems.com.
SYS-CON Events announced today the Enterprise IoT Bootcamp, being held November 1-2, 2016, in conjunction with 19th Cloud Expo | @ThingsExpo at the Santa Clara Convention Center in Santa Clara, CA. Combined with real-world scenarios and use cases, the Enterprise IoT Bootcamp is not just based on presentations but with hands-on demos and detailed walkthroughs. We will introduce you to a variety of real world use cases prototyped using Arduino, Raspberry Pi, BeagleBone, Spark, and Intel Edison. Y...
Most of us already know that adopting new cloud applications can boost a business’s productivity by enabling organizations to be more agile and ready to change course in our fast-moving and connected digital world. But the rapid adoption of cloud apps and services also brings with it profound security threats, including visibility and control challenges that aren’t present in traditional on-premises environments. At the same time, the cloud – because of its interconnected, flexible and adaptable...
Technology vendors and analysts are eager to paint a rosy picture of how wonderful IoT is and why your deployment will be great with the use of their products and services. While it is easy to showcase successful IoT solutions, identifying IoT systems that missed the mark or failed can often provide more in the way of key lessons learned. In his session at @ThingsExpo, Peter Vanderminden, Principal Industry Analyst for IoT & Digital Supply Chain to Flatiron Strategies, will focus on how IoT de...
Fact is, enterprises have significant legacy voice infrastructure that’s costly to replace with pure IP solutions. How can we bring this analog infrastructure into our shiny new cloud applications? There are proven methods to bind both legacy voice applications and traditional PSTN audio into cloud-based applications and services at a carrier scale. Some of the most successful implementations leverage WebRTC, WebSockets, SIP and other open source technologies. In his session at @ThingsExpo, Da...
SYS-CON Events announced today that China Unicom will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. China United Network Communications Group Co. Ltd ("China Unicom") was officially established in 2009 on the basis of the merger of former China Netcom and former China Unicom. China Unicom mainly operates a full range of telecommunications services including mobile broadband (GSM, WCDMA, LTE F...
SYS-CON Events announced today that Roundee / LinearHub will exhibit at the WebRTC Summit at @ThingsExpo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. LinearHub provides Roundee Service, a smart platform for enterprise video conferencing with enhanced features such as automatic recording and transcription service. Slack users can integrate Roundee to their team via Slack’s App Directory, and '/roundee' command lets your video conference ...
DevOps at Cloud Expo, taking place Nov 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 19th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long dev...
Almost two-thirds of companies either have or soon will have IoT as the backbone of their business in 2016. However, IoT is far more complex than most firms expected. How can you not get trapped in the pitfalls? In his session at @ThingsExpo, Tony Shan, a renowned visionary and thought leader, will introduce a holistic method of IoTification, which is the process of IoTifying the existing technology and business models to adopt and leverage IoT. He will drill down to the components in this fra...
There is growing need for data-driven applications and the need for digital platforms to build these apps. In his session at 19th Cloud Expo, Muddu Sudhakar, VP and GM of Security & IoT at Splunk, will cover different PaaS solutions and Big Data platforms that are available to build applications. In addition, AI and machine learning are creating new requirements that developers need in the building of next-gen apps. The next-generation digital platforms have some of the past platform needs a...
Without a clear strategy for cost control and an architecture designed with cloud services in mind, costs and operational performance can quickly get out of control. To avoid multiple architectural redesigns requires extensive thought and planning. Boundary (now part of BMC) launched a new public-facing multi-tenant high resolution monitoring service on Amazon AWS two years ago, facing challenges and learning best practices in the early days of the new service. In his session at 19th Cloud Exp...
I'm a lonely sensor. I spend all day telling the world how I'm feeling, but none of the other sensors seem to care. I want to be connected. I want to build relationships with other sensors to be more useful for my human. I want my human to understand that when my friends next door are too hot for a while, I'll soon be flaming. And when all my friends go outside without me, I may be left behind. Don't just log my data; use the relationship graph. In his session at @ThingsExpo, Ryan Boyd, Engi...
Information technology is an industry that has always experienced change, and the dramatic change sweeping across the industry today could not be truthfully described as the first time we've seen such widespread change impacting customer investments. However, the rate of the change, and the potential outcomes from today's digital transformation has the distinct potential to separate the industry into two camps: Organizations that see the change coming, embrace it, and successful leverage it; and...
SYS-CON Events announced today that Numerex Corp, a leading provider of managed enterprise solutions enabling the Internet of Things (IoT), will exhibit at the 19th International Cloud Expo | @ThingsExpo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Numerex Corp. (NASDAQ:NMRX) is a leading provider of managed enterprise solutions enabling the Internet of Things (IoT). The Company's solutions produce new revenue streams or create operating...
While DevOps promises a better and tighter integration among an organization’s development and operation teams and transforms an application life cycle into a continual deployment, Chef and Azure together provides a speedy, cost-effective and highly scalable vehicle for realizing the business values of this transformation. In his session at @DevOpsSummit at 19th Cloud Expo, Yung Chou, a Technology Evangelist at Microsoft, will present a unique opportunity to witness how Chef and Azure work tog...