Construction of the Phoenix Gold Project Continues on Schedule and on Budget

TORONTO, ONTARIO -- (Marketwired) -- 06/19/14 -- Rubicon Minerals Corporation (TSX: RMX)(NYSE MKT: RBY) ("Rubicon" or the "Company") has substantially advanced the Phoenix Gold Project ("Project"), with project construction and development remaining on budget and on schedule for projected production in mid-2015.

"We are pleased with the progress of the construction and de-risking of the Phoenix Gold Project," said Michael A. Lalonde, President and Chief Executive Officer of Rubicon. "The Project is tracking to schedule and budget compared to the targets we had set earlier this year. We will continue to closely monitor our activities and associated capital costs as the Project progresses toward the projected operating phase in mid-2015."

The Phoenix Gold Project Development and Construction Update

Underground Project Development and Construction

Advance rates on both the lateral and vertical development have been tracking on schedule. Rubicon has completed 875 metres of a planned 8,023 metres (or 10.9%) of total underground development (lateral and vertical) at and above the 685-metre level. The completion of this planned underground development is required to commence projected production. The Company continues lateral development at the 122-, 183-, 244-, 305-, 610-, and 685-metre levels. The 244- and 305-metre levels were previously advanced to the deposit, prior to the completion of shaft sinking. An exploration drift on the 244-metre level is progressing well, with 13 drill stations completed of a planned 18 stations. There are two drills currently operating on the level. The development of the main ventilation pilot raise from the 305-metre level to surface will be completed by the end of June. At the present time, all underground development is being carried out by a contractor. Rubicon is in the process procuring equipment and hiring staff to replace the majority of the contractors engaged in lateral development, which could potentially lower costs and increase productivity. A summary of the total underground development is displayed in Figure 1.

The Company has secured favourable lease terms for all of its underground equipment needs. The lease terms are 4.5% over a 5-year term, with a 10% down payment. The lease will cover $15.0 million of mobile equipment purchases over the next two years, or 25 units. The initial fleet of mobile equipment has started to arrive on site, and is being commissioned.

The Company has approximately $42.0 million (as at May 31, 2014) of total underground development capital remaining to the start of potential production.

Mill Construction

Full mill construction recommenced on April 1, 2014, with civil works in the mill building continuing. Civil, process, and electrical engineering for the mill is approximately 81.0% complete. The Elution plant, which extracts gold from the carbon in the leaching process, is near completion. The equipment for the Elution plant has been installed, with the piping and electrical work remaining to be completed. The formation of the tank bases, pump bases, containment areas and pillars have been completed. Concrete will soon be poured in the mill thickener area, just outside the mill building.

Rubicon has approximately $71.5 million (as at May 31, 2014) of mill capital expenditures remaining to completion. Mill construction is on track to be completed and commissioned by mid-2015.

Surface Infrastructure and On-Site Construction

The Actiflo system, which will be the final stage of effluent water treatment, has been fully commissioned. The raw ore bin has been installed in the head frame. The construction of the tailings management facility, which was halted during the winter months, has resumed and is near completion. Rubicon has approximately $31.7 million (as at May 31, 2014) of on-site construction remaining to completion.

See figures 2, 3, 4 for the pictures of the construction and development progress of the Phoenix Gold Project. For more pictures of the Project construction and development progress, please visit our website at http://www.rubiconminerals.com/Investors/Photo-Galleries/default.aspx.

Pre-Production Capital and Timeline to Potential Production

As of May 31, 2014, Rubicon estimates that pre-production capital to complete the Project is $167.5 million, including contingency. A breakdown of the capital expenditures remaining can be seen in Table 1. Rubicon has approximately $180 million in cash and cash equivalents on its balance sheet to date and anticipates it will receive the US$45 million remaining on the Royal Gold streaming transaction over the next several quarters, as spending on construction and development increases. The construction of the Phoenix Gold Project remains on schedule and on budget. The timeline to projected production remains mid-2015.



Table 1: Capital Expenditures Remaining as of May 31, 2014

----------------------------------------------------------------------------
Project capex spent, October 1, 2011 to May 31, 2014         C$205.2 million
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Remaining capex to projected production
----------------------------------------------------------------------------
  Mill                                                        C$71.5 million
----------------------------------------------------------------------------
  Underground development                                     C$42.0 million
----------------------------------------------------------------------------
  On-site construction                                        C$31.7 million
----------------------------------------------------------------------------
  Indirects & definition drilling                             C$22.3 million
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Total remaining capex to projected production (with
 contingency)                                                C$167.5 million
----------------------------------------------------------------------------

Aboriginal Communities

The Waubaskang First Nation's ("WFN") application for judicial review of the Production Closure Plan for the Phoenix Gold Project was heard by the Ontario Divisional Court between April 15th and 17th. The timeline for a decision was not provided. This application has not impacted construction and development activities at the Phoenix Gold Project. Rubicon continues to believe that the WFN application is without merit and will vigorously defend its position.

To view Figures 1-4, click on the following link: http://media3.marketwire.com/docs/952915f.pdf

About Rubicon Minerals Corporation

Rubicon Minerals Corporation is an advanced stage gold development company. The Company is focused on responsible and environmentally sustainable development of its Phoenix Gold Project in Red Lake, Ontario. The start of potential gold production is projected in mid-2015, based on current forecasts. The Phoenix Gold Project is fully permitted for initial production at 1,250 tonnes per day. In addition, Rubicon controls over 100 square miles of prime exploration ground in the prolific Red Lake gold district which hosts Goldcorp's high-grade, world class Red Lake Mine. Rubicon's shares are listed on the NYSE MKT (RBY) and the Toronto Stock Exchange (RMX).

RUBICON MINERALS CORPORATION

Mike Lalonde, President and Chief Executive Officer

The content of this news release has been read and approved by Daniel Labine, P.Eng., Vice President of Operations and Mark Ross, B.Sc., P.Geo., Chief Mine Geologist, for Rubicon. Both are Qualified Persons as defined by NI 43-101.

Forward-Looking Statements

This news release contains statements that constitute "forward-looking statements" within the meaning of Section 21E of the United States Securities Exchange Act of 1934 and "forward looking information" within the meaning of applicable Canadian provincial securities legislation (collectively, "forward-looking statements"). Forward-looking statements often, but not always, are identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect", "targeting", "look forward" and "intend" and statements that an event or result "may", "will", "would", "should", "could", or "might" occur or be achieved and other similar expressions.

Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and represent management's best judgment based on facts and assumptions that management considers reasonable. The material assumptions upon which such forward-looking statements are based include, among others; that the demand for gold and base metal deposits will develop as anticipated; that the price of gold will remain at levels that will render the Phoenix Gold Project economic; that operating and capital plans will not be disrupted by issues such as mechanical failure, unavailability of parts and supplies, labour disturbances, interruption in transportation or utilities, or adverse weather conditions; that Rubicon will meet its estimated timeline for the development of the Phoenix Gold Project; that Rubicon will continue to have the ability to attract and retain skilled staff; that the mineral resource estimate as disclosed in the New Preliminary Economic Assessment with an effective date of June 25, 2013 and with an issue date of February 28, 2014 ("New PEA") will be realized; and that there are no material unanticipated variations in the cost of energy or supplies, or in the pre-production capital and operating cost estimate as disclosed in the New PEA. Rubicon makes no representation that reasonable business people in possession of the same information would reach the same conclusions.

Capital expenditures and time required to develop new mines are considerable and changes in cost or construction schedules can significantly increase both the time and capital required to build and complete a development project. Additional capital costs may be to be incurred in respect of the Phoenix Gold Project.

The New PEA is preliminary in nature as it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the New PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources referred to in the New PEA are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource category.

Forward-looking statements in this news release include, but are not limited to statements regarding potential production and the projected timing of the completion of certain construction activities associated with the Phoenix Gold Project.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Rubicon to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others: future prices of gold and other metals; possible variations in mineralization, grade or recovery rates; actual results of current exploration activities; actual results of reclamation activities; conclusions of future economic evaluations; changes in project parameters as plans continue to be refined; failure of equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays and other risks related to joint venture operations; timing and receipt of regulatory approvals of operations; the ability of Rubicon and other relevant parties to satisfy regulatory requirements; the availability of financing for proposed transactions and programs on reasonable terms; the ability of third-party service providers to deliver services on reasonable terms and in a timely manner; and delays in the completion of development or construction activities. Other factors that could cause the actual results to differ include market prices, results of exploration, availability of capital and financing on acceptable terms, inability to obtain required regulatory approvals, unanticipated difficulties or costs in any rehabilitation which may be necessary, market conditions and general business, economic, competitive, political and social conditions.

It is important to note that the information provided in this news release is preliminary in nature. There is no certainty that a potential mine will be realized. A mine production decision that is made without a bankable feasibility study carries additional potential risks which include, but are not limited to, the inclusion of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mine design and mining schedules, metallurgical flow sheets and process plant designs may require additional detailed work to ensure satisfactory operational conditions.

Forward-looking statements contained herein are made as of the date of this news release and Rubicon disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

Cautionary Note to U.S. Readers Regarding Estimates of Indicated and Inferred Resources

This news release uses the terms "indicated mineral resources" and "inferred resources". The Company advises U.S. investors that while these terms are recognized and required by Canadian securities administrators, they are not recognized by the SEC. "Inferred resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an "inferred" or "indicated mineral resource" will ever be upgraded to a higher category.

Under Canadian rules, estimates of "inferred mineral resources" may not form the basis of feasibility studies, pre-feasibility studies or other economic studies, except in prescribed cases, such as in a preliminary economic assessment under certain circumstances. The SEC normally only permits issuers to report mineralization that does not constitute "reserves" as in-place tonnage and grade without reference to unit measures. Under U.S. standards, mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. U.S. investors are cautioned not to assume that any part or all of an indicated or inferred resource exists or is economically or legally mineable. Information concerning descriptions of mineralization and resources contained herein may not be comparable to information made public by U.S. companies subject to the reporting and disclosure requirements of the SEC.

Mineral Resources

Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources in this estimation are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource and it is uncertain if further exploration will result in upgrading them to an indicated or measured mineral resource category. The mineral resources in this press release were reported using CIM Standards.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
You think you know what’s in your data. But do you? Most organizations are now aware of the business intelligence represented by their data. Data science stands to take this to a level you never thought of – literally. The techniques of data science, when used with the capabilities of Big Data technologies, can make connections you had not yet imagined, helping you discover new insights and ask new questions of your data. In his session at @ThingsExpo, Sarbjit Sarkaria, data science team lead ...
To leverage Continuous Delivery, enterprises must consider impacts that span functional silos, as well as applications that touch older, slower moving components. Managing the many dependencies can cause slowdowns. See how to achieve continuous delivery in the enterprise.
WebRTC is bringing significant change to the communications landscape that will bridge the worlds of web and telephony, making the Internet the new standard for communications. Cloud9 took the road less traveled and used WebRTC to create a downloadable enterprise-grade communications platform that is changing the communication dynamic in the financial sector. In his session at @ThingsExpo, Leo Papadopoulos, CTO of Cloud9, discussed the importance of WebRTC and how it enables companies to focus...
"My role is working with customers, helping them go through this digital transformation. I spend a lot of time talking to banks, big industries, manufacturers working through how they are integrating and transforming their IT platforms and moving them forward," explained William Morrish, General Manager Product Sales at Interoute, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.
Up until last year, enterprises that were looking into cloud services usually undertook a long-term pilot with one of the large cloud providers, running test and dev workloads in the cloud. With cloud’s transition to mainstream adoption in 2015, and with enterprises migrating more and more workloads into the cloud and in between public and private environments, the single-provider approach must be revisited. In his session at 18th Cloud Expo, Yoav Mor, multi-cloud solution evangelist at Cloudy...
Aspose.Total for .NET is the most complete package of all file format APIs for .NET as offered by Aspose. It empowers developers to create, edit, render, print and convert between a wide range of popular document formats within any .NET, C#, ASP.NET and VB.NET applications. Aspose compiles all .NET APIs on a daily basis to ensure that it contains the most up to date versions of each of Aspose .NET APIs. If a new .NET API or a new version of existing APIs is released during the subscription peri...
Security, data privacy, reliability, and regulatory compliance are critical factors when evaluating whether to move business applications from in-house, client-hosted environments to a cloud platform. Quality assurance plays a vital role in ensuring that the appropriate level of risk assessment, verification, and validation takes place to ensure business continuity during the migration to a new cloud platform.
SYS-CON Events announced today that 910Telecom will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Housed in the classic Denver Gas & Electric Building, 910 15th St., 910Telecom is a carrier-neutral telecom hotel located in the heart of Denver. Adjacent to CenturyLink, AT&T, and Denver Main, 910Telecom offers connectivity to all major carriers, Internet service providers, Internet backbones and ...
Ovum, a leading technology analyst firm, has published an in-depth report, Ovum Decision Matrix: Selecting a DevOps Release Management Solution, 2016–17. The report focuses on the automation aspects of DevOps, Release Management and compares solutions from the leading vendors.
Continuous testing helps bridge the gap between developing quickly and maintaining high quality products. But to implement continuous testing, CTOs must take a strategic approach to building a testing infrastructure and toolset that empowers their team to move fast. Download our guide to laying the groundwork for a scalable continuous testing strategy.
Adding public cloud resources to an existing application can be a daunting process. The tools that you currently use to manage the software and hardware outside the cloud aren’t always the best tools to efficiently grow into the cloud. All of the major configuration management tools have cloud orchestration plugins that can be leveraged, but there are also cloud-native tools that can dramatically improve the efficiency of managing your application lifecycle. In his session at 18th Cloud Expo, ...
SYS-CON Events announced today that LeaseWeb USA, a cloud Infrastructure-as-a-Service (IaaS) provider, will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. LeaseWeb is one of the world's largest hosting brands. The company helps customers define, develop and deploy IT infrastructure tailored to their exact business needs, by combining various kinds cloud solutions.
StackIQ has announced the release of Stacki 3.2. Stacki is an easy-to-use Linux server provisioning tool. Stacki 3.2 delivers new capabilities that simplify the automation and integration of site-specific requirements. StackIQ is the commercial entity behind this open source bare metal provisioning tool. Since the release of Stacki in June of 2015, the Stacki core team has been focused on making the Community Edition meet the needs of members of the community, adding features and value, while ...
Qosmos has announced new milestones in the detection of encrypted traffic and in protocol signature coverage. Qosmos latest software can accurately classify traffic encrypted with SSL/TLS (e.g., Google, Facebook, WhatsApp), P2P traffic (e.g., BitTorrent, MuTorrent, Vuze), and Skype, while preserving the privacy of communication content. These new classification techniques mean that traffic optimization, policy enforcement, and user experience are largely unaffected by encryption. In respect wit...
For basic one-to-one voice or video calling solutions, WebRTC has proven to be a very powerful technology. Although WebRTC’s core functionality is to provide secure, real-time p2p media streaming, leveraging native platform features and server-side components brings up new communication capabilities for web and native mobile applications, allowing for advanced multi-user use cases such as video broadcasting, conferencing, and media recording.