Kirkland Lake Gold Announces Fiscal 2015 Operations Update, Mine Plan, and Three-Year Production Guidance

KIRKLAND LAKE, ONTARIO -- (Marketwired) -- 06/24/14 -- Kirkland Lake Gold Inc. (the "Company") (TSX:KGI) (AIM:KGI), an operating and exploration gold mining company, is pleased to announce an update on operations and production activities for the beginning of its fiscal year 2015 (began May 1, 2014) and a summary of its three-year mine production plan. The mine plan is based on a CAD$1,350 gold price. All figures in the release are stated in Canadian dollars.

OPERATIONS AND PRODUCTION UPDATE FOR FISCAL YEAR 2015

--  Year to date production (May 1 - June 20, or 51 days) totalled 52,987
    tons at a head grade of 0.42 ounces per ton ("opt"), or 14.4 grams per
    tonne ("gpt") to produce 21,426 ounces. 
    
--  Robust gold pour on June 19, 2014 of 4,862 fine ounces based on one
    week's production. 
    
--  A new mining horizon is being developed on the 5,400 foot level of the
    South Mine Complex ("SMC") that saw the first stope, 5417, come online
    in mid-May. This now gives the Company three mining horizons in the SMC.
    Proven and probable reserve blocks from this level up to the 5,300 foot
    level include 481,000 tons at 0.57 opt (19.5 gpt) containing 274,000
    ounces; while proven and probable reserves from this level down to 5,600
    foot level include 299,000 tons at 0.70 (24.0 gpt) opt containing
    209,000 ounces. The Company is planning to mine 5 stopes from the 5,400
    foot level in fiscal 2015. 
    
--  The Company is also developing the main SMC decline ramp as part of its
    sustaining capital budget in fiscal year 2015 in order to mine on the
    5,600 foot level and below where reserve grades are even higher and will
    be incorporated into the Company's fiscal 2016 mine plan. Please refer
    to the summary of reserves and resources table later in the press
    release.  
    
--  On May 12 following a 7 day shutdown the Company commissioned the new
    ball mill with ore, running the mill on a new 5 and 2 day schedule with
    a daily throughput averaging 1700 tons per day ("tpd") run of mine ore
    at better than 96% recovery. At its peak, the mill ran at 2,000 tpd. 
    
--  The mine is currently producing at a rate of 1,050 tpd of ore. The
    Company will take delivery of two new one boom, T1 D, electric hydraulic
    jumbos in the second half of the calendar year. Productivity
    improvements realized with this new equipment are expected to increase
    average daily ore tonnage to 1,150 - 1,250 tpd.  
    
--  The Company remains on track to achieve its fiscal 2015 guidance of
    140,000 to 155,000 ounces of gold produced. 
    
--  The Company currently has 5,400 tons of ore stockpiled in front of the
    mill. 

HIGHLIGHTS OF THE MINE PLAN AND THREE YEAR PRODUCTION GIUDANCE

--  Kirkland Lake Gold's reserve and resource base is as follows: 
    
    --  Proven and probable reserves: 2,784,000 tons at an average grade of
        0.50 opt (17.1 gpt) for 1,385,000 ounces 
    --  Measured and indicated resources: 4,152,000 tons at an average grade
        of 0.49 opt (16.8 gpt) for 2,055,000 ounces 
    --  Inferred resources of 2,092,000 tons at an average grade of 0.54 opt
        (18.5 gpt) for 1,133,000 ounces 
--  Total mine life of 14 years. 
    
--  Average gold production for the next three year totalling: 
    
    --  FY 2015: 140,000 - 155,000 ounces per year at an average grade of
        0.37 opt (12.7 gpt) 
    --  FY 2016: 150,000 - 170,000 ounces per year at an average grade of
        0.39 opt (13.4 gpt) 
    --  FY 2017: 160,000 - 180,000 ounces per year at an average grade of
        0.41 opt (14.0 gpt) 
--  Fiscal 2015 operating cost guidance of CAD$800 - $850 per ounce. 
    
--  Fiscal 2015 AISC of CAD$1,250 - $1,350 per ounce. 
    
--  Fiscal 2015 total sustaining, property, plant, and equipment
    expenditures of $58,000,000 
    
--  Fiscal 2015 revenue of approximately CAD$200,000,000; Cash flow from
    operations of between CAD$ 50,000,000 - $60,000,000 
    
--  Fiscal 2015 free cash flow generation of between CAD$15,000,000 -
    $20,000,000 
    
--  The current three-year mine plan calls for daily ore tonnages to remain
    steady at 1,150 - 1,250 tons per day. Ounces will increase due to higher
    grades coming from the SMC as the 5400, 5600 and 5900 levels are opened
    up and mined over the ensuing years. Therefore, operating costs per
    ounce are expected to continue to decrease in fiscal years 2016 and 2017
    with operating costs per ton remaining relatively flat. The resultant
    outcome will be to increase profitability and maximize free cash flow.
    Over the next three-years, Management's target is to lower AISC to
    CAD$1,190 - $1,250 per ounce. 

Summary of SMC Reserves and Resources by Level

----------------------------------------------------------------------------
                 Proven + Probable     Proven + Probable   Proven + Probable
LEVEL                       (TONS)               (GRADE)            (OUNCES)
----------------------------------------------------------------------------
5025                        89,000   0.44 opt (15.1 gpt)              39,000
----------------------------------------------------------------------------
5300                       620,000   0.47 opt (16.1 gpt)             290,000
----------------------------------------------------------------------------
5400                       481,000   0.57 opt (19.5 gpt)             274,000
----------------------------------------------------------------------------
5600                                           0.70 opt                     
                           299,000            (24.0 gpt)             209,000
----------------------------------------------------------------------------
5700 - 6600                                                                 
----------------------------------------------------------------------------

----------------------------------------------------------------------------
              Measured + Indicated Measured + Indicated Measured + Indicated
LEVEL                       (TONS)              (GRADE)             (OUNCES)
----------------------------------------------------------------------------
5025                        57,000  0.39 opt (13.3 gpt)               22,000
----------------------------------------------------------------------------
5300                       220,000  0.39 opt (13.3 gpt)               86,000
----------------------------------------------------------------------------
5400                       179,000  0.41 opt (14.0 gpt)               71,000
----------------------------------------------------------------------------
5600                       222,000  0.55 opt (18.8 gpt)              122,000
----------------------------------------------------------------------------
5700 - 6600                768,000  0.91 opt (31.1 gpt)              703,000
----------------------------------------------------------------------------

Mr. George Ogilvie, President and CEO commented, "The current fiscal year is off to a strong start with operations thriving under the new strategy of focusing on quality tons to significantly improve head grades. The year-to-date head grade is 0.42 opt (14.4 gpt) which represents a 30% increase over and above the 0.32 opt (10.9 gpt) achieved in fiscal 2013. This approach will continue over the next three years, where the plan calls for keeping daily ore tons constant in order to keep labour and other mining costs stagnant, with an increase in produced ounces coming from higher grades. Grades in the SMC get significantly richer at depth, where development of additional high-grade areas (incorporated in the fiscal years 2015, 2016 and 2017 mine plans) is underway. It's pleasing to see we are now mining on a third mining horizon, 5400L, in the SMC where reserve grades in the block up to the 5,300L are above 0.55 opt (18.8 gpt). Costs are trending down due by previously announced cost-saving measures while others recently implemented (e.g. change in mill schedule) will start to be realized from June. In addition we should see further productivity improvements in the second half of the calendar year with the arrival of two new one boom, T1 D, electric hydraulic jumbos."

"The Company expects to be free cash flow positive at current gold prices in the next 2 - 3 months. The ounces forecast in fiscal years 2016 and 2017 do not take into account any mining from the near surface mineralization. Our recent flow through financing will allow us to accelerate the exploration drilling of the near surface mineralization; which includes a resource expansion and in-fill drilling to define a reserve. In house a preliminary economic assessment is being undertaken to help define the robustness of the near surface mineralization economics. The study is expected to be complete by the end of the calendar year," concluded Mr. Ogilvie.

About the Company

Kirkland Lake Gold's corporate goal is to create a self-sustaining and long-lived intermediate gold mining company based in the historic Kirkland Lake Gold Camp. The Company plans to do this by mining to the reserve grade, generating profits and free cash flow for the shareholders. The Company will also look to take advantage of its increased infrastructure capacity in the appropriate gold price environment. At the same time, the Company is committed to maintaining a significant exploration program aimed at developing and maintaining a property wide reserve and resource base sufficient to sustain a mine life of more than ten years. Over the last several years the Company has invested significant capital to improve the infrastructure of the business including upgrading the production hoist, skips, mill, underground mobile equipment and capital development. From initial discovery to present day there have been over 24 million ounces of gold mined from the Kirkland Lake camp while the current reserve and resource provides for more than 10 years of mining with significant exploration upside.

The reserve estimates and technical disclosure have been reviewed, verified (including sampling, analytical and test data) and compiled by the Company's geological staff (which includes a 'qualified person', Stewart Carmichael P.Geo., the Company's Chief Exploration Geologist, for the purpose of National Instrument 43-101, Standards of Disclosure for Mineral Projects, of the Canadian Securities Administrators). Mr. Carmichael also supervised the preparation of the information that forms the basis of the technical disclosure in this release.

Neither the Toronto Stock Exchange nor the AIM Market of the London Stock Exchange has reviewed and neither accepts responsibility for the adequacy or accuracy of this news release.

Cautionary Note Regarding Forward Looking Statements

This Press Release contains statements which constitute "forward-looking statements", including statements regarding the plans, intentions, beliefs and current expectations of the Company with respect to the future business activities and operating performance of the Company. The words "may", "would", "could", "should", "will", "intend", "plan", "anticipate", "believe", "estimate", "expect" and similar expressions, as they relate to the Company, are intended to identify such forward-looking statements. Forward-looking statements used in this Press Release include, but may not be limited to, statements regarding the Company's production capacity and its exploration program. Investors are cautioned that forward-looking statements are based on the opinions, assumptions and estimates of management considered reasonable at the date the statements are made such as, without limitation, opinion, assumptions and estimates of management regarding the Company's business, its ability to increase its production capacity and decrease its production cost. Such opinions, assumptions and estimates, are inherently subject to a variety of risks and uncertainties and other known and unknown factors that could cause actual events or results to differ materially from those projected in the forward-looking statements.

These factors include the Company's expectations in connection with the projects and exploration programs being met, the impact of general business and economic conditions, global liquidity and credit availability on the timing of cash flows and the values of assets and liabilities based on projected future conditions, fluctuating gold prices, currency exchange rates (such as the Canadian dollar versus the United States Dollar), possible variations in ore grade or recovery rates, changes in accounting policies, changes in the Company's corporate mineral resources, changes in project parameters as plans continue to be refined, changes in project development, construction, production and commissioning time frames, risks related to joint venture operations, the possibility of project cost overruns or unanticipated costs and expenses, higher prices for fuel, power, labour and other consumables contributing to higher costs and general risks of the mining industry, failure of plant, equipment or processes to operate as anticipated, unexpected changes in mine life, seasonality and unanticipated weather changes, costs and timing of the development of new deposits, success of exploration activities, permitting time lines, government regulation of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims, and limitations on insurance, as well as those risk factors discussed or referred to in the Company's annual Management's Discussion and Analysis and Annual Information Form for the year ended April 30, 2013 and the Company's Management's Discussion and Analysis for the interim period ended January 31, 2014 filed with the securities regulatory authorities in certain provinces of Canada and available at www.sedar.com. Should one or more of these risks or uncertainties materialize, or should assumptions underlying the forward-looking statements prove incorrect, actual results may vary materially from those described herein as intended, planned, anticipated, believed, estimated or expected. Although the Company has attempted to identify important risks, uncertainties and factors which could cause actual results to differ materially, there may be others that cause results not to be as anticipated, estimated or intended. The Company does not intend, and does not assume any obligation, to update these forward-looking statements except as otherwise required by applicable law.

Glossary of Terms

National Instrument 43-101 Definitions of Resources and Reserves

The Reserve and Resource estimation classifications as prescribed in National Instrument 43-101 are given here for clarity.

Mineral Resource

Mineral Resources are sub-divided into 3 categories depending on the geological confidence. The highest level with the most confidence is the `Measured' category. The next level of confidence is the `Indicated' category and the lowest level, or the resource with the least confidence, is the `Inferred' category.

Inferred Mineral Resource

An `Inferred Mineral Resource' is that part of a Mineral Resource for which quantity and grade or quality can be estimated on the basis of geological evidence and limited sampling and reasonably assumed, but not verified, geological and grade continuity. The estimate is based on limited information and sampling, gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes.

Indicated Mineral Resource

An `Indicated Mineral Resource' is that part of a Mineral Resource for which quantity, grade or quality, densities, shape and physical characteristics, can be estimated with a level of confidence sufficient to allow the appropriate application of technical and economic parameters, to support mine planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough for geological and grade continuity to be reasonably assumed.

Measured Mineral Resource

A `Measured Mineral Resource' is that part of a Mineral resource for which quantity, grade or quality, densities, shape and physical characteristics are so well established that they can be estimated with confidence sufficient to allow the appropriate application of technical and economic parameters, to support production planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough to confirm both geological and grade continuity.

Mineral Reserve

Mineral Reserves are sub-divided into 2 categories. The highest level of Reserves or the level with the most confidence is the `Proven' category and the lower level of confidence of the Reserves is the `Probable' category. Reserves are distinguished from resources as all of the technical and economic parameters have been applied and the estimated grade and tonnage of the resources should closely approximate the actual results of mining. The guidelines state "Minerals Reserves are inclusive of the diluting material that will be mined in conjunction with the Mineral Reserve and delivered to the treatment plant or equivalent facility." The guidelines also state that, "The term `Mineral Reserve' need not necessarily signify that extraction facilities are in place or operative or that all government approvals have been received. It does signify that there are reasonable expectations of such approvals."

Probable Mineral Reserve

A `Probable Mineral Reserve' is the economically mineable part of an Indicated and in some circumstances a Measured Mineral Resource demonstrated by a least a Preliminary Feasibility Study. This study must include adequate information on mining, processing, metallurgical, economic, and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified.

Proven Mineral Reserve

A `Proven Mineral Reserve' is the economically mineable part of a Measured Mineral Resource demonstrated by at least a Preliminary Feasibility Study. This study must include adequate information on mining, processing, metallurgical, economic, and other relevant factors that demonstrate, at the time of reporting, that economic extraction is justified.

A more detailed list of technical terms can be found at http://klgold.com/cmsAssets/docs/pdfs/2013/2013%20Annual%20Information%20Form.pdf

Contacts:
Kirkland Lake Gold Inc.
George Ogilvie, P.Eng
CEO
+1 709 532 5716
+1 705 568 6444 (FAX)
[email protected]

Kirkland Lake Gold Inc.
Lindsay Dunlop
Director of Investor Relations
+1 416-840-7884
+1 705 568 6444 (FAX)
[email protected]
www.klgold.com

NOMAD: Panmure Gordon (UK) Limited
Callum Stewart / Adam James
+44 (0) 20 7886 2500

Blytheweigh
Tim Blythe/Halimah Hussain/Camilla Horsfall
+44 (0) 20 7138 3204

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Docker containers have brought great opportunities to shorten the deployment process through continuous integration and the delivery of applications and microservices. This applies equally to enterprise data centers as well as the cloud. In his session at 20th Cloud Expo, Jari Kolehmainen, founder and CTO of Kontena, discussed solutions and benefits of a deeply integrated deployment pipeline using technologies such as container management platforms, Docker containers, and the drone.io Cl tool. H...
As more and more companies are making the shift from on-premises to public cloud, the standard approach to DevOps is evolving. From encryption, compliance and regulations like GDPR, security in the cloud has become a hot topic. Many DevOps-focused companies have hired dedicated staff to fulfill these requirements, often creating further siloes, complexity and cost. This session aims to highlight existing DevOps cultural approaches, tooling and how security can be wrapped in every facet of the bu...
In his session at @ThingsExpo, Dr. Robert Cohen, an economist and senior fellow at the Economic Strategy Institute, presented the findings of a series of six detailed case studies of how large corporations are implementing IoT. The session explored how IoT has improved their economic performance, had major impacts on business models and resulted in impressive ROIs. The companies covered span manufacturing and services firms. He also explored servicification, how manufacturing firms shift from se...
Connecting to major cloud service providers is becoming central to doing business. But your cloud provider’s performance is only as good as your connectivity solution. Massive Networks will place you in the driver's seat by exposing how you can extend your LAN from any location to include any cloud platform through an advanced high-performance connection that is secure and dedicated to your business-critical data. In his session at 21st Cloud Expo, Paul Mako, CEO & CIO of Massive Networks, wil...
You know you need the cloud, but you’re hesitant to simply dump everything at Amazon since you know that not all workloads are suitable for cloud. You know that you want the kind of ease of use and scalability that you get with public cloud, but your applications are architected in a way that makes the public cloud a non-starter. You’re looking at private cloud solutions based on hyperconverged infrastructure, but you’re concerned with the limits inherent in those technologies.
The question before companies today is not whether to become intelligent, it’s a question of how and how fast. The key is to adopt and deploy an intelligent application strategy while simultaneously preparing to scale that intelligence. In her session at 21st Cloud Expo, Sangeeta Chakraborty, Chief Customer Officer at Ayasdi, will provide a tactical framework to become a truly intelligent enterprise, including how to identify the right applications for AI, how to build a Center of Excellence to ...
SYS-CON Events announced today that Massive Networks will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Massive Networks mission is simple. To help your business operate seamlessly with fast, reliable, and secure internet and network solutions. Improve your customer's experience with outstanding connections to your cloud.
DevOps is under attack because developers don’t want to mess with infrastructure. They will happily own their code into production, but want to use platforms instead of raw automation. That’s changing the landscape that we understand as DevOps with both architecture concepts (CloudNative) and process redefinition (SRE). Rob Hirschfeld’s recent work in Kubernetes operations has led to the conclusion that containers and related platforms have changed the way we should be thinking about DevOps and...
SYS-CON Events announced today that CAST Software will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CAST was founded more than 25 years ago to make the invisible visible. Built around the idea that even the best analytics on the market still leave blind spots for technical teams looking to deliver better software and prevent outages, CAST provides the software intelligence that matter ...
Given the popularity of the containers, further investment in the telco/cable industry is needed to transition existing VM-based solutions to containerized cloud native deployments. The networking architecture of the solution isolates the network traffic into different network planes (e.g., management, control, and media). This naturally makes support for multiple interfaces in container orchestration engines an indispensable requirement.
Everything run by electricity will eventually be connected to the Internet. Get ahead of the Internet of Things revolution and join Akvelon expert and IoT industry leader, Sergey Grebnov, in his session at @ThingsExpo, for an educational dive into the world of managing your home, workplace and all the devices they contain with the power of machine-based AI and intelligent Bot services for a completely streamlined experience.
Because IoT devices are deployed in mission-critical environments more than ever before, it’s increasingly imperative they be truly smart. IoT sensors simply stockpiling data isn’t useful. IoT must be artificially and naturally intelligent in order to provide more value In his session at @ThingsExpo, John Crupi, Vice President and Engineering System Architect at Greenwave Systems, will discuss how IoT artificial intelligence (AI) can be carried out via edge analytics and machine learning techn...
SYS-CON Events announced today that Datera, that offers a radically new data management architecture, has been named "Exhibitor" of SYS-CON's 21st International Cloud Expo ®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Datera is transforming the traditional datacenter model through modern cloud simplicity. The technology industry is at another major inflection point. The rise of mobile, the Internet of Things, data storage and Big...
As businesses adopt functionalities in cloud computing, it’s imperative that IT operations consistently ensure cloud systems work correctly – all of the time, and to their best capabilities. In his session at @BigDataExpo, Bernd Harzog, CEO and founder of OpsDataStore, presented an industry answer to the common question, “Are you running IT operations as efficiently and as cost effectively as you need to?” He then expounded on the industry issues he frequently came up against as an analyst, and ...
In his session at @ThingsExpo, Arvind Radhakrishnen discussed how IoT offers new business models in banking and financial services organizations with the capability to revolutionize products, payments, channels, business processes and asset management built on strong architectural foundation. The following topics were covered: How IoT stands to impact various business parameters including customer experience, cost and risk management within BFS organizations.