Trevali Provides Caribou Zinc-Lead-Silver Mine Construction Update

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 06/26/14 -- Trevali Mining Corporation ("Trevali" or the "Company") (TSX:TV)(OTCQX:TREVF)(LMA:TV)(FRANKFURT:4TI) provides an update on construction activities at its wholly-owned Caribou mine and mill complex (Figure 1) located in the Bathurst Mining Camp of northeastern New Brunswick, Canada.

Following the successful closing of recently announced $52.5-million corporate debt facility for the Caribou mine operations (see NR TV-NR-14-10 for details) the Company has commenced both surface and underground construction and rehabilitation activities to facilitate Mine and Mill commissioning in the first half of 2015. Due to the highly skilled and available workforce, contractors and service providers, the Company is fortunate to be able to source the majority of its required re-start and future production services locally.

Trevali also continues to liaise closely with local Mi'kmaq First Nations ensuring that the Impact Benefits Agreement signed between the two parties continues to benefit the First Nations involved. Through the planned re-launch of the Underground Miner Training Program and the addition of a Surface and Mill Operator Training Program for First Nations students, the Company looks forward to continuing to offer opportunities to the Mi'kmaq of New Brunswick and further strengthening its relationship with the First Nation people of New Brunswick.

A summary of key current activities is provided below:

SURFACE WORKS


--  The Main Mine Office annex is fully refurbished and now staffed by
    Trevali's development team.  
--  Site communications will be significantly enhanced by a new fibre-optic
    cable which is scheduled to be commissioned in Q3/Q4 of 2014. 
--  A warehouse inventory is nearing completion. 
--  The Mine Dry Facility and Change House, necessary for Underground ("UG")
    activities, is nearing completion. 
--  Site power repairs are predominantly complete, power-line underbrush
    clearing is in progress and the various transformers have been serviced
    and repaired where necessary. 
--  Improved site water management requirements have been identified and
    tendering is in progress.

To view Figure 1 please click the following link: http://media3.marketwire.com/docs/TrevaliFig1.pdf

MILL


--  The new 3,000-tonne-per-day Semi-Autogenous-Grinding (SAG) Mill was
    delivered in late 2013 and the remaining associated componentry during
    the first quarter of 2014. The SAG Mill tender has been completed and
    the Company is currently finalizing installation timing (Figure 2). 
--  Key Mill component spare part purchasing has commenced and is
    progressing well. 
--  The Company is currently updating its Mill hygiene policy following
    which Mill clean-up activities will commence. 
--  Copper metallurgical testwork optimization is ongoing and detailed Cu-
    circuit design is in progress. 
--  Processes water circuit has been repaired and upgraded.

To view Figure 2 please click the following link: http://media3.marketwire.com/docs/TrevaliFig2.pdf

UNDERGROUND


--  All underground equipment and services were pulled to surface and
    securely warehoused prior to mine shut-down in 2008. 
--  Alex Macintyre & Associates Ltd. have been awarded the UG development
    and mining contract following a competitive tender process in which
    seven qualified UG mining contract companies submitted bids. Trevali has
    a strong working relationship with Alex Macintyre who developed the
    Company's Halfmile trial mining operation on time and budget in 2011/12.
--  A general inspection of the primary ramp and Level 2 indicates that
    ground conditions are good and ground support is predominantly intact -
    minor rehabilitation will be required where water levels seasonally
    fluctuated. 
--  Rehabilitation of the surface service raise and secondary egress
    rehabilitation is in progress, following which larger scale UG
    activities can commence. 
--  Ventilation Fan and UG Heating units have been inspected, minor repairs
    will occur in due course. 
--  Mine dewatering is progressing well - UG workings are approximately 40
    percent dewatered to Level 2 where the main mine dewatering sumps are
    located. Primary pumps will be installed in the coming weeks following
    ramp inspection and rehabilitation where required. 
--  A Paste Backfill Study is advancing, which contingent on positive
    results has the potential to significantly increase the life-of-mine, in
    addition to decreasing mine dilution (boosts head-grade) and lower
    operating costs.

STAFFING


--  Phase 1 staffing is ongoing and the Company currently directly and
    indirectly employs 57 people from the Bathurst region. During peak
    construction, commencing in the third quarter of 2014 and ongoing to
    commissioning in 2015, it is estimated that Trevali New Brunswick will
    employ approximately 300-320 people and then approximately 250 people
    during future steady-state production from mid-2015 onwards.

2014 AGM RESULTS

Trevali also reports on results of voting from its 2014 Annual and Special Meeting of Shareholders held June 24, 2014 in Vancouver, BC.

Each of the nominees listed in Trevali's Management Information Circular dated May 15, 2014 was elected as a director of the Company. Shareholders voted in favour of all items of business before the meeting. Detailed results of the election of director nominees are shown in the attached table.


Director            Number of votes in favour  Percentage of votes in favour
----------------------------------------------------------------------------
Mark Cruise                       110,827,486                         99.95%
Anton Drescher                    105,310,985                         94.98%
Christopher Eskdale                98,313,890                         88.67%
Catherine Gignac                  110,694,586                         99.83%
Michael Hoffman                   105,160,185                         94.84%
David Huberman                    110,692,786                         99.83%
Peter Meredith                    105,190,190                         94.87%
Valentin Paniagua                 110,717,786                         99.85%

Shareholders ratified and approved the Company's Appointment of Auditor and the Approval of Stock Option and Stock Bonus Plan and Unallocated Options.

The Company would also like to thank Dr. Paul Klipfel, who did not stand for re-election as director, for his years of service on Trevali's Board and wishes him all the best in his new endeavours.

Detailed voting results for the 2014 Annual and Special Meeting of Shareholders are available on SEDAR.

Qualified Person and Quality Control/Quality Assurance

EurGeol Dr. Mark D. Cruise, Trevali's President and CEO and M. Dayle Rusk, P.Geo, Trevali's Director, Geology, are qualified persons as defined by NI 43-101, have supervised the preparation of the scientific and technical information that forms the basis for this news release. Dr. Cruise is not independent of the Company, as he is an officer, director and shareholder. Ms. Rusk is not independent of the Company as she is an officer and shareholder. On-site personnel at the project rigorously collect and track samples which are then security sealed and shipped to Activation Laboratories preparation facility in Fredericton, New Brunswick, then to Ancaster, Ontario for assay. Activation Laboratories quality system complies with the requirements for the International Standards ISO 9001:2000 and ISO 17025: 1999. Analytical accuracy and precision are monitored by the analysis of reagent blanks, reference material and replicate samples. Quality control is further assured by the use of international and in-house standards. Blind certified reference material is inserted at regular intervals into the sample sequence by Trevali personnel in order to independently assess analytical accuracy. Finally, representative blind duplicate samples are routinely forwarded to an ISO compliant third party laboratory for additional quality control.

ABOUT TREVALI MINING CORPORATION

Trevali is a zinc-focused, base metals mining company with one producing operation currently in Peru and an advanced-stage mine under development in Canada.

In Peru, the Company is actively producing zinc and lead-silver concentrates from its Santander mine and 2,000-tonne-per-day metallurgical plant.

In Canada, Trevali owns the Caribou mine and mill, Halfmile mine and Stratmat deposit all located in the Bathurst Mining Camp of northern New Brunswick. The Company is currently advancing its 3,000-tonne-per-day Caribou Mill Complex and mine towards planned 2015 production.

All of the Company's deposits remain open for expansion.

The common shares of Trevali are listed on the TSX (symbol TV), the OTCQX (symbol TREVF) and on the Lima Stock Exchange (symbol TV). For further details on Trevali, readers are referred to the Company's web site (www.trevali.com) and to Canadian regulatory filings on SEDAR at www.sedar.com.

On Behalf of the Board of Directors of

TREVALI MINING CORPORATION

Mark D. Cruise, President

This news release contains "forward-looking statements" within the meaning of the United States private securities litigation reform act of 1995 and "forward-looking information" within the meaning of applicable Canadian securities legislation. Statements containing forward-looking information express, as at the date of this news release, the Company's plans, estimates, forecasts, projections, expectations, or beliefs as to future events or results and the company does not intend, and does not assume any obligation to, update such statements containing the forward-looking information. Such forward-looking statements and information include, but are not limited to statements as to: the accuracy of estimated mineral reserves and resources, anticipated results of future exploration, and forecast future metal prices, anticipated results of future electrical sales and expectations that environmental, permitting, legal, title, taxation, socio-economic, political, marketing or other issues will not materially affect estimates of mineral reserves. These statements reflect the Company's current views with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by the Company, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies.

These statements reflect the Company's current views with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by the company, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies. Many factors, both known and unknown, could cause actual results, performance or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements contained in this news release and the company has made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: fluctuations in spot and forward markets for silver, zinc, base metals and certain other commodities (such as natural gas, fuel oil and electricity); fluctuations in currency markets (such as the Peruvian sol versus the U.S. dollar); risks related to the technological and operational nature of the Company's business; changes in national and local government, legislation, taxation, controls or regulations and political or economic developments in Canada, the United States, Peru or other countries where the Company may carry on business in the future; risks and hazards associated with the business of mineral exploration, development and mining (including environmental hazards, industrial accidents, unusual or unexpected geological or structural formations, pressures, cave-ins and flooding);

risks relating to the credit worthiness or financial condition of suppliers, refiners and other parties with whom the Company does business; inadequate insurance, or inability to obtain insurance, to cover these risks and hazards; employee relations; relationships with and claims by local communities and indigenous populations; availability and increasing costs associated with mining inputs and labour; the speculative nature of mineral exploration and development, including the risks of obtaining necessary licenses and permits and the presence of laws and regulations that may impose restrictions on mining,; diminishing quantities or grades of mineral reserves as properties are mined; global financial conditions; business opportunities that may be presented to, or pursued by, the Company; the Company's ability to complete and successfully integrate acquisitions and to mitigate other business combination risks; challenges to, or difficulty in maintaining, the Company's title to properties and continued ownership thereof; the actual results of current exploration activities, conclusions of economic evaluations, and changes in project parameters to deal with unanticipated economic or other factors; increased competition in the mining industry for properties, equipment, qualified personnel, and their costs. Investors are cautioned against attributing undue certainty or reliance on forward-looking statements. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated, described or intended. The Company does not intend, and does not assume any obligation, to update these forward-looking statements or information to reflect changes in assumptions or changes in circumstances or any other events affecting such statements or information, other than as required by applicable law.

Trevali's production plans at Caribou-Halfmile-Stratmat and Santander are based only on Indicated and Inferred Mineral Resources and not Mineral Reserves and do not have demonstrated economic viability. Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is therefore no certainty that the conclusions of the production plans and Preliminary Economic Assessment (PEA) will be realized. Additionally where Trevali discusses exploration/expansion potential, any potential quantity and grade is conceptual in nature and there has been insufficient exploration to define a mineral resource and it is uncertain if further exploration will result in the target being delineated as a mineral resource.

We advise US investors that while the terms "measured resources", "indicated resources" and "inferred resources" are recognized and required by Canadian regulations, the US Securities and Exchange Commission does not recognize these terms. US investors are cautioned not to assume that any part or all of the material in these categories will ever be converted into reserves.

This news release does not constitute an offer to sell or a solicitation of an offer to buy any of the securities in the United States. The securities described herein have not been and will not be registered under the United States Securities Act of 1933, as amended, or the securities laws of any state and may not be offered or sold within the United States, absent such registration or an applicable exemption from such registration requirements.

The TSX has not approved or disapproved of the contents of this news release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
IoT is fundamentally transforming the auto industry, turning the vehicle into a hub for connected services, including safety, infotainment and usage-based insurance. Auto manufacturers – and businesses across all verticals – have built an entire ecosystem around the Connected Car, creating new customer touch points and revenue streams. In his session at @ThingsExpo, Macario Namie, Head of IoT Strategy at Cisco Jasper, will share real-world examples of how IoT transforms the car from a static p...
While DevOps promises a better and tighter integration among an organization’s development and operation teams and transforms an application life cycle into a continual deployment, Chef and Azure together provides a speedy, cost-effective and highly scalable vehicle for realizing the business values of this transformation. In his session at @DevOpsSummit at 19th Cloud Expo, Yung Chou, a Technology Evangelist at Microsoft, will present a unique opportunity to witness how Chef and Azure work tog...
Internet of @ThingsExpo, taking place November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with the 19th International Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world and ThingsExpo Silicon Valley Call for Papers is now open.
The Transparent Cloud-computing Consortium (abbreviation: T-Cloud Consortium) will conduct research activities into changes in the computing model as a result of collaboration between "device" and "cloud" and the creation of new value and markets through organic data processing High speed and high quality networks, and dramatic improvements in computer processing capabilities, have greatly changed the nature of applications and made the storing and processing of data on the network commonplace.
Almost two-thirds of companies either have or soon will have IoT as the backbone of their business in 2016. However, IoT is far more complex than most firms expected. How can you not get trapped in the pitfalls? In his session at @ThingsExpo, Tony Shan, a renowned visionary and thought leader, will introduce a holistic method of IoTification, which is the process of IoTifying the existing technology and business models to adopt and leverage IoT. He will drill down to the components in this fra...
We’ve been doing it for years, decades for some. How many websites have you created accounts on? Your bank, your credit card companies, social media sites, hotels and travel sites, online shopping sites, and that’s just the start. We do it often without even thinking about it, quickly entering our personal information, our data, in a plethora of systems. Sometimes we’re not even aware of the information we are providing. It could be very personal information (think of the security questions you ...
SYS-CON Events announced today that ReadyTalk, a leading provider of online conferencing and webinar services, has been named Vendor Presentation Sponsor at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. ReadyTalk delivers audio and web conferencing services that inspire collaboration and enable the Future of Work for today’s increasingly digital and mobile workforce. By combining intuitive, innovative tec...
I'm a lonely sensor. I spend all day telling the world how I'm feeling, but none of the other sensors seem to care. I want to be connected. I want to build relationships with other sensors to be more useful for my human. I want my human to understand that when my friends next door are too hot for a while, I'll soon be flaming. And when all my friends go outside without me, I may be left behind. Don't just log my data; use the relationship graph. In his session at @ThingsExpo, Ryan Boyd, Engi...
IoT offers a value of almost $4 trillion to the manufacturing industry through platforms that can improve margins, optimize operations & drive high performance work teams. By using IoT technologies as a foundation, manufacturing customers are integrating worker safety with manufacturing systems, driving deep collaboration and utilizing analytics to exponentially increased per-unit margins. However, as Benoit Lheureux, the VP for Research at Gartner points out, “IoT project implementers often ...
SYS-CON Events announced today that Pulzze Systems will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Pulzze Systems, Inc. provides infrastructure products for the Internet of Things to enable any connected device and system to carry out matched operations without programming. For more information, visit http://www.pulzzesystems.com.
There is growing need for data-driven applications and the need for digital platforms to build these apps. In his session at 19th Cloud Expo, Muddu Sudhakar, VP and GM of Security & IoT at Splunk, will cover different PaaS solutions and Big Data platforms that are available to build applications. In addition, AI and machine learning are creating new requirements that developers need in the building of next-gen apps. The next-generation digital platforms have some of the past platform needs a...
If you’re responsible for an application that depends on the data or functionality of various IoT endpoints – either sensors or devices – your brand reputation depends on the security, reliability, and compliance of its many integrated parts. If your application fails to deliver the expected business results, your customers and partners won't care if that failure stems from the code you developed or from a component that you integrated. What can you do to ensure that the endpoints work as expect...
As ridesharing competitors and enhanced services increase, notable changes are occurring in the transportation model. Despite the cost-effective means and flexibility of ridesharing, both drivers and users will need to be aware of the connected environment and how it will impact the ridesharing experience. In his session at @ThingsExpo, Timothy Evavold, Executive Director Automotive at Covisint, will discuss key challenges and solutions to powering a ride sharing and/or multimodal model in the a...
Is your aging software platform suffering from technical debt while the market changes and demands new solutions at a faster clip? It’s a bold move, but you might consider walking away from your core platform and starting fresh. ReadyTalk did exactly that. In his General Session at 19th Cloud Expo, Michael Chambliss, Head of Engineering at ReadyTalk, will discuss why and how ReadyTalk diverted from healthy revenue and over a decade of audio conferencing product development to start an innovati...
WebRTC adoption has generated a wave of creative uses of communications and collaboration through websites, sales apps, customer care and business applications. As WebRTC has become more mainstream it has evolved to use cases beyond the original peer-to-peer case, which has led to a repeating requirement for interoperability with existing infrastructures. In his session at @ThingsExpo, Graham Holt, Executive Vice President of Daitan Group, will cover implementation examples that have enabled ea...