Trevali Provides Caribou Zinc-Lead-Silver Mine Construction Update

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 06/26/14 -- Trevali Mining Corporation ("Trevali" or the "Company") (TSX: TV)(OTCQX: TREVF)(LMA: TV)(FRANKFURT: 4TI) provides an update on construction activities at its wholly-owned Caribou mine and mill complex (Figure 1) located in the Bathurst Mining Camp of northeastern New Brunswick, Canada.

Following the successful closing of recently announced $52.5-million corporate debt facility for the Caribou mine operations (see NR TV-NR-14-10 for details) the Company has commenced both surface and underground construction and rehabilitation activities to facilitate Mine and Mill commissioning in the first half of 2015. Due to the highly skilled and available workforce, contractors and service providers, the Company is fortunate to be able to source the majority of its required re-start and future production services locally.

Trevali also continues to liaise closely with local Mi'kmaq First Nations ensuring that the Impact Benefits Agreement signed between the two parties continues to benefit the First Nations involved. Through the planned re-launch of the Underground Miner Training Program and the addition of a Surface and Mill Operator Training Program for First Nations students, the Company looks forward to continuing to offer opportunities to the Mi'kmaq of New Brunswick and further strengthening its relationship with the First Nation people of New Brunswick.

A summary of key current activities is provided below:

SURFACE WORKS


--  The Main Mine Office annex is fully refurbished and now staffed by
    Trevali's development team.
--  Site communications will be significantly enhanced by a new fibre-optic
    cable which is scheduled to be commissioned in Q3/Q4 of 2014.
--  A warehouse inventory is nearing completion.
--  The Mine Dry Facility and Change House, necessary for Underground ("UG")
    activities, is nearing completion.
--  Site power repairs are predominantly complete, power-line underbrush
    clearing is in progress and the various transformers have been serviced
    and repaired where necessary.
--  Improved site water management requirements have been identified and
    tendering is in progress.

To view Figure 1 please click the following link: http://media3.marketwire.com/docs/TrevaliFig1.pdf

MILL


--  The new 3,000-tonne-per-day Semi-Autogenous-Grinding (SAG) Mill was
    delivered in late 2013 and the remaining associated componentry during
    the first quarter of 2014. The SAG Mill tender has been completed and
    the Company is currently finalizing installation timing (Figure 2).
--  Key Mill component spare part purchasing has commenced and is
    progressing well.
--  The Company is currently updating its Mill hygiene policy following
    which Mill clean-up activities will commence.
--  Copper metallurgical testwork optimization is ongoing and detailed Cu-
    circuit design is in progress.
--  Processes water circuit has been repaired and upgraded.

To view Figure 2 please click the following link: http://media3.marketwire.com/docs/TrevaliFig2.pdf

UNDERGROUND


--  All underground equipment and services were pulled to surface and
    securely warehoused prior to mine shut-down in 2008.
--  Alex Macintyre & Associates Ltd. have been awarded the UG development
    and mining contract following a competitive tender process in which
    seven qualified UG mining contract companies submitted bids. Trevali has
    a strong working relationship with Alex Macintyre who developed the
    Company's Halfmile trial mining operation on time and budget in 2011/12.
--  A general inspection of the primary ramp and Level 2 indicates that
    ground conditions are good and ground support is predominantly intact -
    minor rehabilitation will be required where water levels seasonally
    fluctuated.
--  Rehabilitation of the surface service raise and secondary egress
    rehabilitation is in progress, following which larger scale UG
    activities can commence.
--  Ventilation Fan and UG Heating units have been inspected, minor repairs
    will occur in due course.
--  Mine dewatering is progressing well - UG workings are approximately 40
    percent dewatered to Level 2 where the main mine dewatering sumps are
    located. Primary pumps will be installed in the coming weeks following
    ramp inspection and rehabilitation where required.
--  A Paste Backfill Study is advancing, which contingent on positive
    results has the potential to significantly increase the life-of-mine, in
    addition to decreasing mine dilution (boosts head-grade) and lower
    operating costs.

STAFFING


--  Phase 1 staffing is ongoing and the Company currently directly and
    indirectly employs 57 people from the Bathurst region. During peak
    construction, commencing in the third quarter of 2014 and ongoing to
    commissioning in 2015, it is estimated that Trevali New Brunswick will
    employ approximately 300-320 people and then approximately 250 people
    during future steady-state production from mid-2015 onwards.

2014 AGM RESULTS

Trevali also reports on results of voting from its 2014 Annual and Special Meeting of Shareholders held June 24, 2014 in Vancouver, BC.

Each of the nominees listed in Trevali's Management Information Circular dated May 15, 2014 was elected as a director of the Company. Shareholders voted in favour of all items of business before the meeting. Detailed results of the election of director nominees are shown in the attached table.


Director            Number of votes in favour  Percentage of votes in favour
----------------------------------------------------------------------------
Mark Cruise                       110,827,486                         99.95%
Anton Drescher                    105,310,985                         94.98%
Christopher Eskdale                98,313,890                         88.67%
Catherine Gignac                  110,694,586                         99.83%
Michael Hoffman                   105,160,185                         94.84%
David Huberman                    110,692,786                         99.83%
Peter Meredith                    105,190,190                         94.87%
Valentin Paniagua                 110,717,786                         99.85%

Shareholders ratified and approved the Company's Appointment of Auditor and the Approval of Stock Option and Stock Bonus Plan and Unallocated Options.

The Company would also like to thank Dr. Paul Klipfel, who did not stand for re-election as director, for his years of service on Trevali's Board and wishes him all the best in his new endeavours.

Detailed voting results for the 2014 Annual and Special Meeting of Shareholders are available on SEDAR.

Qualified Person and Quality Control/Quality Assurance

EurGeol Dr. Mark D. Cruise, Trevali's President and CEO and M. Dayle Rusk, P.Geo, Trevali's Director, Geology, are qualified persons as defined by NI 43-101, have supervised the preparation of the scientific and technical information that forms the basis for this news release. Dr. Cruise is not independent of the Company, as he is an officer, director and shareholder. Ms. Rusk is not independent of the Company as she is an officer and shareholder. On-site personnel at the project rigorously collect and track samples which are then security sealed and shipped to Activation Laboratories preparation facility in Fredericton, New Brunswick, then to Ancaster, Ontario for assay. Activation Laboratories quality system complies with the requirements for the International Standards ISO 9001:2000 and ISO 17025: 1999. Analytical accuracy and precision are monitored by the analysis of reagent blanks, reference material and replicate samples. Quality control is further assured by the use of international and in-house standards. Blind certified reference material is inserted at regular intervals into the sample sequence by Trevali personnel in order to independently assess analytical accuracy. Finally, representative blind duplicate samples are routinely forwarded to an ISO compliant third party laboratory for additional quality control.

ABOUT TREVALI MINING CORPORATION

Trevali is a zinc-focused, base metals mining company with one producing operation currently in Peru and an advanced-stage mine under development in Canada.

In Peru, the Company is actively producing zinc and lead-silver concentrates from its Santander mine and 2,000-tonne-per-day metallurgical plant.

In Canada, Trevali owns the Caribou mine and mill, Halfmile mine and Stratmat deposit all located in the Bathurst Mining Camp of northern New Brunswick. The Company is currently advancing its 3,000-tonne-per-day Caribou Mill Complex and mine towards planned 2015 production.

All of the Company's deposits remain open for expansion.

The common shares of Trevali are listed on the TSX (symbol TV), the OTCQX (symbol TREVF) and on the Lima Stock Exchange (symbol TV). For further details on Trevali, readers are referred to the Company's web site (www.trevali.com) and to Canadian regulatory filings on SEDAR at www.sedar.com.

On Behalf of the Board of Directors of

TREVALI MINING CORPORATION

Mark D. Cruise, President

This news release contains "forward-looking statements" within the meaning of the United States private securities litigation reform act of 1995 and "forward-looking information" within the meaning of applicable Canadian securities legislation. Statements containing forward-looking information express, as at the date of this news release, the Company's plans, estimates, forecasts, projections, expectations, or beliefs as to future events or results and the company does not intend, and does not assume any obligation to, update such statements containing the forward-looking information. Such forward-looking statements and information include, but are not limited to statements as to: the accuracy of estimated mineral reserves and resources, anticipated results of future exploration, and forecast future metal prices, anticipated results of future electrical sales and expectations that environmental, permitting, legal, title, taxation, socio-economic, political, marketing or other issues will not materially affect estimates of mineral reserves. These statements reflect the Company's current views with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by the Company, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies.

These statements reflect the Company's current views with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by the company, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies. Many factors, both known and unknown, could cause actual results, performance or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements contained in this news release and the company has made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: fluctuations in spot and forward markets for silver, zinc, base metals and certain other commodities (such as natural gas, fuel oil and electricity); fluctuations in currency markets (such as the Peruvian sol versus the U.S. dollar); risks related to the technological and operational nature of the Company's business; changes in national and local government, legislation, taxation, controls or regulations and political or economic developments in Canada, the United States, Peru or other countries where the Company may carry on business in the future; risks and hazards associated with the business of mineral exploration, development and mining (including environmental hazards, industrial accidents, unusual or unexpected geological or structural formations, pressures, cave-ins and flooding);

risks relating to the credit worthiness or financial condition of suppliers, refiners and other parties with whom the Company does business; inadequate insurance, or inability to obtain insurance, to cover these risks and hazards; employee relations; relationships with and claims by local communities and indigenous populations; availability and increasing costs associated with mining inputs and labour; the speculative nature of mineral exploration and development, including the risks of obtaining necessary licenses and permits and the presence of laws and regulations that may impose restrictions on mining,; diminishing quantities or grades of mineral reserves as properties are mined; global financial conditions; business opportunities that may be presented to, or pursued by, the Company; the Company's ability to complete and successfully integrate acquisitions and to mitigate other business combination risks; challenges to, or difficulty in maintaining, the Company's title to properties and continued ownership thereof; the actual results of current exploration activities, conclusions of economic evaluations, and changes in project parameters to deal with unanticipated economic or other factors; increased competition in the mining industry for properties, equipment, qualified personnel, and their costs. Investors are cautioned against attributing undue certainty or reliance on forward-looking statements. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated, described or intended. The Company does not intend, and does not assume any obligation, to update these forward-looking statements or information to reflect changes in assumptions or changes in circumstances or any other events affecting such statements or information, other than as required by applicable law.

Trevali's production plans at Caribou-Halfmile-Stratmat and Santander are based only on Indicated and Inferred Mineral Resources and not Mineral Reserves and do not have demonstrated economic viability. Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is therefore no certainty that the conclusions of the production plans and Preliminary Economic Assessment (PEA) will be realized. Additionally where Trevali discusses exploration/expansion potential, any potential quantity and grade is conceptual in nature and there has been insufficient exploration to define a mineral resource and it is uncertain if further exploration will result in the target being delineated as a mineral resource.

We advise US investors that while the terms "measured resources", "indicated resources" and "inferred resources" are recognized and required by Canadian regulations, the US Securities and Exchange Commission does not recognize these terms. US investors are cautioned not to assume that any part or all of the material in these categories will ever be converted into reserves.

This news release does not constitute an offer to sell or a solicitation of an offer to buy any of the securities in the United States. The securities described herein have not been and will not be registered under the United States Securities Act of 1933, as amended, or the securities laws of any state and may not be offered or sold within the United States, absent such registration or an applicable exemption from such registration requirements.

The TSX has not approved or disapproved of the contents of this news release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Container technology is sending shock waves through the world of cloud computing. Heralded as the 'next big thing,' containers provide software owners a consistent way to package their software and dependencies while infrastructure operators benefit from a standard way to deploy and run them. Containers present new challenges for tracking usage due to their dynamic nature. They can also be deployed to bare metal, virtual machines and various cloud platforms. How do software owners track the usag...
Mobile, social, Big Data, and cloud have fundamentally changed the way we live. “Anytime, anywhere” access to data and information is no longer a luxury; it’s a requirement, in both our personal and professional lives. For IT organizations, this means pressure has never been greater to deliver meaningful services to the business and customers.
SYS-CON Events announced today that MobiDev, a software development company, will exhibit at the 17th International Cloud Expo®, which will take place November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. MobiDev is a software development company with representative offices in Atlanta (US), Sheffield (UK) and Würzburg (Germany); and development centers in Ukraine. Since 2009 it has grown from a small group of passionate engineers and business managers to a full-scale mobi...
In a recent research, analyst firm IDC found that the average cost of a critical application failure is $500,000 to $1 million per hour and the average total cost of unplanned application downtime is $1.25 billion to $2.5 billion per year for Fortune 1000 companies. In addition to the findings on the cost of the downtime, the research also highlighted best practices for development, testing, application support, infrastructure, and operations teams.
There are many considerations when moving applications from on-premise to cloud. It is critical to understand the benefits and also challenges of this migration. A successful migration will result in lower Total Cost of Ownership, yet offer the same or higher level of robustness. In his session at 15th Cloud Expo, Michael Meiner, an Engineering Director at Oracle, Corporation, analyzed a range of cloud offerings (IaaS, PaaS, SaaS) and discussed the benefits/challenges of migrating to each offe...
"We've just seen a huge influx of new partners coming into our ecosystem, and partners building unique offerings on top of our API set," explained Seth Bostock, Chief Executive Officer at IndependenceIT, in this SYS-CON.tv interview at 16th Cloud Expo, held June 9-11, 2015, at the Javits Center in New York City.
Digital Transformation is the ultimate goal of cloud computing and related initiatives. The phrase is certainly not a precise one, and as subject to hand-waving and distortion as any high-falutin' terminology in the world of information technology. Yet it is an excellent choice of words to describe what enterprise IT—and by extension, organizations in general—should be working to achieve. Digital Transformation means: handling all the data types being found and created in the organizat...
SYS-CON Events announced today that HPM Networks will exhibit at the 17th International Cloud Expo®, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. For 20 years, HPM Networks has been integrating technology solutions that solve complex business challenges. HPM Networks has designed solutions for both SMB and enterprise customers throughout the San Francisco Bay Area.
Chuck Piluso presented a study of cloud adoption trends and the power and flexibility of IBM Power and Pureflex cloud solutions. Prior to Secure Infrastructure and Services, Mr. Piluso founded North American Telecommunication Corporation, a facilities-based Competitive Local Exchange Carrier licensed by the Public Service Commission in 10 states, serving as the company's chairman and president from 1997 to 2000. Between 1990 and 1997, Mr. Piluso served as chairman & founder of International Te...
The Software Defined Data Center (SDDC), which enables organizations to seamlessly run in a hybrid cloud model (public + private cloud), is here to stay. IDC estimates that the software-defined networking market will be valued at $3.7 billion by 2016. Security is a key component and benefit of the SDDC, and offers an opportunity to build security 'from the ground up' and weave it into the environment from day one. In his session at 16th Cloud Expo, Reuven Harrison, CTO and Co-Founder of Tufin,...
With SaaS use rampant across organizations, how can IT departments track company data and maintain security? More and more departments are commissioning their own solutions and bypassing IT. A cloud environment is amorphous and powerful, allowing you to set up solutions for all of your user needs: document sharing and collaboration, mobile access, e-mail, even industry-specific applications. In his session at 16th Cloud Expo, Shawn Mills, President and a founder of Green House Data, discussed h...
For IoT to grow as quickly as analyst firms’ project, a lot is going to fall on developers to quickly bring applications to market. But the lack of a standard development platform threatens to slow growth and make application development more time consuming and costly, much like we’ve seen in the mobile space. In his session at @ThingsExpo, Mike Weiner, Product Manager of the Omega DevCloud with KORE Telematics Inc., discussed the evolving requirements for developers as IoT matures and conducte...
One of the hottest areas in cloud right now is DRaaS and related offerings. In his session at 16th Cloud Expo, Dale Levesque, Disaster Recovery Product Manager with Windstream's Cloud and Data Center Marketing team, will discuss the benefits of the cloud model, which far outweigh the traditional approach, and how enterprises need to ensure that their needs are properly being met.
In their session at 17th Cloud Expo, Hal Schwartz, CEO of Secure Infrastructure & Services (SIAS), and Chuck Paolillo, CTO of Secure Infrastructure & Services (SIAS), provide a study of cloud adoption trends and the power and flexibility of IBM Power and Pureflex cloud solutions. In his role as CEO of Secure Infrastructure & Services (SIAS), Hal Schwartz provides leadership and direction for the company.
The Internet of Everything (IoE) brings together people, process, data and things to make networked connections more relevant and valuable than ever before – transforming information into knowledge and knowledge into wisdom. IoE creates new capabilities, richer experiences, and unprecedented opportunities to improve business and government operations, decision making and mission support capabilities.