Continental Gold Files NI 43-101 Technical Report and Announces Commencement of Preliminary Economic Assessment on its Buritica Project, Colombia

TORONTO, ONTARIO -- (Marketwired) -- 06/26/14 -- Continental Gold Limited (TSX: CNL)(OTCQX: CGOOF) ("Continental" or the "Company") is pleased to announce that, further to its press release of May 13, 2014 announcing an updated mineral resource estimate for the Buritica project in Colombia, the Company has filed with Canadian securities regulators an independent technical report prepared in accordance with National Instrument 43-101 ("NI 43-101") entitled "Independent Technical Report and Resource Estimate on the Buritica Gold Project 2013" (the "Technical Report"), containing the updated mineral resource estimates. The Technical Report, dated June 25, 2014, with an effective date of December 31, 2013, was prepared for the Company by Mining Associates Pty Limited. A copy of the Technical Report can be accessed under the Company's SEDAR profile at www.sedar.com, or on the Company's website at www.continentalgold.com.

The Technical Report covers two major vein systems - Yaragua and Veta Sur - with a combined Measured mineral resource of 990,000 tonnes of mineralized material containing 650,000 ounces of gold grading 20.4 g/t gold, 1,540,000 ounces of silver grading 48 g/t silver, and 15,000,000 pounds of zinc grading 0.7% zinc, and a combined Indicated mineral resource of 7,410,000 tonnes of mineralized material containing 2,150,000 ounces of gold grading 9.0 g/t gold, 6,890,000 ounces of silver grading 29 g/t silver, and 75,100,000 pounds of zinc grading 0.5% zinc. The combined Inferred mineral resource is 16,700,000 tonnes of mineralized material containing 4,200,000 ounces of gold grading 7.8 g/t gold, 13,100,000 ounces of silver grading 24 g/t silver and 111,000,000 pounds of zinc grading 0.3% zinc.

---------------------------------------------------------------------------
Combined Yaragua and Veta Sur Mineral Resources above a 3 g/t gold cut-off,
                          as at December 31, 2013
---------------------------------------------------------------------------
      Resource                 Grades                       Metal
---------------------------------------------------------------------------
                                   AuEq                        AuEq
Category  M tonnes Au g/t Ag g/t    g/t   Zn % Au Moz Ag Moz    Moz  Zn Mlb
---------------------------------------------------------------------------
Measured      0.99   20.4     48   21.4   0.7%   0.65   1.54   0.68    15.0
---------------------------------------------------------------------------
Indicated     7.41    9.0     29    9.6   0.5%   2.15   6.89   2.29    75.1
---------------------------------------------------------------------------
M & I         8.39   10.4     31   11.0   0.5%   2.80   8.43   2.97    90.1
---------------------------------------------------------------------------
Inferred      16.7    7.8     24    8.2   0.3%    4.2   13.1    4.4     111
---------------------------------------------------------------------------
Notes - Reported tonnage and grade figures have been rounded from raw
estimates to reflect the order of accuracy of the estimate. Minor
variations may occur during the addition of rounded numbers. There have
been no assumptions made as to metal prices or recoveries in this mineral
resource estimate other than in gold equivalents that are calculated for
AuEq = Au+ Ag/50. M in Figures and Tables represents millions.
---------------------------------------------------------------------------

In addition, the Company announces that it has engaged M3 Engineering & Technology Corp. ("M3"), a full-service international engineering design company headquartered in Tucson, Arizona, to oversee and complete a Preliminary Economic Assessment ("PEA") of the Buritica project in Q4 2014. Since its inception in 1986, M3 has provided architectural, engineering and construction management services, ranging from technical and financial conception to operational startup, on numerous domestic and international mining and other projects with unique technical challenges.

The PEA will be the first economic study for Buritica, to determine the potential mining and processing parameters and associated capital expenditures and operating costs for the project. The following table lists the contributors that will be responsible for the various aspects of the PEA:

---------------------------------------------------------------------------
Component                     Contributor
---------------------------------------------------------------------------
Geology                       Continental Gold Limited
---------------------------------------------------------------------------
Mineral Resource Estimate     Mining Associates Pty Limited (Australia)
---------------------------------------------------------------------------
Mine Planning                 NCL Ingeneiria Y Construccion S.A. (Chile)
---------------------------------------------------------------------------
Metallurgy and Process Plant
Design                        Transmin (Peru)/M3 (US and Mexico)
---------------------------------------------------------------------------
Geotechnical Studies          Ingeroc (Chile)
---------------------------------------------------------------------------
Hydrology and Hydrogeology    SAG (Colombia)
---------------------------------------------------------------------------
Tailings Storage              SVS Ingenieros (division of SRK (Peru))
---------------------------------------------------------------------------
Power Supply                  HMV Ingenieros Ltda (Colombia)
---------------------------------------------------------------------------
Environmental Baseline        SAG (Colombia)
---------------------------------------------------------------------------

The PEA is intended to be a preliminary step and is in addition to, and not a replacement, substitute or proxy for the planned Pre-Feasibility Study ("PFS"), which the Company still intends to complete on schedule in the second half of 2015. The PEA will be based off the updated mineral resource estimate contained in the Technical Report.

"The track record of both M3 and NCL for project design and implementation in Latin America is excellent," commented Ari Sussman, CEO. "We look forward to delivering a realistic PEA in Q4 2014, providing a first-pass outline for the Buritica project."

About Continental

Continental Gold Limited is an advanced-stage exploration and development company with an extensive portfolio of 100%-owned gold projects in Colombia. Spearheaded by a team with over 40 years of exploration and mining experience in Colombia, the Company is focused on advancing its high-grade Buritica gold project to production.

Additional details on the Buritica project and the rest of Continental's suite of exploration properties are available at www.continentalgold.com.

The authors of the Technical Report, Mr. Andrew Vigar, BAppSc Geo, FAusIMM, MSEG, and Mr. Martin Recklies, BAppSc Geo, MAIG, each of Mining Associates Pty Limited, are each a "qualified person" (as such term is defined in NI 43-101) and independent of the Company, and have prepared or supervised the preparation of the technical information upon which the technical information contained in this press release is based.

Forward-Looking Statements

This press release contains or refers to forward-looking information under Canadian securities legislation, including statements regarding the estimation of mineral resources, exploration results, potential mineralization, the anticipated completion of a PEA and PFS, and exploration and mine development plans, and is based on current expectations that involve a number of business risks and uncertainties. Forward- looking statements are subject to significant risks and uncertainties, and other factors that could cause actual results to differ materially from expected results. Readers should not place undue reliance on forward-looking statements. Factors that could cause actual results to differ materially from any forward-looking statement include, but are not limited to, failure to convert estimated mineral resources to reserves, capital and operating costs varying significantly from estimates, the preliminary nature of metallurgical test results, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, political risks, uncertainties relating to the availability and costs of financing needed in the future, changes in equity markets, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects and the other risks involved in the mineral exploration and development industry forward-looking statements are subject to significant risks and uncertainties, and other factors that could cause actual results to differ materially from expected results. These forward-looking statements are made as of the date hereof and the Company assumes no responsibility to update them or revise them to reflect new events or circumstances other than as required by law.

Differences in Reporting of Resource Estimates

This press release was prepared in accordance with Canadian standards, which differ in some respects from United States standards. In particular, and without limiting the generality of the foregoing, the terms "inferred mineral resources," "indicated mineral resources," "measured mineral resources" and "mineral resources" used or referenced in this press release are Canadian mining terms as defined in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects under the guidelines set out in the Canadian Institute of Mining, Metallurgy and Petroleum (the "CIM") Standards on Mineral Resources and Mineral Reserves (the "CIM Standards"). The CIM Standards differ significantly from standards in the United States. While the terms "mineral resource," "measured mineral resources," "indicated mineral resources," and "inferred mineral resources" are recognized and required by Canadian regulations, they are not defined terms under standards in the United States. "Inferred mineral resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian securities laws, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies. Readers are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into reserves. Readers are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally mineable. Disclosure of "contained ounces" in a resource is permitted disclosure under Canadian regulations; however, United States companies are only permitted to report mineralization that does not constitute "reserves" by standards in the United States as in place tonnage and grade without reference to unit measures. Accordingly, information regarding resources contained or referenced in this press release containing descriptions of our mineral deposits may not be comparable to similar information made public by United States companies.

Contacts:
Continental Gold Limited
+1.416.583.5610
[email protected]
www.continentalgold.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Large industrial manufacturing organizations are adopting the agile principles of cloud software companies. The industrial manufacturing development process has not scaled over time. Now that design CAD teams are geographically distributed, centralizing their work is key. With large multi-gigabyte projects, outdated tools have stifled industrial team agility, time-to-market milestones, and impacted P&L stakeholders.
High-velocity engineering teams are applying not only continuous delivery processes, but also lessons in experimentation from established leaders like Amazon, Netflix, and Facebook. These companies have made experimentation a foundation for their release processes, allowing them to try out major feature releases and redesigns within smaller groups before making them broadly available. In his session at 21st Cloud Expo, Brian Lucas, Senior Staff Engineer at Optimizely, discussed how by using ne...
"Cloud Academy is an enterprise training platform for the cloud, specifically public clouds. We offer guided learning experiences on AWS, Azure, Google Cloud and all the surrounding methodologies and technologies that you need to know and your teams need to know in order to leverage the full benefits of the cloud," explained Alex Brower, VP of Marketing at Cloud Academy, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clar...
Widespread fragmentation is stalling the growth of the IIoT and making it difficult for partners to work together. The number of software platforms, apps, hardware and connectivity standards is creating paralysis among businesses that are afraid of being locked into a solution. EdgeX Foundry is unifying the community around a common IoT edge framework and an ecosystem of interoperable components.
"CA has been doing a lot of things in the area of DevOps. Now we have a complete set of tool sets in order to enable customers to go all the way from planning to development to testing down to release into the operations," explained Aruna Ravichandran, Vice President of Global Marketing and Strategy at CA Technologies, in this SYS-CON.tv interview at DevOps Summit at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
"MobiDev is a software development company and we do complex, custom software development for everybody from entrepreneurs to large enterprises," explained Alan Winters, U.S. Head of Business Development at MobiDev, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
Agile has finally jumped the technology shark, expanding outside the software world. Enterprises are now increasingly adopting Agile practices across their organizations in order to successfully navigate the disruptive waters that threaten to drown them. In our quest for establishing change as a core competency in our organizations, this business-centric notion of Agile is an essential component of Agile Digital Transformation. In the years since the publication of the Agile Manifesto, the conn...
In his session at 21st Cloud Expo, James Henry, Co-CEO/CTO of Calgary Scientific Inc., introduced you to the challenges, solutions and benefits of training AI systems to solve visual problems with an emphasis on improving AIs with continuous training in the field. He explored applications in several industries and discussed technologies that allow the deployment of advanced visualization solutions to the cloud.
In his session at 21st Cloud Expo, Carl J. Levine, Senior Technical Evangelist for NS1, will objectively discuss how DNS is used to solve Digital Transformation challenges in large SaaS applications, CDNs, AdTech platforms, and other demanding use cases. Carl J. Levine is the Senior Technical Evangelist for NS1. A veteran of the Internet Infrastructure space, he has over a decade of experience with startups, networking protocols and Internet infrastructure, combined with the unique ability to it...
Vulnerability management is vital for large companies that need to secure containers across thousands of hosts, but many struggle to understand how exposed they are when they discover a new high security vulnerability. In his session at 21st Cloud Expo, John Morello, CTO of Twistlock, addressed this pressing concern by introducing the concept of the “Vulnerability Risk Tree API,” which brings all the data together in a simple REST endpoint, allowing companies to easily grasp the severity of the ...
Enterprises are adopting Kubernetes to accelerate the development and the delivery of cloud-native applications. However, sharing a Kubernetes cluster between members of the same team can be challenging. And, sharing clusters across multiple teams is even harder. Kubernetes offers several constructs to help implement segmentation and isolation. However, these primitives can be complex to understand and apply. As a result, it’s becoming common for enterprises to end up with several clusters. Thi...
While some developers care passionately about how data centers and clouds are architected, for most, it is only the end result that matters. To the majority of companies, technology exists to solve a business problem, and only delivers value when it is solving that problem. 2017 brings the mainstream adoption of containers for production workloads. In his session at 21st Cloud Expo, Ben McCormack, VP of Operations at Evernote, discussed how data centers of the future will be managed, how the p...
"NetApp is known as a data management leader but we do a lot more than just data management on-prem with the data centers of our customers. We're also big in the hybrid cloud," explained Wes Talbert, Principal Architect at NetApp, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
"Space Monkey by Vivent Smart Home is a product that is a distributed cloud-based edge storage network. Vivent Smart Home, our parent company, is a smart home provider that places a lot of hard drives across homes in North America," explained JT Olds, Director of Engineering, and Brandon Crowfeather, Product Manager, at Vivint Smart Home, in this SYS-CON.tv interview at @ThingsExpo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
The question before companies today is not whether to become intelligent, it’s a question of how and how fast. The key is to adopt and deploy an intelligent application strategy while simultaneously preparing to scale that intelligence. In her session at 21st Cloud Expo, Sangeeta Chakraborty, Chief Customer Officer at Ayasdi, provided a tactical framework to become a truly intelligent enterprise, including how to identify the right applications for AI, how to build a Center of Excellence to oper...